CN108678179B - A kind of prefabricated buildings - Google Patents

A kind of prefabricated buildings Download PDF

Info

Publication number
CN108678179B
CN108678179B CN201810475993.6A CN201810475993A CN108678179B CN 108678179 B CN108678179 B CN 108678179B CN 201810475993 A CN201810475993 A CN 201810475993A CN 108678179 B CN108678179 B CN 108678179B
Authority
CN
China
Prior art keywords
bearing
plate body
bearing column
hole
wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201810475993.6A
Other languages
Chinese (zh)
Other versions
CN108678179A (en
Inventor
林显志
王煜
陈瑄
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fujian Province Huidong Construction Engineering Co Ltd
Original Assignee
Fujian Province Huidong Construction Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fujian Province Huidong Construction Engineering Co Ltd filed Critical Fujian Province Huidong Construction Engineering Co Ltd
Priority to CN201810475993.6A priority Critical patent/CN108678179B/en
Publication of CN108678179A publication Critical patent/CN108678179A/en
Application granted granted Critical
Publication of CN108678179B publication Critical patent/CN108678179B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/348Structures composed of units comprising at least considerable parts of two sides of a room, e.g. box-like or cell-like units closed or in skeleton form
    • E04B1/34815Elements not integrated in a skeleton
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/348Structures composed of units comprising at least considerable parts of two sides of a room, e.g. box-like or cell-like units closed or in skeleton form
    • E04B1/34815Elements not integrated in a skeleton
    • E04B1/34823Elements not integrated in a skeleton the supporting structure consisting of concrete
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/38Connections for building structures in general
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/38Connections for building structures in general
    • E04B1/48Dowels, i.e. members adapted to penetrate the surfaces of two parts and to take the shear stresses
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/38Connections for building structures in general
    • E04B1/48Dowels, i.e. members adapted to penetrate the surfaces of two parts and to take the shear stresses
    • E04B1/483Shear dowels to be embedded in concrete

Abstract

A kind of prefabricated buildings, there is top plate body in the upper end formed by integrally casting of eight bearing columns, the top surface of the top plate body of pouring molding is equipped with one layer of waterproof layer, going back formed by integrally casting between the upper end of adjacent bearing column has crossbeam, there is bottom-plate body in the lower end formed by integrally casting of eight bearing columns, be connected to the first vertical hitching post of the bottom of bearing column lower semisection can with ground or positioned at lower layer bearing column top realize be fastenedly connected, the upper semisection for being connected to the second vertical hitching post at the top of bearing column can be realized with the bottom for the bearing column for being located at upper layer to be fastenedly connected, it is fastenedly connected between the bottom edge and bottom-plate body of wall by the realization of two cover locking mechanisms of left and right, it is fastenedly connected between the left side and right edge of wall and the side wall of bearing column by the realization of upper and lower two cover locking mechanism.The present invention has the characteristics that structure novel, assembling are flexible, practical.

