CN105133500B - Without measuring the prefabricated installation method of the prefabricated box-beam sections of tower - Google Patents

Without measuring the prefabricated installation method of the prefabricated box-beam sections of tower Download PDF

Info

Publication number
CN105133500B
CN105133500B CN201510541018.7A CN201510541018A CN105133500B CN 105133500 B CN105133500 B CN 105133500B CN 201510541018 A CN201510541018 A CN 201510541018A CN 105133500 B CN105133500 B CN 105133500B
Authority
CN
China
Prior art keywords
measuring point
beam sections
prefabricated
measuring
prefabricated box
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510541018.7A
Other languages
Chinese (zh)
Other versions
CN105133500A (en
Inventor
王敏
陈鸣
吴玉刚
崖岗
鲜荣
汪存书
邹晖
巫兴发
郑和晖
黄跃
游新鹏
黄灿
彭成明
陈龙
陈少林
邹龙颜
李鑫
曹志
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Provincial Highway Construction Co Ltd
CCCC Second Harbor Engineering Co
China Communications 2nd Navigational Bureau 2nd Engineering Co Ltd
CCCC Highway Long Bridge Construction National Engineering Research Center Co Ltd
Original Assignee
Guangdong Provincial Highway Construction Co Ltd
CCCC Second Harbor Engineering Co
China Communications 2nd Navigational Bureau 2nd Engineering Co Ltd
CCCC Highway Long Bridge Construction National Engineering Research Center Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Provincial Highway Construction Co Ltd, CCCC Second Harbor Engineering Co, China Communications 2nd Navigational Bureau 2nd Engineering Co Ltd, CCCC Highway Long Bridge Construction National Engineering Research Center Co Ltd filed Critical Guangdong Provincial Highway Construction Co Ltd
Priority to CN201510541018.7A priority Critical patent/CN105133500B/en
Publication of CN105133500A publication Critical patent/CN105133500A/en
Application granted granted Critical
Publication of CN105133500B publication Critical patent/CN105133500B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The invention discloses the prefabricated installation method of a kind of prefabricated box-beam sections without measuring tower, comprise the following steps: step one, fixing Side Template is set, adjacent described fixing Side Template pours the first prefabricated box-beam sections, at described first prefabricated box-beam sections surface configuration 4 measuring points A, B, C, D;Step 2, described first prefabricated box-beam sections is moved to position set in advance;Step 3, pouring into a mould the second prefabricated box-beam sections between described first prefabricated box-beam sections and described fixing Side Template, wherein, pouring into a mould the second prefabricated box-beam sections is repeating said steps one;The present invention is by controlling the relative position between the beam prefabricated sections of adjacent tank, realize the Linear Control of prefabricated box-beam sections, avoid prior art use measure tower be controlled install and exist can be moved at weak soil area, variations in temperature region measurement tower frequently and cause bigger error, and this error eventually runs up to bridge completion state, unfavorable to structure stress.

Description

Without measuring the prefabricated installation method of the prefabricated box-beam sections of tower
Technical field
The invention belongs to the prefabricated installation method field of prefabricated box-beam sections, be specifically related to a kind of without measuring tower The prefabricated installation method of prefabricated box-beam sections.
Background technology
Traditional method is to establish two measurement towers of thirty years of age in opposite directions, with the fixing end used by prefabricated short segment Coordinate system is set up on the basis of template, and by measuring tower control coupling beam section end face control point coordinate, with Reach to control the relative space position between matching beam and new precast beam.Measure tower and need to have the highest steady Qualitative, under the operating mode effects such as sedimentation, variations in temperature, keep stable duty, on some weak soil ground Band, variations in temperature are the most regional, use and have the control method measuring tower, can cause bigger error, And this error eventually runs up to bridge completion state, unfavorable to structure stress.And on the other hand, if In order to resist the external and internal compositions that various rough sledding is reinforced or improved measurement tower, cost is the highest.
Summary of the invention
It is an object of the invention to provide the prefabricated installation of a kind of prefabricated box-beam sections without measuring tower Method, the present invention is by controlling the relative position between the beam prefabricated sections of adjacent tank, it is achieved prefabricated box-beam saves Section prefabricated installation, it is to avoid prior art use measure tower be controlled install and exist in weak soil area, Variations in temperature region measurement tower frequently can be moved and cause bigger error, and this error is final Bridge completion state can be run up to, unfavorable to structure stress.
The technical scheme that the present invention provides is:
The prefabricated installation method of a kind of prefabricated box-beam sections without measuring tower, comprises the following steps:
Step one, arranging fixing Side Template, adjacent described fixing Side Template pours the first prefabricated box-beam sections, The web making described first prefabricated box-beam sections is perpendicular to described fixing Side Template, pre-in described first box beam Sections surface configuration processed 2 measuring points A, B, wherein, described measuring point A, measuring point B lay respectively at described Two coxostermums of the first prefabricated box-beam sections are near the top of described fixing Side Template one end;
At described first prefabricated box-beam sections surface configuration 2 measuring points C, D, measuring point C and measuring point D divides It is not positioned at two coxostermums top away from described fixing Side Template one end of described first prefabricated box-beam sections, Measure the distance between any 2 measuring points, respectively L in 4 measuring points A, B, C, DAB、LAC、 LAD、LBC、LBD、LCD, and measure the elevation H of 4 measuring points respectivelyA、HB、HC、HD, determine The position at measuring point A, B, C, D place;
Step 2, described first prefabricated box-beam sections is moved to position set in advance, wherein it is determined that Described position set in advance particularly as follows:
Will be moved into 4 measuring points on described first prefabricated box-beam sections surface of position set in advance respectively Be set to A1, B1, C1, D1, its respectively with measuring point A, B, C, D one_to_one corresponding, surveyed by control Distance L between some A and measuring point A1AA1, distance L between measuring point B and measuring point A1BA1For in advance Value of calculation, and by the elevation of control measuring point A1 for precalculating value, so that it is determined that the position of measuring point A1, By controlling distance L between measuring point A and measuring point B1AB1, distance L between measuring point B and measuring point B1BB1For precalculating value, and by the elevation of control measuring point B1 for precalculating value, so that it is determined that measuring point The position of B1;
By the elevation of control measuring point C1, D1 for precalculating value, so that it is determined that described set in advance Position;
Step 3, between described first prefabricated box-beam sections and described fixing Side Template, pour into a mould the second box beam Prefabricated subsection, wherein, pouring into a mould the second prefabricated box-beam sections is repeating said steps one, and makes described second On prefabricated box-beam sections, two measuring points near described fixing Side Template overlap with described measuring point A, B.
Preferably, the prefabricated installation method of the described prefabricated box-beam sections without measuring tower, measuring point C with Measuring point A is corresponding, is positioned at above the web of the same side, and measuring point B is corresponding with measuring point D, is positioned at opposite side Above web.
Preferably, the prefabricated installation method of the described prefabricated box-beam sections without measuring tower, also include step Rapid four, repeat the above steps one, step 2 and step 3, until completing all of prefabricated box-beam sections Pour.
Preferably, the prefabricated installation method of the described prefabricated box-beam sections without measuring tower, described fixing Side Template is perpendicular to ground and arranges.
The present invention at least includes following beneficial effect: the present invention is by controlling between the beam prefabricated sections of adjacent tank Relative position, it is achieved the prefabricated installation of prefabricated box-beam sections, it is to avoid prior art use measure tower carry out What control was installed and existed can be moved at weak soil area, variations in temperature region measurement tower frequently and draw Play bigger error, and this error eventually runs up to bridge completion state, unfavorable to structure stress;And It is avoided to resist various rough sledding and reinforces or improve the high one-tenth that the external and internal compositions of measurement tower is caused This.
