- CN108889772A CN108889772A CN201810975927.5A CN201810975927A CN108889772A CN 108889772 A CN108889772 A CN 108889772A CN 201810975927 A CN201810975927 A CN 201810975927A CN 108889772 A CN108889772 A CN 108889772A
- Authority
- CN
- China
- Prior art keywords
- production line
- raw material
- solid waste
- building stones
- tailing
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000004519 manufacturing process Methods 0.000 title claims abstract description 79
- 238000010276 construction Methods 0.000 title claims abstract description 26
- 239000010813 municipal solid waste Substances 0.000 title claims abstract description 21
- 239000002910 solid waste Substances 0.000 title claims abstract description 19
- 239000004575 stone Substances 0.000 claims abstract description 61
- 239000002994 raw material Substances 0.000 claims abstract description 57
- 239000000463 material Substances 0.000 claims abstract description 46
- 238000003860 storage Methods 0.000 claims description 21
- 238000012546 transfer Methods 0.000 claims description 14
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 claims description 10
- 229910052742 iron Inorganic materials 0.000 claims description 5
- 239000002689 soil Substances 0.000 claims description 5
- 230000005540 biological transmission Effects 0.000 claims description 3
- 238000003032 molecular docking Methods 0.000 claims description 2
- 239000002893 slag Substances 0.000 claims description 2
- 239000002699 waste material Substances 0.000 abstract description 17
- 238000000034 method Methods 0.000 abstract description 8
- 230000008569 process Effects 0.000 abstract description 5
- 239000002245 particle Substances 0.000 description 5
- 238000010586 diagram Methods 0.000 description 4
- 239000000203 mixture Substances 0.000 description 4
- 238000012545 processing Methods 0.000 description 4
- 239000008187 granular material Substances 0.000 description 3
- 230000008901 benefit Effects 0.000 description 2
- 239000000428 dust Substances 0.000 description 2
- 230000032258 transport Effects 0.000 description 2
- 208000027418 Wounds and injury Diseases 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 239000011449 brick Substances 0.000 description 1
- 230000008859 change Effects 0.000 description 1
- 230000006378 damage Effects 0.000 description 1
- 230000001627 detrimental effect Effects 0.000 description 1
- 238000011161 development Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000003912 environmental pollution Methods 0.000 description 1
- 239000004615 ingredient Substances 0.000 description 1
- 208000014674 injury Diseases 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000005453 pelletization Methods 0.000 description 1
- 239000000843 powder Substances 0.000 description 1
- 238000004064 recycling Methods 0.000 description 1
- 238000011160 research Methods 0.000 description 1
- 238000012216 screening Methods 0.000 description 1
- 230000004083 survival effect Effects 0.000 description 1
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B09—DISPOSAL OF SOLID WASTE; RECLAMATION OF CONTAMINATED SOIL
- B09B—DISPOSAL OF SOLID WASTE NOT OTHERWISE PROVIDED FOR
- B09B3/00—Destroying solid waste or transforming solid waste into something useful or harmless
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B02—CRUSHING, PULVERISING, OR DISINTEGRATING; PREPARATORY TREATMENT OF GRAIN FOR MILLING
- B02C—CRUSHING, PULVERISING, OR DISINTEGRATING IN GENERAL; MILLING GRAIN
- B02C21/00—Disintegrating plant with or without drying of the material
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B02—CRUSHING, PULVERISING, OR DISINTEGRATING; PREPARATORY TREATMENT OF GRAIN FOR MILLING
- B02C—CRUSHING, PULVERISING, OR DISINTEGRATING IN GENERAL; MILLING GRAIN
- B02C23/00—Auxiliary methods or auxiliary devices or accessories specially adapted for crushing or disintegrating not provided for in preceding groups or not specially adapted to apparatus covered by a single preceding group
- B02C23/08—Separating or sorting of material, associated with crushing or disintegrating
- B02C23/16—Separating or sorting of material, associated with crushing or disintegrating with separator defining termination of crushing or disintegrating zone, e.g. screen denying egress of oversize material
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B09—DISPOSAL OF SOLID WASTE; RECLAMATION OF CONTAMINATED SOIL
- B09B—DISPOSAL OF SOLID WASTE NOT OTHERWISE PROVIDED FOR
- B09B5/00—Operations not covered by a single other subclass or by a single other group in this subclass
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02W—CLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO WASTEWATER TREATMENT OR WASTE MANAGEMENT
- Y02W30/00—Technologies for solid waste management
- Y02W30/50—Reuse, recycling or recovery technologies
- Y02W30/58—Construction or demolition [C&D] waste
Landscapes
- Engineering & Computer Science (AREA)
- Environmental & Geological Engineering (AREA)
- Food Science & Technology (AREA)
- Processing Of Solid Wastes (AREA)
Abstract
Solid waste tailing and tailings construction rubbish of the present invention comprehensively utilize production line, belong to construction machinery equipment field, and in particular to a kind of aggregate production line;The invention proposes a kind of solid waste tailings and tailings construction rubbish to comprehensively utilize production line, which can produce and process building waste and industrial tailings, while also be capable of handling traditional raw material, such as the working process of cobblestone;There is provided technical solution is:Solid waste tailing and tailings construction rubbish comprehensively utilize production line, and the comprehensive utilization production line includes:Tailing production line, stone production line and integrated production line;The tailing production line, stone production line discharge port docked respectively with integrated production line by feed belt;The material for handling different material according to customer requirement, producing variable grain size may be implemented in the present invention, has multiple combinations mode, can satisfy production requirement, while reducing cost of investment, product competitiveness is greatly improved.
Description
Technical field
Solid waste tailing and tailings construction rubbish of the present invention comprehensively utilize production line, belong to construction machinery equipment field, specifically
It is related to a kind of aggregate production line.
Background technique
Construction industry is grown rapidly in recent two decades as one of mainstay of the national economy industry, with urban construction
Flourishing progress, remove become each city theme.Removal can generate a large amount of building waste.
These rubbish are mainly common brick, armored concrete and its mixture.Currently, the quantity of China's building waste has accounted for
The 30%~40% of municipal refuse total amount.Oneself is more than 400,000,000 tons to building waste annual emissions, wherein the big cities such as Beijing, Shanghai year row
High-volume at 30,000,000 tons or more.The unprocessed countryside or rural area just directly transported to of these building wastes overwhelming majority is using dew
It is stacked or the mode of landfill is handled, and stacking and filling then needs to consume the construction investments such as a large amount of expropriation of land, refuse collection,
Meanwhile it clearing and having aggravated environmental pollution again with fugitive dust with dropping in stacking process.Modern metropolitan cities towards industrialization, urbanization
The today accelerated development, the rubbish that a large amount of engineering constructions generate just are threaten the natural environment of human survival.Developed country is more early
With regard to having carried out a series of fruitful researchs and practice for this problem, it was demonstrated that the recycling for realizing building waste is to solve conscientiously
The certainly good recipe of this social concern.But so far, the related work of China's construction refuse resource relatively lags behind, and thus gives society
Meeting, environment and resource bring various detrimental effects.
It is main trend in recent years using building waste and industrial tailings production aggregate etc. other industrial products, but
It is that General Production Lines cannot be considered in terms of traditional raw material(Cobblestone etc.)With the production and processing of building waste and industrial tailings, it is arranged two
Production line significantly improves cost of investment, reduces production efficiency.
Summary of the invention
To overcome above-mentioned technical problem, the invention proposes a kind of solid waste tailing and the comprehensive utilization productions of tailings construction rubbish
Line, the production line can produce and process building waste and industrial tailings, while also be capable of handling traditional raw material, such as cobblestone
Working process.
In order to solve the above technical problems, present invention offer technical solution is:Solid waste tailing and the comprehensive benefit of tailings construction rubbish
With production line, the comprehensive utilization production line includes:Tailing production line, stone production line and integrated production line;The tailing is raw
Producing line, stone production line discharge port docked respectively with integrated production line by feed belt.
The tailing production line includes:Raw material cabin, raw material batcher, jaw crusher, material transfer belt, dregs storehouse,
Dregs feed belt, raw material intermediate bin and impact crusher;Raw material batcher is installed at the raw material cabin outlet at bottom, it is described
Raw material batcher discharge port is docked with jaw crushing machine inlet, is equipped with material transmission skin under the jaw crusher discharge port
Band, material transfer belt centre side are also equipped with dregs storehouse and dregs feed belt, the dregs feed belt and object
Expect feed belt docking, the other end of material transfer belt is set to above raw material intermediate bin, and the raw material intermediate bin is set to
On ground, impact crusher is provided with below the raw material intermediate bin.
The stone production line includes:Building stones storehouse, building stones batcher, building stones feed belt, building stones intermediate bin and multi-cylinder circle
Conic crusher;The stone bin outlet is equipped with building stones batcher, is provided between the building stones batcher and building stones intermediate bin
Building stones feed belt, building stones intermediate bin outlet lower section are provided with multi-cylinder cone crusher.
The integrated production line includes:Circular shale shaker, impact crusher, separating sieve, mixes wet machine and object at material intermediate bin
Expect storage warehouse;It is connected between the circular shale shaker and above-mentioned impact crusher and multi-cylinder cone crusher by feed belt, institute
It states circular shale shaker to set gradually material intermediate bin, impact crusher, separating sieve later and mix wet machine, the circular shale shaker, object
Expect to connect between intermediate bin, impact crusher and separating sieve by feed belt, it is described to mix wet machine and be set to separating sieve lower section,
The material storage storage includes several warehouses, and the warehouse of the material storage storage is connect by several feed belts with separating sieve.
The raw material intermediate bin and building stones intermediate bin lower end are provided with oscillating feeder.
The raw material batcher uses grizzly feeder TSW1345.
Be provided with the feed belt for being connected to dregs storehouse below the raw material batcher, and dregs storehouse and raw material batcher it
Between be provided with except soil sieve.
Iron remover is also equipped between the material intermediate bin and impact crusher.
Discharge port is additionally provided with the feed belt of connection impact crusher feed inlet below the separating sieve.
Deduster is mounted at the dregs storehouse, building stones storehouse and separating sieve.
The jaw crusher uses PEW860.
The impact crusher uses PFW1318 III.
The multi-cylinder cone crusher uses HPT300.
The oscillating feeder uses ZG400 type.
The circular shale shaker uses 3Y2460 formula vibrating screen.
The deduster in the dregs storehouse and building stones storehouse uses the box deduster of PPCS.
The separating sieve uses VUT120 dust pelletizing system.
Compared with the prior art, the invention has the beneficial effects that:
One, the present invention improves production line in such a way that tailing production line, stone production line are matched with integrated production line
Utilization efficiency reduces cost of investment, improves economic benefit.
Two, raw material batcher of the present invention uses grizzly feeder, is convenient for bulk materials uniform feeding, is conducive to jaw crushing
Machine continually and steadily works.
Three, the present invention is in such a way that jaw crusher is matched with impact breaker, convenient for bulk building waste
It directly handles, effectively improves working efficiency.
Four, the present invention is mutual using jaw crusher, impact breaker, multi-cylinder cone crusher and impact crusher
The mode of cooperation, convenient for producing various hardness, quality and the material of granular size according to demand.
Five, the present invention uses separating sieve and feed belt, different material can be stored to corresponding storage bin.
Detailed description of the invention
Fig. 1 is production line schematic diagram of the present invention;
Fig. 2 is production line E of the present invention to schematic diagram;
Fig. 3 is production line G of the present invention to schematic diagram;
Fig. 4 is production line F of the present invention to schematic diagram;
In figure:1 is tailing production line, and 2 be stone production line, and 3 be integrated production line, and 11 be raw material cabin, and 12 be raw material batcher,
13 be jaw crusher, and 14 be material transfer belt, and 15 be dregs storehouse, and 16 be dregs feed belt, and 17 be raw material intermediate bin, 18
For impact crusher, 19 is sieve except soil, and 21 be building stones storehouse, and 22 be building stones batcher, and 23 be building stones feed belt, and 24 is in building stones
Between storehouse, 25 be multi-cylinder cone crusher, and 31 be circular shale shaker, and 32 be material intermediate bin, and 33 be impact crusher, and 34 be sorting
Sieve, 35 is mix wet machine, and 36 be material storage storage, and 37 be iron remover.
Specific embodiment
It should be noted that structure, ratio, size etc. that Figure of description is drawn, only to cooperate specification to be taken off
The content shown is not intended to limit the invention enforceable range, therefore does not have so that those skilled in the art understands and reads
Technical essential meaning, the modification of any structure, the change of proportionate relationship or the adjustment of size are not influencing institute's energy of the present invention
Under the effect of generation and the purpose that can reach, the range that disclosed technology contents can be covered should all be still fallen in
It is interior.
It is described further combined with specific embodiments below.
As shown in figures 1-4, solid waste tailing and tailings construction rubbish comprehensively utilize production line, the comprehensive utilization production line
Including:Tailing production line 1, stone production line 2 and integrated production line 3;The discharge port of the tailing production line 1, stone production line 2
It is docked respectively with integrated production line 3 by feed belt.
The tailing production line 1 includes:Raw material cabin 11, raw material batcher 12, jaw crusher 13, material transfer belt
14, dregs storehouse 15, dregs feed belt 16, raw material intermediate bin 17 and impact crusher 18;At 11 outlet at bottom of raw material cabin
Raw material batcher 12 is installed, 12 discharge port of raw material batcher is docked with 13 feed inlet of jaw crusher, and the jaw is broken
Material transfer belt 14 is installed, the intermediate side of the material transfer belt 14 is also equipped with dregs storehouse 15 under broken 13 discharge port of machine
With dregs feed belt 16, the dregs feed belt 16 is docked with material transfer belt 14, material transfer belt 14 it is another
End is set to 17 top of raw material intermediate bin, and the raw material intermediate bin 17 is set on ground, sets below the raw material intermediate bin 17
It is equipped with impact crusher 18.
The stone production line 2 includes:Building stones storehouse 21, building stones batcher 22, building stones feed belt 23, building stones intermediate bin 24
With multi-cylinder cone crusher 25;The outlet of building stones storehouse 21 is equipped with building stones batcher 22, the building stones batcher 22 and building stones
Building stones feed belt 23 is provided between intermediate bin 24, the outlet of building stones intermediate bin 24 lower section is provided with multi-cylinder cone crusher
25。
The integrated production line 3 includes:Circular shale shaker 31, material intermediate bin 32, impact crusher 33, separating sieve 34,
Mix wet machine 35 and material storage storage 36;Between the circular shale shaker 31 and above-mentioned impact crusher 18 and multi-cylinder cone crusher 25
It is connected by feed belt, sets gradually material intermediate bin 32, impact crusher 33, separating sieve after the circular shale shaker 31
34 and wet machine 35 is mixed, passes through transmission between the circular shale shaker 31, material intermediate bin 32, impact crusher 33 and separating sieve 34
Belt connection, described to mix wet machine 35 and be set to the lower section of separating sieve 34, the material storage storage 36 includes several warehouses, the material
The warehouse of storage warehouse 36 is connect by several feed belts with separating sieve 34.
The raw material intermediate bin 17 and 24 lower end of building stones intermediate bin are provided with oscillating feeder.
The raw material batcher 12 uses grizzly feeder TSW1345.
The feed belt for being connected to dregs storehouse 15 is provided with below the raw material batcher 12, and dregs storehouse 15 is given with raw material
It is provided between material machine 12 except soil sieve 19.
Iron remover 37 is also equipped between the material intermediate bin 32 and impact crusher 33.
The 34 lower section discharge port of separating sieve is additionally provided with the feed belt of connection 33 feed inlet of impact crusher.
Deduster is mounted at the dregs storehouse 15, building stones storehouse 21 and separating sieve 34.
The tailing production line 1 mainly handles bulk building waste and other industrial tailings, by taking building waste as an example:Lorry
After building waste is transported to raw material cabin 11, by grizzly feeder uniformly by bulk building waste feeding to jaw crusher 13, warp
Raw material bulk particle is formed after processing, while after fritter building waste falls off from grizzly feeder, having feed belt to be transported to slag
Native Cang15Chu mixes again with raw material bulk particle with ingredient dregs after except soil processing, is then transported to raw material intermediate bin
17, raw material fritter particle is formed after being further processed using impact crusher 18, it then will after the screening of circular shale shaker 31
The biggish raw material fritter particulate transportation of particle to raw material intermediate bin 17 is handled again, qualified raw material fritter particle delivery to impact
Formula crusher 33 is further processed into raw material molecule, then passes through separating sieve 34, is transported to different material storage storage 36
It is interior.
Similarly, the stone production line 2 mainly handles traditional raw material, such as cobblestone, lorry transport cobblestone to stone
In feed bin 21, then building stones feed belt 23 transports cobblestone to building stones intermediate bin 24, by 25 powder of multi-cylinder cone crusher
The step of forming granule stone after broken, granule stone be then transported to circular shale shaker 31 and is handled, next handling granule stone
It is consistent with the method for above-mentioned processing building waste with method.
The material that different material is handled according to customer requirement, produces variable grain size may be implemented in this way,
With multiple combinations mode, production requirement can satisfy, while reducing cost of investment, product competitiveness is greatly improved.
It should be noted that:It is additionally provided with and removes between material intermediate bin 32 and impact crusher 33 in integrated production line 3
Ironware, can effectively remove the iron in abrasive grit in raw material, especially building waste, the injury of abrasive grit impingement crusher 33 compared with
Greatly, removal abrasive grit can effectively improve 33 service life of impact crusher.
Claims (10)
1. solid waste tailing and tailings construction rubbish comprehensively utilize production line, it is characterised in that:The comprehensive utilization production line includes:
Tailing production line(1), stone production line(2)And integrated production line(3);The tailing production line(1), stone production line(2)'s
Discharge port respectively with integrated production line(3)It is docked by feed belt.
2. solid waste tailing and tailings construction rubbish comprehensively utilize production line according to claim 1, it is characterised in that:The tail
Mine production line(1)Including:Raw material cabin(11), raw material batcher(12), jaw crusher(13), material transfer belt(14), slag
Tu Cang(15), dregs feed belt(16), raw material intermediate bin(17)And impact crusher(18);The raw material cabin(11)Bottom goes out
Raw material batcher is installed at mouthful(12), the raw material batcher(12)Discharge port and jaw crusher(13)Feed inlet docking,
The jaw crusher(13)Material transfer belt is installed under discharge port(14), the material transfer belt(14)Intermediate side
It is also equipped with dregs storehouse(15)With dregs feed belt(16), the dregs feed belt(16)With material transfer belt(14)It is right
It connects, material transfer belt(14)The other end be set to raw material intermediate bin(17)Top, the raw material intermediate bin(17)It is set to
On ground, the raw material intermediate bin(17)Lower section is provided with impact crusher(18).
3. solid waste tailing and tailings construction rubbish comprehensively utilize production line according to claim 1, it is characterised in that:The stone
Expect production line(2)Including:Building stones storehouse(21), building stones batcher(22), building stones feed belt(23), building stones intermediate bin(24)With it is more
Cylinder gyratory crusher(25);The building stones storehouse(21)Outlet is equipped with building stones batcher(22), the building stones batcher(22)With
Building stones intermediate bin(24)Between be provided with building stones feed belt(23), the building stones intermediate bin(24)Outlet lower section is provided with multi-cylinder
Gyratory crusher(25).
4. according to claim 1, solid waste tailing described in 2 or 3 any claims and tailings construction rubbish comprehensively utilize production line,
It is characterized in that:The integrated production line(3)Including:Circular shale shaker(31), material intermediate bin(32), impact crusher
(33), separating sieve(34), mix wet machine(35)With material storage storage(36);The circular shale shaker(31)With above-mentioned impact crusher
(18)And multi-cylinder cone crusher(25)Between pass through feed belt connect, the circular shale shaker(31)Material is set gradually later
Intermediate bin(32), impact crusher(33), separating sieve(34)With mix wet machine(35), the circular shale shaker(31), among material
Storehouse(32), impact crusher(33)And separating sieve(34)Between by feed belt connect, it is described to mix wet machine(35)It is set to
Separating sieve(34)Lower section, the material storage storage(36)Including several warehouses, the material storage storage(36)If warehouse by
Dry feed belt and separating sieve(34)Connection.
5. solid waste tailing according to claim 1 or claim 2 and tailings construction rubbish comprehensively utilize production line, it is characterised in that:Institute
State raw material intermediate bin(17)With building stones intermediate bin(24)Lower end is provided with oscillating feeder.
6. solid waste tailing according to claim 1 or claim 2 and tailings construction rubbish comprehensively utilize production line, it is characterised in that:Institute
State raw material batcher(12)Using grizzly feeder TSW1345.
7. solid waste tailing according to claim 1 or claim 2 and tailings construction rubbish comprehensively utilize production line, it is characterised in that:Institute
State raw material batcher(12)Lower section, which is provided with, is connected to dregs storehouse(15)Feed belt, and dregs storehouse(15)With raw material batcher
(12)Between be provided with except soil sieve(19).
8. according to claim 1, solid waste tailing described in 2 or 3 any claims and tailings construction rubbish comprehensively utilize production line,
It is characterized in that:The material intermediate bin(32)With impact crusher(33)Between be also equipped with iron remover(37).
9. according to claim 1, solid waste tailing described in 2 or 3 any claims and tailings construction rubbish comprehensively utilize production line,
It is characterized in that:The separating sieve(34)Lower section discharge port is additionally provided with connection impact crusher(33)The transmission skin of feed inlet
Band.
10. according to claim 1, solid waste tailing described in 2 or 3 any claims and the comprehensive utilization production of tailings construction rubbish
Line, it is characterised in that:The dregs storehouse(15), building stones storehouse(21)And separating sieve(34)Place is mounted on deduster.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810975927.5A CN108889772A (en) | 2018-08-24 | 2018-08-24 | Solid waste tailing and tailings construction rubbish comprehensively utilize production line |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810975927.5A CN108889772A (en) | 2018-08-24 | 2018-08-24 | Solid waste tailing and tailings construction rubbish comprehensively utilize production line |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108889772A true CN108889772A (en) | 2018-11-27 |
Family
ID=64358870
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810975927.5A Pending CN108889772A (en) | 2018-08-24 | 2018-08-24 | Solid waste tailing and tailings construction rubbish comprehensively utilize production line |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108889772A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112090941A (en) * | 2020-09-25 | 2020-12-18 | 瑞图明盛环保建材(昌江)有限公司 | General type tailing comprehensive treatment production line and system |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP3052126U (en) * | 1998-03-10 | 1998-09-14 | 人善企業株式会社 | Construction waste treatment equipment |
CN101229660A (en) * | 2008-02-11 | 2008-07-30 | 苏峰 | Method of preparing regenerative concrete products |
CN201596527U (en) * | 2010-02-05 | 2010-10-06 | 宝钢集团新疆八一钢铁有限公司 | Mineral ore crushing and dressing device |
CN202055143U (en) * | 2011-01-31 | 2011-11-30 | 上海寰保渣业处置有限公司 | Production device of road base material produced by brick-concrete type building rubbish |
CN107445543A (en) * | 2017-08-03 | 2017-12-08 | 河北建筑工程学院 | A kind of iron tailings regeneration concrete and preparation method thereof |
CN108176697A (en) * | 2017-12-27 | 2018-06-19 | 广东昕旺环保科技发展有限公司 | Build composting sorting total system and processing method |
CN209393717U (en) * | 2018-08-24 | 2019-09-17 | 临汾市华基建材科技有限公司 | A kind of solid waste tailing and tailings construction rubbish comprehensively utilize production line |
-
2018
- 2018-08-24 CN CN201810975927.5A patent/CN108889772A/en active Pending
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP3052126U (en) * | 1998-03-10 | 1998-09-14 | 人善企業株式会社 | Construction waste treatment equipment |
CN101229660A (en) * | 2008-02-11 | 2008-07-30 | 苏峰 | Method of preparing regenerative concrete products |
CN201596527U (en) * | 2010-02-05 | 2010-10-06 | 宝钢集团新疆八一钢铁有限公司 | Mineral ore crushing and dressing device |
CN202055143U (en) * | 2011-01-31 | 2011-11-30 | 上海寰保渣业处置有限公司 | Production device of road base material produced by brick-concrete type building rubbish |
CN107445543A (en) * | 2017-08-03 | 2017-12-08 | 河北建筑工程学院 | A kind of iron tailings regeneration concrete and preparation method thereof |
CN108176697A (en) * | 2017-12-27 | 2018-06-19 | 广东昕旺环保科技发展有限公司 | Build composting sorting total system and processing method |
CN209393717U (en) * | 2018-08-24 | 2019-09-17 | 临汾市华基建材科技有限公司 | A kind of solid waste tailing and tailings construction rubbish comprehensively utilize production line |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112090941A (en) * | 2020-09-25 | 2020-12-18 | 瑞图明盛环保建材(昌江)有限公司 | General type tailing comprehensive treatment production line and system |
CN112090941B (en) * | 2020-09-25 | 2023-11-03 | 瑞图明盛环保建材(昌江)有限公司 | General tailing comprehensive treatment production line and system |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101549351B (en) | Building refuse treatment regeneration system | |
CN201511034U (en) | Construction waste treatment regeneration system | |
CN102838307A (en) | Method and system for treating construction waste | |
CN206535848U (en) | Building waste processing system | |
CN113019648B (en) | High-efficient preparation system of abandonment concrete regeneration sand powder | |
CN109675906A (en) | A kind of wholly-owned source recycling and reusing system of building castoff | |
CN109734335A (en) | A method of high-quality steel-making slag powder is produced based on steel slag modifying agent | |
CN209576975U (en) | A kind of high-quality sandstone aggregate impacts dry milling production line entirely | |
CN206526918U (en) | Building rubbish treatment device | |
CN207643427U (en) | Spoil slag dry powder and mortar production system | |
CN207238203U (en) | A kind of Machine-made Sand production system | |
CN106824986A (en) | A kind of pollution-free treatment of electronic waste and the method for recycling | |
CN216125816U (en) | Waste ceramic tile system sand powder process all-in-one | |
CN209393717U (en) | A kind of solid waste tailing and tailings construction rubbish comprehensively utilize production line | |
CN215047092U (en) | Dry-mixed mortar production system | |
CN106116195A (en) | A kind of vertical mill grinding slag, lithium slag add modifying agent composite powder production method | |
CN203991634U (en) | A kind of high resource utilization system containing civil engineering building refuse | |
CN106116196A (en) | A kind of vertical mill grinding slag, lithium slag composite powder production method | |
CN209393314U (en) | A kind of solid waste tailing and building waste comprehensively utilize workshop | |
CN109985715A (en) | A kind of lime stone system of processing | |
CN203173995U (en) | Device for building waste residue associated grinding resource processing system | |
CN108889772A (en) | Solid waste tailing and tailings construction rubbish comprehensively utilize production line | |
CN209968608U (en) | Limestone processing system | |
CN109013015A (en) | Solid waste tailing and building waste comprehensively utilize workshop | |
CN219334474U (en) | Optimize construction waste and rubble system sand production line |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20181127 |