CN108871893A - A kind of method that scene Soil Direct Shear test prepares the soil body with soil body preparation device - Google Patents

A kind of method that scene Soil Direct Shear test prepares the soil body with soil body preparation device Download PDF

Info

Publication number
CN108871893A
CN108871893A CN201810651257.1A CN201810651257A CN108871893A CN 108871893 A CN108871893 A CN 108871893A CN 201810651257 A CN201810651257 A CN 201810651257A CN 108871893 A CN108871893 A CN 108871893A
Authority
CN
China
Prior art keywords
soil body
box
jack
cut
soil
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810651257.1A
Other languages
Chinese (zh)
Other versions
CN108871893B (en
Inventor
邓华锋
胡亚运
肖志勇
李建林
孙旭曙
周美玲
胡安龙
李春波
常德龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Three Gorges University CTGU
Original Assignee
China Three Gorges University CTGU
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Three Gorges University CTGU filed Critical China Three Gorges University CTGU
Priority to CN201810651257.1A priority Critical patent/CN108871893B/en
Publication of CN108871893A publication Critical patent/CN108871893A/en
Application granted granted Critical
Publication of CN108871893B publication Critical patent/CN108871893B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01NINVESTIGATING OR ANALYSING MATERIALS BY DETERMINING THEIR CHEMICAL OR PHYSICAL PROPERTIES
    • G01N1/00Sampling; Preparing specimens for investigation
    • G01N1/28Preparing specimens for investigation including physical details of (bio-)chemical methods covered elsewhere, e.g. G01N33/50, C12Q
    • G01N1/286Preparing specimens for investigation including physical details of (bio-)chemical methods covered elsewhere, e.g. G01N33/50, C12Q involving mechanical work, e.g. chopping, disintegrating, compacting, homogenising
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01NINVESTIGATING OR ANALYSING MATERIALS BY DETERMINING THEIR CHEMICAL OR PHYSICAL PROPERTIES
    • G01N3/00Investigating strength properties of solid materials by application of mechanical stress
    • G01N3/24Investigating strength properties of solid materials by application of mechanical stress by applying steady shearing forces
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01NINVESTIGATING OR ANALYSING MATERIALS BY DETERMINING THEIR CHEMICAL OR PHYSICAL PROPERTIES
    • G01N1/00Sampling; Preparing specimens for investigation
    • G01N1/28Preparing specimens for investigation including physical details of (bio-)chemical methods covered elsewhere, e.g. G01N33/50, C12Q
    • G01N1/286Preparing specimens for investigation including physical details of (bio-)chemical methods covered elsewhere, e.g. G01N33/50, C12Q involving mechanical work, e.g. chopping, disintegrating, compacting, homogenising
    • G01N2001/2873Cutting or cleaving
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01NINVESTIGATING OR ANALYSING MATERIALS BY DETERMINING THEIR CHEMICAL OR PHYSICAL PROPERTIES
    • G01N2203/00Investigating strength properties of solid materials by application of mechanical stress
    • G01N2203/0014Type of force applied
    • G01N2203/0025Shearing

Abstract

A kind of method that scene Soil Direct Shear test prepares the soil body with soil body preparation device, including component and charging assembly are prepared, prepare component:Including bottom frame, bottom plate, telescopic component and on cut box, telescopic component is hinged on bottom frame, and bottom plate is movably arranged in bottom frame, above cut box and be located in telescopic component, charging assembly:Including the first jack, force transmission rack, the fixed frame for being fixedly connected on telescopic component top, one end of the first jack is fixedly connected on fixed frame, and other end is resisted against on the end face of force transmission rack, and force transmission rack is resisted against far from one end of the first jack and cuts on box.

Description

A kind of method that scene Soil Direct Shear test prepares the soil body with soil body preparation device
The present invention is application number " 2016102125710 ", and patent name is that " soil body is used in a kind of scene Soil Direct Shear test The divisional application of the device and method of preparation and direct shear test ".
Technical field
The present invention relates to a kind of methods that live Soil Direct Shear test prepares the soil body with soil body preparation device.
Background technique
In recent years, underground engineering and the related theoretical, design of slope project, construction have obtained in-depth study, geotechnical engineering The deformation failure overwhelming majority be due to caused by failure by shear, the accurate shear strength parameter for measuring Rock And Soil is in rock Critically important effect is played in geotechnological journey.In the test of test Rock And Soil shearing strength, direct shearing test is due to its operating method Simply, definite principle and be widely used.
Due to the limitation of field test condition and funds, Rock And Soil direct shear test is still with the test of laboratory small size It is main.It the advantage is that boundary condition is easy to control, can be obtained using a variety of methods such as direct shear test, triaxial test, torsion shear tests Obtain the Rock And Soil shear strength parameter under different conditions;Its disadvantage is mainly manifested in following two aspects:First is that in sampling, fortune During defeated, sample preparation, test, the states such as the integrality of sample, structural, moisture content are inevitably disturbed or destroy; Second is that indoor specimen size is small, the authenticity and representativeness namely dimensional effect of test result are affected to a certain extent.Cause This, the engineerings such as landslide, slope stability analysis in practice, laboratory test shear strength parameter obtained is difficult to directly answer With.And in field direct shear test, specimen size is big and carries out at the scene, the heterogeneity and weak structural face of the soil body can be fought The influence for cutting intensity more realistically reflects, and more tallies with the actual situation than the test of the indoor soil body.Therefore, in many cases, have Necessity carries out live Soil Direct Shear test, to obtain the actual mechanics parameter of the soil body, and then instructs the design and construction of engineering.
Apparent difficult there are two but during large-scale Soil Direct Shear is tested at the scene at present, one is the examination of soil body standard Sample prepares problem, and common scene Soil Direct Shear test sample size is generally:Length × width × height=500mm × 500mm × 300mm.It is general first to excavate preparation one compared with the bulk specimen soil body in the test site of selection when field test(Length is big In 500mm), then use cuts the tools such as native knife and prepares sample by hand, but prepares geometric dimension, the angle of sample by hand Degree, flatness are often nonstandard, are extremely difficult to the requirement of test specification, and then directly result in the discreteness of test result, influence The order of accuarcy of test result;On the other hand, it is the Normal stress application problem of direct shear test, generallys use earth anchor, preloading etc. Method, still, the embedded workload applied with preloading of earth anchor are very big, time cost and high labor cost, therefore, there is an urgent need to A kind of more easily Normal stress applying method.
Summary of the invention
The object of the invention is that overcoming disadvantages mentioned above and shortcoming of the existing technology, a kind of scene soil is provided The method that body direct shear test prepares the soil body with soil body preparation device can very easily be prepared direct shear test with the soil body, After preparing at the scene to the soil body, soil body preparation device can be directly adapted as to experimental rig, and do corresponding staight scissors examination It tests, structure is simple, and in-site installation convenient disassembly is readily transported, the produced on-site and teaching test suitable for the soil body.
To solve the above-mentioned problems, the technical scheme is that:A kind of scene Soil Direct Shear test soil body preparation dress It sets, it is characterised in that:Including preparing component and charging assembly,
Prepare component:Including bottom frame, bottom plate, telescopic component and on cut box, telescopic component is hinged on bottom frame, bottom plate activity installation In bottom frame, above cuts box and be located in telescopic component;
Charging assembly:Including the first jack, force transmission rack, the fixed frame for being fixedly connected on telescopic component top, the first jack One end be fixedly connected on fixed frame, other end is resisted against on the end face of force transmission rack, and force transmission rack is far from the first jack One end, which is resisted against, cuts on box.
Further, force transmission rack is " n " shape, is installed with a card slot respectively in two ends of force transmission rack.
Further, cutting box on described is the rectangular tube surrounded by four blocks of steel plates, is mounted with a plurality of cut in upper box lower end of cutting Knife is installed with a wing plate at the upper edge for cutting box lower end two sides respectively, and the lower end for above cutting box is resisted against the upper surface of cutter On, the outer wall for above cutting box is located in card slot.
Further, the bottom frame includes two strips, and two strips are located at the two sides of the soil body, the one of strip Side is equipped with slideway, and multiple hinges are equipped on the end face of strip, and bottom plate is located in slideway, can slide in slideway, in strip End face is equipped with multiple holdfast holes.
Further, the telescopic component includes more telescopic rods, and one end of telescopic rod is hinged in branch hinge, other end It being socketed on fixed frame, the telescopic rod includes casing and screw rod, and tapped through hole is equipped in casing, and screw rod has two, point It is not screwed onto the both ends of casing, is installed in the end of screw rod for the steel pipe hinged with branch, is equipped with one at the middle part of casing Locking hole is socketed with extension bar in locking hole.