Accompanying drawing explanation
Fig. 1 is that the structure without the prefabricated installation method of the prefabricated box-beam sections measuring tower of the present invention is shown It is intended to.
Detailed description of the invention
The present invention is described in further detail below in conjunction with the accompanying drawings, to make those skilled in the art's reference Description word can be implemented according to this.
As it is shown in figure 1,
The prefabricated installation method of a kind of prefabricated box-beam sections without measuring tower, comprises the following steps:
Step one, arranging fixing Side Template 1, described fixing Side Template 1 can play positioning action, adjacent Described fixing Side Template 1 pours the first prefabricated box-beam sections, makes the web of described first prefabricated box-beam sections It is perpendicular to described fixing Side Template 1, at described first prefabricated box-beam sections surface configuration 2 measuring points A, B, Wherein, to lay respectively at two coxostermums of described first prefabricated box-beam sections close for described measuring point A, measuring point B The top of described fixing Side Template one end, and really pinpoint with on fixing Side Template when non-casting concrete Interim fixing (i.e. determining with the relative position of fixing Side Template, the later stage can release);
At described first prefabricated box-beam sections surface configuration 2 measuring points C, D, measuring point C and measuring point D divides It is not positioned at upper away from described fixing Side Template 1 one end of two coxostermums of described first prefabricated box-beam sections Side, measures the distance between any 2 measuring points, respectively L in 4 measuring points A, B, C, DAB、 LAC、LAD、LBC、LBD、LCD, and measure the elevation H of 4 measuring points respectivelyA、HB、HC、HD, Determine the position at measuring point A, B, C, D place;
During practice of construction, the position of 4 measuring points A, B, C, D need not accurately determine herein, Probably it is positioned at two pleurosternal tops of the first prefabricated box-beam sections,;Herein measure determine measuring point A, The position at B, C, D place, is that standard is done in the position released for calculated for subsequent the first prefabricated box-beam sections;
Step 2, described first prefabricated box-beam sections is moved to position set in advance, wherein it is determined that Described position set in advance particularly as follows:
Will be moved into 4 measuring points on described first prefabricated box-beam sections surface of position set in advance respectively Be set to A1, B1, C1, D1, its respectively with measuring point A, B, C, D one_to_one corresponding, surveyed by control Distance L between some A and measuring point A1AA1, distance L between measuring point B and measuring point A1BA1For in advance Value of calculation, and by the elevation of control measuring point A1 for precalculating value, so that it is determined that the position of measuring point A1, By controlling distance L between measuring point A and measuring point B1AB1, distance L between measuring point B and measuring point B1BB1For precalculating value, and by the elevation of control measuring point B1 for precalculating value, so that it is determined that measuring point The position of B1;
By the elevation of control measuring point C1, D1 for precalculating value, so that it is determined that described set in advance Position;
First, it is determined that measuring the position of A1, B1, we are assured that and i.e. will be moved into setting in advance With the straight line that A1, B1 are 2 on first prefabricated box-beam sections of fixed position, determine the most again One point, it is possible to determine a face, the position of the first prefabricated box-beam sections after i.e. moving, but real Border operation generally uses 4 points, it is ensured that safety is higher;Precalculated value herein is all to utilize The position of A, B, C, D that determines of pre-test, obtain through a series of industry correlation computations.
Step 3, between described first prefabricated box-beam sections and described fixing Side Template 1, pour into a mould the second case Beam prefabricated sections, wherein, pouring into a mould the second prefabricated box-beam sections is repeating said steps one, and makes described On two prefabricated box-beam sections, two measuring points near described fixing Side Template 1 overlap with described measuring point A, B, And described first prefabricated box-beam sections splices mutually with described second prefabricated box-beam sections.
The prefabricated installation method of the described prefabricated box-beam sections without measuring tower, measuring point C is relative with measuring point A Should, it is positioned at above the web of the same side, measuring point B is corresponding with measuring point D, is positioned at above opposite side web.
The prefabricated installation method of the described prefabricated box-beam sections without measuring tower, also includes step 4, repetition Above-mentioned steps one, step 2 and step 3, until completing pouring of all of prefabricated box-beam sections.
The prefabricated installation method of the described prefabricated box-beam sections without measuring tower, described fixing Side Template is vertical Arranging in ground, working security is more preferable, the most more convenient.
Although embodiment of the present invention are disclosed as above, but it is not restricted to description and embodiment party Listed utilization in formula, it can be applied to various applicable the field of the invention completely, for being familiar with ability For the personnel in territory, be easily achieved other amendment, therefore without departing substantially from claim and etc. homotype Enclosing under limited general concept, the present invention is not limited to specific details and shown here as the figure with description Example.

Claims (4)

1. one kind without measuring the prefabricated installation method of prefabricated box-beam sections of tower, it is characterised in that include with Lower step:
Step one, arranging fixing Side Template, adjacent described fixing Side Template pours the first prefabricated box-beam sections, The web making described first prefabricated box-beam sections is perpendicular to described fixing Side Template, pre-in described first box beam Sections surface configuration processed 2 measuring points A, B, wherein, described measuring point A, measuring point B lay respectively at described Two coxostermums of the first prefabricated box-beam sections are near the top of described fixing Side Template one end;
At described first prefabricated box-beam sections surface configuration 2 measuring points C, D, measuring point C and measuring point D divides It is not positioned at two coxostermums top away from described fixing Side Template one end of described first prefabricated box-beam sections, Measure the distance between any 2 measuring points, respectively L in 4 measuring points A, B, C, DAB、LAC、 LAD、LBC、LBD、LCD, and measure the elevation H of 4 measuring points respectivelyA、HB、HC、HD, determine The position at measuring point A, B, C, D place;
Step 2, described first prefabricated box-beam sections is moved to position set in advance, wherein it is determined that Described position set in advance particularly as follows:
Will be moved into 4 measuring points on described first prefabricated box-beam sections surface of position set in advance respectively Be set to A1, B1, C1, D1, its respectively with measuring point A, B, C, D one_to_one corresponding, surveyed by control Distance L between some A and measuring point A1AA1, distance L between measuring point B and measuring point A1BA1For in advance Value of calculation, and by the elevation of control measuring point A1 for precalculating value, so that it is determined that the position of measuring point A1, By controlling distance L between measuring point A and measuring point B1AB1, distance L between measuring point B and measuring point B1BB1For precalculating value, and by the elevation of control measuring point B1 for precalculating value, so that it is determined that measuring point The position of B1;
By the elevation of control measuring point C1, D1 for precalculating value, so that it is determined that described set in advance Position;
Step 3, between described first prefabricated box-beam sections and described fixing Side Template, pour into a mould the second box beam Prefabricated subsection, wherein, pouring into a mould the second prefabricated box-beam sections is repeating said steps one, and makes described second On prefabricated box-beam sections, two measuring points near described fixing Side Template overlap with described measuring point A, B.
2. the prefabricated installation method of the prefabricated box-beam sections without measuring tower as claimed in claim 1, it is special Levying and be, measuring point C is corresponding with measuring point A, is positioned at above the web of the same side, measuring point B and measuring point D Corresponding, it is positioned at above opposite side web.
3. the prefabricated installation method of the prefabricated box-beam sections without measuring tower as claimed in claim 1, it is special Levy and be, also include:
Step 4, repeat the above steps one, step 2 and step 3, until it is pre-to complete all of box beam Pouring of sections processed.
4. the prefabricated installation method of the prefabricated box-beam sections without measuring tower as claimed in claim 1, it is special Levying and be, described fixing Side Template is perpendicular to ground and arranges.
CN201510541018.7A 2015-08-28 2015-08-28 Without measuring the prefabricated installation method of the prefabricated box-beam sections of tower Active CN105133500B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510541018.7A CN105133500B (en) 2015-08-28 2015-08-28 Without measuring the prefabricated installation method of the prefabricated box-beam sections of tower

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510541018.7A CN105133500B (en) 2015-08-28 2015-08-28 Without measuring the prefabricated installation method of the prefabricated box-beam sections of tower

Publications (2)

Publication Number Publication Date
CN105133500A CN105133500A (en) 2015-12-09
CN105133500B true CN105133500B (en) 2016-11-23

Family

ID=54719050

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510541018.7A Active CN105133500B (en) 2015-08-28 2015-08-28 Without measuring the prefabricated installation method of the prefabricated box-beam sections of tower

Country Status (1)

Country Link
CN (1) CN105133500B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108385527A (en) * 2018-02-07 2018-08-10 中交公局第二工程有限公司 A kind of superelevation runoff section segment girder precast measures and monitoring method
CN108762059A (en) * 2018-08-12 2018-11-06 广州瀚阳工程咨询有限公司 A kind of automatic control system applied to short-line prefabrication bridge subsection

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101158145A (en) * 2007-11-08 2008-04-09 中国第一冶金建设有限责任公司 Method for mounting trestle bridge segment box girder
CN101684638A (en) * 2008-09-23 2010-03-31 中交第三航务工程局有限公司 Assembly method of section box girder
CN201648975U (en) * 2010-04-14 2010-11-24 江苏中泰钢结构股份有限公司 General assembly structure for bridge sections of large steel box girder
CN101985826A (en) * 2010-09-19 2011-03-16 湖南路桥建设集团公司 Construction method for high-altitude section prefabricating, beam moving, beam storing and assembling of large concrete box beam
CN103696369A (en) * 2013-11-26 2014-04-02 武汉一冶钢结构有限责任公司 Four-point locating and installing method of steel box beam sections

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US7296317B2 (en) * 2006-02-09 2007-11-20 Lawrence Technological University Box beam bridge and method of construction

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101158145A (en) * 2007-11-08 2008-04-09 中国第一冶金建设有限责任公司 Method for mounting trestle bridge segment box girder
CN101684638A (en) * 2008-09-23 2010-03-31 中交第三航务工程局有限公司 Assembly method of section box girder
CN201648975U (en) * 2010-04-14 2010-11-24 江苏中泰钢结构股份有限公司 General assembly structure for bridge sections of large steel box girder
CN101985826A (en) * 2010-09-19 2011-03-16 湖南路桥建设集团公司 Construction method for high-altitude section prefabricating, beam moving, beam storing and assembling of large concrete box beam
CN103696369A (en) * 2013-11-26 2014-04-02 武汉一冶钢结构有限责任公司 Four-point locating and installing method of steel box beam sections

Also Published As

Publication number Publication date
CN105133500A (en) 2015-12-09

Similar Documents

Publication Publication Date Title
CN102322071B (en) Universal base structure of main transformer of 220kV substation
CN103669216A (en) Steel box girder scattered-splicing sliding device and installation method
CN105133500B (en) Without measuring the prefabricated installation method of the prefabricated box-beam sections of tower
CN102943565A (en) Construction method of large-sized arc-shaped wall
CN105157671A (en) Monitoring method for bridge deformation in shield construction and system employed by method
CN102708267B (en) High speed railway sound barrier insertion loss calculation method
CN103388343A (en) Super-long and large horizontal embedded part reverse construction method
CN103924528A (en) Overall long-distance pushing slippage construction method for large-span bridge box girder structure of large-span bridge
CN108179877A (en) Mitigate the cast-in-place torsion plate circular arc track construction method of helical curve multilayer
CN109918763A (en) The factor of safety against cracking design method of door opening shape section lining side wall concrete temperature crack control
CN203881339U (en) Detachable monitoring pier
CN108385538A (en) The method that the prefabricated head tower of cable-stayed bridge is installed on concrete king-post
CN105821727B (en) A kind of plane net measuring methods of CP III
CN104631819A (en) Template system of arc-shaped facade arch-shaped concrete door beam and erection method of template system
CN205100236U (en) Connected node device suitable for transmission line angle -steel tower column foot is connected with basis
CN103482042B (en) A kind of deep water comb shape slideway cross beam construction method of installation
CN109778617A (en) A kind of lateral platform trackless pipeline construction method of Subway Tunnel
CN106017607A (en) Upward floating monitoring system of model board trolley in self-compacting concrete and monitoring method thereof
CN102848198B (en) Distance tinuous production unit equipment installs method for preventing skidding of wheels
FR3115765B1 (en) Nacelle for an aircraft propulsion system, comprising a multifunctional structure forming a structural reinforcement or means of access
CN108625296A (en) One kind installing linear control method for precast segment bridge
CN105926387B (en) A kind of plane net measuring methods of CP III
CN105064681B (en) Installing method of steel structure foundation screw bolt
CN104807412A (en) Tunnel overall deformation monitoring device based on GPS positioning
CN106284442A (en) Point control superchargings based on three phase variables hypervelocity sedimentation

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C41 Transfer of patent application or patent right or utility model
CB03 Change of inventor or designer information

Inventor after: Wang Min

Inventor after: Huang Yue

Inventor after: You Xinpeng

Inventor after: Huang Can

Inventor after: Peng Chengming

Inventor after: Chen Long

Inventor after: Chen Shaolin

Inventor after: Zou Longyan

Inventor after: Li Xin

Inventor after: Cao Zhi

Inventor after: Chen Ming

Inventor after: Wu Yugang

Inventor after: Ya Gang

Inventor after: Xian Rong

Inventor after: Wang Cunshu

Inventor after: Zou Hui

Inventor after: Wu Xingfa

Inventor after: Zheng Hehui

Inventor before: Zhang Yongtao

Inventor before: Zou Longyan

Inventor before: Li Xin

Inventor before: Cao Zhi

Inventor before: Wang Min

Inventor before: Wu Xingfa

Inventor before: Zheng Hehui

Inventor before: Huang Yue

Inventor before: You Xinpeng

Inventor before: Huang Can

Inventor before: Peng Chengming

Inventor before: Chen Shaolin

COR Change of bibliographic data
TA01 Transfer of patent application right

Effective date of registration: 20160720

Address after: 430048 Wuhan, East Lake District, Hubei Jin Lake Road, No. 11

Applicant after: China Communications 2nd Navigational Bureau

Applicant after: Long Highway Bridge Construction CCCC National Engineering Research Center Co., Ltd.

Applicant after: China Communications 2nd Navigational Bureau 2nd Engineering Co., Ltd.

Applicant after: GUANGDONG PROVINCIAL HIGHWAY CONSTRUCTION CO., LTD.

Address before: 430048 Wuhan, East Lake District, Hubei Jin Lake Road, No. 11

Applicant before: China Communications 2nd Navigational Bureau

Applicant before: Long Highway Bridge Construction CCCC National Engineering Research Center Co., Ltd.

C14 Grant of patent or utility model
GR01 Patent grant