CN108889772A CN201810975927.5A CN201810975927A CN108889772A CN 108889772 A CN108889772 A CN 108889772A CN 201810975927 A CN201810975927 A CN 201810975927A CN 108889772 A CN108889772 A CN 108889772A
Authority
CN
China
Prior art keywords
production line
raw material
solid waste
building stones
tailing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810975927.5A
Other languages
Chinese (zh)
Inventor
郭幸福
张真弟
赵建强
裴林昊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Linfen City China Building Materials Science And Technology Ltd Co
Original Assignee
Linfen City China Building Materials Science And Technology Ltd Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Linfen City China Building Materials Science And Technology Ltd Co filed Critical Linfen City China Building Materials Science And Technology Ltd Co
Priority to CN201810975927.5A priority Critical patent/CN108889772A/en
Publication of CN108889772A publication Critical patent/CN108889772A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B09DISPOSAL OF SOLID WASTE; RECLAMATION OF CONTAMINATED SOIL
    • B09BDISPOSAL OF SOLID WASTE NOT OTHERWISE PROVIDED FOR
    • B09B3/00Destroying solid waste or transforming solid waste into something useful or harmless
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B02CRUSHING, PULVERISING, OR DISINTEGRATING; PREPARATORY TREATMENT OF GRAIN FOR MILLING
    • B02CCRUSHING, PULVERISING, OR DISINTEGRATING IN GENERAL; MILLING GRAIN
    • B02C21/00Disintegrating plant with or without drying of the material
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B02CRUSHING, PULVERISING, OR DISINTEGRATING; PREPARATORY TREATMENT OF GRAIN FOR MILLING
    • B02CCRUSHING, PULVERISING, OR DISINTEGRATING IN GENERAL; MILLING GRAIN
    • B02C23/00Auxiliary methods or auxiliary devices or accessories specially adapted for crushing or disintegrating not provided for in preceding groups or not specially adapted to apparatus covered by a single preceding group
    • B02C23/08Separating or sorting of material, associated with crushing or disintegrating
    • B02C23/16Separating or sorting of material, associated with crushing or disintegrating with separator defining termination of crushing or disintegrating zone, e.g. screen denying egress of oversize material
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B09DISPOSAL OF SOLID WASTE; RECLAMATION OF CONTAMINATED SOIL
    • B09BDISPOSAL OF SOLID WASTE NOT OTHERWISE PROVIDED FOR
    • B09B5/00Operations not covered by a single other subclass or by a single other group in this subclass
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02WCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO WASTEWATER TREATMENT OR WASTE MANAGEMENT
    • Y02W30/00Technologies for solid waste management
    • Y02W30/50Reuse, recycling or recovery technologies
    • Y02W30/58Construction or demolition [C&D] waste

Landscapes

  • Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Food Science & Technology (AREA)
  • Processing Of Solid Wastes (AREA)

Abstract

Solid waste tailing and tailings construction rubbish of the present invention comprehensively utilize production line, belong to construction machinery equipment field, and in particular to a kind of aggregate production line;The invention proposes a kind of solid waste tailings and tailings construction rubbish to comprehensively utilize production line, which can produce and process building waste and industrial tailings, while also be capable of handling traditional raw material, such as the working process of cobblestone;There is provided technical solution is:Solid waste tailing and tailings construction rubbish comprehensively utilize production line, and the comprehensive utilization production line includes:Tailing production line, stone production line and integrated production line;The tailing production line, stone production line discharge port docked respectively with integrated production line by feed belt;The material for handling different material according to customer requirement, producing variable grain size may be implemented in the present invention, has multiple combinations mode, can satisfy production requirement, while reducing cost of investment, product competitiveness is greatly improved.

Description

Solid waste tailing and tailings construction rubbish comprehensively utilize production line
Technical field
Solid waste tailing and tailings construction rubbish of the present invention comprehensively utilize production line, belong to construction machinery equipment field, specifically It is related to a kind of aggregate production line.
Background technique
Construction industry is grown rapidly in recent two decades as one of mainstay of the national economy industry, with urban construction Flourishing progress, remove become each city theme.Removal can generate a large amount of building waste.
These rubbish are mainly common brick, armored concrete and its mixture.Currently, the quantity of China's building waste has accounted for The 30%~40% of municipal refuse total amount.Oneself is more than 400,000,000 tons to building waste annual emissions, wherein the big cities such as Beijing, Shanghai year row High-volume at 30,000,000 tons or more.The unprocessed countryside or rural area just directly transported to of these building wastes overwhelming majority is using dew It is stacked or the mode of landfill is handled, and stacking and filling then needs to consume the construction investments such as a large amount of expropriation of land, refuse collection, Meanwhile it clearing and having aggravated environmental pollution again with fugitive dust with dropping in stacking process.Modern metropolitan cities towards industrialization, urbanization The today accelerated development, the rubbish that a large amount of engineering constructions generate just are threaten the natural environment of human survival.Developed country is more early With regard to having carried out a series of fruitful researchs and practice for this problem, it was demonstrated that the recycling for realizing building waste is to solve conscientiously The certainly good recipe of this social concern.But so far, the related work of China's construction refuse resource relatively lags behind, and thus gives society Meeting, environment and resource bring various detrimental effects.
It is main trend in recent years using building waste and industrial tailings production aggregate etc. other industrial products, but It is that General Production Lines cannot be considered in terms of traditional raw material(Cobblestone etc.)With the production and processing of building waste and industrial tailings, it is arranged two Production line significantly improves cost of investment, reduces production efficiency.
Summary of the invention
To overcome above-mentioned technical problem, the invention proposes a kind of solid waste tailing and the comprehensive utilization productions of tailings construction rubbish Line, the production line can produce and process building waste and industrial tailings, while also be capable of handling traditional raw material, such as cobblestone Working process.
In order to solve the above technical problems, present invention offer technical solution is:Solid waste tailing and the comprehensive benefit of tailings construction rubbish With production line, the comprehensive utilization production line includes:Tailing production line, stone production line and integrated production line;The tailing is raw Producing line, stone production line discharge port docked respectively with integrated production line by feed belt.
The tailing production line includes:Raw material cabin, raw material batcher, jaw crusher, material transfer belt, dregs storehouse, Dregs feed belt, raw material intermediate bin and impact crusher;Raw material batcher is installed at the raw material cabin outlet at bottom, it is described Raw material batcher discharge port is docked with jaw crushing machine inlet, is equipped with material transmission skin under the jaw crusher discharge port Band, material transfer belt centre side are also equipped with dregs storehouse and dregs feed belt, the dregs feed belt and object Expect feed belt docking, the other end of material transfer belt is set to above raw material intermediate bin, and the raw material intermediate bin is set to On ground, impact crusher is provided with below the raw material intermediate bin.
The stone production line includes:Building stones storehouse, building stones batcher, building stones feed belt, building stones intermediate bin and multi-cylinder circle Conic crusher;The stone bin outlet is equipped with building stones batcher, is provided between the building stones batcher and building stones intermediate bin Building stones feed belt, building stones intermediate bin outlet lower section are provided with multi-cylinder cone crusher.
The integrated production line includes:Circular shale shaker, impact crusher, separating sieve, mixes wet machine and object at material intermediate bin Expect storage warehouse;It is connected between the circular shale shaker and above-mentioned impact crusher and multi-cylinder cone crusher by feed belt, institute It states circular shale shaker to set gradually material intermediate bin, impact crusher, separating sieve later and mix wet machine, the circular shale shaker, object Expect to connect between intermediate bin, impact crusher and separating sieve by feed belt, it is described to mix wet machine and be set to separating sieve lower section, The material storage storage includes several warehouses, and the warehouse of the material storage storage is connect by several feed belts with separating sieve.
The raw material intermediate bin and building stones intermediate bin lower end are provided with oscillating feeder.
The raw material batcher uses grizzly feeder TSW1345.
Be provided with the feed belt for being connected to dregs storehouse below the raw material batcher, and dregs storehouse and raw material batcher it Between be provided with except soil sieve.
Iron remover is also equipped between the material intermediate bin and impact crusher.
Discharge port is additionally provided with the feed belt of connection impact crusher feed inlet below the separating sieve.
Deduster is mounted at the dregs storehouse, building stones storehouse and separating sieve.
The jaw crusher uses PEW860.
The impact crusher uses PFW1318 III.
The multi-cylinder cone crusher uses HPT300.
The oscillating feeder uses ZG400 type.
The circular shale shaker uses 3Y2460 formula vibrating screen.
The deduster in the dregs storehouse and building stones storehouse uses the box deduster of PPCS.
The separating sieve uses VUT120 dust pelletizing system.
Compared with the prior art, the invention has the beneficial effects that:
One, the present invention improves production line in such a way that tailing production line, stone production line are matched with integrated production line Utilization efficiency reduces cost of investment, improves economic benefit.
Two, raw material batcher of the present invention uses grizzly feeder, is convenient for bulk materials uniform feeding, is conducive to jaw crushing Machine continually and steadily works.
Three, the present invention is in such a way that jaw crusher is matched with impact breaker, convenient for bulk building waste It directly handles, effectively improves working efficiency.
Four, the present invention is mutual using jaw crusher, impact breaker, multi-cylinder cone crusher and impact crusher The mode of cooperation, convenient for producing various hardness, quality and the material of granular size according to demand.
Five, the present invention uses separating sieve and feed belt, different material can be stored to corresponding storage bin.
Detailed description of the invention
Fig. 1 is production line schematic diagram of the present invention;
Fig. 2 is production line E of the present invention to schematic diagram;
Fig. 3 is production line G of the present invention to schematic diagram;
Fig. 4 is production line F of the present invention to schematic diagram;
In figure:1 is tailing production line, and 2 be stone production line, and 3 be integrated production line, and 11 be raw material cabin, and 12 be raw material batcher, 13 be jaw crusher, and 14 be material transfer belt, and 15 be dregs storehouse, and 16 be dregs feed belt, and 17 be raw material intermediate bin, 18 For impact crusher, 19 is sieve except soil, and 21 be building stones storehouse, and 22 be building stones batcher, and 23 be building stones feed belt, and 24 is in building stones Between storehouse, 25 be multi-cylinder cone crusher, and 31 be circular shale shaker, and 32 be material intermediate bin, and 33 be impact crusher, and 34 be sorting Sieve, 35 is mix wet machine, and 36 be material storage storage, and 37 be iron remover.
Specific embodiment
It should be noted that structure, ratio, size etc. that Figure of description is drawn, only to cooperate specification to be taken off The content shown is not intended to limit the invention enforceable range, therefore does not have so that those skilled in the art understands and reads Technical essential meaning, the modification of any structure, the change of proportionate relationship or the adjustment of size are not influencing institute's energy of the present invention Under the effect of generation and the purpose that can reach, the range that disclosed technology contents can be covered should all be still fallen in It is interior.
It is described further combined with specific embodiments below.
As shown in figures 1-4, solid waste tailing and tailings construction rubbish comprehensively utilize production line, the comprehensive utilization production line Including:Tailing production line 1, stone production line 2 and integrated production line 3;The discharge port of the tailing production line 1, stone production line 2 It is docked respectively with integrated production line 3 by feed belt.
The tailing production line 1 includes:Raw material cabin 11, raw material batcher 12, jaw crusher 13, material transfer belt 14, dregs storehouse 15, dregs feed belt 16, raw material intermediate bin 17 and impact crusher 18;At 11 outlet at bottom of raw material cabin Raw material batcher 12 is installed, 12 discharge port of raw material batcher is docked with 13 feed inlet of jaw crusher, and the jaw is broken Material transfer belt 14 is installed, the intermediate side of the material transfer belt 14 is also equipped with dregs storehouse 15 under broken 13 discharge port of machine With dregs feed belt 16, the dregs feed belt 16 is docked with material transfer belt 14, material transfer belt 14 it is another End is set to 17 top of raw material intermediate bin, and the raw material intermediate bin 17 is set on ground, sets below the raw material intermediate bin 17 It is equipped with impact crusher 18.
The stone production line 2 includes:Building stones storehouse 21, building stones batcher 22, building stones feed belt 23, building stones intermediate bin 24 With multi-cylinder cone crusher 25;The outlet of building stones storehouse 21 is equipped with building stones batcher 22, the building stones batcher 22 and building stones Building stones feed belt 23 is provided between intermediate bin 24, the outlet of building stones intermediate bin 24 lower section is provided with multi-cylinder cone crusher 25。
The integrated production line 3 includes:Circular shale shaker 31, material intermediate bin 32, impact crusher 33, separating sieve 34, Mix wet machine 35 and material storage storage 36;Between the circular shale shaker 31 and above-mentioned impact crusher 18 and multi-cylinder cone crusher 25 It is connected by feed belt, sets gradually material intermediate bin 32, impact crusher 33, separating sieve after the circular shale shaker 31 34 and wet machine 35 is mixed, passes through transmission between the circular shale shaker 31, material intermediate bin 32, impact crusher 33 and separating sieve 34 Belt connection, described to mix wet machine 35 and be set to the lower section of separating sieve 34, the material storage storage 36 includes several warehouses, the material The warehouse of storage warehouse 36 is connect by several feed belts with separating sieve 34.
The raw material intermediate bin 17 and 24 lower end of building stones intermediate bin are provided with oscillating feeder.
The raw material batcher 12 uses grizzly feeder TSW1345.
The feed belt for being connected to dregs storehouse 15 is provided with below the raw material batcher 12, and dregs storehouse 15 is given with raw material It is provided between material machine 12 except soil sieve 19.
Iron remover 37 is also equipped between the material intermediate bin 32 and impact crusher 33.
The 34 lower section discharge port of separating sieve is additionally provided with the feed belt of connection 33 feed inlet of impact crusher.
Deduster is mounted at the dregs storehouse 15, building stones storehouse 21 and separating sieve 34.
The tailing production line 1 mainly handles bulk building waste and other industrial tailings, by taking building waste as an example:Lorry After building waste is transported to raw material cabin 11, by grizzly feeder uniformly by bulk building waste feeding to jaw crusher 13, warp Raw material bulk particle is formed after processing, while after fritter building waste falls off from grizzly feeder, having feed belt to be transported to slag Native Cang15Chu mixes again with raw material bulk particle with ingredient dregs after except soil processing, is then transported to raw material intermediate bin 17, raw material fritter particle is formed after being further processed using impact crusher 18, it then will after the screening of circular shale shaker 31 The biggish raw material fritter particulate transportation of particle to raw material intermediate bin 17 is handled again, qualified raw material fritter particle delivery to impact Formula crusher 33 is further processed into raw material molecule, then passes through separating sieve 34, is transported to different material storage storage 36 It is interior.
Similarly, the stone production line 2 mainly handles traditional raw material, such as cobblestone, lorry transport cobblestone to stone In feed bin 21, then building stones feed belt 23 transports cobblestone to building stones intermediate bin 24, by 25 powder of multi-cylinder cone crusher The step of forming granule stone after broken, granule stone be then transported to circular shale shaker 31 and is handled, next handling granule stone It is consistent with the method for above-mentioned processing building waste with method.
The material that different material is handled according to customer requirement, produces variable grain size may be implemented in this way, With multiple combinations mode, production requirement can satisfy, while reducing cost of investment, product competitiveness is greatly improved.
It should be noted that:It is additionally provided with and removes between material intermediate bin 32 and impact crusher 33 in integrated production line 3 Ironware, can effectively remove the iron in abrasive grit in raw material, especially building waste, the injury of abrasive grit impingement crusher 33 compared with Greatly, removal abrasive grit can effectively improve 33 service life of impact crusher.

Claims (10)

1. solid waste tailing and tailings construction rubbish comprehensively utilize production line, it is characterised in that:The comprehensive utilization production line includes: Tailing production line(1), stone production line(2)And integrated production line(3);The tailing production line(1), stone production line(2)'s Discharge port respectively with integrated production line(3)It is docked by feed belt.
2. solid waste tailing and tailings construction rubbish comprehensively utilize production line according to claim 1, it is characterised in that:The tail Mine production line(1)Including:Raw material cabin(11), raw material batcher(12), jaw crusher(13), material transfer belt(14), slag Tu Cang(15), dregs feed belt(16), raw material intermediate bin(17)And impact crusher(18);The raw material cabin(11)Bottom goes out Raw material batcher is installed at mouthful(12), the raw material batcher(12)Discharge port and jaw crusher(13)Feed inlet docking, The jaw crusher(13)Material transfer belt is installed under discharge port(14), the material transfer belt(14)Intermediate side It is also equipped with dregs storehouse(15)With dregs feed belt(16), the dregs feed belt(16)With material transfer belt(14)It is right It connects, material transfer belt(14)The other end be set to raw material intermediate bin(17)Top, the raw material intermediate bin(17)It is set to On ground, the raw material intermediate bin(17)Lower section is provided with impact crusher(18).
3. solid waste tailing and tailings construction rubbish comprehensively utilize production line according to claim 1, it is characterised in that:The stone Expect production line(2)Including:Building stones storehouse(21), building stones batcher(22), building stones feed belt(23), building stones intermediate bin(24)With it is more Cylinder gyratory crusher(25);The building stones storehouse(21)Outlet is equipped with building stones batcher(22), the building stones batcher(22)With Building stones intermediate bin(24)Between be provided with building stones feed belt(23), the building stones intermediate bin(24)Outlet lower section is provided with multi-cylinder Gyratory crusher(25).
4. according to claim 1, solid waste tailing described in 2 or 3 any claims and tailings construction rubbish comprehensively utilize production line, It is characterized in that:The integrated production line(3)Including:Circular shale shaker(31), material intermediate bin(32), impact crusher (33), separating sieve(34), mix wet machine(35)With material storage storage(36);The circular shale shaker(31)With above-mentioned impact crusher (18)And multi-cylinder cone crusher(25)Between pass through feed belt connect, the circular shale shaker(31)Material is set gradually later Intermediate bin(32), impact crusher(33), separating sieve(34)With mix wet machine(35), the circular shale shaker(31), among material Storehouse(32), impact crusher(33)And separating sieve(34)Between by feed belt connect, it is described to mix wet machine(35)It is set to Separating sieve(34)Lower section, the material storage storage(36)Including several warehouses, the material storage storage(36)If warehouse by Dry feed belt and separating sieve(34)Connection.
5. solid waste tailing according to claim 1 or claim 2 and tailings construction rubbish comprehensively utilize production line, it is characterised in that:Institute State raw material intermediate bin(17)With building stones intermediate bin(24)Lower end is provided with oscillating feeder.
6. solid waste tailing according to claim 1 or claim 2 and tailings construction rubbish comprehensively utilize production line, it is characterised in that:Institute State raw material batcher(12)Using grizzly feeder TSW1345.
7. solid waste tailing according to claim 1 or claim 2 and tailings construction rubbish comprehensively utilize production line, it is characterised in that:Institute State raw material batcher(12)Lower section, which is provided with, is connected to dregs storehouse(15)Feed belt, and dregs storehouse(15)With raw material batcher (12)Between be provided with except soil sieve(19).
8. according to claim 1, solid waste tailing described in 2 or 3 any claims and tailings construction rubbish comprehensively utilize production line, It is characterized in that:The material intermediate bin(32)With impact crusher(33)Between be also equipped with iron remover(37).
9. according to claim 1, solid waste tailing described in 2 or 3 any claims and tailings construction rubbish comprehensively utilize production line, It is characterized in that:The separating sieve(34)Lower section discharge port is additionally provided with connection impact crusher(33)The transmission skin of feed inlet Band.
10. according to claim 1, solid waste tailing described in 2 or 3 any claims and the comprehensive utilization production of tailings construction rubbish Line, it is characterised in that:The dregs storehouse(15), building stones storehouse(21)And separating sieve(34)Place is mounted on deduster.
CN201810975927.5A 2018-08-24 2018-08-24 Solid waste tailing and tailings construction rubbish comprehensively utilize production line Pending CN108889772A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810975927.5A CN108889772A (en) 2018-08-24 2018-08-24 Solid waste tailing and tailings construction rubbish comprehensively utilize production line

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810975927.5A CN108889772A (en) 2018-08-24 2018-08-24 Solid waste tailing and tailings construction rubbish comprehensively utilize production line

Publications (1)

Publication Number Publication Date
CN108889772A true CN108889772A (en) 2018-11-27

Family

ID=64358870

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810975927.5A Pending CN108889772A (en) 2018-08-24 2018-08-24 Solid waste tailing and tailings construction rubbish comprehensively utilize production line

Country Status (1)

Country Link
CN (1) CN108889772A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112090941A (en) * 2020-09-25 2020-12-18 瑞图明盛环保建材(昌江)有限公司 General type tailing comprehensive treatment production line and system

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3052126U (en) * 1998-03-10 1998-09-14 人善企業株式会社 Construction waste treatment equipment
CN101229660A (en) * 2008-02-11 2008-07-30 苏峰 Method of preparing regenerative concrete products
CN201596527U (en) * 2010-02-05 2010-10-06 宝钢集团新疆八一钢铁有限公司 Mineral ore crushing and dressing device
CN202055143U (en) * 2011-01-31 2011-11-30 上海寰保渣业处置有限公司 Production device of road base material produced by brick-concrete type building rubbish
CN107445543A (en) * 2017-08-03 2017-12-08 河北建筑工程学院 A kind of iron tailings regeneration concrete and preparation method thereof
CN108176697A (en) * 2017-12-27 2018-06-19 广东昕旺环保科技发展有限公司 Build composting sorting total system and processing method
CN209393717U (en) * 2018-08-24 2019-09-17 临汾市华基建材科技有限公司 A kind of solid waste tailing and tailings construction rubbish comprehensively utilize production line

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3052126U (en) * 1998-03-10 1998-09-14 人善企業株式会社 Construction waste treatment equipment
CN101229660A (en) * 2008-02-11 2008-07-30 苏峰 Method of preparing regenerative concrete products
CN201596527U (en) * 2010-02-05 2010-10-06 宝钢集团新疆八一钢铁有限公司 Mineral ore crushing and dressing device
CN202055143U (en) * 2011-01-31 2011-11-30 上海寰保渣业处置有限公司 Production device of road base material produced by brick-concrete type building rubbish
CN107445543A (en) * 2017-08-03 2017-12-08 河北建筑工程学院 A kind of iron tailings regeneration concrete and preparation method thereof
CN108176697A (en) * 2017-12-27 2018-06-19 广东昕旺环保科技发展有限公司 Build composting sorting total system and processing method
CN209393717U (en) * 2018-08-24 2019-09-17 临汾市华基建材科技有限公司 A kind of solid waste tailing and tailings construction rubbish comprehensively utilize production line

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112090941A (en) * 2020-09-25 2020-12-18 瑞图明盛环保建材(昌江)有限公司 General type tailing comprehensive treatment production line and system
CN112090941B (en) * 2020-09-25 2023-11-03 瑞图明盛环保建材(昌江)有限公司 General tailing comprehensive treatment production line and system

Similar Documents

Publication Publication Date Title
CN101549351B (en) Building refuse treatment regeneration system
CN201511034U (en) Construction waste treatment regeneration system
CN102838307A (en) Method and system for treating construction waste
CN206535848U (en) Building waste processing system
CN113019648B (en) High-efficient preparation system of abandonment concrete regeneration sand powder
CN109675906A (en) A kind of wholly-owned source recycling and reusing system of building castoff
CN109734335A (en) A method of high-quality steel-making slag powder is produced based on steel slag modifying agent
CN209576975U (en) A kind of high-quality sandstone aggregate impacts dry milling production line entirely
CN206526918U (en) Building rubbish treatment device
CN207643427U (en) Spoil slag dry powder and mortar production system
CN207238203U (en) A kind of Machine-made Sand production system
CN106824986A (en) A kind of pollution-free treatment of electronic waste and the method for recycling
CN216125816U (en) Waste ceramic tile system sand powder process all-in-one
CN209393717U (en) A kind of solid waste tailing and tailings construction rubbish comprehensively utilize production line
CN215047092U (en) Dry-mixed mortar production system
CN106116195A (en) A kind of vertical mill grinding slag, lithium slag add modifying agent composite powder production method
CN203991634U (en) A kind of high resource utilization system containing civil engineering building refuse
CN106116196A (en) A kind of vertical mill grinding slag, lithium slag composite powder production method
CN209393314U (en) A kind of solid waste tailing and building waste comprehensively utilize workshop
CN109985715A (en) A kind of lime stone system of processing
CN203173995U (en) Device for building waste residue associated grinding resource processing system
CN108889772A (en) Solid waste tailing and tailings construction rubbish comprehensively utilize production line
CN209968608U (en) Limestone processing system
CN109013015A (en) Solid waste tailing and building waste comprehensively utilize workshop
CN219334474U (en) Optimize construction waste and rubble system sand production line

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20181127