CN108915690A - Prevent the new method of shaft wall water burst in the driving of vertical shaft water-bearing layer - Google Patents

Prevent the new method of shaft wall water burst in the driving of vertical shaft water-bearing layer Download PDF

Info

Publication number
CN108915690A
CN108915690A CN201810737000.8A CN201810737000A CN108915690A CN 108915690 A CN108915690 A CN 108915690A CN 201810737000 A CN201810737000 A CN 201810737000A CN 108915690 A CN108915690 A CN 108915690A
Authority
CN
China
Prior art keywords
water
injection hole
suction eye
slip casting
pressure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810737000.8A
Other languages
Chinese (zh)
Other versions
CN108915690B (en
Inventor
肖益盖
李鸿飞
孙国权
汪为平
刘海林
王雨波
李宁
刘帅
李彩丽
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Huawei National Engineering Research Center of High Efficient Cyclic and Utilization of Metallic Mineral Resources Co Ltd
Sinosteel Maanshan General Institute of Mining Research Co Ltd
Original Assignee
Huawei National Engineering Research Center of High Efficient Cyclic and Utilization of Metallic Mineral Resources Co Ltd
Sinosteel Maanshan General Institute of Mining Research Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Huawei National Engineering Research Center of High Efficient Cyclic and Utilization of Metallic Mineral Resources Co Ltd, Sinosteel Maanshan General Institute of Mining Research Co Ltd filed Critical Huawei National Engineering Research Center of High Efficient Cyclic and Utilization of Metallic Mineral Resources Co Ltd
Priority to CN201810737000.8A priority Critical patent/CN108915690B/en
Publication of CN108915690A publication Critical patent/CN108915690A/en
Application granted granted Critical
Publication of CN108915690B publication Critical patent/CN108915690B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D5/00Lining shafts; Linings therefor
    • E21D5/04Lining shafts; Linings therefor with brick, concrete, stone, or similar building materials

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

The invention discloses the new methods for preventing shaft wall water burst in a kind of driving of vertical shaft water-bearing layer, pour grout cover (4), set up workbench (5) on the grout cover (4) poured;From grout cover (4), Drilling injected hole (3), water injection hole (2) and suction eye (9), suction eye (9) are arranged in the upstream of water flow field (10) diagonally downward, outward on workbench (5);Water injection hole (2) is filled the water, is drawn water to suction eye (9), then carries out slip casting from injected hole (3).The present invention controls and is distributed to the water flow field and hydraulic pressure in slip casting region, so that slurries be made uniformly to be diffused into slip casting region, reduce slurries running pulp phenomenon, while suitably reducing grouting pressure, while reducing grouting cost by drawing water and draining.

Description

Prevent the new method of shaft wall water burst in the driving of vertical shaft water-bearing layer
Technical field
The invention belongs to shaft wall grouting for water plugging technical fields, and in particular to prevention is perpendicular in a kind of driving of vertical shaft water-bearing layer The grouting strengthening method of well borehole wall water burst.
Background technique
In deep shaft construction, since mine surrounding rock body often meets permeable water guide layer, underground accumulates a large amount of cracks deposited Water can constantly be oozed out with work surface, and full pit shaft has percolating water under serious conditions, especially at several tomographies that pit shaft passes through There is concentration water burst, and water yield is big, hydraulic pressure is high.If pit shaft water burst cannot be blocked effectively, prominent watered-out well thing is easily led to Therefore.There are two types of methods for common vertical shaft water-bearing layer piercing technique:
First method is " freezing+slip casting " method.Freezing process be widely used in mine construction, foundation, hydraulic engineering, In the engineering constructions such as underground railway, subfluvial tunnel, freezing process is chiefly used in the cutting of vertical in mine construction, is also used for otherly The caving ground of lower engineering or aqueous profuse fractured rock construction.But this method not only needs a large amount of energy freezing shaft wall Surrounding country rock, and after freezing releasing, structural stability decline in frozen region is right so as to cause the decline of borehole wall surrounding Surrounding Rock Strength Under deep shaft high temperature, high pressure, heavily stressed complex environment, such method cost is costly.
Second of grouting strengthening method is direct slip casting.The method has good applicability in superficial part, but in deep height Running pulp and the larger problem of grouting pump type selecting are easy to produce under pressure-bearing bottom.And existing grouting and sealing technique is mostly with traditional Slip casting slurry is wanted based on ordinary cement slurries, and cement grout can only block big crack conduit pipe since partial size is larger, Microfissure still cannot be blocked effectively, if mine shaft depth is big, and the borehole wall does not use impervious concrete, then due to hydrostatic pressing The higher water that will lead to of power is constantly oozed out from wall-rock crack, is then seeped on the borehole wall by the capillary porosity of borehole wall concrete.For Solve the problems, such as to want the direct slip casting method of slip casting slurry exist based on ordinary cement slurries, 2015.04 publish《Mining industry dress It is standby》On " application of the chemical grouting in processing shaft wall water burst " delivered in a text, using selecting national approved product urea Urea formaldehyde, oxalic acid solution and nontoxic, harmless, free of contamination ep-type material nanometer filling agent can be solved effectively as injecting paste material The microfissure that certainly common injecting paste material can not block, reaches slip casting effect.But the injecting paste material is expensive, and construction cost is high.
Summary of the invention
That the purpose of the present invention is to construction costs of the existing technology is high, be easy to cause freezing shaft wall rupture and The problems such as being easy to produce running pulp, and the new method for preventing shaft wall water burst in a kind of driving of vertical shaft water-bearing layer is provided.
Above-mentioned purpose to realize the present invention prevents the new of shaft wall water burst in a kind of driving of vertical shaft water-bearing layer of the present invention Method is realized using following technique, step:
The new method for preventing shaft wall water burst in a kind of vertical shaft water-bearing layer driving of the present invention, is containing water barrier first The downward excavating shaft in position forms the cast-in-situ steel reinforced concrete borehole wall, and uses following technique, step:
The first step:Advance geology exploration and forecast are carried out to vertical shaft using Transient Electromagnetic Apparatus, hydrology bore mode, grasped perpendicular The engineering geology and hydrogeology of well;
Second step:Grout cover is poured at the development end apart from aqueous 5~8m of the crushed zone distance of high pressure-bearing;
Third step:Workbench is set up on the grout cover poured;On workbench diagonally downward, outward from grout cover Drilling injected hole, water injection hole and suction eye, the quantity of injected hole are 3~6, and the water injection hole and suction eye are distributed in water flow On the same streamline of field, the angle between water injection hole and suction eye is 30~75 °;The injected hole is evenly distributed on suction eye Inside the adjustable flow field of water injection hole;The suction eye is arranged in the upstream of water flow field;
4th step:Flood-pot experiment is carried out to water injection hole, water-bearing layer water absorption rate, aquifer water pressure parameter is obtained, is set for slip casting It counts Scheme Choice and foundation is provided;Then water injection hole is filled the water, is drawn water to suction eye, to will grouting and reinforcing Gao Cheng It presses aqueous crushed zone to be rinsed, expands rock gap, to be easy to slurries diffusion;
5th step:After the completion of flushing, slip casting is carried out from injected hole, draws water from suction eye, carries out pressure water from water injection hole, After slurries reach design concentration in suction eye, stopping draws water from suction eye and from water filling pore pressure water, continues to carry out from injected hole Slip casting, and concentration of slurry in water injection hole is monitored, reach design concentration to concentration of slurry in water injection hole and continues 5~10 points Zhong Hou stops slip casting, then carries out washing pipe to grouting pipeline;Cement-sodium silicate double liquid is used when slip casting;
6th step:After grout cures, using electrical prospecting apparatus or the geology detecting equipment with similar performance is to grouting quality It is checked, after the slip casting effect for reaching design, just can be carried out the excavation of grouting and reinforcing area development end;
It is step by step rapid to repeat the above-mentioned first step, second step, third step, the 4th step, the 5th step, the 6th, until passing through high pressure-bearing Aqueous crushed zone.
In the cement-sodium silicate double liquid that the 5th step uses, the ratio of mud of cement grout is 1.8: 1~1: 0.6, is mixed Adding waterglass is 1.5%~3.5%.
Since high pressure-bearing broken rock gap hydraulic pressure is larger, overdrainage will lead to formation damage.Therefore, the above-mentioned 4th In step, the hydraulic pressure when being drawn water from suction eye is reduced to the 1/4 of the aqueous crushed zone corresponding position aquifer water pressure of high pressure-bearing When~1/2, the hydraulic pressure that draws water is kept to terminate to drawing water.
It under normal circumstances, is that the aqueous crushed zone corresponding position of high pressure-bearing is aqueous from the pressure of water filling, pressure water in water injection hole 1.8~2.8 times of layer hydraulic pressure are advisable.Too small water filling, pressure water pressure, it is difficult to play the aqueous crushed zone of high pressure-bearing is carried out it is good Flushing effect;Excessive water filling, pressure water pressure, will definitely increase equipment and construction operation cost.
The new method for preventing shaft wall water burst in a kind of vertical shaft water-bearing layer driving of the present invention is controlled by drawing water and draining It makes and is distributed to the water flow field and hydraulic pressure in slip casting region, so that slurries be made uniformly to be diffused into slip casting region, reduce slurries running pulp Phenomenon, while suitably reducing grouting pressure.
The new method for preventing shaft wall water burst in a kind of vertical shaft water-bearing layer driving of the present invention, has the advantages that:
(1) this method is filled the water while drawing water by suitably increasing suction eye, decline aquifer water pressure will not It is too fast, while the head that draws water is controlled, make aquifer water pressure keep in the reasonable scope, ensure that water-bearing with high pressure crushed zone Stability.
(2) this method adjusts a certain range of high aqueous crushed zone water flow field of pressure-bearing by suction eye and water injection hole, Induction slurries take the lead in spreading to water flow upstream, then spread to the slip casting area in water flow downstream, reduce the running pulp during slip casting Phenomenon spreads slurries uniformly in slip casting area.
(3) the present invention overcomes " freezing+slip casting " method construction cost height and existing " grouting and reinforcing method " in deep Gao Cheng Running pulp and the larger problem of grouting pump type selecting, strong applicability are easy to produce under pressure bottom.
(4) present invention is by adjusting the aqueous crushed zone water flow field of the high pressure-bearing in deep and water pressure, not only can be to avoid Caused by freezing process the problem of Sidewall Surrounding Rock structural instability, while can suitably reduce grouting pressure, thus reduce slip casting at This.
(5) overcome that " chemical grouting method " injecting paste material is expensive, construction cost is high, is possible to bring environmental pollution etc. Problem.
(6) cement-waterglass dual slurry is used, which has following features:Gel time can be at several seconds to several It adjusts, and can accurately control within the scope of ten minutes;Slurries Seed harvest compression strength, tensile strength are high, and calculus rate is up to 100%; Material source is abundant, and cheap, grouting cost is low, and River Bank Stability is convenient, to underground water and environmental nonpollution;Slurry viscosity Low, good flowing properties, the property infused is strong, compares the geological condition for being suitble to this vertical shaft.
Detailed description of the invention
Fig. 1 is that the vertical shaft for the new method for preventing shaft wall water burst in a kind of vertical shaft water-bearing layer driving of the present invention induces slip casting Reinforce diagrammatic cross-section;
Fig. 2 is water flow field schematic diagram after slip casting of the present invention, i.e. the A-A direction view of Fig. 1;
Fig. 3 is the high aqueous crushed zone water flow schematic diagram of pressure-bearing under native state, i.e. the B-B direction view of Fig. 1;
Fig. 4 is the present invention using water flow field schematic diagram after developing technique;
Appended drawing reference is:1-high aqueous the crushed zone of pressure-bearing;2-water injection holes;3-injected holes;4-grout covers;5-work Platform;6-grouting and reinforcing areas;7-cast-in-situ steel reinforced concrete the boreholes wall;8-water barriers;9-suction eyes;10-water flow fields; 11- vertical shaft.
Specific embodiment
To further describe the present invention, with reference to the accompanying drawings and examples to pre- in a kind of driving of vertical shaft water-bearing layer of the present invention The new method of anti-shaft wall water burst is described in further details.
The vertical shaft for the new method for preventing shaft wall water burst in a kind of vertical shaft water-bearing layer driving of the present invention as shown in Figure 1 lures It leads grouting and reinforcing diagrammatic cross-section to find out, prevents the new method of shaft wall water burst in a kind of vertical shaft water-bearing layer driving of the present invention, Using following technique, step:
The new method for preventing shaft wall water burst in a kind of driving of vertical shaft water-bearing layer of the present invention, according to ore body distribution characteristics and Local hydrological geological conditions select vertical shaft installation location, in the downward excavating shaft in the position containing water barrier, form cast in place reinforced bar Concrete walling, and use following technique, step:
The first step:Advance geology exploration and forecast are carried out to vertical shaft 11 using Transient Electromagnetic Apparatus, hydrology bore mode, grasped The engineering geology and hydrogeology of vertical shaft 11.
Second step:Grout cover 4 is poured at the development end of 5~8m of distance apart from the aqueous crushed zone 1 of high pressure-bearing.
Third step:Workbench 5 is set up on the grout cover 4 poured;On workbench 5 from grout cover 4 diagonally downward, Outside Drilling injected hole 3, water injection hole 2 and suction eye 9, the quantity of injected hole 3 are 3~6, the water injection hole 2 and suction eye 9 It is distributed on the same streamline of water flow field, the angle between water injection hole and suction eye is 30~75 °;The injected hole 3 is uniform It is distributed in inside suction eye 9 and the adjustable flow field of water injection hole 2;The suction eye 9 is arranged in the upstream of water flow field 10, described Suction eye 9 is arranged in water flow field upstream, and when slowly drawing water, low hydraulic pressure area is formed around it, to make to inject from injected hole Slurries can quickly be spread along the direction that water flow gradient declines, by water flow upstream to slip casting aqueous broken zone into Row is anti-blocking, to reduce the running pulp phenomenon in subsequent water flow downstream, while slip casting is suitably reduced under the premise of ensuring rock stability Pressure.
4th step:Flood-pot experiment is carried out to water injection hole 2, water-bearing layer water absorption rate, aquifer water pressure parameter is obtained, is set for slip casting It counts Scheme Choice and foundation is provided;Then water injection hole 2 is filled the water, is drawn water to suction eye 9, the water filling from water injection hole 2 Pressure is 1.8~2.8 times of the aqueous 1 corresponding position aquifer water pressure of crushed zone of high pressure-bearing, by water filling to will grouting and reinforcing The aqueous crushed zone 1 of high pressure-bearing be rinsed, expand rock gap, be easy to slurries diffusion;When being drawn water from suction eye 9 Hydraulic pressure when being reduced to the 1/4~1/2 of the aqueous 1 corresponding position aquifer water pressure of crushed zone of high pressure-bearing, keep the hydraulic pressure that draws water to arrive It draws water end.
5th step:After the completion of flushing, slip casting is carried out from injected hole 3, draws water from suction eye 9, is pressed from water injection hole 2 Water, after slurries reach design concentration in suction eye 9, stopping draws water from suction eye 9 and presses water from water injection hole 2, continues from slip casting Hole 3 carries out slip casting, and is monitored to concentration of slurry in water injection hole 2, reaches design concentration to concentration of slurry in water injection hole 2 and holds Continuous 5~after ten minutes, stop slip casting, then grouting pipeline is carried out to wash pipe;Cement-sodium silicate double liquid, water are used when slip casting The ratio of mud of slurry liquid is 1.8: 1~1: 0.6, and adding waterglass is 1.5%~3.5%.
6th step:After grout cures, using electrical prospecting apparatus or the geology detecting equipment with similar performance is to grouting quality It is checked, after the slip casting effect for reaching design, just can be carried out the excavation of 6 development end of grouting and reinforcing area.
It is step by step rapid to repeat the above-mentioned first step, second step, third step, the 4th step, the 5th step, the 6th, until passing through high pressure-bearing Aqueous crushed zone 1.
Water flow field schematic diagram is found out after the slip casting of the present invention as described in Fig. 2, the high aqueous crushed zone 1 of pressure-bearing by after slip casting, The streamline of water flow field 10 gets around grouting and reinforcing area 6.
The high aqueous crushed zone water flow schematic diagram of pressure-bearing is found out under native state as shown in Figure 3, the streamline of water flow field 10 Run through the aqueous crushed zone 1 of high pressure-bearing with rectilinear direction.
The present invention as shown in Figure 4 uses water flow field schematic diagram after developing technique to find out, Drilling injected hole 3, water injection hole 2 And suction eye 9, after being filled the water to water injection hole 2, being drawn water to suction eye 9, the streamline of the water flow field 10 of water injection hole 2 is not only It is connected by rock gap and suction eye 9, and arranges other low pressure directions into the aqueous crushed zone 1 of high pressure-bearing;Suction eye 9 is not only It is drawn water from water injection hole 2 by rock gap, and also by rock gap by other high pressure sides in the aqueous crushed zone 1 of high pressure-bearing To water extraction.Find out that the method for the present invention can be right from the present invention shown in Fig. 4 using water flow field schematic diagram after developing technique Rock gap in the high aqueous crushed zone 1 of pressure-bearing is rinsed well, the blocking of silt in lashing gap, in favor of slurry Liquid diffusion, to create conditions to through aqueous 1 slip casting of crushed zone of high pressure-bearing.
The method of the present invention in grouting program by increasing in water injection hole 2 and the aqueous crushed zone 1 of 9 pairs of suction eye high pressure-bearing Water flow field 10 is adjusted, so that slurries be made uniformly to spread.

