CN108625296A - One kind installing linear control method for precast segment bridge - Google Patents

One kind installing linear control method for precast segment bridge Download PDF

Info

Publication number
CN108625296A
CN108625296A CN201810673199.2A CN201810673199A CN108625296A CN 108625296 A CN108625296 A CN 108625296A CN 201810673199 A CN201810673199 A CN 201810673199A CN 108625296 A CN108625296 A CN 108625296A
Authority
CN
China
Prior art keywords
beam sections
measuring point
coordinate
piece
sections
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810673199.2A
Other languages
Chinese (zh)
Other versions
CN108625296B (en
Inventor
石雪飞
宋军
刘志权
李小祥
朱荣
余曾
巴文鹏
凌坡
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Baini Engineering Consulting Co Ltd
Original Assignee
Shanghai Baini Engineering Consulting Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Baini Engineering Consulting Co Ltd filed Critical Shanghai Baini Engineering Consulting Co Ltd
Priority to CN201810673199.2A priority Critical patent/CN108625296B/en
Publication of CN108625296A publication Critical patent/CN108625296A/en
Application granted granted Critical
Publication of CN108625296B publication Critical patent/CN108625296B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The present invention relates to one kind installing linear control method for precast segment bridge, after the completion of segment girder precast, installs measuring point, measures coordinate of the measuring point under factory's coordinate system, converted by coordinate, measuring point coordinate of the beam sections under mounting coordinate system is calculated;After first beam sections is installed, measures measuring point coordinate and verified with the coordinate being calculated, ensure error≤± 2mm, first beam sections is fixed temporarily with pier top block;According to it is existing it is linear carry out Coordinates after installation is complete in three pieces beam sections, measure the mounting coordinate of third piece beam sections, compared with the measuring point coordinate for calculating third piece beam sections, if the error of third piece beam sections>± 2mm, first beam of releasing are fixed temporarily, and realize that the unitary rotation of three pieces beam sections retightens first beam sections in error≤± 2mm of third piece beam sections.The method of the present invention can effectively reduce the frequency of use of gasket, can improve the durability of seam with the construction quality of control joint.

Description

One kind installing linear control method for precast segment bridge
Technical field
The present invention relates to method for bridge construction, and linear controlling party is installed for precast segment bridge more particularly, to one kind Method.
Background technology
Measurement error can not completely eliminate in being positioned due to reference block, if there are still larger spaces after carrying out positioning adjustment Position deviation can cause follow-up beam section to install linear deviation and persistently amplify.The method used in traditional beam section alignment control It is to increase gasket after the completion of a piece of erection in seam crossing and adjusted into line displacement, after meeting needs, then carry out down a piece of beam Assembly.But such method is related to the problem of gasket usage quantity, not only influences the construction quality and durability of seam, goes back shadow Ring construction efficiency.
Invention content
The purpose of the present invention installs linear offset to control precast segment beam, and provides a kind of for precast segment bridge Linear control method is installed.
Since when carrying out beam sections positioning, measurement error can not completely eliminate, and there are still larger space positions after positioning Deviation, therefore persistently amplify to avoid follow-up beam section from installing linear deviation proposes a kind of erection stage three pieces beam unitary rotation Method of adjustment is linear to reference block to be optimized, and it is linear to control beam section by three pieces unitary rotation adjusting method.
The purpose of the present invention can be achieved through the following technical solutions:
One kind installing linear control method for precast segment bridge, includes the following steps:
After the completion of segment girder precast, measuring point is installed, coordinate of the measuring point under factory's coordinate system is measured, turned by coordinate It changes, measuring point coordinate of the beam sections under mounting coordinate system is calculated;
After first beam sections is installed, measures measuring point coordinate and verified with the coordinate being calculated, guarantee error≤± First beam sections is fixed temporarily by 2mm with pier top block;
According to it is existing it is linear carry out Coordinates after installation is complete in three pieces beam sections, measure the peace of third piece beam sections Coordinate is filled, is compared with the measuring point coordinate for calculating third piece beam sections, if the error of third piece beam sections>± 2mm releases the A piece of beam is fixed temporarily, and using first segment in small-size jack top beam-ends face, realizes the unitary rotation of three pieces beam sections, The error of third piece beam sections≤± 2mm retightens first beam sections.Based on error enlarge-effect, to excessive error into Row adjustment, the error of coordinate of first beam is necessarily satisfying for requiring at this time.
After first beam sections installation meets needs, first beam sections is fixed temporarily with pier top block, continues to pacify Second beam sections is filled, is adhesively fixed between second beam sections and first beam sections;Third piece beam sections, third are installed again It is adhesively fixed between piece beam sections and second beam sections, carries out beam sections installation locking again after Coordinate Adjusting meets needs.
After the completion of segment girder precast, the method for installing measuring point is:6 conventional measuring points are first arranged, in beam sections lateral position Two newly-increased measuring points are set, and 6 conventional measuring points are located at two middle side parts of beam sections using symmetrical structure setting, beam sections Three conventional measuring points are respectively provided with per side, three conventional measuring points are located on the same line, and two newly-increased measuring points are located at beam sections Side is located on the same line with three conventional measuring points of beam sections homonymy.
Two newly-increased measuring points are arranged close to the side of the length direction of beam sections, and the newly-increased specific arrangement principle of measuring point is:Newly Increase distance of the measuring point apart from the nearest side of beam sections width direction, i.e., vertical bridge to distance be 0.05m≤Dz≤0.10m;It is newly-increased Distance of the measuring point apart from the nearest side of beam sections length direction, i.e. direction across bridge distance are 0.05m≤Dh≤0.10m.
When carrying out beam sections positioning, local coordinate system is established, arrangement principle is as follows in local coordinate system:
X-axis:Perpendicular to the two pier lines of centres,
Y-axis:The two pier lines of centres are parallel to,
Origin:Set up the nearest pier center line of beam sections reference block.
In the present invention, after carrying out beam sections reference block positioning, since measurement error can not completely eliminate, at first After the completion of the erection of segment, if error is unsatisfactory for needing, deviation adjusting wouldn't be carried out, three segments are installed according to existing alignment consistency Duan Liang, is based on error linear amplification principle, the angular errors of first beam sections obtained in third piece beam sections it is greatly enlarged, The coordinate that adjustment third piece beam sections are rotated using three pieces beam sections global approach, to control the coordinate of preceding two panels beam sections reasonable In range.
The present invention is to be based on error enlarge-effect to the adjustment of beam sections, by the adjustment to excessive error, come control compared with The deviation of small error.
Method of adjustment is adjusted using three pieces unitary rotation when beam sections are installed, and can effectively reduce gasket uses frequency Rate ensures the construction quality and durability of seam.
Compared with prior art, the present invention has the following advantages and beneficial effects:
1, inventive process ensures that error is in smaller range;
2, three pieces beam unitary rotation adjusts, and is conducive to improve working efficiency.
3, reduce gasket usage quantity, control the construction quality and durability of seam..
Description of the drawings
Fig. 1 is the linear deviation floor map of beam section;
Fig. 2 is the linear longitudinal bias schematic diagram of beam section;
Fig. 3 is the linear deviation adjusting schematic diagram of beam section;
Fig. 4 is beam sections point layout schematic diagram.
Specific implementation mode
The present invention is described in detail with specific embodiment below in conjunction with the accompanying drawings.
Embodiment
With reference to figure 1, Fig. 2, Fig. 3, one kind being installed linear control method for precast segment bridge, included the following steps: After the completion of segment girder precast, measuring point is installed, coordinate of the measuring point under factory's coordinate system is measured, converts, be calculated by coordinate Measuring point coordinate of the beam sections under mounting coordinate system;
After first beam sections 3 is installed, measures measuring point coordinate and verified with the coordinate being calculated, guarantee error≤± First beam sections 3 is fixed temporarily by 2mm with pier top block 1;
Continue that second beam sections 4 is installed, is adhesively fixed between second beam sections 4 and first beam sections 3;It installs again Third piece beam sections 5 are adhesively fixed between third piece beam sections 5 and second beam sections 4, according to existing linear in three pieces segment Beam 3,4,5 carries out Coordinates after installation is complete, measures the mounting coordinate of third piece beam sections 5, and calculates third piece beam sections 5 measuring point coordinate is compared, if the error of third piece beam sections 5>± 2mm, first beam of releasing are fixed temporarily, and utilization is small Type jack 2 pushes up first 3 end face of beam sections, the unitary rotation of three pieces beam sections 3,4,5 is realized, in third piece beam sections 5 Error≤± 2mm retightens first beam sections 3.
With reference to figure 4, after the completion of segment girder precast, the method for installing measuring point is:First arrange 6 conventional measuring point a b c d e F, beam sections lateral position be arranged two newly-increased measuring point g h, 6 conventional measuring points are located at segment using symmetrical structure setting Every side of two middle side parts of beam, beam sections is respectively provided with three conventional measuring points, and three conventional measuring points are located on the same line, two Newly-increased measuring point is located at the side of beam sections, is located on the same line with three conventional measuring points of beam sections homonymy.Two newly-increased Measuring point is arranged close to the side of the length direction of beam sections, and the newly-increased specific arrangement principle of measuring point is:Newly-increased measuring point is apart from beam sections The distance of the nearest side of width direction, i.e., vertical bridge to distance be 0.05m≤Dz≤0.10m;Newly-increased measuring point is apart from segment beam length The distance of the nearest side in direction is spent, i.e. direction across bridge distance is 0.05m≤Dh≤0.10m.
When carrying out beam sections positioning, local coordinate system is established, arrangement principle is as follows in local coordinate system:X-axis:Perpendicular to The two pier lines of centres, Y-axis:It is parallel to the two pier lines of centres, origin:Set up the nearest pier center line of beam sections reference block.
In the present invention, after carrying out beam sections reference block positioning, since measurement error can not completely eliminate, at first After the completion of the erection of segment, if error is unsatisfactory for needing, deviation adjusting wouldn't be carried out, three segments are installed according to existing alignment consistency Duan Liang, is based on error linear amplification principle, the angular errors of first beam sections obtained in third piece beam sections it is greatly enlarged, The coordinate that adjustment third piece beam sections are rotated using three pieces beam sections global approach, to control the coordinate of preceding two panels beam sections reasonable In range.The present invention is to be based on error enlarge-effect to the adjustment of beam sections, smaller to control by the adjustment to excessive error The deviation of error.Method of adjustment is adjusted using three pieces unitary rotation when beam sections are installed, and can effectively reduce making for gasket With frequency, ensure the construction quality and durability of seam.
The above description of the embodiments is intended to facilitate ordinary skill in the art to understand and use the invention. Person skilled in the art obviously easily can make various modifications to these embodiments, and described herein general Principle is applied in other embodiment without having to go through creative labor.Therefore, the present invention is not limited to the above embodiments, ability Field technique personnel announcement according to the present invention, improvement and modification made without departing from the scope of the present invention all should be the present invention's Within protection domain.

Claims (6)

1. one kind installing linear control method for precast segment bridge, which is characterized in that include the following steps:
After the completion of segment girder precast, measuring point is installed, coordinate of the measuring point under factory's coordinate system is measured, is converted by coordinate, counted Calculation obtains measuring point coordinate of the beam sections under mounting coordinate system;
After first beam sections is installed, measures measuring point coordinate and is verified with the coordinate being calculated, ensure error≤± 2mm, First beam sections is fixed temporarily with pier top block;
According to it is existing it is linear carry out Coordinates after installation is complete in three pieces beam sections, the installation for measuring third piece beam sections is sat Mark is compared with the measuring point coordinate for calculating third piece beam sections, if the error of third piece beam sections>± 2mm releases first Beam is fixed temporarily, and realizes the unitary rotation of three pieces beam sections, in error≤± 2mm of third piece beam sections, retightens the A piece of beam sections.
2. according to claim 1 a kind of for precast segment bridge installation linear control method, which is characterized in that first After the installation of piece beam sections meets needs, first beam sections is fixed temporarily with pier top block, continues that second segment is installed Beam is adhesively fixed between second beam sections and first beam sections;Third piece beam sections are installed again, third piece beam sections and the It is adhesively fixed between two beam sections, carries out beam sections installation locking again after Coordinate Adjusting meets needs.
3. according to claim 1 a kind of for precast segment bridge installation linear control method, which is characterized in that segment After the completion of beam prefabricated, the method for installing measuring point is:
It first arranges 6 conventional measuring points, two newly-increased measuring points is set in beam sections lateral position, 6 conventional measuring points are using symmetrical Structure setting be located at two middle side parts of beam sections, every side of beam sections is respectively provided with three conventional measuring points, three conventional measuring point positions In on same straight line, two newly-increased measuring points are located at the side of beam sections, are located at three conventional measuring points of beam sections homonymy same On straight line.
4. according to claim 3 a kind of for precast segment bridge installation linear control method, which is characterized in that two Newly-increased measuring point is arranged close to the side of the length direction of beam sections, and the newly-increased specific arrangement principle of measuring point is:
Newly-increased distance of the measuring point apart from the nearest side of beam sections width direction, i.e., vertical bridge to distance be 0.05m≤Dz≤ 0.10m;
Newly-increased distance of the measuring point apart from the nearest side of beam sections length direction, i.e. direction across bridge distance be 0.05m≤Dh≤ 0.10m。
A kind of linear control method being installed for precast segment bridge 5. according to claim 1, which is characterized in that into When row beam sections position, local coordinate system is established, arrangement principle is as follows in local coordinate system:
X-axis:Perpendicular to the two pier lines of centres,
Y-axis:The two pier lines of centres are parallel to,
Origin:Set up the nearest pier center line of beam sections reference block.
6. according to claim 1 a kind of for precast segment bridge installation linear control method, which is characterized in that utilize The unitary rotation of three pieces beam sections is realized in first segment in small-size jack top beam-ends face.
CN201810673199.2A 2018-06-26 2018-06-26 Installation linear control method for segmental precast bridge Active CN108625296B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810673199.2A CN108625296B (en) 2018-06-26 2018-06-26 Installation linear control method for segmental precast bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810673199.2A CN108625296B (en) 2018-06-26 2018-06-26 Installation linear control method for segmental precast bridge

Publications (2)

Publication Number Publication Date
CN108625296A true CN108625296A (en) 2018-10-09
CN108625296B CN108625296B (en) 2020-01-07

Family

ID=63689307

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810673199.2A Active CN108625296B (en) 2018-06-26 2018-06-26 Installation linear control method for segmental precast bridge

Country Status (1)

Country Link
CN (1) CN108625296B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109440648A (en) * 2018-11-20 2019-03-08 湖南工业大学 Double wet seam precast segment bridge assembly LFM signal devices
CN110777669A (en) * 2019-11-15 2020-02-11 中铁北京工程局集团有限公司 High-speed rail continuous beam short line matching prefabricated cantilever assembly line shape control method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08142034A (en) * 1994-11-24 1996-06-04 Kumagai Gumi Co Ltd Automatic control device of form for short line match casting
CN102733311A (en) * 2012-07-02 2012-10-17 中铁大桥局集团武汉桥梁科学研究院有限公司 Line shape control method for short line method segment prefabrication construction
CN104748732A (en) * 2015-03-26 2015-07-01 广州瀚阳工程咨询有限公司 Measurement method for segmental precast bridge erection field
CN106223201A (en) * 2016-07-26 2016-12-14 中南大学 The method for correcting error of beam section bridge linear monitoring

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08142034A (en) * 1994-11-24 1996-06-04 Kumagai Gumi Co Ltd Automatic control device of form for short line match casting
CN102733311A (en) * 2012-07-02 2012-10-17 中铁大桥局集团武汉桥梁科学研究院有限公司 Line shape control method for short line method segment prefabrication construction
CN104748732A (en) * 2015-03-26 2015-07-01 广州瀚阳工程咨询有限公司 Measurement method for segmental precast bridge erection field
CN106223201A (en) * 2016-07-26 2016-12-14 中南大学 The method for correcting error of beam section bridge linear monitoring

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
黄跃等: "跨海桥梁超高渐变段预制和安装控制技术", 《中国港湾建设》 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109440648A (en) * 2018-11-20 2019-03-08 湖南工业大学 Double wet seam precast segment bridge assembly LFM signal devices
CN110777669A (en) * 2019-11-15 2020-02-11 中铁北京工程局集团有限公司 High-speed rail continuous beam short line matching prefabricated cantilever assembly line shape control method

Also Published As

Publication number Publication date
CN108625296B (en) 2020-01-07

Similar Documents

Publication Publication Date Title
CN103711080B (en) Utilize the method for locating between coordinate method of comparison determination steel pipe arch bridge arch rib
CN107587429B (en) Cord clip of suspension bridge installation site modification method
CN102733545B (en) Section steel column for high-rise building section steel concrete combination structure, and construction method thereof
CN108345318A (en) A kind of beam sections free cantilever erection pier top block installation measurement method
CN103669114B (en) Ballast bed base prefabricated slab and application thereof
CN108625296A (en) One kind installing linear control method for precast segment bridge
CN108678398B (en) Pre-assembly method for steel structure truss of reinforced layer of super high-rise building
CN104110140A (en) Net rack node location adjusting device and location adjusting method
CN103696369B (en) Steel box girder segment four point positioning mounting method
CN106223623A (en) Steel construction box arched roof truss installation method
CN110470193B (en) Method for monitoring relative displacement between box girder and pier
CN203213372U (en) F-shaped hanging piece and suspended ceiling system employing same
CN210395849U (en) Large-span high-section steel truss
CN208734102U (en) A kind of large-span truss assembly sliding construction falsework
CN106869319A (en) Large span steel truss installation method
CN208649894U (en) A kind of steel anchor beam and steel corbel unit spelling moulding bed
CN108914775A (en) A method of it is positioned for beam sections
CN115186328A (en) Line and slope adjusting method for shield tunnel
CN107060832B (en) A kind of vault template and its support construction suitable for the construction of variable cross-section bend cave depot
CN105113418A (en) Construction layout method for bearing pad stone
CN105133500B (en) Without measuring the prefabricated installation method of the prefabricated box-beam sections of tower
CN203361020U (en) Full framing
CN206888999U (en) A kind of vault formwork support structure suitable for the construction of variable cross-section bend cave depot
CN111664832A (en) Method for establishing independent elevation system for bridge construction in area with abnormal and significant gravity
CN102286928B (en) Cableway pipe three-dimensional coordinate controller and manufacturing method thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant