CN209393717U - A kind of solid waste tailing and tailings construction rubbish comprehensively utilize production line - Google Patents

A kind of solid waste tailing and tailings construction rubbish comprehensively utilize production line Download PDF

Info

Publication number
CN209393717U
CN209393717U CN201821375473.XU CN201821375473U CN209393717U CN 209393717 U CN209393717 U CN 209393717U CN 201821375473 U CN201821375473 U CN 201821375473U CN 209393717 U CN209393717 U CN 209393717U
Authority
CN
China
Prior art keywords
production line
raw material
tailing
solid waste
building stones
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201821375473.XU
Other languages
Chinese (zh)
Inventor
郭幸福
张真弟
赵建强
裴林昊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Linfen City China Building Materials Science And Technology Ltd Co
Original Assignee
Linfen City China Building Materials Science And Technology Ltd Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Linfen City China Building Materials Science And Technology Ltd Co filed Critical Linfen City China Building Materials Science And Technology Ltd Co
Priority to CN201821375473.XU priority Critical patent/CN209393717U/en
Application granted granted Critical
Publication of CN209393717U publication Critical patent/CN209393717U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02WCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO WASTEWATER TREATMENT OR WASTE MANAGEMENT
    • Y02W30/00Technologies for solid waste management
    • Y02W30/50Reuse, recycling or recovery technologies
    • Y02W30/58Construction or demolition [C&D] waste

Landscapes

  • Processing Of Solid Wastes (AREA)

Abstract

A kind of solid waste tailing of the utility model and tailings construction rubbish comprehensively utilize production line, belong to construction machinery equipment field, and in particular to a kind of aggregate production line;The utility model proposes a kind of solid waste tailings and tailings construction rubbish to comprehensively utilize production line, which can produce and process building waste and industrial tailings, while also be capable of handling traditional raw material, such as the working process of cobblestone;There is provided technical solution are as follows: a kind of solid waste tailing and tailings construction rubbish comprehensively utilize production line, and the comprehensive utilization production line includes: tailing production line, stone production line and integrated production line;The tailing production line, stone production line discharge port docked respectively with integrated production line by feed belt;The material for handling different material according to customer requirement, producing variable grain size may be implemented in the utility model, has multiple combinations mode, can satisfy production requirement, while reducing cost of investment, product competitiveness is greatly improved.

Description

A kind of solid waste tailing and tailings construction rubbish comprehensively utilize production line
Technical field
A kind of solid waste tailing of the utility model and tailings construction rubbish comprehensively utilize production line, belong to construction machinery equipment neck A kind of domain, and in particular to aggregate production line.
Background technique
Construction industry is grown rapidly in recent two decades as one of mainstay of the national economy industry, with urban construction Flourishing progress, remove become each city theme.Removal can generate a large amount of building waste.
These rubbish are mainly common brick, armored concrete and its mixture.Currently, the quantity of China's building waste has accounted for The 30%~40% of municipal refuse total amount.Oneself is more than 400,000,000 tons to building waste annual emissions, wherein the big cities such as Beijing, Shanghai year row High-volume at 30,000,000 tons or more.The unprocessed countryside or rural area just directly transported to of these building wastes overwhelming majority is using dew It is stacked or the mode of landfill is handled, and stacking and filling then needs to consume the construction investments such as a large amount of expropriation of land, refuse collection, Meanwhile it clearing and having aggravated environmental pollution again with fugitive dust with dropping in stacking process.Modern metropolitan cities towards industrialization, urbanization The today accelerated development, the rubbish that a large amount of engineering constructions generate just are threaten the natural environment of human survival.Developed country is more early With regard to having carried out a series of fruitful researchs and practice for this problem, it was demonstrated that the recycling for realizing building waste is to solve conscientiously The certainly good recipe of this social concern.But so far, the related work of China's construction refuse resource relatively lags behind, and thus gives society Meeting, environment and resource bring various detrimental effects.
It is main trend in recent years using building waste and industrial tailings production aggregate etc. other industrial products, but It is the production and processing that General Production Lines cannot be considered in terms of traditional raw material (cobblestone etc.) and building waste and industrial tailings, is arranged two Production line significantly improves cost of investment, reduces production efficiency.
Utility model content
To overcome above-mentioned technical problem, the utility model proposes a kind of solid waste tailing and tailings construction rubbish are comprehensive Using production line, which can produce and process building waste and industrial tailings, while also be capable of handling traditional raw material, example Such as the working process of cobblestone.
In order to solve the above technical problems, the utility model provides technical solution are as follows: a kind of solid waste tailing and tailings construction rubbish Rubbish comprehensively utilizes production line, and the comprehensive utilization production line includes: tailing production line, stone production line and integrated production line;Institute State tailing production line, the discharge port of stone production line is docked with integrated production line by feed belt respectively.
The tailing production line include: raw material cabin, raw material batcher, jaw crusher, material transfer belt, dregs storehouse, Dregs feed belt, raw material intermediate bin and impact crusher;Raw material batcher is installed at the raw material cabin outlet at bottom, it is described Raw material batcher discharge port is docked with jaw crushing machine inlet, is equipped with material transmission skin under the jaw crusher discharge port Band, material transfer belt centre side are also equipped with dregs storehouse and dregs feed belt, the dregs feed belt and object Expect feed belt docking, the other end of material transfer belt is set to above raw material intermediate bin, and the raw material intermediate bin is set to On ground, impact crusher is provided with below the raw material intermediate bin.
The stone production line includes: building stones storehouse, building stones batcher, building stones feed belt, building stones intermediate bin and multi-cylinder circle Conic crusher;The stone bin outlet is equipped with building stones batcher, is provided between the building stones batcher and building stones intermediate bin Building stones feed belt, building stones intermediate bin outlet lower section are provided with multi-cylinder cone crusher.
The integrated production line includes: circular shale shaker, material intermediate bin, impact crusher, separating sieve, mixes wet machine and object Expect storage warehouse;It is connected between the circular shale shaker and above-mentioned impact crusher and multi-cylinder cone crusher by feed belt, institute It states circular shale shaker to set gradually material intermediate bin, impact crusher, separating sieve later and mix wet machine, the circular shale shaker, object Expect to connect between intermediate bin, impact crusher and separating sieve by feed belt, it is described to mix wet machine and be set to separating sieve lower section, The material storage storage includes several warehouses, and the warehouse of the material storage storage is connect by several feed belts with separating sieve.
The raw material intermediate bin and building stones intermediate bin lower end are provided with oscillating feeder.
The raw material batcher uses grizzly feeder TSW1345.
Be provided with the feed belt for being connected to dregs storehouse below the raw material batcher, and dregs storehouse and raw material batcher it Between be provided with except soil sieve.
Iron remover is also equipped between the material intermediate bin and impact crusher.
Discharge port is additionally provided with the feed belt of connection impact crusher feed inlet below the separating sieve.
Deduster is mounted at the dregs storehouse, building stones storehouse and separating sieve.
The jaw crusher uses PEW860.
The impact crusher uses PFW1318 III.
The multi-cylinder cone crusher uses HPT300.
The oscillating feeder uses ZG400 type.
The circular shale shaker uses 3Y2460 formula vibrating screen.
The deduster in the dregs storehouse and building stones storehouse uses the box deduster of PPCS.
The separating sieve uses VUT120 dust pelletizing system.
The utility model has the beneficial effect that compared with prior art
One, the utility model improves in such a way that tailing production line, stone production line are matched with integrated production line The utilization efficiency of production line, reduces cost of investment, improves economic benefit.
Two, the utility model raw material batcher uses grizzly feeder, is convenient for bulk materials uniform feeding, is conducive to jaw Crusher continually and steadily works.
Three, the utility model is in such a way that jaw crusher is matched with impact breaker, convenient for building to bulk Rubbish is directly handled, and effectively improves working efficiency.
Four, the utility model uses jaw crusher, impact breaker, multi-cylinder cone crusher and impact crusher Mutually matched mode, convenient for producing various hardness, quality and the material of granular size according to demand.
Five, the utility model uses separating sieve and feed belt, different material can be stored to corresponding storage bin.
Detailed description of the invention
Fig. 1 is the utility model production line schematic diagram;
Fig. 2 is the utility model production line E to schematic diagram;
Fig. 3 is the utility model production line G to schematic diagram;
Fig. 4 is the utility model production line F to schematic diagram;
In figure: 1 is tailing production line, and 2 be stone production line, and 3 be integrated production line, and 11 be raw material cabin, and 12 give for raw material Material machine, 13 be jaw crusher, and 14 be material transfer belt, and 15 be dregs storehouse, and 16 be dregs feed belt, and 17 is among raw materials Storehouse, 18 be impact crusher, and 19 is sieve except soil, and 21 be building stones storehouse, and 22 be building stones batcher, and 23 be building stones feed belt, and 24 are Building stones intermediate bin, 25 be multi-cylinder cone crusher, and 31 be circular shale shaker, and 32 be material intermediate bin, and 33 be impact crusher, and 34 are Separating sieve, 35 is mix wet machine, and 36 be material storage storage, and 37 be iron remover.
Specific embodiment
It should be noted that structure, ratio, size etc. that Figure of description is drawn, only to cooperate specification to be taken off The content shown is not intended to limit the utility model enforceable range so that those skilled in the art understands and reads, therefore Do not have technical essential meaning, the modification of any structure, the change of proportionate relationship or the adjustment of size, this is practical not influencing Under novel the effect of can be generated and the purpose that can reach, the revealed technology contents institute energy of the utility model should all be still fallen in In the range of covering.
It is described further combined with specific embodiments below.
As shown in figures 1-4, a kind of solid waste tailing and tailings construction rubbish comprehensively utilize production line, the comprehensive utilization life Producing line includes: tailing production line 1, stone production line 2 and integrated production line 3;The tailing production line 1, stone production line 2 go out Material mouth is docked with integrated production line 3 by feed belt respectively.
The tailing production line 1 includes: raw material cabin 11, raw material batcher 12, jaw crusher 13, material transfer belt 14, dregs storehouse 15, dregs feed belt 16, raw material intermediate bin 17 and impact crusher 18;At 11 outlet at bottom of raw material cabin Raw material batcher 12 is installed, 12 discharge port of raw material batcher is docked with 13 feed inlet of jaw crusher, and the jaw is broken Material transfer belt 14 is installed, the intermediate side of the material transfer belt 14 is also equipped with dregs storehouse 15 under broken 13 discharge port of machine With dregs feed belt 16, the dregs feed belt 16 is docked with material transfer belt 14, material transfer belt 14 it is another End is set to 17 top of raw material intermediate bin, and the raw material intermediate bin 17 is set on ground, sets below the raw material intermediate bin 17 It is equipped with impact crusher 18.
The stone production line 2 includes: building stones storehouse 21, building stones batcher 22, building stones feed belt 23, building stones intermediate bin 24 With multi-cylinder cone crusher 25;The outlet of building stones storehouse 21 is equipped with building stones batcher 22, the building stones batcher 22 and building stones Building stones feed belt 23 is provided between intermediate bin 24, the outlet of building stones intermediate bin 24 lower section is provided with multi-cylinder cone crusher 25。
The integrated production line 3 include: circular shale shaker 31, material intermediate bin 32, impact crusher 33, separating sieve 34, Mix wet machine 35 and material storage storage 36;Between the circular shale shaker 31 and above-mentioned impact crusher 18 and multi-cylinder cone crusher 25 It is connected by feed belt, sets gradually material intermediate bin 32, impact crusher 33, separating sieve after the circular shale shaker 31 34 and wet machine 35 is mixed, passes through transmission between the circular shale shaker 31, material intermediate bin 32, impact crusher 33 and separating sieve 34 Belt connection, described to mix wet machine 35 and be set to the lower section of separating sieve 34, the material storage storage 36 includes several warehouses, the material The warehouse of storage warehouse 36 is connect by several feed belts with separating sieve 34.
The raw material intermediate bin 17 and 24 lower end of building stones intermediate bin are provided with oscillating feeder.
The raw material batcher 12 uses grizzly feeder TSW1345.
The feed belt for being connected to dregs storehouse 15 is provided with below the raw material batcher 12, and dregs storehouse 15 is given with raw material It is provided between material machine 12 except soil sieve 19.
Iron remover 37 is also equipped between the material intermediate bin 32 and impact crusher 33.
The 34 lower section discharge port of separating sieve is additionally provided with the feed belt of connection 33 feed inlet of impact crusher.
Deduster is mounted at the dregs storehouse 15, building stones storehouse 21 and separating sieve 34.
The tailing production line 1 mainly handles bulk building waste and other industrial tailings, by taking building waste as an example: lorry After building waste is transported to raw material cabin 11, by grizzly feeder uniformly by bulk building waste feeding to jaw crusher 13, warp Raw material bulk particle is formed after processing, while after fritter building waste falls off from grizzly feeder, having feed belt to be transported to slag Native Cang15Chu mixes again with raw material bulk particle with ingredient dregs after except soil processing, is then transported to raw material intermediate bin 17, raw material fritter particle is formed after being further processed using impact crusher 18, it then will after the screening of circular shale shaker 31 The biggish raw material fritter particulate transportation of particle to raw material intermediate bin 17 is handled again, qualified raw material fritter particle delivery to impact Formula crusher 33 is further processed into raw material molecule, then passes through separating sieve 34, is transported to different material storage storage 36 It is interior.
Similarly, the stone production line 2 mainly handles traditional raw material, such as cobblestone, lorry transport cobblestone to stone In feed bin 21, then building stones feed belt 23 transports cobblestone to building stones intermediate bin 24, by 25 powder of multi-cylinder cone crusher The step of forming granule stone after broken, granule stone be then transported to circular shale shaker 31 and is handled, next handling granule stone It is consistent with the method for above-mentioned processing building waste with method.
The material that different material is handled according to customer requirement, produces variable grain size may be implemented in this way, With multiple combinations mode, production requirement can satisfy, while reducing cost of investment, product competitiveness is greatly improved.
It is removed it should be understood that being additionally provided between material intermediate bin 32 and impact crusher 33 in integrated production line 3 Ironware, can effectively remove the iron in abrasive grit in raw material, especially building waste, the injury of abrasive grit impingement crusher 33 compared with Greatly, removal abrasive grit can effectively improve 33 service life of impact crusher.

Claims (10)

1. a kind of solid waste tailing and tailings construction rubbish comprehensively utilize production line, it is characterised in that: the comprehensive utilization production line It include: tailing production line (1), stone production line (2) and integrated production line (3);The tailing production line (1), stone production line (2) discharge port is docked with integrated production line (3) by feed belt respectively.
2. a kind of solid waste tailing and tailings construction rubbish comprehensively utilize production line according to claim 1, it is characterised in that: institute Stating tailing production line (1) includes: raw material cabin (11), raw material batcher (12), jaw crusher (13), material transfer belt (14), dregs storehouse (15), dregs feed belt (16), raw material intermediate bin (17) and impact crusher (18);The raw material cabin (11) be equipped at outlet at bottom raw material batcher (12), raw material batcher (12) discharge port and jaw crusher (13) into Material mouth is docked, and is equipped with material transfer belt (14), the material transfer belt under jaw crusher (13) discharge port (14) intermediate side is also equipped with dregs storehouse (15) and dregs feed belt (16), and the dregs feed belt (16) and material pass Belt (14) are sent to dock, the other end of material transfer belt (14) is set to above raw material intermediate bin (17), among the raw material Storehouse (17) is set on ground, is provided with impact crusher (18) below the raw material intermediate bin (17).
3. a kind of solid waste tailing and tailings construction rubbish comprehensively utilize production line according to claim 2, it is characterised in that: institute Stating stone production line (2) includes: building stones storehouse (21), building stones batcher (22), building stones feed belt (23), building stones intermediate bin (24) With multi-cylinder cone crusher (25);Building stones storehouse (21) outlet is equipped with building stones batcher (22), the building stones batcher (22) it is provided between building stones intermediate bin (24) building stones feed belt (23), building stones intermediate bin (24) outlet lower section setting There are multi-cylinder cone crusher (25).
4. a kind of solid waste tailing and tailings construction rubbish comprehensively utilize production line according to claim 3, it is characterised in that: institute State integrated production line (3) include: circular shale shaker (31), material intermediate bin (32), impact crusher (33), separating sieve (34), Mix wet machine (35) and material storage storage (36);The circular shale shaker (31) and above-mentioned impact crusher (18) and multi-cylinder cone crusher It is connected between machine (25) by feed belt, material intermediate bin (32), impact type is set gradually after the circular shale shaker (31) It crusher (33), separating sieve (34) and mixes wet machine (35), the circular shale shaker (31), material intermediate bin (32), impact type are broken It is connected between machine (33) and separating sieve (34) by feed belt, the wet machine (35) of mixing is set to below separating sieve (34), institute Stating material storage storage (36) includes several warehouses, and the warehouse of the material storage storage (36) passes through several feed belts and separating sieve (34) it connects.
5. a kind of solid waste tailing and tailings construction rubbish comprehensively utilize production line according to claim 3, it is characterised in that: institute It states raw material intermediate bin (17) and building stones intermediate bin (24) lower end is provided with oscillating feeder.
6. a kind of solid waste tailing and tailings construction rubbish according to Claims 2 or 3 comprehensively utilize production line, feature exists In: the raw material batcher (12) uses grizzly feeder TSW1345.
7. a kind of solid waste tailing and tailings construction rubbish according to Claims 2 or 3 comprehensively utilize production line, feature exists In: the feed belt for being connected to dregs storehouse (15), and dregs storehouse (15) and raw material are provided with below the raw material batcher (12) It is provided between batcher (12) except soil sieve (19).
8. a kind of solid waste tailing and tailings construction rubbish comprehensively utilize production line according to claim 4, it is characterised in that: institute It states and is also equipped with iron remover (37) between material intermediate bin (32) and impact crusher (33).
9. a kind of solid waste tailing and tailings construction rubbish comprehensively utilize production line according to claim 4, it is characterised in that: institute State the feed belt that discharge port below separating sieve (34) is additionally provided with connection impact crusher (33) feed inlet.
10. a kind of solid waste tailing and tailings construction rubbish comprehensively utilize production line according to claim 4, it is characterised in that: Deduster is mounted at the dregs storehouse (15), building stones storehouse (21) and separating sieve (34).
CN201821375473.XU 2018-08-24 2018-08-24 A kind of solid waste tailing and tailings construction rubbish comprehensively utilize production line Active CN209393717U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821375473.XU CN209393717U (en) 2018-08-24 2018-08-24 A kind of solid waste tailing and tailings construction rubbish comprehensively utilize production line

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821375473.XU CN209393717U (en) 2018-08-24 2018-08-24 A kind of solid waste tailing and tailings construction rubbish comprehensively utilize production line

Publications (1)

Publication Number Publication Date
CN209393717U true CN209393717U (en) 2019-09-17

Family

ID=67877852

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821375473.XU Active CN209393717U (en) 2018-08-24 2018-08-24 A kind of solid waste tailing and tailings construction rubbish comprehensively utilize production line

Country Status (1)

Country Link
CN (1) CN209393717U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108889772A (en) * 2018-08-24 2018-11-27 临汾市华基建材科技有限公司 Solid waste tailing and tailings construction rubbish comprehensively utilize production line

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108889772A (en) * 2018-08-24 2018-11-27 临汾市华基建材科技有限公司 Solid waste tailing and tailings construction rubbish comprehensively utilize production line

Similar Documents

Publication Publication Date Title
CN101549351B (en) Building refuse treatment regeneration system
CN201511034U (en) Construction waste treatment regeneration system
CN102838307A (en) Method and system for treating construction waste
CN206535848U (en) Building waste processing system
CN104291714A (en) Production method for grinding steel-iron slag powder, mineral slag powder and steel slag powder by using vertical mill
CN113019648B (en) High-efficient preparation system of abandonment concrete regeneration sand powder
CN203816740U (en) Modularized sand making equipment
CN109734335A (en) A method of high-quality steel-making slag powder is produced based on steel slag modifying agent
CN109675906A (en) A kind of wholly-owned source recycling and reusing system of building castoff
CN106182409A (en) A kind of joint use type dry-mixed mortar production line
CN207643427U (en) Spoil slag dry powder and mortar production system
CN106824986A (en) A kind of pollution-free treatment of electronic waste and the method for recycling
CN104446071A (en) Dry sand making process
CN216125816U (en) Waste ceramic tile system sand powder process all-in-one
CN209576975U (en) A kind of high-quality sandstone aggregate impacts dry milling production line entirely
CN209393717U (en) A kind of solid waste tailing and tailings construction rubbish comprehensively utilize production line
CN215047092U (en) Dry-mixed mortar production system
CN103816978A (en) Modular sand-making equipment and sand-making method
CN209393314U (en) A kind of solid waste tailing and building waste comprehensively utilize workshop
CN206526918U (en) Building rubbish treatment device
CN106116196A (en) A kind of vertical mill grinding slag, lithium slag composite powder production method
CN203991634U (en) A kind of high resource utilization system containing civil engineering building refuse
CN203173995U (en) Device for building waste residue associated grinding resource processing system
CN206066689U (en) A kind of joint use type dry-mixed mortar production line
CN209968608U (en) Limestone processing system

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant