CN105926549A - Transportation construction method for in-tunnel pressure steel tube - Google Patents

Transportation construction method for in-tunnel pressure steel tube Download PDF

Info

Publication number
CN105926549A
CN105926549A CN201610526637.3A CN201610526637A CN105926549A CN 105926549 A CN105926549 A CN 105926549A CN 201610526637 A CN201610526637 A CN 201610526637A CN 105926549 A CN105926549 A CN 105926549A
Authority
CN
China
Prior art keywords
penstock
construction method
steel
hole
skate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610526637.3A
Other languages
Chinese (zh)
Inventor
王建利
李凤伦
桑鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sinohydro Bureau 14 Co Ltd
Original Assignee
Sinohydro Bureau 14 Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinohydro Bureau 14 Co Ltd filed Critical Sinohydro Bureau 14 Co Ltd
Priority to CN201610526637.3A priority Critical patent/CN105926549A/en
Publication of CN105926549A publication Critical patent/CN105926549A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B9/00Water-power plants; Layout, construction or equipment, methods of, or apparatus for, making same
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B9/00Water-power plants; Layout, construction or equipment, methods of, or apparatus for, making same
    • E02B9/02Water-ways
    • E02B9/06Pressure galleries or pressure conduits; Galleries specially adapted to house pressure conduits; Means specially adapted for use therewith, e.g. housings, valves, gates
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Abstract

The invention discloses a transportation construction method for an in-tunnel pressure steel tube, and aims to provide a transportation construction method, capable of improving transportation efficiency, for the in-tunnel pressure steel tube. The transportation construction method comprises the following steps: (1) laying a transportation platform and a transportation rail and arranging a traction system; (3) mounting steel supporting legs and brake shoes; and (3) lifting and transporting the pressure steel tube. According to the transportation construction method, the transportation platform and the transportation rail are laid, the steel supporting legs and the brake shoes are mounted in the pressure steel tube, so that under action of traction force, the pressure steel tube slides on a rail with lubricating oil, and is transported to a to-be-mounted position. The transportation construction method solves the problems that large lifting machinery cannot be lifted in a tunnel and a transport vehicle cannot be used for transporting in the tunnel, so that the safety risks are reduced.

Description

The transport construction method of penstock in a kind of hole
Technical field
The present invention relates to Hydropower Station Construction technical field, especially relate to the transport construction method of penstock in a kind of hole.
Background technology
Large, medium and small type underground workshop diversion system typically uses steel liner structure, and construction passage is narrow and small, and the volume of steel lining own, weight are big, and in hole, general lifting machine, Transport Machinery cannot be constructed, and the construction period is longer.
Use existing construction method, need to be before the excavation supporting of civil engineering penstock hole, the a large amount of degree of depth of specific placement and the bigger grasp of intensity above in hole, lifting and position adjustment for penstock in transportation, grasp also needs to spend after arranging very greatly manually and the duration carries out grasp pull-out test, calculate grasp bears pulling force, and grasp Reusability exists certain potential safety hazard.
Use existing construction method, need penstock uses outside hole plant equipment lifting, transport unload in hole, unloading place the most all can from installation site farther out, need artificial secondary conveying, during secondary conveying, as being not added with reinforcing to it, in the case of hoist engine draws, tube coupling can overturn rolling, there is security risk;Secondary conveying needs to carry out bigger adjustment work to installation site, increases the construction period.
Therefore, it is necessary to the transport construction of penstock in hole is improved, the limitation avoided penstock transport in hole, unload in hole, the efficiency of size adjusting, reduction of erection time, reduction security risk can be improved again.
Summary of the invention
Instant invention overcomes shortcoming of the prior art, it is provided that one is applicable to limited space in hole, the transport construction method of penstock in the hole of conevying efficiency, reduction of erection time can be improved.
In order to solve above-mentioned technical problem, the present invention is achieved by the following technical solutions:
The transport construction method of penstock in a kind of hole, it comprises the following steps:
(1) shipping platform, conveying track are laid and trailer system layout:
Diversion tunnel exit set up with diversion tunnel bottom with high shipping platform to lay track, in diversion tunnel, then lay conveying track, and arrange rack winch;The joint location of two parallel orbits staggers, the diameter being smaller than penstock of two parallel orbits;
(2) steel leg and skate are installed:
After penstock weld seam detection is qualified, being parallel to axis and install two row's steel legs on penstock, one end of steel leg is welded to connect with penstock periphery, and the other end welds with skate;Center distance and rail span between two skates are basically identical;
(3) penstock lifting and transport:
Crane is utilized to be lifted to conveying track by the penstock installing steel leg and skate so that skate can slide just in orbit;Conveying track is smeared the lubricating grease that can reduce frictional force, then utilizes the rack winch traction pressure steel pipe laid to transport in carrying out hole so that penstock slides into position to be installed.
Preferably, the joint location of two parallel orbits staggers;The dislocation that each rail joint is left and right, upper three is respectively less than 1mm, and rail joint gap is less than 1mm.
Preferably, described penstock using stiffening ring be fixed, supporting leg is arranged on stiffening ring.
Preferably, the height calculation method of described steel leg is: set penstock attachment rail elevation as H1, the Center elevation of penstock is H2, penstock radius is R1, penstock wall thickness D1, skate channel-section steel thickness D2, height of landing leg H3, then the height of steel leg is: H3=H2-H1-R1-D1-D2.
Compared with prior art, present invention have the advantage that
(1) present invention is by laying shipping platform and conveying track, and penstock installs steel leg and skate, under tractive force draws, makes penstock slide on the track smeared lubricating oil, transport to position to be installed.The method solves large-scale hoisting machinery and can not lift in hole, the problem that haulage vehicle can not transport in hole, reduces security risk.
(2) present invention is by installing steel leg and skate transport pressure steel pipe, and in solving penstock hole, anti-body is difficult, and after transport puts in place, position deviation is big, the problem that size adjusting is difficult.The present invention not only can be from upstream to a section installation the in downstream in hole and dock, it is also possible to several sections of penstocks complete for welding outside hole transport to hole installation together, improves transport installation effectiveness, reduction of erection time.
Accompanying drawing explanation
In order to be illustrated more clearly that the embodiment of the present invention or technical scheme of the prior art, the accompanying drawing used required in embodiment or description of the prior art will be briefly described below, apparently, accompanying drawing in describing below is only some embodiments of the present invention, for those of ordinary skill in the art, on the premise of not paying creative work, it is also possible to obtain other accompanying drawing according to these accompanying drawings.
Fig. 1 is the structural representation that penstock of the present invention is in travel position.
In figure: 1, steel leg;2, skate;3, penstock;4, conveying track.
Detailed description of the invention
Below in conjunction with the accompanying drawing in the embodiment of the present invention, the technical scheme in the embodiment of the present invention is clearly and completely described, it is clear that described embodiment is only a part of embodiment of the present invention rather than whole embodiments.Based on the embodiment in the present invention, the every other embodiment that those of ordinary skill in the art are obtained under not paying creative work premise, broadly fall into the scope of protection of the invention.
According to general line-putting method before penstock transport, setting-out goes out to install center line and Installation Elevation controls datum mark.The most as shown in Figure 1, carry out the transport construction method of penstock in hole, mainly comprise the steps that
(1) shipping platform, conveying track are laid and trailer system layout:
Diversion tunnel exit set up with diversion tunnel bottom with high shipping platform to lay track, in diversion tunnel, then lay conveying track, and arrange rack winch (conventionally meeting the location arrangements of safety standard);The joint location of two parallel orbits staggers;The dislocation that each rail joint is left and right, upper three is respectively less than 1mm, and rail joint gap is less than 1mm;Track uses with built-in fitting in diversion tunnel and is welded and fixed;The diameter being smaller than penstock of two parallel orbits.
(2) steel leg and skate are installed:
After penstock weld seam detection is qualified, penstock is parallel to axis two row's steel legs are installed (supporting leg can have suitable angle of inclination, general each tube coupling installs the supporting leg of 4 steel), one end of steel leg is welded to connect with penstock periphery, and the other end welds with skate;Center distance between two skates is basically identical with rail span, and two row's skates will be made just to slide on two parallel orbits;Skate plays anti-slip in hauling operation, overturning-preventing effect;Steel leg is used for supporting penstock.
If using stiffening ring to be fixed on penstock, supporting leg also may be installed on stiffening ring;The height of steel leg, computational methods are: setting penstock attachment rail elevation as H1, the Center elevation of penstock is H2, penstock radius is R1, penstock wall thickness D1, skate channel-section steel thickness D2, height of landing leg H3, the height of steel leg is the most in theory: H3=H2-H1-R1-D1-D2.
(3) penstock lifting and transport:
Bridge crane is utilized to be lifted to conveying track by the penstock installing steel leg and skate so that skate can slide just in orbit.Conveying track is smeared the lubricating grease that can reduce frictional force, then the rack winch traction pressure steel pipe laid is utilized to transport in carrying out hole, after making penstock slide into position to be installed, utilize jack and chain block to adjust penstock position and fit like a glove with installing control point.
If when the firm pipe of pressure is band Taper Pipe form, according to penstock, center and tapering (gradient) and the installation site of supporting leg, the Installation Elevation of track will be installed, with CAD drawing instrument setting-out errant face to this Taper Pipe penstock center, measure height of landing leg, conveying track is laid simultaneously and be adjusted according to the gradient, it is ensured that penstock Taper Pipe is installed consistent with normal pressures penstock installation.
The foregoing is only presently preferred embodiments of the present invention, not in order to limit the present invention, all within the spirit and principles in the present invention, any modification, equivalent substitution and improvement etc. made, should be included within the scope of the present invention.

Claims (4)

1. the transport construction method of penstock in a hole, it is characterised in that comprise the following steps:
(1) shipping platform, conveying track are laid and trailer system layout:
Diversion tunnel exit set up with diversion tunnel bottom with high shipping platform to lay track, in diversion tunnel, then lay conveying track, and arrange rack winch;The joint location of two parallel orbits staggers, the diameter being smaller than penstock of two parallel orbits;
(2) steel leg and skate are installed:
After penstock weld seam detection is qualified, being parallel to axis and install two row's steel legs on penstock, one end of steel leg is welded to connect with penstock periphery, and the other end welds with skate;Center distance and rail span between two skates are basically identical;
(3) penstock lifting and transport:
Crane is utilized to be lifted to conveying track by the penstock installing steel leg and skate so that skate can slide just in orbit;Conveying track is smeared the lubricating grease that can reduce frictional force, then utilizes the rack winch traction pressure steel pipe laid to transport in carrying out hole so that penstock slides into position to be installed.
The transport construction method of penstock in hole the most according to claim 1, it is characterised in that: the joint location of two parallel orbits staggers;The dislocation that each rail joint is left and right, upper three is respectively less than 1mm, and rail joint gap is less than 1mm.
The transport construction method of penstock in hole the most according to claim 1, it is characterised in that: using stiffening ring to be fixed on described penstock, supporting leg is arranged on stiffening ring.
The transport construction method of penstock in hole the most according to claim 1, it is characterized in that: the height calculation method of described steel leg is: set penstock attachment rail elevation as H1, the Center elevation of penstock is H2, penstock radius is R1, penstock wall thickness D1, skate channel-section steel thickness D2, height of landing leg H3, then the height of steel leg is: H3=H2-H1-R1-D1-D2.
CN201610526637.3A 2016-07-06 2016-07-06 Transportation construction method for in-tunnel pressure steel tube Pending CN105926549A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610526637.3A CN105926549A (en) 2016-07-06 2016-07-06 Transportation construction method for in-tunnel pressure steel tube

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610526637.3A CN105926549A (en) 2016-07-06 2016-07-06 Transportation construction method for in-tunnel pressure steel tube

Publications (1)

Publication Number Publication Date
CN105926549A true CN105926549A (en) 2016-09-07

Family

ID=56827706

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610526637.3A Pending CN105926549A (en) 2016-07-06 2016-07-06 Transportation construction method for in-tunnel pressure steel tube

Country Status (1)

Country Link
CN (1) CN105926549A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111422576A (en) * 2020-04-27 2020-07-17 中国水利水电第四工程局有限公司 Loading and transporting device for choke plug of hydropower station unit
CN114960896A (en) * 2022-06-24 2022-08-30 湖北省长湖建设工程有限公司 Pipeline system for industrial sewage treatment and installation method thereof
CN114960896B (en) * 2022-06-24 2024-04-12 湖北省长湖建设工程有限公司 Pipeline system for industrial sewage treatment and installation method thereof

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH093902A (en) * 1995-06-26 1997-01-07 Japan Steel & Tube Constr Co Ltd Earth retaining construction method in open-cutting civil engineering work
CN205012299U (en) * 2015-08-25 2016-02-03 中国葛洲坝集团第二工程有限公司 Pressure steel pipe installation shaped steel rail set
CN205088653U (en) * 2015-10-28 2016-03-16 中国葛洲坝集团股份有限公司 Pressure steel pipe haul installation combination track
CN105464060A (en) * 2015-12-08 2016-04-06 中国水利水电第十四工程局有限公司 Supporting leg and iron shoe transportation construction method of inner-hole pressure steel pipe

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH093902A (en) * 1995-06-26 1997-01-07 Japan Steel & Tube Constr Co Ltd Earth retaining construction method in open-cutting civil engineering work
CN205012299U (en) * 2015-08-25 2016-02-03 中国葛洲坝集团第二工程有限公司 Pressure steel pipe installation shaped steel rail set
CN205088653U (en) * 2015-10-28 2016-03-16 中国葛洲坝集团股份有限公司 Pressure steel pipe haul installation combination track
CN105464060A (en) * 2015-12-08 2016-04-06 中国水利水电第十四工程局有限公司 Supporting leg and iron shoe transportation construction method of inner-hole pressure steel pipe

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111422576A (en) * 2020-04-27 2020-07-17 中国水利水电第四工程局有限公司 Loading and transporting device for choke plug of hydropower station unit
CN111422576B (en) * 2020-04-27 2021-07-13 中国水利水电第四工程局有限公司 Loading and transporting device for choke plug of hydropower station unit
CN114960896A (en) * 2022-06-24 2022-08-30 湖北省长湖建设工程有限公司 Pipeline system for industrial sewage treatment and installation method thereof
CN114960896B (en) * 2022-06-24 2024-04-12 湖北省长湖建设工程有限公司 Pipeline system for industrial sewage treatment and installation method thereof

Similar Documents

Publication Publication Date Title
CN203925507U (en) A kind of metro shield assembling and the system of going into the well
CN101967886B (en) Assembly and installation methods of steel containment vessel of nuclear power station
CN201494438U (en) Simple and fast installation cableway for maintenance and rush repair of mountain pipeline
CN106151682B (en) The large-scale penstock installation downward putting device of high slope and penstock installation method
CN105443871B (en) A kind of new suspension and support and construction technology for the connection of horizontal multi-pipeline counterpart
CN103821376B (en) Single-layer latticed shell high-altitude oblique rail accumulation slippage construction
CN103669216A (en) Steel box girder scattered-splicing sliding device and installation method
CN104195948B (en) Bridge suspension pipe pushing installation construction method
CN101907202A (en) Portable support type jack-based pipe installation construction method
WO2011044203A2 (en) Lightweight high-performance pipelayer
CN103277582A (en) Method for mounting inclined shaft internal pressure steel tube
US20120241402A1 (en) Formulations for c-met kinase inhibitors
CN107165046B (en) A kind of installation method of bridge inspection car
CN103047478B (en) In-hole sectioning installation method for penstocks with overlarge diameters
CN103574158B (en) Super-large diameter pressure steel tube inclined shaft three-hanging-point installation method
CN103967284A (en) Method for installing steel column in butt joint with reserved column head
CN205417623U (en) Machine is transported to long step material
CN106121248A (en) The installation method of sintering large flue in a kind of restricted area
CN105926549A (en) Transportation construction method for in-tunnel pressure steel tube
CN103775734B (en) Gas drainage pipeline system construction method under large-diameter well
CN105781108B (en) A kind of construction method for being used to close on large-scale steel-mould trolley entirety transition between place
CN105448366A (en) Nuclear power plant condenser mounting method
CN203114336U (en) Device for transporting slag discharging vehicle in inclined shaft section and steep slope section
CN110145317B (en) Shield tunneling machine station-crossing construction method
CN110053936B (en) Pipeline conveying device and pipeline conveying method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20160907