Claims (5)

1. preventing the new method of shaft wall water burst in a kind of vertical shaft water-bearing layer driving, first in the position for containing water barrier (8) Downward excavating shaft (11), forms the cast-in-situ steel reinforced concrete borehole wall (7), it is characterised in that also uses following technique, step:
The first step:Advance geology exploration and forecast are carried out to vertical shaft (11) using Transient Electromagnetic Apparatus, hydrology bore mode, grasped perpendicular The engineering geology and hydrogeology of well (11);
Second step:Grout cover (4) are poured at the development end apart from aqueous (1) 5~8m distance of crushed zone of high pressure-bearing;
Third step:Workbench (5) are set up on the grout cover (4) poured;It is tilted on workbench (5) from grout cover (4) Downwards, Drilling injected hole (3), water injection hole (2) and suction eye (9), the quantity of injected hole (3) are 3~6 outward, the note Water hole (2) and suction eye (9) are distributed on the same streamline of water flow field, and the angle between water injection hole and suction eye is 30~75 °; The injected hole (3) is evenly distributed on inside suction eye (9) and water injection hole (2) adjustable flow field;Suction eye (9) cloth Set the upstream in water flow field (10);
4th step:Flood-pot experiment is carried out to water injection hole (2), obtains water-bearing layer water absorption rate, aquifer water pressure parameter, is grouting design Scheme Choice provides foundation;Then water injection hole (2) is filled the water, is drawn water to suction eye (9), to will grouting and reinforcing The high aqueous crushed zone of pressure-bearing (1) is rinsed, and expands rock gap, to be easy to slurries diffusion;
5th step:After the completion of flushing, slip casting is carried out from injected hole (3), is drawn water from suction eye (9), is carried out from water injection hole (2) Water is pressed, after slurries reach design concentration in suction eye (9), stopping draws water from suction eye (9) and presses water from water injection hole (2), after It is continuous to carry out slip casting from injected hole (3), and water injection hole (2) interior concentration of slurry is monitored, it is reached to water injection hole (2) interior concentration of slurry To design concentration and continue 5~after ten minutes, stop slip casting, then grouting pipeline carried out to wash pipe;Cement-is used when slip casting Waterglass dual slurry;
6th step:After grout cures, using electrical prospecting apparatus or the geology detecting equipment with similar performance carries out grouting quality It checks, after the slip casting effect for reaching design, just can be carried out the excavation of grouting and reinforcing area (6) development end;
It is step by step rapid to repeat the above-mentioned first step, second step, third step, the 4th step, the 5th step, the 6th, until aqueous by high pressure-bearing Crushed zone (1).
2. preventing the new method of shaft wall water burst in a kind of vertical shaft water-bearing layer driving as described in claim 1, feature exists In:In the cement-sodium silicate double liquid that the 5th step uses, the ratio of mud of cement grout is 1.8: 1~1: 0.6, adds water glass Glass is 1.5%~3.5%.
3. preventing the new method of shaft wall water burst, feature in a kind of vertical shaft water-bearing layer driving as claimed in claim 1 or 2 It is:In above-mentioned 4th step, it is corresponding that the hydraulic pressure when being drawn water from suction eye (9) is reduced to the aqueous crushed zone of high pressure-bearing (1) Position aquifer water pressure 1/4~1/2 when, keep this draw water hydraulic pressure to draw water terminate.
4. preventing the new method of shaft wall water burst in a kind of vertical shaft water-bearing layer driving as claimed in claim 3, feature exists In:From 1.8~2.8 that the water injection pressure in water injection hole (2) is the aqueous crushed zone of high pressure-bearing (1) corresponding position aquifer water pressure Times.
5. preventing the new method of shaft wall water burst in a kind of vertical shaft water-bearing layer driving as claimed in claim 4, feature exists In:The quantity of the injected hole (3) is 4, and 4 injected hole (3) intervals are evenly and symmetrically laid.
CN201810737000.8A 2018-07-06 2018-07-06 Novel method for preventing water gushing of vertical shaft well wall in vertical shaft aquifer tunneling Active CN108915690B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810737000.8A CN108915690B (en) 2018-07-06 2018-07-06 Novel method for preventing water gushing of vertical shaft well wall in vertical shaft aquifer tunneling

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810737000.8A CN108915690B (en) 2018-07-06 2018-07-06 Novel method for preventing water gushing of vertical shaft well wall in vertical shaft aquifer tunneling

Publications (2)

Publication Number Publication Date
CN108915690A true CN108915690A (en) 2018-11-30
CN108915690B CN108915690B (en) 2020-01-17

Family

ID=64425736

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810737000.8A Active CN108915690B (en) 2018-07-06 2018-07-06 Novel method for preventing water gushing of vertical shaft well wall in vertical shaft aquifer tunneling

Country Status (1)

Country Link
CN (1) CN108915690B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110206018A (en) * 2019-06-10 2019-09-06 广西大学 A kind of induction type grouting construction method
CN112031778A (en) * 2020-09-11 2020-12-04 北京住总集团有限责任公司 Construction method for shaft excavation based on multi-angle pre-reinforcement
CN113153365A (en) * 2021-03-16 2021-07-23 中铁四局集团第五工程有限公司 Cross tunneling rapid construction method suitable for water-rich ventilation inclined shaft
CN114703921A (en) * 2020-09-11 2022-07-05 北京住总集团有限责任公司 Construction method for preventing surge based on temporary bottom sealing structure

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08144686A (en) * 1994-11-17 1996-06-04 Ohbayashi Corp Construction method of shaft
CN1225974A (en) * 1998-02-09 1999-08-18 山东矿业学院 Technology for quickly resuming normal construction after wellhole submerged by sudden water
CN102011591A (en) * 2010-11-15 2011-04-13 中煤第五建设公司第三工程处 Grouting process for working surface of deep well
CN102536269A (en) * 2010-12-15 2012-07-04 山东黄金矿业(莱州)有限公司三山岛金矿 Underground grouting and water-plugging process
CN102606175A (en) * 2012-03-12 2012-07-25 山东新阳能源有限公司 Method for plugging confined water in underground coal mine sandstone crack
CN104453913A (en) * 2014-12-19 2015-03-25 玉溪大红山矿业有限公司 Vertical shaft working face ahead pre-grouting method
CN107313788A (en) * 2017-08-17 2017-11-03 新疆龟兹矿业有限公司 The method and device of grouting for water blocking under strong hydraulic connection
CN107558948A (en) * 2017-10-31 2018-01-09 平煤神马建工集团有限公司 It is a kind of that the method for slip casting closure and the method using its excavation shaft of vertical well are carried out to the crack in water-bearing layer by receiving water pipe
CN108119143A (en) * 2017-12-20 2018-06-05 湖南科技大学 A kind of vertical shaft working surface cement soluble glass paste combines grouting method with chemical grout double-round curtain

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08144686A (en) * 1994-11-17 1996-06-04 Ohbayashi Corp Construction method of shaft
CN1225974A (en) * 1998-02-09 1999-08-18 山东矿业学院 Technology for quickly resuming normal construction after wellhole submerged by sudden water
CN102011591A (en) * 2010-11-15 2011-04-13 中煤第五建设公司第三工程处 Grouting process for working surface of deep well
CN102536269A (en) * 2010-12-15 2012-07-04 山东黄金矿业(莱州)有限公司三山岛金矿 Underground grouting and water-plugging process
CN102606175A (en) * 2012-03-12 2012-07-25 山东新阳能源有限公司 Method for plugging confined water in underground coal mine sandstone crack
CN104453913A (en) * 2014-12-19 2015-03-25 玉溪大红山矿业有限公司 Vertical shaft working face ahead pre-grouting method
CN107313788A (en) * 2017-08-17 2017-11-03 新疆龟兹矿业有限公司 The method and device of grouting for water blocking under strong hydraulic connection
CN107558948A (en) * 2017-10-31 2018-01-09 平煤神马建工集团有限公司 It is a kind of that the method for slip casting closure and the method using its excavation shaft of vertical well are carried out to the crack in water-bearing layer by receiving water pipe
CN108119143A (en) * 2017-12-20 2018-06-05 湖南科技大学 A kind of vertical shaft working surface cement soluble glass paste combines grouting method with chemical grout double-round curtain

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110206018A (en) * 2019-06-10 2019-09-06 广西大学 A kind of induction type grouting construction method
CN112031778A (en) * 2020-09-11 2020-12-04 北京住总集团有限责任公司 Construction method for shaft excavation based on multi-angle pre-reinforcement
CN114703921A (en) * 2020-09-11 2022-07-05 北京住总集团有限责任公司 Construction method for preventing surge based on temporary bottom sealing structure
CN114703921B (en) * 2020-09-11 2024-05-28 北京住总集团有限责任公司 Construction method for preventing surging based on temporary back cover structure
CN113153365A (en) * 2021-03-16 2021-07-23 中铁四局集团第五工程有限公司 Cross tunneling rapid construction method suitable for water-rich ventilation inclined shaft

Also Published As

Publication number Publication date
CN108915690B (en) 2020-01-17

Similar Documents

Publication Publication Date Title
CN107288657B (en) The weak cementing rock mass seepage failure area slip casting integrated control method of top of underground
CN108240234B (en) A kind of Along Railway underlies coal mine gob Grouting method
CN108868776B (en) The high pressure-bearing broken rock of deep-well induces pre-pouring grout reinforcement means in advance
CN103967507B (en) A kind of curtain-grouting technique being suitable for rich water mine down-hole exploitation water blockoff
CN100591866C (en) Drifting sand layer and gravel stratum water-moving double-liquid high pressure slip-casting water-blocking construction method
CN102926770B (en) Underground draining and grouting process in thin bedrock and thick loose sand layer rich water areas
CN105201448B (en) Block water slip casting method for blocking in a kind of high-pressure high-flow water gushing channelway
CN102705005B (en) Technology for plugging water bursting in mine by directional diversion grouting
CN108915690A (en) Prevent the new method of shaft wall water burst in the driving of vertical shaft water-bearing layer
CN103277120B (en) A kind of non-fully deeply freeze vertical thaw after water burst prevention and controls
CN103334770B (en) One is grown up reverse-slope tunnel ultra high water pressure rich water zone of fracture construction method
CN103410119B (en) A kind of seepage inside concrete waterproof of man grouting method
CN107740701A (en) A kind of method of the accurate grout transformation of top plate thin layer limestone aquifer
CN109322699A (en) Pollution isolation blocking technology under a kind of mine
CN106320354A (en) Anti-seepage construction method for karst cave development stratum under overburden
CN108729438A (en) A kind of administering method in karst area channel
CN104370508A (en) Coal mine floor rock mass grouting reinforcement method and grouting slurry
CN115419384B (en) Dynamic grouting interception water shutoff method for aquifer with fully broken mining overburden
CN104612606A (en) Mine grouting technology and device with hole opening closed and circulation performed in hole
CN110130936A (en) It dashes forward in a kind of shield tunneling process and meets the construction method of untreated solution cavity or crack
CN217841648U (en) Existing shield stratum grouting reinforcement system based on WSS construction method for tunnel downward penetration
CN113374440A (en) Rapid plugging method and construction method for water inrush channel of hidden collapse column
CN111287769A (en) Tunnel surrounding rock advanced grouting reinforcement structure and construction method thereof
CN105731978A (en) Grouting slurry for reinforcing tunnel face of jacking culvert of fine-sand layer and grouting method
CN102817361B (en) Double bushing top cover for broken rock curtain grouting and construction method of double bushing top cover

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 243000 Xitang Road, Ma'anshan Economic Development Zone, Anhui, No. 666

Co-patentee after: HUAWEI METAL MINERAL RESOURCE EFFICIENT RECYCLING UTILIZATION NATIONAL ENGINEERING RESEARCH CENTER Co.,Ltd.

Patentee after: MAANSHAN Mine Research Institute Co.,Ltd.

Address before: 243000 Xitang Road, Ma'anshan Economic Development Zone, Anhui, No. 666

Co-patentee before: HUAWEI METAL MINERAL RESOURCE EFFICIENT RECYCLING UTILIZATION NATIONAL ENGINEERING RESEARCH CENTER Co.,Ltd.

Patentee before: SINOSTEEL MAANSHAN INSTITUTE OF MINING RESEARCH Co.,Ltd.