Description

A kind of prefabricated buildings
Technical field
The present invention relates to a kind of prefabricated buildings.
Background technique
With the rapid development of society, science and technology is widely used in building field, and therefore, prefabricated buildings are as pre- Product becomes the market demand, and client can be according to the individual needs of oneself come custom fit formula house, therefore prefabricated buildings Moulding is more flexible, design is more humane, in addition, prefabricated buildings as prefabricated component are transported to now after being come out by the factorial production Field carries out assembly construction, and this Construction Mode can greatly reduce the generation of building waste but also greatly reduce the row of building sewage It puts, this Construction Mode can not only reduce construction noise, and can also reduce pernicious gas and build the discharge of dust, scene Construction and the number of administrative staff can also greatly reduce, and this Construction Mode, which has, saves construction material, water-saving and energy-efficient Advantage.
Summary of the invention
In order to achieve the above object, the present invention provides a kind of prefabricated buildings, and the present invention has structure novel, assembling spirit Living, practical feature.
The specific technical solution of the present invention is as follows: a kind of prefabricated buildings, it is by cuboid-type frame, crossbeam, top plate Body, bottom-plate body, wall, vertical hitching post, pin rod, rectangular horizontal even steel plate, core bar, jam plate composition, which is characterized in that
Cuboid-type frame includes eight bearing columns, and eight bearing columns arrange in a manner of three rows, front first row, after One row of side is the bearing column of left, center, right three, and an intermediate row is then two bearing columns in left and right;
There are top plate body, the top of the steel bar framework inside every bearing column in the upper end formed by integrally casting of eight bearing columns It is connected with steel bar framework in top plate body, the top surface of the top plate body of pouring molding is equipped with one layer of waterproof layer, the thickness of top plate body ≤15cm;
Formed by integrally casting is gone back between the upper end of adjacent bearing column crossbeam, the steel bar framework inside crossbeam and every load-bearing Steel bar framework inside column is connected;
There are bottom-plate body, the bottom end of the steel bar framework inside every bearing column in the lower end formed by integrally casting of eight bearing columns It is connected with steel bar framework in bottom-plate body, is embedded with water pipe inside the bottom-plate body of pouring molding and electric wire walks pipe;
The bottom of each bearing column is integrally formed with a cylinder type sleeve one, the side of each bearing column There are a lateral pin hole one, the upper semisection of the first vertical hitching post can be inserted upwardly into the cylinder type sleeve one for wall lower end, Integrally formed with upper and lower twice, laterally concatenation through-hole one, the first pin rod can be inserted into lateral pin hole one every first vertical hitching post And through-hole one can be concatenated with the transverse direction of the first vertical hitching post upper semisection and realize concatenation;
The lower semisection for being connected to the first vertical hitching post of the bottom of bearing column can be with ground or positioned at the load-bearing of lower layer It realizes and is fastenedly connected in the top of column;
The top of each bearing column is integrally formed with a cylinder type sleeve two, the side of each bearing column There are a lateral pin hole two, the lower semisection of the second vertical hitching post can be downwardly into the cylinder type sleeve two for wall upper end, Integrally formed with upper and lower twice, laterally concatenation through-hole two, the second pin rod can be inserted into lateral pin hole two every second vertical hitching post And through-hole two can be concatenated with the transverse direction of the second vertical hitching post lower semisection and realize concatenation;
When lifting by crane cuboid-type frame, the second pin rod can be as lifting fulcrum after being inserted into lateral pin hole two;
The upper semisection for being connected to the second vertical hitching post at the top of bearing column can be with the bottom for the bearing column for being located at upper layer It realizes and is fastenedly connected in portion;
After in front of left side the left side wall of three bearing columns and before right side in after three bearing columns The equal indwelling of right side wall have the upper and lower two rectangular caulking grooves with round keyhole, rectangular horizontal even steel plate is integrally formed with two circles in left and right Shape series winding hole, half section of rectangular horizontal even half section of a left side for steel plate or the right side can be embedded in the rectangular caulking groove with round keyhole and pass through spiral shell The other half section of bolt realization locking, rectangular horizontal even steel plate is then locked with the band circle on another group of cuboid-type frame of side The rectangular caulking groove in hole realizes connection, to realize being fastenedly connected side by side for two groups of left and right cuboid-type frame;
Wall is installed, wall is reserved with as needed for installing window or door between adjacent bearing column Hole is fastenedly connected between the bottom edge and bottom-plate body of wall by the realization of two cover locking mechanisms of left and right, the left side of wall and the right side It is fastenedly connected between side and the side wall of bearing column by the realization of upper and lower two cover locking mechanism, the bottom edge and left and right two of wall Side is reserved with the chamber for built-in retaining mechanism;
Retaining mechanism includes three core bars, jam plates, is recessed card slot in the middle part of the side wall of every core bar, three in chamber piece Core bar or so is arranged in parallel, tri- rod aperture of chamber Zhong You, and the corresponding rod aperture of every core bar, the waist of three rod aperture is connected simultaneously Lockhole is formed, jam plate is built in lockhole, and jam plate is welded with draw bar, and the outer rod end of draw bar is exported from wall and as manipulation Bar, jam plate can move under the guidance of control stick in lockhole, be bored on jam plate there are three round boom hole, core bar can be attached at Movement is realized in magnet traction on metope, when needing to stretch out core bar, makes the round boom on jam plate by the control of control stick Hole and the indoor rod aperture of chamber align, at this point, core bar can be mobile to the outlet end of rod aperture, the head end of core bar, which can be finally embedded in, is located at bottom In lockhole on plate body or bearing column side wall, at this point, the control by control stick enables the round boom hole on jam plate to block Card slot in the middle part of the every core bar side wall in position finally realizes the purpose tightly locked.
The beneficial effects of the present invention are it has the characteristics that structure novel, assembling are flexible, practical.
Present invention will be further explained below with reference to the attached drawings and examples.
Detailed description of the invention
Fig. 1 is exploded structure dissection figure of the present invention;
Fig. 2 is local overlooking structural perspective of the present invention;
Fig. 3 is exploded cross-sectional view of the structure between wall and bottom-plate body in the present invention.
In figure: A1- bearing column, A11- cylinder type sleeve one, A12- cylinder type sleeve two, the rectangular caulking groove of A13-, A14- transverse direction pin hole two, A2- top plate body, A3- bottom-plate body, A31- lockhole, A4- crossbeam, the vertical hitching post of B1- second, C1- second are sold Bar, D1- rectangular horizontal even steel plate, E- wall, F1- core bar, F2- jam plate, F21- circle boom hole.
Specific embodiment
As shown in Figure 1, Figure 2, Figure 3 shows, a kind of prefabricated buildings, it be by cuboid-type frame, crossbeam A4, top plate body A2, Bottom-plate body A3, wall E, vertical hitching post, pin rod, rectangular horizontal even steel plate D1, core bar F1, jam plate F2 composition, which is characterized in that
Cuboid-type frame includes eight bearing column A1, and eight bearing column A1 are arranged in a manner of three rows, front first Row, one row of rear are the bearing column of left, center, right three, and an intermediate row is then two bearing columns in left and right;
There is top plate body A2 in the upper end formed by integrally casting of eight bearing column A1, the steel bar framework inside every bearing column A1 Top be connected with steel bar framework in top plate body A2, the top surface of the top plate body A2 of pouring molding is equipped with one layer of waterproof layer, top Thickness≤15cm of plate body A2;
Formed by integrally casting is gone back between the upper end of adjacent bearing column A1 crossbeam A4, the steel bar framework inside crossbeam A4 and every Steel bar framework inside root bearing column A1 is connected;
There is bottom-plate body A3 in the lower end formed by integrally casting of eight bearing column A1, the steel bar framework inside every bearing column A1 Bottom end be connected with steel bar framework in bottom-plate body A3, be embedded with water pipe inside the bottom-plate body A3 of pouring molding and electric wire walk Pipe;
Integrally formed with one A11 of cylinder type sleeve, each load-bearing is vertical for the bottom of each bearing column A1 For the side wall lower ends of column A1 there are a lateral pin hole one, the upper semisection of the first vertical hitching post can be inserted upwardly into the cylindrical body jacket In one A11 of cylinder, integrally formed with upper and lower twice, laterally concatenation through-hole one, the first pin rod can be inserted into cross to every first vertical hitching post The realization concatenation of through-hole one can be concatenated into pin hole one and with the transverse direction of the first vertical hitching post upper semisection;
The lower semisection for being connected to the first vertical hitching post of the bottom of bearing column A1 can be with ground or holding positioned at lower layer The top of weight column A1, which is realized, to be fastenedly connected;
Integrally formed with two A12 of cylinder type sleeve, each load-bearing is vertical at the top of each bearing column A1 For the sidewall upper of column A1 there are two A14 of lateral pin hole, the lower semisection of the second vertical hitching post B1 can be downwardly into the cylinder In two A12 of figure sleeve, every second vertical hitching post B1 laterally concatenates through-hole two, the second pin rod integrally formed with upper and lower twice C1, which can be inserted into lateral two A14 of pin hole and can concatenate through-hole two with the transverse direction of the second vertical hitching post B1 lower semisection, realizes concatenation;
When lifting by crane cuboid-type frame, the second pin rod C1 can be as lifting fulcrum after being inserted into two A14 of lateral pin hole;
The upper semisection for being connected to the second vertical hitching post B1 at the top of bearing column A1 can be with the bearing column positioned at upper layer It realizes and is fastenedly connected in the bottom of A1;
After in front of left side the left side wall of three bearing columns and before right side in after three bearing columns The equal indwelling of right side wall have the upper and lower two rectangular caulking groove A13 with round keyhole, rectangular horizontal even steel plate D1 is integrally formed with left and right Two round series winding holes, half section of rectangular horizontal even half section of a left side of steel plate D1 or the right side can be embedded in the rectangular caulking groove with round keyhole Realize locking in A13 and by bolt, the other half section of rectangular horizontal even steel plate D1 then with another group of cuboid-type positioned at side The rectangular caulking groove with round keyhole on frame realizes connection, to realize that the fastening side by side of two groups of left and right cuboid-type frame connects It connects;
Wall E is installed, wall E is reserved with as needed for installing window or door between adjacent bearing column A1 Hole, between the bottom edge and bottom-plate body A3 of wall E by left and right two cover locking mechanisms realization be fastenedly connected, the left side of wall E And it is fastenedly connected between right edge and the side wall of bearing column A1 by the realization of upper and lower two cover locking mechanism, the bottom edge of wall E And left and right sides are reserved with the chamber for built-in retaining mechanism;
Retaining mechanism includes three core bar F1, jam plate F2, is recessed card slot in the middle part of the side wall of every core bar F1, in chamber Arranged in parallel, tri- rod aperture of chamber Zhong You of three core bar F1 or so, the corresponding rod aperture of every core bar F1, the waist of three rod aperture Portion is connected and forms lockhole, and jam plate F2 is built in lockhole, and jam plate F2 is welded with draw bar, and the outer rod end of draw bar is from wall E It exports and as control stick, jam plate F2 can be moved under the guidance of control stick in lockhole, bore that there are three round strings on jam plate F2 Rod aperture F21, core bar F1 can be attached at the traction of the magnet on metope and realize movement, when needing to stretch out core bar F1, pass through manipulation The control of bar aligns round boom hole F21 and the indoor rod aperture of chamber on jam plate F2, at this point, core bar F1 can be to the outlet of rod aperture End movement, the head end of core bar F1 can be finally embedded in the lockhole A31 on bottom-plate body A3 or bearing column A1 side wall, this When, keep the card slot in the middle part of every core bar F1 side wall of the round boom hole detent on jam plate F2 finally real by the control of control stick The purpose now tightly locked.

Claims (1)

1. a kind of prefabricated buildings, it is by cuboid-type frame, crossbeam (A4), top plate body (A2), bottom-plate body (A3), wall (E), vertical hitching post, pin rod, rectangular horizontal even steel plate (D1), core bar (F1), jam plate (F2) composition, which is characterized in that
Cuboid-type frame includes eight bearing columns (A1), and eight bearing columns (A1) are arranged in a manner of three rows, front first Row, one row of rear are the bearing column of left, center, right three, and an intermediate row is then two bearing columns in left and right;
Have top plate body (A2) in the upper end formed by integrally casting of eight bearing columns (A1), the internal reinforcing steel bar frame of every bearing column (A1) The top of frame is connected with steel bar framework in top plate body (A2), and the top surface of the top plate body (A2) of pouring molding is equipped with one layer of waterproof Layer, thickness≤15cm of top plate body (A2);
Going back formed by integrally casting between the upper end of adjacent bearing column (A1) has crossbeam (A4), the internal steel bar framework of crossbeam (A4) with The internal steel bar framework of every bearing column (A1) is connected;
Have bottom-plate body (A3) in the lower end formed by integrally casting of eight bearing columns (A1), the internal reinforcing steel bar frame of every bearing column (A1) The bottom end of frame is connected with steel bar framework in bottom-plate body (A3), is embedded with water pipe and electric wire inside the bottom-plate body (A3) of pouring molding Walk pipe;
Integrally formed with a cylinder type sleeve one (A11), each load-bearing is vertical for the bottom of each bearing column (A1) For the side wall lower ends of column (A1) there are a lateral pin hole one, the upper semisection of the first vertical hitching post can be inserted upwardly into the cylinder type In sleeve one (A11), integrally formed with upper and lower twice, laterally concatenation through-hole one, the first pin rod can be inserted every first vertical hitching post Enter in lateral pin hole one and through-hole one can be concatenated with the transverse direction of the first vertical hitching post upper semisection and realizes concatenation;
The lower semisection for being connected to the first vertical hitching post of the bottom of bearing column (A1) can be with ground or positioned at the load-bearing of lower layer It realizes and is fastenedly connected in the top of column (A1);
Integrally formed with a cylinder type sleeve two (A12), each load-bearing is vertical at the top of each bearing column (A1) There are a lateral pin hole two (A14), the lower semisection of the second vertical hitching post (B1) can be downwardly into the sidewall upper of column (A1) In the cylinder type sleeve two (A12), every second vertical hitching post (B1) laterally concatenates through-hole integrally formed with upper and lower twice Two, the second pin rod (C1) can be inserted into lateral pin hole two (A14) and can go here and there with the transverse direction of the second vertical hitching post (B1) lower semisection It connects hole two and realizes concatenation;
When lifting by crane cuboid-type frame, the second pin rod (C1) can be as lifting fulcrum after being inserted into lateral pin hole two (A14);
The upper semisection for being connected to the second vertical hitching post (B1) at the top of bearing column (A1) can be with the bearing column positioned at upper layer (A1) it realizes and is fastenedly connected in bottom;
After in front of left side the left side wall of three bearing columns and before right side in after three bearing columns the right side The equal indwelling of side wall has the upper and lower two rectangular caulking grooves (A13) with round keyhole, and rectangular horizontal even steel plate (D1) is integrally formed with left and right Two round series winding holes, half section of rectangular horizontal even half section of the left side of steel plate (D1) or the right side can be embedded in the rectangular caulking groove with round keyhole (A13) realize locking in and by bolt, the other half section of rectangular horizontal even steel plate (D1) then with it is rectangular positioned at another group of side The rectangular caulking groove with round keyhole on figure frame realizes connection, to realize the tight side by side of two groups of left and right cuboid-type frame It is solidly connected;
Be equipped with wall (E) between adjacent bearing column (A1), wall (E) as needed be reserved with for install window or The hole of door is fastenedly connected between the bottom edge and bottom-plate body (A3) of wall (E) by the realization of two cover locking mechanisms of left and right, wall (E) Left side and right edge and the side wall of bearing column (A1) between by upper and lower two cover locking mechanism realization be fastenedly connected, wall The bottom edge of body (E) and left and right sides are reserved with the chamber for built-in retaining mechanism;
Retaining mechanism includes three core bars (F1), jam plate (F2), is recessed card slot, chamber in the middle part of the side wall of every core bar (F1) In three core bar (F1) left and right it is arranged in parallel, tri- rod aperture of chamber Zhong You, the corresponding rod aperture of every core bar (F1), three bars The waist in hole is connected and forms lockhole, and jam plate (F2) is built in lockhole, and jam plate (F2) is welded with draw bar, draw bar outer bar End exports from wall (E) and as control stick, and jam plate (F2) can move under the guidance of control stick in lockhole, on jam plate (F2) It bores there are three round boom hole (F21), core bar (F1) can be attached at the traction of the magnet on metope and realize movement, when needing to stretch out When core bar (F1), align round boom hole (F21) and the indoor rod aperture of chamber on jam plate (F2) by the control of control stick, core Bar (F1) can be mobile to the outlet end of rod aperture, and the head end of core bar (F1), which can be finally embedded in, is located at bottom-plate body (A3) or bearing column (A1) in the lockhole on side wall (A31), round boom hole every core of detent on jam plate (F2) is enable by the control of control stick Card slot in the middle part of bar (F1) side wall finally realizes the purpose tightly locked.
CN201810475993.6A 2018-05-17 2018-05-17 A kind of prefabricated buildings Active CN108678179B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810475993.6A CN108678179B (en) 2018-05-17 2018-05-17 A kind of prefabricated buildings

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810475993.6A CN108678179B (en) 2018-05-17 2018-05-17 A kind of prefabricated buildings

Publications (2)

Publication Number Publication Date
CN108678179A CN108678179A (en) 2018-10-19
CN108678179B true CN108678179B (en) 2019-10-29

Family

ID=63806666

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810475993.6A Active CN108678179B (en) 2018-05-17 2018-05-17 A kind of prefabricated buildings

Country Status (1)

Country Link
CN (1) CN108678179B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111676802B (en) * 2018-12-11 2021-09-14 江山市发发科技有限公司 Bridge plate and pier connecting structure of prefabricated bridge

Family Cites Families (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06117022A (en) * 1992-10-06 1994-04-26 Shokusan Jutaku Sogo Co Ltd Structural fitting for wooden architecture
BR9407011A (en) * 1993-07-08 1996-08-06 Leftminster Pty Ltd Prefabricated building system
CN2632183Y (en) * 2003-03-11 2004-08-11 陈来 Normalized assembled house
JP4080419B2 (en) * 2003-12-01 2008-04-23 積水ハウス株式会社 Mounting structure of the joint fitting at the beam-column joint
CN100402765C (en) * 2004-12-24 2008-07-16 张东川 Box shaped house model of construction and fabricating method
EP1859108B1 (en) * 2005-03-17 2011-08-10 Wolf Modul GmbH Frames for buildings
CN202706198U (en) * 2012-04-01 2013-01-30 杨东佐 Building structure
CN203769069U (en) * 2014-02-26 2014-08-13 山东大学 Rapidly-assembled integrated house
KR102392409B1 (en) * 2014-04-30 2022-04-29 지-모듈러 홀딩, 인크. Structural modular building connector
CN104563288B (en) * 2014-10-30 2017-02-15 徐曼 Reinforced concrete frame gridding slab prefabricated energy-saving house
CN206245469U (en) * 2016-12-06 2017-06-13 浙江汉农建设有限公司 Assembled beam frame structure

Also Published As

Publication number Publication date
CN108678179A (en) 2018-10-19

Similar Documents

Publication Publication Date Title
CN106522372B (en) A kind of hybrid integrated house and construction method
CN108678179B (en) A kind of prefabricated buildings
CN205024993U (en) Whole stair
CN207369673U (en) A kind of Combined flower bed
CN104652608A (en) Assembly type exterior wall and beam connecting structure
CN209468856U (en) A kind of assembly concrete column beam connecting node
CN105839566A (en) Stand column of glass fiber reinforced plastic protective fence and protective fence
CN207419867U (en) Steel house panel splicing module
CN203113514U (en) Combined split-mounting-type house device
CN109798020A (en) A kind of Prefabricated enclosure wall structure
CN201835439U (en) Concrete column with steel pipe
CN217481708U (en) Plastic expansion pipe
JP6676129B2 (en) block
CN106761254B (en) A kind of modular house door and window of buckle structure
CN201003212Y (en) Movable supporting bracket
CN201172949Y (en) Connecting piece for floor
CN106013421B (en) A kind of method of construction of the compound assembled fiber concrete building of steel wood
CN205224269U (en) Can assemble roof beam and post module into building frame
CN211622867U (en) Assembled enclosure and modularization enclosure unit thereof
RU73904U1 (en) BORDER POST
CN220301795U (en) Prefabricated forming die in bathroom
CN218116907U (en) Assembled building floor
CN203625931U (en) Combined type cable pit
CN103046554A (en) Construction method for improving integrity and lateral rigidity of double-row supporting piles of foundation pit
CN201786083U (en) Waterproof ring for fence

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant