CN108660930A - A kind of end template integral hoisting method - Google Patents

A kind of end template integral hoisting method Download PDF

Info

Publication number
CN108660930A
CN108660930A CN201810400196.1A CN201810400196A CN108660930A CN 108660930 A CN108660930 A CN 108660930A CN 201810400196 A CN201810400196 A CN 201810400196A CN 108660930 A CN108660930 A CN 108660930A
Authority
CN
China
Prior art keywords
template
girder steel
integral hoisting
scaffold
end template
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810400196.1A
Other languages
Chinese (zh)
Other versions
CN108660930B (en
Inventor
尹景燕
安秀山
张长财
刘俊
付培培
王祾
刘泳志
翟永贞
吴浩
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Cccc First Navigation Bureau Southwest Engineering Co ltd
CCCC First Harbor Engineering Co Ltd
No 1 Engineering Co Ltd of CCCC First Harbor Engineering Co Ltd
Original Assignee
CCCC First Harbor Engineering Co Ltd
No 1 Engineering Co Ltd of CCCC First Harbor Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC First Harbor Engineering Co Ltd, No 1 Engineering Co Ltd of CCCC First Harbor Engineering Co Ltd filed Critical CCCC First Harbor Engineering Co Ltd
Priority to CN201810400196.1A priority Critical patent/CN108660930B/en
Publication of CN108660930A publication Critical patent/CN108660930A/en
Application granted granted Critical
Publication of CN108660930B publication Critical patent/CN108660930B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2/00Bridges characterised by the cross-section of their bearing spanning structure
    • E01D2/04Bridges characterised by the cross-section of their bearing spanning structure of the box-girder type

Abstract

The step of present invention is a kind of end template integral hoisting method, end template integral hoisting be:1. the silk support to scaffold is adjusted;2. the assembled single-chip template completed is hung to corresponding position on bridge, after template center line is aligned with center line on operation platform using line pendant whereabouts template to scaffold Si Tuonei;3. the girder steel of template bottom is connect with silk support, girder steel is equipped with eyelet;4. installing remaining template successively by the above process, formation construction channel is connected using bamboo slab rubber temporarily between each single-chip template;5. survey crew sets and elevation setting-out in the enterprising line position of template, thin portion adjustment is carried out to template position absolute altitude according to setting-out result;6. starting large area after the completion of adjustment is laid with bamboo slab rubber panel.The present invention uses steel wood articulated system, ground spliced molding, Integral Lifting Technology technique, all bed dies to be begun preparing for before going into operation at the scene, and spicing forming type, substantially increases construction efficiency at the scene.

Description

A kind of end template integral hoisting method
Technical field
The present invention relates to technical field of bridge engineering more particularly to a kind of end template integral hoisting methods.
Background technology
Commonly used cast-in-situ box girder structure is the bridge box and beam structure within 150m, and it is prefabricated that the country mostly uses single span single-unit The structure of installation, being influenced by region limitation, prefabricated fabricating yard limitation etc. due to, cast-in-situ box girder structure may be used, Cast-in-situ box girder is also the structure applied to science of bridge building, especially in the case where place is limited or complex environment, cast-in-place afterward stretch box beam Using will be more and more.
It needs to use end template during cast-in-place afterward stretch box beam, end template is the basis of cast-in-situ box girder technology, good Bed die plate technique determines the engineering design of cast-in-situ box girder technology, working procedure, construction budget etc..So end template engineering Construction technology is most important, it is concerning the quality to whole building engineering.
Originally, end template engineering is that concrete blinding not only expends material, also delay engineering because it cannot be recycled The time of construction, labor intensive and material resources.Early in the twentieth century, there is assembled sizing plank sheathing, be conducive to making again for template With, so that the development of template is had big leap, it is subsequent machine-building occur again, thus instead of handmade, greatly save Time, in the 1960s, there is Combined type sizing template.Later, with the gradual development of end template engineering technology, The technology of end template engineering is also more and more ripe, keeps engineering construction more flexible.
End template engineering technology mostly uses the raw materials group such as timber, steel plate and glued board and builds up panel body system and support system. After engineering, which is then needed to be removed using long crowbar, only from project cost, the engineering is just The 15-30% of overall cost is accounted for, which has a very important role for whole bridge construction engineering.
End template engineering technology will meet building foundation requirement, need to keep building from installation quality, when installation Shape and position, it is ensured that sealing not spillage;From security performance, bearing capacity, rigidity and stability are taken into account;From economy From the point of view of angle, need to meet assembly and disassembly simplicity, nonexpondable requirement.
For 33 construction of cast-in-situ box-beam, quantities is huge, if scene carries out the assembly of bed die after having set up scaffold, Construction safety restraining factors are big, inefficiency.
Invention content
Present invention seek to address that the deficiencies in the prior art, and a kind of end template integral hoisting method is provided.
The present invention to achieve the above object, using following technical scheme:A kind of end template integral hoisting method, feature exist It is as follows in, the end template integral hoisting the step of:
1. adjusting
The silk support of scaffold is adjusted according to calculating absolute altitude first, survey crew is in scaffold construction after the completion of adjusting Bridge center line is released on platform;
2. single-chip template is hung oneself
The assembled single-chip template completed is hung to corresponding position on bridge with crane, using line pendant by template center line with apply On work platform center line alignment after whereabouts template to scaffold Si Tuonei;
3. connecting
It being buckled with dovetail and connect the girder steel of template bottom with the silk support, the girder steel is a kind of porous girder steel of hollow out, The girder steel is equipped with eyelet, and the eyelet is for fixation and connection between the girder steel and other supplementary materials, the steel The connection of the corner of beam is connected using bent angle girder steel, and the support of the girder steel uses retractable support lever, is connected in Lin Bianchu Security protection scaffold tubes play and face side safety protection function;
4. splicing installation
Remaining template is installed successively by the above process, remaining template includes wooden frame and scaffold, on the wooden frame side wall Groove is each provided at the both ends in portion, the girder steel is fixedly connected in the groove;
Formation construction channel is connected using bamboo slab rubber temporarily between each single-chip template, is carried out using fillet device at fillet Fillet processing;
5. thin portion adjusts
Installation is complete and after connecting, survey crew sets and elevation setting-out in the enterprising line position of template, according to setting-out for all templates As a result thin portion adjustment is carried out to template position absolute altitude;
6. being laid with
Start large area after the completion of adjustment and be laid with the bamboo slab rubber panel, so that all templates is connected, complete box beam bottom The laying of plate.
Particularly, the step 2. in crane be 25t.
Particularly, the step 3. in girder steel be RMD main body girder steels.
Particularly, the step 3. in the cross sectional dimensions of girder steel be 225*176mm, the bending strength of the girder steel is 4020KN/m2
Particularly, the step 4. in the cross sectional dimensions of wooden frame be 150*65mm, the bending strength of the wooden frame is 186KN/m2
Particularly, the step 4. in depth of groove be 9mm.
Particularly, the step 4. in fillet device be first spread three-ply board, then nail on one on the three-ply board surface Layer galvanized iron sheet.
The beneficial effects of the invention are as follows:The present invention uses steel wood articulated system, ground spliced molding, Integral Lifting Technology work Skill, all bed dies are begun preparing for before going into operation at the scene, and spicing forming type, in advance carries out an acceptance inspection to various sizes at the scene, and nothing is asked After topic while scaffold building, the integral hoisting of bed die is carried out, construction efficiency is substantially increased.
Description of the drawings
Fig. 1 is the vertical view of the present invention;
Fig. 2 is the partial enlarged view at A in Fig. 1;
Fig. 3 is the cross-sectional view of the present invention;
Fig. 4 is the partial enlarged view at B in Fig. 3
In figure:1- security protection scaffold tubes;2- bamboo slab rubbers;3- fillet devices;4- bent angle girder steels;5- retractable support levers; 6- wooden frames;7- girder steels;8- scaffolds;
It is described in detail with reference to attached drawing below with reference to the embodiment of the present invention.
Specific implementation mode
The invention will be further described with reference to the accompanying drawings and examples:
As shown in Figs 1-4, a kind of end template integral hoisting method, which is characterized in that the step of the end template integral hoisting It is rapid as follows:
1. adjusting
The silk support of scaffold 8 is adjusted according to calculating absolute altitude first, survey crew applies in scaffold 8 after the completion of adjusting Bridge center line is released on work platform;
2. single-chip template is hung oneself
The assembled single-chip template completed is hung to corresponding position on bridge with crane, using line pendant by template center line with apply On work platform center line alignment after whereabouts template to scaffold 8 Si Tuonei;
3. connecting
It is buckled with dovetail and connect the girder steel 7 of template bottom with the silk support, the girder steel 7 is a kind of porous girder steel of hollow out 7, the girder steel 7 is equipped with eyelet, and the eyelet is for fixation and connection between the girder steel 7 and other supplementary materials, institute The connection for stating the corner of girder steel 7 is connected using bent angle girder steel 4, and the support of the girder steel 7 uses retractable support lever 5, is facing It is connected with security protection scaffold tubes 1 at side, plays and faces side safety protection function;
4. splicing installation
Remaining template is installed successively by the above process, remaining template includes wooden frame 6 and scaffold 8,6 side wall of the wooden frame Groove is each provided at the both ends on top, the girder steel 7 is fixedly connected in the groove;
Between each single-chip template using bamboo slab rubber 2 temporarily connection formed construction channel, at fillet using fillet device 3 into The processing of row fillet;
5. thin portion adjusts
Installation is complete and after connecting, survey crew sets and elevation setting-out in the enterprising line position of template, according to setting-out for all templates As a result thin portion adjustment is carried out to template position absolute altitude;
6. being laid with
Start large area after the completion of adjustment and be laid with 2 panel of bamboo slab rubber, so that all templates is connected, complete box beam bottom The laying of plate.
Particularly, the step 2. in crane be 25t.
Particularly, the step 3. in girder steel 7 be RMD main body girder steels.
Particularly, the step 3. in the cross sectional dimensions of girder steel 7 be 225*176mm, the bending strength of the girder steel 7 is 4020KN/m2
Particularly, the step 4. in wooden frame 6 cross sectional dimensions be 150*65mm, bending strength 186KN/m2
Particularly, the step 4. in depth of groove be 9mm.
Particularly, the step 4. in fillet device 3 be first spread three-ply board, then nail on one on the three-ply board surface Layer galvanized iron sheet.
When the present invention works, all bed dies are begun preparing for before going into operation at the scene, at the scene spicing forming type, in advance to various Size carries out an acceptance inspection, and after no problem, while scaffold 8 is set up, carries out the integral hoisting of end template, substantially increases construction Efficiency, before construction, it is necessary to which stringent demonstration ensures the stability of end template entirety, the connection fastener and intensity of all end templates Rigidity passes through stringent calculating, ensures the stability of whole bed die, ensures Hoisting Security.
The present invention is exemplarily described above in conjunction with attached drawing, it is clear that the present invention implements not by aforesaid way Limitation, as long as using the various improvement of inventive concept and technical scheme of the present invention progress, or not improved direct application In other occasions, within protection scope of the present invention.

Claims (7)

1. a kind of end template integral hoisting method, which is characterized in that the step of end template integral hoisting is as follows:
1. adjusting
The silk support of scaffold (8) is adjusted according to calculating absolute altitude first, survey crew applies in scaffold (8) after the completion of adjusting Bridge center line is released on work platform;
2. single-chip template is hung oneself
The assembled single-chip template completed is hung to corresponding position on bridge with crane, it is using line pendant that template center line is flat with construction On platform center line alignment after whereabouts template to scaffold (8) Si Tuonei;
3. connecting
It is buckled with dovetail and connect the girder steel (7) of template bottom with the silk support, the girder steel (7) is a kind of porous girder steel of hollow out (7), the girder steel (7) is equipped with eyelet, and the eyelet is used for the fixation between the girder steel (7) and other supplementary materials and company It connects, the connection of the corner of the girder steel (7) is connected using bent angle girder steel (4), and the support of the girder steel (7) uses scalable branch Strut (5) is connected with security protection scaffold tubes (1) in Lin Bianchu;
4. splicing installation
Remaining template is installed successively by the above process, remaining template includes wooden frame (6) and scaffold (8), wooden frame (6) side Groove is each provided at the both ends on wall top, the girder steel (7) is fixedly connected in the groove;
Between each single-chip template using bamboo slab rubber (2) temporarily connection formed construction channel, at fillet using fillet device (3) into The processing of row fillet;
5. thin portion adjusts
Installation is complete and after connecting, survey crew sets and elevation setting-out in the enterprising line position of template, according to setting-out result for all templates Thin portion adjustment is carried out to template position absolute altitude;
6. being laid with
Start large area after the completion of adjustment and be laid with bamboo slab rubber (2) panel, so that all templates is connected, complete box beam bottom plate Laying.
2. a kind of end template integral hoisting method according to claim 1, which is characterized in that the step 2. in lifting Machine is 25t.
3. a kind of end template integral hoisting method according to claim 2, which is characterized in that the step 3. in girder steel (7) it is RMD main body girder steels.
4. a kind of end template integral hoisting method according to claim 3, which is characterized in that the step 3. in girder steel (7) cross sectional dimensions is 225*176mm, and the bending strength of the girder steel (7) is 4020KN/m2
5. a kind of end template integral hoisting method according to claim 4, which is characterized in that the step 4. in wooden frame (6) cross sectional dimensions is 150*65mm, and the bending strength of the wooden frame (6) is 186KN/m2
6. a kind of end template integral hoisting method according to claim 5, which is characterized in that the step 4. in groove Depth is 9mm.
7. a kind of end template integral hoisting method according to claim 6, which is characterized in that the step 4. in fillet Device (3) is first to spread three-ply board, then follows closely last layer galvanized iron sheet on the three-ply board surface.
CN201810400196.1A 2018-04-28 2018-04-28 Bottom template integral hoisting method Active CN108660930B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810400196.1A CN108660930B (en) 2018-04-28 2018-04-28 Bottom template integral hoisting method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810400196.1A CN108660930B (en) 2018-04-28 2018-04-28 Bottom template integral hoisting method

Publications (2)

Publication Number Publication Date
CN108660930A true CN108660930A (en) 2018-10-16
CN108660930B CN108660930B (en) 2020-06-23

Family

ID=63781365

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810400196.1A Active CN108660930B (en) 2018-04-28 2018-04-28 Bottom template integral hoisting method

Country Status (1)

Country Link
CN (1) CN108660930B (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101333801A (en) * 2007-06-25 2008-12-31 中铁二十局集团有限公司 Cast-in-situ beam-making construction method of assembled support
KR20100034097A (en) * 2008-09-23 2010-04-01 삼표이앤씨 주식회사 Carriage system used for manufacturing u-typed channel brige
CN103382702A (en) * 2013-07-11 2013-11-06 中国建筑第六工程局有限公司 Cast-in-situ box grider bracket and constructing method thereof
CN104963290A (en) * 2015-07-08 2015-10-07 杭州江润科技有限公司 Mold supporting structure for variable cross-section cast-in-place box girder at section combining horizontal and longitudinal curves, and construction method of the mold supporting structure
CN106120561A (en) * 2016-07-04 2016-11-16 中国三冶集团有限公司 A kind of cast-in-situ box girder template construct installation method
CN107916623A (en) * 2017-12-22 2018-04-17 宁波二十冶建设有限公司 A kind of bent cap elevation adjusting device and adjusting method

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101333801A (en) * 2007-06-25 2008-12-31 中铁二十局集团有限公司 Cast-in-situ beam-making construction method of assembled support
KR20100034097A (en) * 2008-09-23 2010-04-01 삼표이앤씨 주식회사 Carriage system used for manufacturing u-typed channel brige
CN103382702A (en) * 2013-07-11 2013-11-06 中国建筑第六工程局有限公司 Cast-in-situ box grider bracket and constructing method thereof
CN104963290A (en) * 2015-07-08 2015-10-07 杭州江润科技有限公司 Mold supporting structure for variable cross-section cast-in-place box girder at section combining horizontal and longitudinal curves, and construction method of the mold supporting structure
CN106120561A (en) * 2016-07-04 2016-11-16 中国三冶集团有限公司 A kind of cast-in-situ box girder template construct installation method
CN107916623A (en) * 2017-12-22 2018-04-17 宁波二十冶建设有限公司 A kind of bent cap elevation adjusting device and adjusting method

Also Published As

Publication number Publication date
CN108660930B (en) 2020-06-23

Similar Documents

Publication Publication Date Title
CN209620585U (en) Strip, which is poured, after a kind of assembled architecture laminated floor slab hangs die body system
CN105696789A (en) Vertical aluminum mould building system and construction method thereof
CN105544887B (en) A kind of construction method of tang style simulation building wing angle cornice
CN206352391U (en) Socket joint type key slot type Quick Release support system
CN108643558A (en) The type steel bar truss floor support plate and construction method of the detachable end template of welded type
CN106088480B (en) Girder truss, the combination beam using girder truss and the compound superstructure using girder truss
CN110439265A (en) Bilateral column or wall method for synchronously constructing at a kind of narrow expansion joint
CN113323216A (en) Support-free laminated slab and construction method thereof
CN203878995U (en) Side wall stair formwork
CN109403200A (en) The construction method and its small box girder bridge of the small box girder bridge poured after a kind of partition
CN101761232A (en) Construction technology of large-scale fair-faced concrete cylindrical structural part with paper tube template
CN108660930A (en) A kind of end template integral hoisting method
CN205839568U (en) A kind of cast-in-situ box girder model sheetinstallat structure
CN110499857A (en) A kind of precast concrete superimposed sheet vertically goes out the installation method of muscle and readjustment
CN207048314U (en) A kind of shaping type stair wooden model board component
CN105908883A (en) Construction method for preventing upward floating of composite floor system lightweight core formwork
CN103541548B (en) Fish belly sill construction method
CN205476468U (en) Non - design, can all rotary die plate bodys be prefabricated staircase bench template
CN204418666U (en) A kind of building site is with there being side wall stair template
CN104405069B (en) A kind of curved surface hollow top board and construction method thereof
CN108999326A (en) Light steel grating concrete folding plate
CN103967188B (en) Special-shaped sculpture modeling ceiling assembled type installation structure
CN206942134U (en) A kind of embedded stair template device
CN204626965U (en) For the steel stair template of poured up at a time between architectural stair
CN209686249U (en) A kind of longitudinal prestressing stretching end anchor device structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20220901

Address after: 7th Floor, Dongsheng Building, No. 39, Shuangyong Road, Yulin City, Guangxi Zhuang Autonomous Region 537000

Patentee after: CCCC first navigation bureau Southwest Engineering Co.,Ltd.

Patentee after: NO.1 ENGINEERING COMPANY CO., LTD. OF CCCC FIRST HARBOR ENGINEERING Co.,Ltd.

Patentee after: CCCC First Harbor Engineering Co.,Ltd.

Address before: 300456 No. 14, room 300, Xingang, Tianjin Free Trade Zone (central business district), Binhai New Area, Tianjin

Patentee before: NO.1 ENGINEERING COMPANY CO., LTD. OF CCCC FIRST HARBOR ENGINEERING Co.,Ltd.

Patentee before: CCCC First Harbor Engineering Co.,Ltd.