A kind of method that scene Soil Direct Shear test prepares sample with soil body preparation device, includes the following steps:
The first step excavates out a biggish foundation pit in the test site of selection, the initial soil body is reserved in the middle part of foundation pit, initially The soil body all around all reserves certain space;
Two strips are respectively placed at the two sides of the initial soil body, and require the strip of initial soil body two sides mutual by second step In parallel, strip is fixed on the bottom of foundation pit using holdfast towards the initial soil body by the one end of strip with slideway;
Each telescopic rod is hinged in the hinge of the branch on strip by third step;
Each telescopic rod is erected by the 4th step, in the upper end that fixed frame is fixedly mounted on to each telescopic rod;
In 5th step, the fixed frame for being fixedly connected with one end of the first jack, box is cut by and is placed on the upper surface of the soil body;
6th step is cut box by and is lifted, and each piece of cutter is caught in the supreme lower end for cutting box, force transmission rack is being cut to box card by Firmly;
7th step, the first jack withstand force transmission rack far from one end of fixed frame, and the height of each telescopic rod is adjusted using extension bar Degree, and apply certain pressure to box is above cut, after each piece cutter is uniformly embedded in the soil body, so that it may be parked in adjusting and stretch Contracting bar;
8th step, by the first jack extend, to the soil body carry out normal direction cutting, after the completion of cutting, clear up be cut it is extra Native slag, and cut box by and force transmission rack is removed from the soil body, the soil body above cut after the completion of box cutting is the finished product soil body;
Bottom plate is caught in the slideway to strip by the 9th step, and the side wall at foundation pit rear portion disposes overwood side, then in flitch and bottom Upper third jack is disposed between plate, pedestal of the flitch as third jack extends third jack, and third jack pushes Bottom plate, bottom plate carry out transverse cuts to the finished product soil body, are just the live soil body to the soil body after the cutting of the finished product soil body to bottom plate The test soil body of direct shear test.
A kind of device of Soil Direct Shear test, including prepare component, pressure-applying unit, staight scissors component and measurement part;
Prepare component:Including bottom frame, bottom plate and telescopic component, telescopic component is hinged on bottom frame, and bottom plate is movably arranged on bottom frame It is interior;The bottom frame includes two strips, and two strips are located at the two sides of the soil body, is equipped with slideway in the side of strip, The end face of strip is equipped with multiple hinges, and bottom plate is located in slideway, can slide in slideway, is equipped on the end face of strip multiple Holdfast hole;The telescopic component includes more telescopic rods, and one end of telescopic rod is hinged in branch hinge, and other end is socketed in fixation On frame, the telescopic rod includes casing and screw rod, and tapped through hole is equipped in casing, and screw rod has two, is screwed onto set respectively The both ends of pipe are installed with for the steel pipe hinged with branch in the end of screw rod, are equipped with a locking hole at the middle part of casing, are locking Extension bar is socketed in tieholen.
Pressure-applying unit:It is second very heavy by the way that branch is hinged on the support frame of strip side, one end is in contact with support frame Top;
Staight scissors component:Including be coated on outside the soil body on cut box and incision box, further include include the first jack, be fixedly connected on One end of the fixed frame on telescopic component top, the first jack is fixedly connected on fixed frame, in incision box close to above cutting box Ball is mounted on end face, further include be placed on cut in box, lower force transmitting board and upper force transmitting board on soil body top surface, in upper power transmission Putting between plate and lower force transmitting board has roller bearing row, and one end of the separate fixed frame of the first jack is resisted against the end face of force transmitting board On, the second jack is resisted against the side for cutting box far from one end of support frame, it is described on to cut box surrounded by four blocks of steel plates Rectangular tube is installed with a wing plate at the upper edge for cutting box lower end two sides respectively, and the ball is placed on wing plate, under described The shape size for cutting box is identical as box is above cut, and is installed with muti-piece support plate in the two sides of incision box, support plate is hinged on branch hinge On;
Measure part:The first dial gauge of upper force transmitting board Normal Displacement amount is measured including one, box lateral displacement amount is cut in a measurement Second dial gauge.
Further, support frame as described above is " n " font, and the both ends of support frame are respectively articulated in the branch hinge of soil body two sides.
Further, one piece of pressure gauge is separately installed on the first jack and the second jack.
A kind of Soil Direct Shear test method, it is characterised in that:
The first step is inserted in outside the finished product soil body and cuts box and incision box, and ball is filled in upper box and the incision box two sides of cutting On the corresponding end face of wing plate, the support plate in the face of incision box two sides is hinged in branch hinge;
Telescopic rod and support frame are mounted on strip by second step, and by the second jack be tucked into support frame with above cut box it Between gap in;
Third step, successively by lower force transmitting board, roller bearing row and upper force transmitting board be placed on the top surface of the soil body;
Fixed frame after erecting telescopic rod, is mounted on the top of telescopic rod by the 4th step, and the first jack is tucked into fixed frame In gap between upper force transmitting board, the first jack, which is extended, applies Normal stress to the soil body, and observes the level of fixed frame;
5th step, the second jack of elongation apply lateral load to box is above cut, box are cut in promotion and is moved, the first dial gauge of observation, The variation numerical value of second dial gauge and pressure gauge can stop testing, test after the soil body reaches code requirement shear displacemant Test data is recorded and saved in journey;
The advantage of the invention is that:The present invention can easily prepare the soil body standard sample of Pass Test demand, avoid Error caused by artificial sample preparation;
When testing at the scene, entire pilot system constitutes a closed system, can be by Normal stress and horizontal lotus by bottom frame Idling turns to the internal force of loading device, without additional counterforce device;
Incision box is completely fixed during test, and above cutting box can only be translatable, and is not able to rotate, and therefore, shearing seam will not be because of sample Cut it is swollen effect and mutate, to make the shear-deformable more uniform of sample;
Ball between upper incision box can effectively reduce friction effect, keep test result truer;Between upper and lower force transmitting board Roller bearing row guarantees that normal pressure acts on sample middle always, avoids the wobbler action of Normal stress;
The configuration of the present invention is simple, in-site installation convenient disassembly, is readily transported, the produced on-site and teaching test suitable for the soil body.
Detailed description of the invention
Following further describes the present invention with reference to the drawings:
Fig. 1 is the schematic perspective view of preparation facilities of the present invention,
Fig. 2 is the schematic perspective view of experimental rig of the present invention,
Fig. 3 is the main view of preparation facilities of the present invention,
Fig. 4 is the side view of preparation facilities of the present invention,
Fig. 5 is the main view of experimental rig of the present invention,
Fig. 6 is the side view of experimental rig of the present invention,
Fig. 7 is the schematic top plan view of the present invention when in use, and shown in figure is to carry out transverse cuts to the finished product soil body,
Fig. 8 is the diagrammatic cross-section in Fig. 7 at A-A.
Specific embodiment
A kind of scene Soil Direct Shear test soil body preparation device, including component and charging assembly are prepared,
Prepare component:Including bottom frame, bottom plate 1, telescopic component and on cut box 5, telescopic component is hinged on bottom frame, the activity of bottom plate 1 It is mounted in bottom frame, above cuts box 5 and be located in telescopic component;
Charging assembly:Including the first jack 7, force transmission rack 6, the fixed frame 8 for being fixedly connected on telescopic component top, first is very heavy The one end on top 7 is fixedly connected on fixed frame 8, and other end is resisted against on the end face of force transmission rack 6, and force transmission rack 6 is far from the 1000th The one end on jin top 7, which is resisted against, cuts on box 5.
Further, force transmission rack 6 is " n " shape, is installed with a card slot 601 respectively in two ends of force transmission rack 6.
Further, cutting box 5 on described is the rectangular tube surrounded by four blocks of steel plates, it is upper cut 5 lower end of box be mounted with it is a plurality of Cutter 4 is installed with a wing plate 501 at the upper edge for cutting 5 lower end two sides of box respectively, and the lower end for above cutting box 5 is resisted against cutter 4 Upper surface on, the outer wall for above cutting box 5 is located in card slot 601.
Further, the bottom frame includes two strips 2, and two strips 2 are located at the two sides of the soil body, in strip 2 Side be equipped with slideway 201, on the end face of strip 2 be equipped with multiple hinge 202, bottom plate 1 is located in slideway 201, can be in slideway Sliding in 201, is equipped with multiple holdfast holes 203 on the end face of strip 2.
Further, the telescopic component includes more telescopic rods 3, and one end of telescopic rod 3 is hinged in branch hinge 202, separately Outer one end is socketed on fixed frame 8, and the telescopic rod 3 includes casing 301 and screw rod 302, is led in casing 301 equipped with screw thread Hole, screw rod 302 have two, are screwed onto the both ends of casing 301 respectively, are installed in the end of screw rod 302 for cutting with scissors 202 with branch Hinged steel pipe 303 is equipped with a locking hole at the middle part of casing 301, extension bar 18 is socketed in locking hole.
A kind of method that scene 101 direct shear test of the soil body prepares sample with 101 preparation facilities of the soil body, includes the following steps:
The first step excavates out a biggish foundation pit 102 in the test site of selection, reserves initial soil at the middle part of foundation pit 102 Body 101, the initial soil body 101 all around all reserve certain space;
Second step, the two sides that two strips 2 are respectively placed to the initial soil body 101, and require the card of initial 101 two sides of the soil body Item 2 is parallel to each other, the one end of strip 2 with slideway 201 is towards the initial soil body 101, and strip 2 is fixed on foundation pit using holdfast 21 102 bottom;
Each telescopic rod 3 is hinged in the hinge of the branch on strip 2 202 by third step;
Each telescopic rod 3 is erected by the 4th step, in the upper end that fixed frame 8 is fixedly mounted on to each telescopic rod 3;
In 5th step, the fixed frame 8 for being fixedly connected with one end of the first jack 7, box 5 is cut by and is placed on the upper of the soil body 101 On end face;
6th step is cut box 5 by and is lifted, and each piece of cutter 4 is caught in the supreme lower end for cutting box 5, force transmission rack 6 is being cut box by 5 block;
7th step, the first jack 7 withstand force transmission rack 6 far from one end of fixed frame 8, adjust each telescopic rod using extension bar 18 3 height, and apply certain pressure to box 5 is above cut, after each piece of cutter 4 is uniformly embedded in the soil body 101, so that it may It is parked in and adjusts telescopic rod 3;
8th step extends the first jack 7, carries out normal direction cutting to the soil body 101, after the completion of cutting, clears up and is cut Extra native slag, and box 5 is cut by and force transmission rack 6 is removed from the soil body 101, above cut the soil body 101 after the completion of box 5 is cut For the finished product soil body 101;
Bottom plate 1 is caught in the slideway 201 on strip 2 by the 9th step, and the side wall at 102 rear portion of foundation pit disposes overwood side 20, then Upper third jack 11, pedestal of the flitch 20 as third jack 11, elongation the 3000th are disposed between flitch 20 and bottom plate 1 Jin top 11, third jack 11 push bottom plate 1, and bottom plate 1 carries out transverse cuts to the finished product soil body 101, to bottom plate 1 to the finished product soil body The soil body 101 after 101 cuttings is just the test soil body 101 of 101 direct shear test of the live soil body.
It, can be with after completing to the preparation of the soil body 101 with 101 preparation facilities of the soil body using live 101 direct shear test of the soil body Preparation facilities is changed as experimental rig;
Installing pressure-applying unit, staight scissors component and measurement part on preparation facilities again just is live 101 direct shear test of soil body dress It sets.
Pressure-applying unit:The support frame 12 of 2 side of strip, one end is hinged on by branch hinge 202 to be in contact with support frame 12 Second jack 11;
Staight scissors component:Including be coated on outside the soil body 101 on cut box 5 and incision box 10, in incision box 10 close to the end for above cutting box 5 Ball 9 is mounted on face, further include be placed on cut in box 5, lower force transmitting board 13 and upper force transmitting board 15 on 101 top surface of the soil body, Putting between upper force transmitting board 15 and lower force transmitting board 13 has roller bearing to arrange 14, one end of the separate fixed frame 8 of the first jack 7 against On the end face of upper force transmitting board 15, the second jack 11 is resisted against the side for cutting box 5 far from one end of support frame 12, under described The shape size for cutting box 10 is identical as box 5 is above cut, and is installed with muti-piece support plate 110 in the two sides of incision box, support plate 110 is cut with scissors It connects in branch hinge 202;
Measure part:Box lateral displacement is cut in the first dial gauge 17, one measurement for measuring upper 15 Normal Displacement amount of force transmitting board including one Second dial gauge 171 of amount.
Further, support frame as described above 12 is " n " font, and the both ends of support frame 12 are respectively articulated with the branch of 101 two sides of the soil body In hinge 202.
Further, one piece of pressure gauge 170 is separately installed on the first jack 7 and the second jack 11.
A kind of scene Soil Direct Shear test method, includes the following steps:
The first step is inserted in outside the finished product soil body 101 and cuts box 5 and incision box 10, and ball 9 is filled in and cuts box 5 and incision upper On the corresponding end face of wing plate 501 of 10 two sides of box, the support plate 110 in the face of 10 two sides of incision box is hinged in branch hinge 202;
Telescopic rod 3 and support frame 12 are mounted on strip 2 by second step, and by the second jack 11 be tucked into support frame 12 with On cut in gap between box 5;
Third step, successively by lower force transmitting board 13, roller bearing row 14 and upper force transmitting board 15 be placed on the top surface of the soil body 101;
Fixed frame 8 after erecting telescopic rod 3, is mounted on the top of telescopic rod 3 by the 4th step, the first jack 7 is tucked into solid Determine in the gap between frame 8 and upper force transmitting board 15, the elongation of the first jack 7 applies Normal stress to the soil body 101, and observes fixation The level of frame 8;
5th step, the second jack 11 of elongation apply lateral load to box 5 is above cut, the movement of box 5, observation the 100th are cut in promotion The variation numerical value for dividing table 17, the second dial gauge 171 and pressure gauge 170, after the soil body 101 reaches code requirement shear displacemant Stop test, test data is recorded and saved during test;
The present invention is the instrument based on Coulomb block effect test soil shear strength test, main by above cutting box 5 and incision box 10 Between generate horizontal displacement reach scene the soil body 101 is sheared.When test, the soil body 101, which is loaded into, cuts box 5 and incision box Among 10, above cuts and be connected between box 5 and incision box 10 by ball 9;Incision box 10 is hinged on bottom frame by support plate 110 On, and bottom surface is contacted with bottom plate 1, the top for above cutting box 5, which is put, upper force transmitting board 15 and lower force transmitting board 13 and roller bearing row 14. The first dial gauge 17 of measurement normal direction displacement is placed on upper force transmitting board 15.On cut box 5 can be in horizontal direction hydraulic jack The horizontal sliding between ball 9 and roller bearing row 14 under driving, to achieve the effect that shear the soil body.Horizontal thrust can be by connecting Pressure gauge 170 on the second jack 11 is read, and horizontal displacement is measured by the second dial gauge 171;Normal pressure can be by Pressure gauge 170 on one jack is read.During the whole test process, dial gauge is recorded(Or displacement sensor)And jack The data of pressure gauge, until the relative displacement between upper incision box 10 reaches code requirement, off-test at this time.
The present invention can easily prepare the soil body standard sample of Pass Test demand, caused by avoiding artificial sample preparation Error;When testing at the scene, entire pilot system constitutes a closed system, can be by Normal stress and horizontal lotus by bottom frame Idling turns to the internal force of loading device, without additional counterforce device;Incision box is completely fixed during test, above cuts 5, box It can be translatable, not be able to rotate, therefore, shearing seam will not mutate because of the cutting swollen effect of sample, to make the shearing of sample It deforms more uniform;On the ball 9 cut between box 5 and incision box 10 can effectively reduce friction effect, keep test result trueer It is real;14 guarantee normal pressure of roller bearing row between upper force transmitting board 15 and lower force transmitting board 13 acts on soil body middle always, avoids The wobbler action of Normal stress;The present invention, structure is simple, and in-site installation convenient disassembly is readily transported, the scene suitable for the soil body Production and teaching test.

Claims (1)

1. a kind of method that scene Soil Direct Shear test prepares the soil body with soil body preparation device, it is characterised in that:Including live soil Body direct shear test soil body preparation device, the scene Soil Direct Shear test soil body preparation device includes preparing component and load Component,
Prepare component:Including bottom frame, bottom plate(1), telescopic component and on cut box(5), telescopic component is hinged on bottom frame, bottom plate (1)It is movably arranged in bottom frame, above cuts box(5)In telescopic component;
Charging assembly:Including the first jack(7), force transmission rack(6), be fixedly connected on the fixed frame on telescopic component top(8), the One jack(7)One end be fixedly connected on fixed frame(8)On, other end is resisted against force transmission rack(6)End face on, force transmission rack (6)Far from the first jack(7)One end be resisted against and cut box(5)On;
Force transmission rack(6)For " n " shape, in force transmission rack(6)Two ends be installed with a card slot respectively(601);
Box is cut on described(5)It is the rectangular tube surrounded by four blocks of steel plates, cuts box upper(5)Lower end is mounted with a plurality of cutter(4), On cut box(5)The edge of lower end two sides is installed with a wing plate respectively(501), above cut box(5)Lower end be resisted against cutter(4) Upper surface on, above cut box(5)Outer wall be located at card slot(601)It is interior;
The bottom frame includes two strips(2), and two strips(2)The two sides of the soil body are located at, in strip(2)Side set There is slideway(201), in strip(2)End face be equipped with multiple hinge(202), bottom plate(1)Positioned at slideway(201)It is interior, it can be in cunning Road(201)Interior sliding, in strip(2)End face be equipped with multiple holdfast holes(203);
The telescopic component includes more telescopic rods(3), telescopic rod(3)One end be hinged on branch hinge(202)On, other end set It connects in fixed frame(8)On, the telescopic rod(3)Including casing(301)And screw rod(302), in casing(301)It is interior logical equipped with screw thread Hole, screw rod(302)With two, it is screwed onto casing respectively(301)Both ends, in screw rod(302)End be installed with for Branch hinge(202)Hinged steel pipe(303), in casing(301)Middle part be equipped with a locking hole, extension bar is socketed in locking hole (18);
A kind of method that the test of use site Soil Direct Shear prepares the soil body with soil body preparation device, includes the following steps:
The first step excavates out a biggish foundation pit in the test site of selection(102), in foundation pit(102)Middle part reserve just The beginning soil body(101), the initial soil body(101)All around all reserve certain space;
Second step, by two strips(2)It is respectively placed at the initial soil body(101)Two sides, and require initial soil body two sides Strip(2)It is parallel to each other, strip(2)With slideway(201)One end towards the initial soil body(101), use holdfast(21)It will card Item(2)It is fixed on foundation pit(102)Bottom;
Third step, by each telescopic rod(3)It is hinged on strip(2)On branch hinge(202)On;
4th step, by each telescopic rod(3)It erects and, by fixed frame(8)It is fixedly mounted on each telescopic rod(3)Upper end;
5th step, by the first jack(7)The fixed frame that is fixedly connected of one end(8)On, box is cut by(5)It is placed on the soil body (101)Upper surface on;
6th step cuts box by(5)It lifts, by each piece of cutter(4)It is caught in and supreme cuts box(5)Lower end, by force transmission rack(6) Box is cut by(5)It blocks;
7th step, the first jack(7)Far from fixed frame(8)One end withstand force transmission rack(6), utilize extension bar(18)It adjusts each A telescopic rod(3)Height, and to above cutting box(5)Apply certain pressure, to each piece of cutter(4)Uniformly it is embedded in the soil body (101)In after, so that it may be parked in adjusting telescopic rod(3);
8th step, by the first jack(7)Elongation, to the soil body(101)Normal direction cutting is carried out, after the completion of cutting, cleaning is cut Under extra native slag, and box is cut by(5)And force transmission rack(6)From the soil body(101)On remove, above cut box(5)It has cut The soil body after(101)For the finished product soil body;
9th step, by bottom plate(1)It is caught in strip(2)On slideway(201)It is interior, in foundation pit(102)In the side wall disposition at rear portion Flitch(20), then in flitch(20)And bottom plate(1)Between dispose upper third jack(11), flitch(20)As third jack (11)Pedestal, extend third jack(11), third jack(11)Push bottom plate(1), bottom plate(1)The finished product soil body is carried out Transverse cuts, to bottom plate(1)To the soil body after the cutting of the finished product soil body(101)It is just the test of live Soil Direct Shear test The soil body.
CN201810651257.1A 2016-04-07 2016-04-07 Method for preparing soil body by soil body preparation device for on-site soil body direct shear test Active CN108871893B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810651257.1A CN108871893B (en) 2016-04-07 2016-04-07 Method for preparing soil body by soil body preparation device for on-site soil body direct shear test

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN201610212571.0A CN105890947B (en) 2016-04-07 2016-04-07 A kind of device and method of scene Soil Direct Shear experiment soil body preparation and direct shear test
CN201810651257.1A CN108871893B (en) 2016-04-07 2016-04-07 Method for preparing soil body by soil body preparation device for on-site soil body direct shear test

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
CN201610212571.0A Division CN105890947B (en) 2016-04-07 2016-04-07 A kind of device and method of scene Soil Direct Shear experiment soil body preparation and direct shear test

Publications (2)

Publication Number Publication Date
CN108871893A true CN108871893A (en) 2018-11-23
CN108871893B CN108871893B (en) 2021-01-26

Family

ID=57013476

Family Applications (2)

Application Number Title Priority Date Filing Date
CN201810651257.1A Active CN108871893B (en) 2016-04-07 2016-04-07 Method for preparing soil body by soil body preparation device for on-site soil body direct shear test
CN201610212571.0A Active CN105890947B (en) 2016-04-07 2016-04-07 A kind of device and method of scene Soil Direct Shear experiment soil body preparation and direct shear test

Family Applications After (1)

Application Number Title Priority Date Filing Date
CN201610212571.0A Active CN105890947B (en) 2016-04-07 2016-04-07 A kind of device and method of scene Soil Direct Shear experiment soil body preparation and direct shear test

Country Status (1)

Country Link
CN (2) CN108871893B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114739729A (en) * 2022-04-29 2022-07-12 中国电建集团成都勘测设计研究院有限公司 Construction method for rapidly obtaining undisturbed soil samples in batches

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106525588B (en) * 2016-12-01 2023-06-23 华侨大学 Multi-deformation-mode self-adaptive extensometer
CN107942031A (en) * 2017-10-18 2018-04-20 华南理工大学 The simulation experiment method of soil body weather alternating and staight scissors
CN107817173B (en) * 2017-10-31 2023-10-20 华侨大学 In-situ diagonal shear test system for raw soil wall and application method thereof
CN110455713B (en) * 2019-09-09 2024-03-22 南京林业大学 Pressurized single-interface micro-distance rotary cutting testing device and testing method

Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3795721B2 (en) * 2000-01-19 2006-07-12 独立行政法人科学技術振興機構 Small automatic repetitive one side shear test equipment
CN101105433A (en) * 2007-07-26 2008-01-16 河海大学 Portable on-spot and indoor dual-purpose direct-cutting experiment instrument and its sampling method
JP2008241247A (en) * 2007-03-23 2008-10-09 Chugoku Electric Power Co Inc:The Shear tester for rock-bed discontinuous surface
CN201145658Y (en) * 2007-07-26 2008-11-05 河海大学 Portable on site and indoor dual-purpose direct shear test instrument
CN102042937A (en) * 2009-10-14 2011-05-04 同济大学 Site large-scale direct shearing test device of shearing strength of concrete and basement adhesion surface
CN102313673A (en) * 2011-08-04 2012-01-11 北京交通大学 Full-automatic, digital and large frozen soil direct shear apparatus
KR20120054274A (en) * 2010-11-19 2012-05-30 한국건설기술연구원 Equipment for testing shearing force of secure mesh window for building construction using knife
KR101166522B1 (en) * 2012-05-17 2012-07-19 한국지질자원연구원 Ring shear apparatus for enforcing sealing and rotation control
CN204536105U (en) * 2015-03-30 2015-08-05 西南交通大学 A kind of shear box group for original state sandy soil direct shear test
CN104849151A (en) * 2015-05-29 2015-08-19 武汉大学 Movable plate stacking ring shearing apparatus capable of adapting to free shearing deformation
CN104977216A (en) * 2015-07-09 2015-10-14 北京神州龙鼎科技有限公司 In situ direct shear apparatus
CN204731116U (en) * 2015-07-09 2015-10-28 北京神州龙鼎科技有限公司 Original position direct shear apparatus

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3684376B2 (en) * 2001-01-22 2005-08-17 国立大学法人山口大学 In-situ shear tester
CN102410962B (en) * 2011-08-09 2013-09-11 中国地质大学(武汉) Portable rock mass structural plane direct shear test apparatus for field and indoor use
CN103884607A (en) * 2014-03-28 2014-06-25 黄斌 On-site large-scale coarse-grained soil direct shear testing equipment
CN104807706A (en) * 2015-04-27 2015-07-29 中国地质科学院探矿工艺研究所 Portable soft and weak layer in-situ direct shear tester and testing method thereof

Patent Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3795721B2 (en) * 2000-01-19 2006-07-12 独立行政法人科学技術振興機構 Small automatic repetitive one side shear test equipment
JP2008241247A (en) * 2007-03-23 2008-10-09 Chugoku Electric Power Co Inc:The Shear tester for rock-bed discontinuous surface
CN101105433A (en) * 2007-07-26 2008-01-16 河海大学 Portable on-spot and indoor dual-purpose direct-cutting experiment instrument and its sampling method
CN201145658Y (en) * 2007-07-26 2008-11-05 河海大学 Portable on site and indoor dual-purpose direct shear test instrument
CN102042937A (en) * 2009-10-14 2011-05-04 同济大学 Site large-scale direct shearing test device of shearing strength of concrete and basement adhesion surface
KR20120054274A (en) * 2010-11-19 2012-05-30 한국건설기술연구원 Equipment for testing shearing force of secure mesh window for building construction using knife
CN102313673A (en) * 2011-08-04 2012-01-11 北京交通大学 Full-automatic, digital and large frozen soil direct shear apparatus
KR101166522B1 (en) * 2012-05-17 2012-07-19 한국지질자원연구원 Ring shear apparatus for enforcing sealing and rotation control
CN204536105U (en) * 2015-03-30 2015-08-05 西南交通大学 A kind of shear box group for original state sandy soil direct shear test
CN104849151A (en) * 2015-05-29 2015-08-19 武汉大学 Movable plate stacking ring shearing apparatus capable of adapting to free shearing deformation
CN104977216A (en) * 2015-07-09 2015-10-14 北京神州龙鼎科技有限公司 In situ direct shear apparatus
CN204731116U (en) * 2015-07-09 2015-10-28 北京神州龙鼎科技有限公司 Original position direct shear apparatus

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114739729A (en) * 2022-04-29 2022-07-12 中国电建集团成都勘测设计研究院有限公司 Construction method for rapidly obtaining undisturbed soil samples in batches

Also Published As

Publication number Publication date
CN105890947A (en) 2016-08-24
CN105890947B (en) 2018-07-31
CN108871893B (en) 2021-01-26

Similar Documents

Publication Publication Date Title
CN105890947B (en) A kind of device and method of scene Soil Direct Shear experiment soil body preparation and direct shear test
CN106124341A (en) The field direct shear test sample preparation of a kind of Tu Yan interface and assay device
CN105806721B (en) A kind of large size Rock And Soil in-situ direct shear test device
CN111595682B (en) Large-scale complex surrounding rock condition anchoring and grouting integrated coupling effect test system and method
CN105928791B (en) Rock mass interlayer weak intercalated layer base sample sample field direct shear test method
CN103806906A (en) Rock mass/soil mass drilling in-situ test device and method
CN103884607A (en) On-site large-scale coarse-grained soil direct shear testing equipment
CN107063895B (en) A kind of rock mass interlayer weak intercalated layer field direct shear test method
CN208239220U (en) Shear tester in hole in situ
CN208254978U (en) Shearing test system in the hole of deep layer original position
CN110261234B (en) Fractured rock mass separation layer anchoring control simulation test device and method
CN105319130A (en) Testing method for testing compression-shear performance of jointed rock
CN114624126B (en) Rock-soil in-situ shearing test equipment and method
CN110686980B (en) Tunnel excavation analogue means under inhomogeneous side direction load
CN105223080B (en) Evaluation method for jointed rock performance and bolting and grouting effects under compression-shear condition
CN206740531U (en) The vertical side friction test machine people of in-situ three-dimensional dead load under ground body opening
CN113089624A (en) Adjacent foundation pit asynchronous excavation simulation test device and test method
CN105738225B (en) Deep hole rock/upper home position testing method and test machine people
CN110779800A (en) Method and device for predicting pullout resistance of compacted grouting soil nail and device application method
CN108519257B (en) Method and device for preparing root-containing soil sample and detecting shear strength
CN110455712B (en) Sample preparation device and test method for measuring adhesion force between special curved surface and soil interface by inverted sample preparation
CN205679487U (en) A kind of large-scale Rock And Soil in-situ direct shear test device
CN109238888A (en) The removable marine jack-up unit shoe model loading test device of one kind and method
CN111458238A (en) Assembled rock-soil body slope in-situ direct shear test device and method
CN208507079U (en) Simulate the centrifugal test device of multi-thread shield crossing existing structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant