CN103775734B - Gas drainage pipeline system construction method under large-diameter well - Google Patents

Gas drainage pipeline system construction method under large-diameter well Download PDF

Info

Publication number
CN103775734B
CN103775734B CN201310747888.0A CN201310747888A CN103775734B CN 103775734 B CN103775734 B CN 103775734B CN 201310747888 A CN201310747888 A CN 201310747888A CN 103775734 B CN103775734 B CN 103775734B
Authority
CN
China
Prior art keywords
pipeline
pipe
vehicle
rope
jack
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201310747888.0A
Other languages
Chinese (zh)
Other versions
CN103775734A (en
Inventor
张兵
王文涌
李芳�
祁勇
籍跃奎
罗旭
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Shanxi Sijian Group Co Ltd
Original Assignee
China Shanxi Sijian Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Shanxi Sijian Group Co Ltd filed Critical China Shanxi Sijian Group Co Ltd
Priority to CN201310747888.0A priority Critical patent/CN103775734B/en
Publication of CN103775734A publication Critical patent/CN103775734A/en
Application granted granted Critical
Publication of CN103775734B publication Critical patent/CN103775734B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L1/00Laying or reclaiming pipes; Repairing or joining pipes on or under water
    • F16L1/024Laying or reclaiming pipes on land, e.g. above the ground
    • F16L1/028Laying or reclaiming pipes on land, e.g. above the ground in the ground
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F7/00Methods or devices for drawing- off gases with or without subsequent use of the gas for any purpose

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • General Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Mechanical Engineering (AREA)
  • Sewage (AREA)
  • Pipeline Systems (AREA)

Abstract

The present invention relates to a kind of gas tube construction method, gas drainage pipeline system construction method under specially a kind of large-diameter well.The technical issues of solving the suspension construction of gas tube, method is the preparation before construction, surveying setting-out first, then steel pipe pipeline section or pipe fitting both ends are burn-on flange on well, carry out preservative treatment, underground infield is delivered to by mine car, pipeline section is promoted to mounting height using jack, pipeline section is suspended under prior mounted anchor pole or anchor cable with steel wire rope and strainer, it is fastened by bolts centre and is lined with the adjacent tubular segments of asbestos rubber pad or the flange of pipe fitting or valve, achieve the effect that sealing, last pipeline pressure experiment, trial operation, handing-over.Method of the present invention provides standard set coal mine roadway gas pipe suspension pipeline construction method, solves the technical issues of existing gas tube system influences bottom surface equipment and current personnel mounted on ground.

Description

Gas drainage pipeline system construction method under large-diameter well
Technical field
The present invention designs a kind of gas tube construction method, and gas drainage pipeline system is applied under specially a kind of large-diameter well Work method.
Background technology
As country is to the pay attention to day by day of safety in production, more and more coal mines carry out safety in production technological transformation project, gas Improvement is the major tasks in coal mining, and it is one of effective measures that gas pre-drainage, which is put,.The major way that gas pre-drainage is put is logical It crosses a large amount of gas tube and concentrates the gas in working face and transfer out.Traditional gas drainage pipeline system is by pipeline On the bracket away from tunnel ground 500mm high, lane space inherently at full stretch is occupied.In coal mine roadway also Many machineries, vehicle and walkway are arranged, therefore actually other constructions bring certain resistance to gas tube to tunnel Hinder, therefore it is contemplated that by lifting pipeline in tunnel upper space, make tunnel lower part can be with personnel and vehicle pass-through.
Invention content
The technical issues of present invention is in order to solve the suspension of gas tube construction provides a kind of heavy caliber fire damp and takes out Put pipe-line system construction method.
The technical scheme is that a kind of gas drainage pipeline system construction method under large-diameter well,
Then preparation before construction, first surveying setting-out burn-on steel pipe pipeline section or pipe fitting both ends flange on well, carry out Preservative treatment, underground infield is delivered to by mine car, pipeline section is promoted to mounting height using jack, with steel wire rope and drawing Pipeline section is suspended under prior mounted anchor pole or anchor cable by tight device, is fastened by bolts centre and is lined with the adjacent of asbestos rubber pad The flange of pipeline section or pipe fitting or valve achievees the effect that sealing, last pipeline pressure experiment, trial operation, handing-over.
Gas drainage pipeline system construction method, specifically comprises the following steps under a kind of large-diameter well:
1 surveying setting-out
Before anchor pole, anchor cable construction, unwrapping wire need to be measured by design, first determines that pipeline is specific according to design requirement before unwrapping wire Then position carries out unwrapping wire according to the datum line provided in ore deposit.During unwrapping wire using datum line and two intersect datum lines intersection point as according to According to the intersection point of the right-angled intersection point alignment fiducials line of laser level and making two cross hairs with intersecting benchmark line overlap, so Push up the crosspoint for measuring and orienting pipeline in tunnel with tape measure afterwards.With this crosspoint cooperation laser level, it is mining directly to instrument, Engineering cotton rope carries out unwrapping wire, after determining pipeline line position, is measured with tape measure, and every 3 meters are pushed up in tunnel with paint(Anchor pole position) And every 12 meters(Anchor cable position)It makes marks, with this alternately unwrapping wire;
2 pipeline sections, pipe fitting processing
According to underground survey data, the processing work of elbow is carried out on well, one end of elbow or threeway uses kink method Orchid, when connecting slag-discharging device, tailrace and valve, pipeline section end should also use lap joint flange;
3 pipelines transport
When pipeline ships, 3 are filled with flat car encapsulation per car, flower column vehicle or the mine car such as threeway, pipe nipple, elbow of processing Shipment, with φ 12.5mm steel wire ropes and rope card envelope vehicle, jail is covered in pipeline both sides with timber wedge, with crowbar in haulage vehicle both ends steel wire rope Simultaneously fixation is tightened, and is tightened at steel wire rope knotting with 8# iron wires, pipeline both ends are protected with plank, to prevent breaking Other objects;During entrucking, the center of gravity of pipeline will be consistent with the center of gravity of vehicle;Pipeline is transported to specified ground by ore deposit transport team Then point arranges personnel to transport to job location, scatters by erection sequence by unit in charge of construction;During gallery cart, primary standard pushes away one Vehicle, and in both ends cart, the spacing of cart in the same direction when track grade is less than or equal to 5 ‰, cannot be less than 10 meters, the gradient is big When 5 ‰, 30 meters are cannot be less than;
4th, lifting pipeline, connection
During lifting pipeline, the appropriate selecting pipe of power is born according to the maximum hoisting weight and anchor pole of jack, the maximum of anchor cable Road radical;Before lifting, jack is first fixed on anchor cable, the pipe ends connected are fixed with jack, during lifting, first Pipeline pull-up ground 200mm is waited for 3 minutes, it is ensured that recurrence is hung to design height after safety, when forgetting about it chain, it is to be ensured that fall at both ends Chain uniformly lifts by crane, and after the completion of lifting, pipeline is fixed with corresponding steel wire rope, rope card and strainer,
The hanging of gas pipeline is using the wire rope hanging of φ 12.5-6*19, and hanging spacing is 3 meters, and hanging position is located at Line connection, when gas pipeline is hung, sling point must hang two rope cards, pipeline installation on each sling point on anchor disk Gradient deviation is no more than the 1/3 of design, and pipeline is mounted on position in gallery and hangs down with stringcourse away from tolerance ± 30mm.
5th, connecting pipe flange, pipeline pressure experiment, trial operation, handing-over.
Method of the present invention provides standard set coal mine roadway gas pipe suspension pipeline construction method, solves existing There is gas tube system to be mounted on the technical issues of ground influences bottom surface equipment and current personnel.
Description of the drawings
Fig. 1 is the construction method design sketch of the present invention
1- anchor poles or anchor cable 2- strainer 3- steel wire rope 4- gas tube 5- tunnels in figure.
Specific embodiment
A kind of gas drainage pipeline system construction method under large-diameter well,
1 surveying setting-out
Before anchor pole, anchor cable construction, unwrapping wire need to be measured by design, first determines that pipeline is specific according to design requirement before unwrapping wire Then position carries out unwrapping wire according to the datum line provided in ore deposit.During unwrapping wire using datum line and two intersect datum lines intersection point as according to According to the intersection point of the right-angled intersection point alignment fiducials line of laser level and making two cross hairs with intersecting benchmark line overlap, so Push up the crosspoint for measuring and orienting pipeline in tunnel with tape measure afterwards.With this crosspoint cooperation laser level, it is mining directly to instrument, Engineering cotton rope carries out unwrapping wire, after determining pipeline line position, is measured with tape measure, and every 3 meters are pushed up in tunnel with paint(Anchor pole position) And every 12 meters(Anchor cable position)It makes marks, with this alternately unwrapping wire;
2 pipeline sections, pipe fitting processing
Underworkings height rises and falls, is winding, is needed in construction using many elbows, since underground does not allow to carry out Electricity, gas welding operation, the processing work needs of elbow are completed on well.
According to underground survey data, the processing work of elbow is carried out on well, one end of elbow or threeway uses kink method Orchid, when connecting slag-discharging device, tailrace and valve, pipeline section end should also use lap joint flange;
3 pipelines transport
3.1st, when pipeline ships, 529 tunnels of φ encapsulate per car with flat car and fill 3, the use such as threeway, pipe nipple, elbow of processing Flower column vehicle or mine car shipment, with φ 12.5mm steel wire ropes and rope card envelope vehicle, jail is covered in pipeline both sides with timber wedge, with crowbar in transport vehicle Both ends steel wire rope is tightened and fixation, and is tightened at steel wire rope knotting with 8# iron wires, and pipeline both ends are carried out with plank Protection, to prevent breaking other objects;
3.2nd, during entrucking, the center of gravity of pipeline will be consistent with the center of gravity of vehicle;
3.3rd, pipeline is transported to appointed place by ore deposit transport team, then personnel is arranged to beat by unit in charge of construction and transport to construction ground Point, scatters by erection sequence;
3.4th, during gallery cart, primary standard pushes away a vehicle, forbids in vehicle both sides cart;The spacing of cart in the same direction, it is in-orbit When the road gradient is less than or equal to 5 ‰, 10 meters are cannot be less than, when the gradient is more than 5 ‰, cannot be less than 30 meters.
3.5th, when roadway gradient is more than 7 ‰, forbid hutching.
3.6th, must pay attention to front during cart the moment, start cart, stop, slide down, find in front of someone or have obstacle During object, from the larger downward cart in place of the gradient and close to when track switch, bend, access adit, air door, chamber outlet, trammer Warning signal must be sent out in time.
3.7th, forbid not charged loose vehicle when winch beats fortune and let vehicle fly away.
3.8th, oblique lane transport will carry out following several respects work.
1) winch sound and light signal must be complete intact on the way for inclined gallery.
2) " slope three is kept off " wants complete intact.
3) pin, ring chain, gib head, safety rope have to comply with regulation.
4) drumman, signalman, cager must take appointment with certificate.
5) oblique lane transport strict implement " pedestrian, pedestrian do not drive a vehicle for driving " system.
6) drumman is before driving, it is necessary to check winch take root whether securely, whether damper brake, clutch sensitive can Lean on, whether fracture of wire transfinites or has knotting phenomenon, operation button intact etc. steel wire rope, timely processing of pinpointing the problems is forbidden to twist Vehicle " in spite of illness " operation.
7) whether cager should check whether envelope vehicle is secured before winch startup, have barrier, chain turner tool to be on track It is no complete, intact, timely processing of pinpointing the problems.
8) drumman will accomplish slow start, middling speed operation, steady parking when starting winch.
9) forbid super trailer.
10) for vehicle before inclined gallery are not entered, " slope three is kept off " should be at closed state.
11) when vehicle slides down in inclined gallery, forbid winch hard draw rerail, when finding that vehicle slides down, cager joins in time It is drumman parking, then slowly steel wire rope is tensed and tight brake of stopping, disengaging winch drag brake handle is not allowed in drumman hand.Rerail Personnel cover wheel with timber wedge, and personnel should stand in vehicle up direction or the both sides rerails tool rerail such as cucurbit, crowbar.Vehicle exists During lifting, if special messenger observes the situation of change of lifting point, under-vehicle forbids the people that stands during vehicle rerail.
12) when inclined gallery are unloaded, drumman should be stopped tight brake, then cut off the power, the personnel of unloading should after vehicle comes to a complete stop, Vehicle is fixed with car arrester or with anchor chain, then master scatters one by one from top to bottom.It is to cover firm vehicle with timber wedge that gallery, which is unloaded, Pipeline is scattered one by one.Footman personnel on site commands, and personnel's action should be harmonious, avoids that accident occurs.
13) spacing that pipe fitting is unloaded is advisable in order to install, and inclined gallery pipeline rope belt is tight, prevents from gliding.
4 lifting pipelines, connection
During lifting pipeline, the appropriate selecting pipe of power is born according to the maximum hoisting weight and anchor pole of jack, the maximum of anchor cable Road radical;Before lifting, jack is first fixed on anchor cable, the pipe ends connected are fixed with jack,
It during lifting, first pipeline pull-up ground 200mm, waits for 3 minutes, it is ensured that recurrence is hung to design height after safety, draws During jack, it is to be ensured that both ends jack uniformly lifts by crane,
After the completion of lifting, pipeline is fixed with corresponding steel wire rope, rope card and strainer.
The hanging of gas pipeline is using the wire rope hanging of φ 12.5-6*19, and hanging spacing is 3 meters, and hanging position is located at Line connection(Unified leftward or rightward 500mm),
When gas pipeline is hung, sling point must hang on anchor disk two ropes on each sling point and block, and gas pipeline is hung During extension, sling point must be hung on anchor disk, must not be hung on bar-mat reinforcement or wire netting.
5 pipelines connect, and pipeline flange installs its contact and answers keeping parallelism and keep alignment, bolt that can freely pass into, Ensure that connection bolt is worn to consistent, well-balanced, the elastic appropriateness of fastening, 2-4 screw pitch of exposing.
Pipeline installation and its connector installation site meet design requirement, install must not be close to help wall, towards it is reasonable, be convenient for Maintenance, often saving ensures a suspension centre on pipeline, two rope cards on each suspension centre.
The pipeline installation gradient meets design requirement, and gradient deviation is no more than the 1/3 of design.
Pipeline is mounted on position in gallery and hangs down with stringcourse away from tolerance ± 30mm.
The model of valve meets design requirement, and installation site inlet and outlet are in the right direction, are connected firmly, closely, open and close flexibly, Handwheel, handle will be cleaned towards reasonable, valve surface.

Claims (1)

1. a kind of gas drainage pipeline system construction method under large-diameter well, it is characterised in that:Preparation before construction, measures first Then unwrapping wire burn-ons steel pipe pipeline section or pipe fitting both ends flange on well, carry out preservative treatment, and being delivered to underground by mine car pacifies Place is filled, pipeline section is promoted to mounting height using jack, is suspended on pipeline section with steel wire rope and strainer mounted in advance Under anchor pole or anchor cable, it is fastened by bolts centre and is lined with the adjacent tubular segments of asbestos rubber pad or the flange of pipe fitting or valve, reach The effect of sealing, last pipeline pressure experiment, trial operation, handing-over;
Specifically comprise the following steps:
(1)Surveying setting-out
Before anchor pole, anchor cable construction, unwrapping wire need to be measured by design, first the specific position of pipeline is determined according to design requirement before unwrapping wire It puts, unwrapping wire is then carried out according to the datum line provided in ore deposit;Using the intersection point of datum line and two intersection datum lines as foundation during unwrapping wire, With the intersection point of the right-angled intersection point alignment fiducials line of laser level and make two cross hairs with intersecting benchmark line overlap, Ran Houyong Tape measure pushes up the crosspoint for measuring and orienting pipeline in tunnel;With this crosspoint cooperation laser level, mining directly to instrument, engineering Cotton rope carries out unwrapping wire, after determining pipeline line position, is measured with tape measure, and every 3 meters of anchor pole position and every is pushed up in tunnel with paint 12 meters of anchor cable position makes marks, with this alternately unwrapping wire;
(2)Pipeline section, pipe fitting processing
According to underground survey data, the processing work of elbow is carried out on well, one end of elbow or threeway is using lap joint flange, even When connecing slag-discharging device, tailrace and valve, pipeline section end should also use lap joint flange;
(3)Pipeline transports
When pipeline ships, 3 are filled with flat car encapsulation per car, the threeway of processing, pipe nipple, elbow are shipped with flower column vehicle or mine car, With φ 12.5mm steel wire ropes and rope card envelope vehicle, pipeline both sides are covered jail with timber wedge, are tightened with crowbar in haulage vehicle both ends steel wire rope And fixation, and tightened at steel wire rope knotting with 8# iron wires, pipeline both ends are protected with plank, it is other to prevent breaking Object, during entrucking, the center of gravity of pipeline will be consistent with the center of gravity of vehicle, pipeline be transported to appointed place by ore deposit transport team, so Personnel being arranged to transport to job location by unit in charge of construction afterwards, scattered by erection sequence, during gallery cart, primary standard pushes away a vehicle, and In both ends cart, the spacing of cart in the same direction when track grade is less than or equal to 5 ‰, cannot be less than 10 meters, the gradient is more than 5 ‰ When, it cannot be less than 30 meters;
(4)Lifting pipeline, connection;
During lifting pipeline, power born according to the maximum hoisting weight and anchor pole of jack, the maximum of anchor cable and suitably select pipeline root Number;Before lifting, jack is first fixed on anchor cable, the pipe ends connected are fixed with jack, during lifting, first pipeline Pull-up ground 200mm is waited for 3 minutes, it is ensured that recurrence is hung to design height after safety, when forgetting about it chain, it is to be ensured that both ends jack is equal After the completion of lifting, pipeline is fixed with corresponding steel wire rope, rope card and strainer for even lifting,
The hanging of gas pipeline is using the wire rope hanging of φ 12.5mm-6*19, and hanging spacing is 3 meters, and hanging position is located at pipe Road junction, when gas pipeline is hung, sling point must be hung on anchor disk, two rope cards on each sling point, pipeline installation Gradient deviation is no more than the 1/3 of design, and pipeline is mounted on position in gallery and hangs down with stringcourse away from tolerance ± 30mm,
(5)Connecting pipe flange, pipeline pressure experiment, trial operation, handing-over.
CN201310747888.0A 2013-12-31 2013-12-31 Gas drainage pipeline system construction method under large-diameter well Active CN103775734B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310747888.0A CN103775734B (en) 2013-12-31 2013-12-31 Gas drainage pipeline system construction method under large-diameter well

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310747888.0A CN103775734B (en) 2013-12-31 2013-12-31 Gas drainage pipeline system construction method under large-diameter well

Publications (2)

Publication Number Publication Date
CN103775734A CN103775734A (en) 2014-05-07
CN103775734B true CN103775734B (en) 2018-07-06

Family

ID=50568306

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310747888.0A Active CN103775734B (en) 2013-12-31 2013-12-31 Gas drainage pipeline system construction method under large-diameter well

Country Status (1)

Country Link
CN (1) CN103775734B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104344075B (en) * 2014-10-24 2017-03-29 铜陵有色金属集团铜冠矿山建设股份有限公司 Shaft construction hangs the quick handling of interim edema due to wind pathogen pipeline and installation method using the borehole wall
CN107013245A (en) * 2017-05-31 2017-08-04 中国恩菲工程技术有限公司 Pipeline fixing device
CN110318804A (en) * 2018-03-28 2019-10-11 中国有色集团抚顺红透山矿业有限公司 Underground mining field hoisting structure and installation method
CN108626482B (en) * 2018-04-23 2019-10-08 西山煤电建筑工程集团有限公司矿建第一分公司 Utilize the construction method of anti-well drilling machine installation vertical gas pipe

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE619511C (en) * 1935-10-02 Helmut Dueker Device for pipe suspension
DE886290C (en) * 1951-09-27 1953-08-13 Paul Baehr Connection clamp for the ends of wire loops in pipe suspensions
US5474274A (en) * 1993-10-22 1995-12-12 Bernosky; John Coupling and load support for suspending a load from the head of a coal mine roof bolt
CN201902703U (en) * 2010-12-09 2011-07-20 西安建筑科技大学 Suspension protective device for underground pipeline
CN202061584U (en) * 2011-03-30 2011-12-07 鞍钢股份有限公司 Water adding pipe of secondary mixing machine
CN202829277U (en) * 2012-08-31 2013-03-27 山西晋城无烟煤矿业集团有限责任公司 Lifting device for pipeline installation

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CH606891A5 (en) * 1975-06-12 1978-11-15 Impex Essen Vertrieb

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE619511C (en) * 1935-10-02 Helmut Dueker Device for pipe suspension
DE886290C (en) * 1951-09-27 1953-08-13 Paul Baehr Connection clamp for the ends of wire loops in pipe suspensions
US5474274A (en) * 1993-10-22 1995-12-12 Bernosky; John Coupling and load support for suspending a load from the head of a coal mine roof bolt
CN201902703U (en) * 2010-12-09 2011-07-20 西安建筑科技大学 Suspension protective device for underground pipeline
CN202061584U (en) * 2011-03-30 2011-12-07 鞍钢股份有限公司 Water adding pipe of secondary mixing machine
CN202829277U (en) * 2012-08-31 2013-03-27 山西晋城无烟煤矿业集团有限责任公司 Lifting device for pipeline installation

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
浅谈煤矿大直径瓦斯抽采管道安装工艺及施工方法;陶祥;《现代物业》;20130505;第12卷(第5期);第100-102页 *

Also Published As

Publication number Publication date
CN103775734A (en) 2014-05-07

Similar Documents

Publication Publication Date Title
CN203925507U (en) A kind of metro shield assembling and the system of going into the well
CN201494438U (en) Simple and fast installation cableway for maintenance and rush repair of mountain pipeline
CN103775734B (en) Gas drainage pipeline system construction method under large-diameter well
CN104088449B (en) Safe and fast double-track construction platform of super high-rise curtain wall
CN102536267B (en) Method for performing large-gradient deviated well construction by using full-section needle beam trolley and needle beam trolley
CN204251168U (en) Multi-rope friction hoist head rope changes system without stable car
CN205955237U (en) Plug -type platform of unloading of encorbelmenting
CN108278034B (en) Difficult location electric pole replaces construction method
CN107237649A (en) The long steep inclined shaft transportation system of light section and construction method
CN105460759B (en) A kind of method that main shaft winch tail rope is changed
CN102587284B (en) Independent derrick mast and beam plate mounting method
CN206987883U (en) The long steep inclined shaft transportation system of light section
CN204434116U (en) A kind of hanging device for interior courtyard lifting pipeline
CN101905840A (en) Underground coal mine crane
CN102926388B (en) Earth moving method for deep foundation pit excavation
CN107142966A (en) Top for reverse construction fills slide rail type horizontal transporter and its construction method
CN103950453A (en) Drive advancing train
CN101806377B (en) Construction method for installing medium and large size bluff pipeline
CN105040592B (en) A kind of horizontal drawing cable bridge and its erection method
CN207192618U (en) Down-hole pipe erecting device
CN103274165B (en) Conveying arrangement in gallery
CN206626333U (en) Suitable for the Winch for mine dispatch of coal mine roadway
CN214660350U (en) Split initial tunneling pipeline extension supporting device of shield tunneling machine
CN203174605U (en) Gravity type anchor body applied in special geology
CN105926549A (en) Transportation construction method for in-tunnel pressure steel tube

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information
CB03 Change of inventor or designer information

Inventor after: Zhang Bing

Inventor after: Wang Wenyong

Inventor after: Li Fang

Inventor after: Qi Yong

Inventor after: Ji Yuekui

Inventor after: Luo Xu

Inventor before: Zhang Bing

Inventor before: Wang Wenyong

Inventor before: Li Fang

Inventor before: Qi Yong

Inventor before: Luo Xu

GR01 Patent grant
GR01 Patent grant