CN108775243A - A kind of shield machine narrow space originates construction method - Google Patents

A kind of shield machine narrow space originates construction method Download PDF

Info

Publication number
CN108775243A
CN108775243A CN201810667836.5A CN201810667836A CN108775243A CN 108775243 A CN108775243 A CN 108775243A CN 201810667836 A CN201810667836 A CN 201810667836A CN 108775243 A CN108775243 A CN 108775243A
Authority
CN
China
Prior art keywords
installation
shield
shield machine
construction method
steps
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810667836.5A
Other languages
Chinese (zh)
Other versions
CN108775243B (en
Inventor
孙振川
韩伟锋
张兵
李栋
周建军
陈馈
李凤远
杨振兴
吕乾乾
陈瑞祥
许华国
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Key Laboratory of Shield Machine and Boring Technology
China Railway Tunnel Group Co Ltd CRTG
Original Assignee
State Key Laboratory of Shield Machine and Boring Technology
China Railway Tunnel Group Co Ltd CRTG
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Key Laboratory of Shield Machine and Boring Technology, China Railway Tunnel Group Co Ltd CRTG filed Critical State Key Laboratory of Shield Machine and Boring Technology
Priority to CN201810667836.5A priority Critical patent/CN108775243B/en
Publication of CN108775243A publication Critical patent/CN108775243A/en
Application granted granted Critical
Publication of CN108775243B publication Critical patent/CN108775243B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining

Abstract

The invention discloses a kind of shield machine narrow spaces to originate construction method, which includes mainly that ground installation installation, the installation of borehole wall equipment, bottom equipment installation and shield machine install four steps;By to above-mentioned steps, the especially combing and process optimization of shield machine installation steps, the present invention proposes the shield launching construction method of a set of safe and efficient narrow space on the whole, can ensure the security and stability of subsequent construction by this method, and can save construction cost and duration.

Description

A kind of shield machine narrow space originates construction method
Technical field
The present invention relates to a kind of construction method of tunneling shield, specially a kind of shield machine narrow space originates construction party Method.
Background technology
Currently, slurry shield has been subway tunnel, the main construction party in the fields such as gas supply tunnel, electric power tunnel of supplying water Method.During slurry shield is constructed, shield launching technology plays the role of vital, the beginning in entire work progress Hair construction operation is the process for the accident that most easily produces, and can be directly related to shield tunnel smoothly penetrate through.And due to very much The place of shield launching is in big city, so originating, place is often very narrow, this development to shield launching preparation Prodigious influence is caused, therefore, for narrow shield launching place, it is necessary to propose a kind of shield machine of narrow space Originate construction method.
Invention content
It is an object of the invention to propose that a kind of shield machine narrow space originates construction method, to solve the above-mentioned prior art In deficiency.
Shield machine narrow space of the present invention originates construction method, and steps are as follows for Specific construction:
(1)Ground installation installation steps are carried out first, which includes successively:Box-type substation installation, gantry crane installation, pneumatics Machine installation, the installation of Slurry treatment system, mortar stirring device installation, cooling pond installation, assembling, grouting equipment installation.
Wherein, box-type substation is 1000KVA substations, and substation is built first, in accordance with the position of horizontal layout before installation Basis, it is in place on the basis of being installed to box-type substation with crane after the completion of basic, then bury ground around box-type substation Line installs lightning protection system.
Slurry treatment system includes two groups of bypass circulations, and one group is installed on and originates silo bottom, is mainly used for pipeline continued access When, maintain the normal circulation of muddy water in pipeline(Partial circulating), in addition, being blocked as our portions of muddy water occur, can also utilize this bypass Circuit carries out back flush, and another group is mounted in Suporting structure host, is mainly used for adjusting into row's mud flow rate;Slurry treatment System mainly include a treating capacity be 500 m3/h mud and water separating equipment and two treating capacities be 60 m3/h seperator, Mud and water separating equipment is mainly used for firsts and seconds separation, and seperator is mainly used for three-level separation.
(2)Then borehole wall equipment installation steps are carried out, which includes successively:Lift installation, power cable installation, mud Starch Pipe installing, cooling water pipe installation, compression gas pipe installation, air hose installation, telephone wire installation, sewage pipe installation;
(3)Then bottom equipment installation steps are carried out, which includes successively:Dredge pump installation, counter force wall installation, hole sealing Installation measures holder installation, the installation of steel construction pedestal, the installation of shield guide rail, the installation of trailer rack;
(4)Shield machine installation steps are finally carried out, the shield machine installation steps are specially:(a)Ground is spelled with hanging device The shield machine first segment installed, hangs onto on the guide rail for filling lubricant grease, is pushed ahead it along guide rail by hydraulic cylinder, Until cutterhead stops promoting when fully entering portal sealing ring;(b)The section of shield machine second is hung in vertical shaft, guide rail is placed in On, it is proper that adjustment position makes it put, and starts hydraulic cylinder, pushes it against first segment, when it is inserted into first segment, slows down propulsion Speed measures insertion, when reaching precalculated position, stops promoting, fit sealing circle hold-down bolt, connects guiding oil cylinder, even Various cables and cooling water, compressed air, supply and discharge mud and fluid pressure line are connect, to complete the connection of the section of shield machine first and second Work;(c)Shield shield tail is hung in vertical shaft with hanging device, connection shield machine second section and the shield tail for having been placed in steel loop, The related oil cylinder of connection, cable and pipeline;(d)After steel pushing pad is mounted on shield tail, its edge and shield tail edge weight are made by crane It closes, is welded and fixed plate and fixes;(e)Transformer trailer is mounted on the holder in vertical shaft, connects all cables, and test electric leakage Defencive function;(f)Gone through before formal driving shield hydraulic system components, electrical system components, supply and discharge water pipeline, for plasma discharge Pipeline, air line etc., and its sealing and installation accuracy are gone through, shield launching track and shield machine initial attitude are carried out Check repetition measurement, it is ensured that after all parameter qualifications, could start to tunnel.
The present invention can generate following advantageous effect:
Four installations such as the present invention is by installing ground installation, borehole wall equipment is installed, bottom equipment is installed and shield machine is installed The combing and process optimization of step propose a set of safe and efficient shield launching construction method, pass through this method on the whole It can ensure the security and stability of subsequent construction, and construction cost and duration can be saved.
The present invention optimizes setting to shield machine installation steps, and by shield machine be divided into first segment, the second section, shield tail and They, are then carried out installation connection by other corollary equipments respectively in starting well successively, ensure that shield in narrow space above Structure machine originates the effect of preparation, and has saved construction land tenure, and security risk is low.
Description of the drawings
Fig. 1 is the schematic diagram that shield machine narrow space of the present invention originates construction method.
Specific implementation mode
With reference to embodiment, invention is further described in detail, and embodiments of the present invention are not limited thereto.
Shield machine narrow space of the present invention originates construction method, and steps are as follows for Specific construction:
(1)Ground installation installation steps are carried out first, which includes successively:Box-type substation installation, gantry crane installation, pneumatics Machine installation, the installation of Slurry treatment system, mortar stirring device installation, cooling pond installation, assembling, grouting equipment installation.
Wherein, box-type substation is 1000KVA substations, and substation is built first, in accordance with the position of horizontal layout before installation Basis, it is in place on the basis of being installed to box-type substation with crane after the completion of basic, then bury ground around box-type substation Line installs lightning protection system.
Slurry treatment system includes two groups of bypass circulations, and one group is installed on and originates silo bottom, is mainly used for pipeline continued access When, maintain the normal circulation of muddy water in pipeline(Partial circulating), in addition, being blocked as our portions of muddy water occur, can also utilize this bypass Circuit carries out back flush, and another group is mounted in Suporting structure host, is mainly used for adjusting into row's mud flow rate;Slurry treatment System mainly include a treating capacity be 500 m3/h mud and water separating equipment and two treating capacities be 60 m3/h seperator, Mud and water separating equipment is mainly used for firsts and seconds separation, and seperator is mainly used for three-level separation.
(2)Then borehole wall equipment installation steps are carried out, which includes successively:Lift installation, power cable installation, mud Starch Pipe installing, cooling water pipe installation, compression gas pipe installation, air hose installation, telephone wire installation, sewage pipe installation;
(3)Then bottom equipment installation steps are carried out, which includes successively:Dredge pump installation, counter force wall installation, hole sealing Installation measures holder installation, the installation of steel construction pedestal, the installation of shield guide rail, the installation of trailer rack;
(4)Shield machine installation steps are finally carried out, the shield machine installation steps are specially:(a)Ground is spelled with hanging device The shield machine first segment installed, hangs onto on the guide rail for filling lubricant grease, is pushed ahead it along guide rail by hydraulic cylinder, Until cutterhead stops promoting when fully entering portal sealing ring;(b)The section of shield machine second is hung in vertical shaft, guide rail is placed in On, it is proper that adjustment position makes it put, and starts hydraulic cylinder, pushes it against first segment, when it is inserted into first segment, slows down propulsion Speed measures insertion, when reaching precalculated position, stops promoting, fit sealing circle hold-down bolt, connects guiding oil cylinder, even Various cables and cooling water, compressed air, supply and discharge mud and fluid pressure line are connect, to complete the connection of the section of shield machine first and second Work;(c)Shield shield tail is hung in vertical shaft with hanging device, connection shield machine second section and the shield tail for having been placed in steel loop, The related oil cylinder of connection, cable and pipeline;(d)After steel pushing pad is mounted on shield tail, its edge and shield tail edge weight are made by crane It closes, is welded and fixed plate and fixes;(e)Transformer trailer is mounted on the holder in vertical shaft, connects all cables, and test electric leakage Defencive function;(f)Gone through before formal driving shield hydraulic system components, electrical system components, supply and discharge water pipeline, for plasma discharge Pipeline, air line etc., and its sealing and installation accuracy are gone through, shield launching track and shield machine initial attitude are carried out Check repetition measurement, it is ensured that after all parameter qualifications, could start to tunnel.
The foregoing is only a preferred embodiment of the present invention, is not limited to invent, although with reference to aforementioned implementation Invention is explained in detail for example, still can be to foregoing embodiments for the technical staff in the wooden field Recorded technical solution is modified or equivalent replacement of some of the technical features.It is all invention spirit and Within principle, any modification, equivalent replacement, improvement and so on should be included within the protection domain of invention.

Claims (3)

1. a kind of shield machine narrow space originates construction method, which is characterized in that steps are as follows for the construction method Specific construction:
(1)Ground installation installation steps are carried out first, which includes successively:Box-type substation installation, gantry crane installation, pneumatics Machine installation, the installation of Slurry treatment system, mortar stirring device installation, cooling pond installation, assembling, grouting equipment installation;
(2)Then borehole wall equipment installation steps are carried out, which includes successively:Lift installation, power cable installation, mud tube Road installation, cooling water pipe installation, compression gas pipe installation, air hose installation, telephone wire installation, sewage pipe installation;
(3)Then bottom equipment installation steps are carried out, which includes successively:Dredge pump installation, counter force wall installation, hole sealing Installation measures holder installation, the installation of steel construction pedestal, the installation of shield guide rail, the installation of trailer rack;
(4)Shield machine installation steps are finally carried out, the shield machine installation steps are specially:(a)Ground is spelled with hanging device The shield machine first segment installed, hangs onto on the guide rail for filling lubricant grease, is pushed ahead it along guide rail by hydraulic cylinder, Until cutterhead stops promoting when fully entering portal sealing ring;(b)The section of shield machine second is hung in vertical shaft, guide rail is placed in On, it is proper that adjustment position makes it put, and starts hydraulic cylinder, pushes it against first segment, when it is inserted into first segment, slows down propulsion Speed measures insertion, when reaching precalculated position, stops promoting, fit sealing circle hold-down bolt, connects guiding oil cylinder, even Various cables and cooling water, compressed air, supply and discharge mud and fluid pressure line are connect, to complete the connection of the section of shield machine first and second Work;(c)Shield shield tail is hung in vertical shaft with hanging device, connection shield machine second section and the shield tail for having been placed in steel loop, The related oil cylinder of connection, cable and pipeline;(d)After steel pushing pad is mounted on shield tail, its edge and shield tail edge weight are made by crane It closes, is welded and fixed plate and fixes;(e)Transformer trailer is mounted on the holder in vertical shaft, connects all cables, and test electric leakage Defencive function;(f)Gone through before formal driving shield hydraulic system components, electrical system components, supply and discharge water pipeline, for plasma discharge Pipeline, air line etc., and its sealing and installation accuracy are gone through, shield launching track and shield machine initial attitude are carried out Check repetition measurement, it is ensured that after all parameter qualifications, start to tunnel.
2. river-crossing tunnel shield launching construction method as described in claim 1, which is characterized in that described(1)Step In:Box-type substation is 1000KVA substations, and transformer substation foundation, basis are built first, in accordance with the position of horizontal layout before installation After the completion, in place on the basis of being installed to box-type substation with crane, ground wire is then buried around box-type substation, installation is kept away Thunder system.
3. river-crossing tunnel shield launching construction method as described in claim 1, which is characterized in that described(1)Step In:Slurry treatment system includes two groups of bypass circulations, and one group is installed on and originates silo bottom, and another group is mounted on Suporting structure master In machine;Slurry treatment system includes mainly the mud and water separating equipment that a treating capacity is 500 m3/h and two treating capacities are 60 m The seperator of 3/h, mud and water separating equipment are mainly used for firsts and seconds separation, and seperator is mainly used for three-level separation.
CN201810667836.5A 2018-06-26 2018-06-26 Shield tunneling machine narrow space starting construction method Active CN108775243B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810667836.5A CN108775243B (en) 2018-06-26 2018-06-26 Shield tunneling machine narrow space starting construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810667836.5A CN108775243B (en) 2018-06-26 2018-06-26 Shield tunneling machine narrow space starting construction method

Publications (2)

Publication Number Publication Date
CN108775243A true CN108775243A (en) 2018-11-09
CN108775243B CN108775243B (en) 2020-06-26

Family

ID=64025558

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810667836.5A Active CN108775243B (en) 2018-06-26 2018-06-26 Shield tunneling machine narrow space starting construction method

Country Status (1)

Country Link
CN (1) CN108775243B (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005042546A (en) * 2004-11-15 2005-02-17 Kajima Corp Branch type propulsive excavator
CN203891887U (en) * 2014-05-27 2014-10-22 中铁十九局集团轨道交通工程有限公司 Split starting shield tunneling machine
CN105298503A (en) * 2015-09-16 2016-02-03 中铁十局集团第三建设有限公司 Separate launching construction method of shield tunneling machine in narrow space
CN107725059A (en) * 2017-09-27 2018-02-23 中铁十二局集团有限公司 The ultrashort miniature shield machine main frame separate launching construction method originated under steric requirements

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005042546A (en) * 2004-11-15 2005-02-17 Kajima Corp Branch type propulsive excavator
CN203891887U (en) * 2014-05-27 2014-10-22 中铁十九局集团轨道交通工程有限公司 Split starting shield tunneling machine
CN105298503A (en) * 2015-09-16 2016-02-03 中铁十局集团第三建设有限公司 Separate launching construction method of shield tunneling machine in narrow space
CN107725059A (en) * 2017-09-27 2018-02-23 中铁十二局集团有限公司 The ultrashort miniature shield machine main frame separate launching construction method originated under steric requirements

Also Published As

Publication number Publication date
CN108775243B (en) 2020-06-26

Similar Documents

Publication Publication Date Title
CN105041271B (en) A kind of buck exploiting ocean natural gas hydrates method and sub-sea production systems
CN206298888U (en) For the pin shoe jacket structure of offshore boosting station
CN107449569A (en) A kind of shield tail brush sealing property testing equipment and its method of testing
CN202990947U (en) Basement type underwater dry wellhead structure
CN102691314A (en) Internal deviation correcting fine adjusting system and adjusting technology for immersed tubes
CN110409509A (en) A kind of seabed submerged floating tunnel and subterranean tunnel connection construction device and its construction method
CN107972828A (en) A kind of offshore platform
EP3683438B1 (en) Pump storage unit in a body of water and method of operation
CN102913177A (en) Template type underwater dry-type well head structure
CN108775243A (en) A kind of shield machine narrow space originates construction method
CN103574158A (en) Super-large diameter pressure steel tube inclined shaft three-hanging-point installation method
CN110714774B (en) Bidirectional split starting method for small shield in narrow shaft
CN102704512B (en) Immersed tube bottom jack type deviation rectifying fine adjusting system and adjusting technology
CN204370466U (en) A kind of jacket offshore wind turbine foundation with bracket
CN203516978U (en) Underwater pipe-jacking propelling separating device
CN207420160U (en) A kind of vertical shaft type garage arrangement form and hanging scaffold
CN206928255U (en) The maintenance arrangement of the permanent plug of induced joint diversion tunnel
CN104929650B (en) A kind of overall originating method in shield machine underground
CN108425362A (en) A kind of earthwork transportation system and construction method for base pit engineering
CN105178416B (en) Box culvert accesses construction method under water
CN202913431U (en) Immersed tube bottom end jack type deviation-rectifying accurate adjustment system
CN108868787B (en) Shield starting construction method for river-crossing tunnel
CN107153242A (en) A kind of optical fiber laying device
CN105926549A (en) Transportation construction method for in-tunnel pressure steel tube
JPH0275730A (en) Underground storage method for compressed air and device thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CB03 Change of inventor or designer information

Inventor after: Sun Zhenchuan

Inventor after: Yang Zhenxing

Inventor after: Lv Qianqian

Inventor after: Chen Ruixiang

Inventor after: Xu Huaguo

Inventor after: Luo Qiong

Inventor after: Guo Weishe

Inventor after: Han Weifeng

Inventor after: Zhang Bing

Inventor after: Li Dong

Inventor after: Zhou Jianjun

Inventor after: Chen Kui

Inventor after: Li Fengyuan

Inventor before: Sun Zhenchuan

Inventor before: Chen Ruixiang

Inventor before: Xu Huaguo

Inventor before: Han Weifeng

Inventor before: Zhang Bing

Inventor before: Li Dong

Inventor before: Zhou Jianjun

Inventor before: Chen Kui

Inventor before: Li Fengyuan

Inventor before: Yang Zhenxing

Inventor before: Lv Qianqian

CB03 Change of inventor or designer information