CN103344214A - 1.6-degree parabolic extralarge pier measuring and pier body linear control method - Google Patents

1.6-degree parabolic extralarge pier measuring and pier body linear control method Download PDF

Info

Publication number
CN103344214A
CN103344214A CN2013102817915A CN201310281791A CN103344214A CN 103344214 A CN103344214 A CN 103344214A CN 2013102817915 A CN2013102817915 A CN 2013102817915A CN 201310281791 A CN201310281791 A CN 201310281791A CN 103344214 A CN103344214 A CN 103344214A
Authority
CN
China
Prior art keywords
pier
elevation
measurement
control
bridge pier
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2013102817915A
Other languages
Chinese (zh)
Other versions
CN103344214B (en
Inventor
杨小礼
刘义立
王路路
任高峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Central South University
China Railway 20th Bureau Group Corp
Original Assignee
Central South University
China Railway 20th Bureau Group Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Central South University, China Railway 20th Bureau Group Corp filed Critical Central South University
Priority to CN201310281791.5A priority Critical patent/CN103344214B/en
Publication of CN103344214A publication Critical patent/CN103344214A/en
Application granted granted Critical
Publication of CN103344214B publication Critical patent/CN103344214B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

一种1.6次抛物线型特大桥墩测量及墩身线形控制方法,包括桥墩测量与墩身线形控制方法,其中,桥墩测量采用控制网测量,控制网为四边形结构,控制网处设置有控制点,且控制网包括平面控制网和高程控制网,平面控制网按四等控制网布设,高程控制网按五等高程控制网布设,桥墩的基线边与全线控制网联测;墩身为抛物线型空心结构,其线形控制方法包括对空心墩中心定位测量、高程测量及空心墩垂直度测量,通过测量空心墩中心、高程及空心墩垂直度,为控制高程预抛高值提供参考依据。本发明操作工艺简便;且桥墩测量速度快,控制精度准确;为控制高程预抛高值提供参考依据,同时有效控制墩身线形,提高工程安全系数,控制成本低,工效高。A 1.6-order parabolic super large bridge pier measurement and pier body alignment control method, including the bridge pier measurement and pier body alignment control method, wherein the bridge pier measurement adopts control network measurement, the control network is a quadrilateral structure, and control points are arranged at the control network, and The control network includes the plane control network and the elevation control network. The plane control network is arranged according to the fourth-class control network, and the elevation control network is arranged according to the fifth-class elevation control network. , the linear control method includes the center positioning measurement of the hollow pier, the elevation measurement and the verticality measurement of the hollow pier. By measuring the center, elevation and verticality of the hollow pier, it provides a reference for controlling the pre-throwing height value of the elevation. The invention has simple and convenient operation process; the measurement speed of the bridge pier is fast, and the control precision is accurate; it provides a reference basis for controlling the elevation pre-throwing height, effectively controls the line shape of the pier body, improves the engineering safety factor, and has low control cost and high work efficiency.

Description

一种1.6次抛物线型特大桥墩测量及墩身线形控制方法A 1.6-degree parabolic super-large bridge pier measurement and pier shape control method

技术领域 technical field

本发明涉及特大桥墩测量与施工技术领域,具体为一种1.6次抛物线型特大桥墩测量及墩身线形控制方法。 The invention relates to the technical field of measurement and construction of extra-large bridge piers, in particular to a 1.6-order parabolic super-large bridge piers measurement and pier line shape control method.

背景技术 Background technique

随着国民经济持续快速发展,当前我国正处于大跨度、深水桥梁建设快速发展时期,采用先进的设计和施工技术,以达到节省投资、缩短工期、确保安全的施工目标一直是工程界所追求的。如纵目沟特大桥全长834.12米,位于陕西省白水县纵目乡群英村纵目沟“V”字形支沟内,桥址位于黄土沟壑区,地形陡峻,沟谷深切;桥高129米,最高墩105米,居西北铁路桥梁第一,全国铁路桥梁第二;其特殊的地理位置对施工技术提出了更高的要求,同时也增加了施工难度。 With the continuous and rapid development of the national economy, my country is currently in a period of rapid development of long-span and deep-water bridge construction. The use of advanced design and construction technology to achieve the construction goals of saving investment, shortening the construction period, and ensuring safety has always been pursued by the engineering community. . For example, the Zongmugou Bridge has a total length of 834.12 meters and is located in the "V"-shaped branch ditch of Zongmugou, Qunying Village, Zongmu Township, Baishui County, Shaanxi Province. The bridge site is located in the loess gully area, with steep terrain and deep valleys; meters, ranking first in Northwest railway bridges and second in national railway bridges; its special geographical location puts forward higher requirements for construction technology, and also increases the difficulty of construction.

传统的桥墩施工方法是通过在地下桩基上支立模板,而后在模板内部灌注混凝土而成,在施工过程中,缺乏对桥墩的墩身监测,同时在墩身的施工过程中没有考虑桥墩沉降值和桥墩竖向变形,建造高达数百米的桥墩必须考虑地质、风力等相关因素对桥墩的影响,否则易导致后期桥墩发生严重变形,存在安全隐患。 The traditional bridge pier construction method is to support the formwork on the underground pile foundation, and then pour concrete inside the formwork. During the construction process, there is a lack of monitoring of the pier body, and the settlement of the pier is not considered during the construction process of the pier body. The value and vertical deformation of the pier, the construction of piers up to hundreds of meters must consider the influence of geology, wind and other related factors on the pier, otherwise it will easily lead to serious deformation of the pier in the later stage, posing safety hazards.

发明内容 Contents of the invention

本发明所解决的技术问题在于提供一种1.6次抛物线型特大桥墩测量及墩身线形控制方法,以解决上述背景技术中的缺点。 The technical problem to be solved by the present invention is to provide a 1.6-order parabolic super large bridge pier measurement and pier line shape control method to solve the above-mentioned shortcomings in the background technology.

本发明所解决的技术问题采用以下技术方案来实现: The technical problem solved by the present invention adopts following technical scheme to realize:

一种1.6次抛物线型特大桥墩测量及墩身线形控制方法,包括桥墩测量与墩身线形控制方法,其中,桥墩测量采用控制网测量,控制网为四边形结构,控制网处设置有控制点,且控制网包括平面控制网和高程控制网,平面控制网按四等控制网布设,高程控制网按五等高程控制网布设,桥墩的基线边与全线控制网联测,可有效保证主桥控制测量,测量速度快,控制精度准确;墩身为抛物线型空心结构,其线形控制方法包括对空心墩中心定位测量、高程测量及空心墩垂直度测量,通过测量空心墩中心、高程及空心墩垂直度,为控制高程预抛高值提供参考依据,同时有效控制墩身线形,提高工程安全系数。 A 1.6-order parabolic super large bridge pier measurement and pier body alignment control method, including the bridge pier measurement and pier body alignment control method, wherein the bridge pier measurement adopts control network measurement, the control network is a quadrilateral structure, and control points are arranged at the control network, and The control network includes the plane control network and the elevation control network. The plane control network is arranged according to the fourth-class control network, and the elevation control network is arranged according to the fifth-class elevation control network. , the measurement speed is fast, and the control accuracy is accurate; the pier body is a parabolic hollow structure. , to provide a reference basis for controlling the elevation pre-throwing height, and at the same time effectively control the shape of the pier body and improve the safety factor of the project.

在本发明中,控制网的控制点设置在施工现场外,且采用混凝土埋设,桩顶埋设刻有“+”的钢筋头;控制点每隔2个月复测一次,放样时经常检查和校核。 In the present invention, the control point of the control network is set outside the construction site, and is buried in concrete, and the steel bar head engraved with "+" is buried on the top of the pile; nuclear.

在本发明中,墩身线形控制主要通过施工测量,其具体步骤如下: In the present invention, pier body alignment control is mainly through construction measurement, and its specific steps are as follows:

1)、在一节段混凝土浇筑完成后,采用三角高程法测出混凝土顶面高程,根据实测标高,绘出该标高处断面图,并采用全站仪按坐标法,将轮廓线放样到混凝土顶面上,作为支立上一节段模板的控制基线; 1) After a section of concrete pouring is completed, use the triangular elevation method to measure the elevation of the concrete top surface, draw a cross-sectional view at the elevation according to the actual measurement elevation, and use the total station to set out the contour line to the concrete according to the coordinate method On the top surface, it serves as the control baseline for supporting the formwork of the previous segment;

2)、上一节段模板支立完成后,采用三角高程法测出模板顶面高程,并绘出模板顶处桥墩横断面图,然后采用全站仪按坐标法,逐点校核模板位置,如有偏差,进行调整,直到符合要求为止; 2) After the formwork support of the previous section is completed, use the triangular elevation method to measure the elevation of the top surface of the formwork, and draw the cross-sectional view of the pier at the top of the formwork, and then use the total station to check the position of the formwork point by point according to the coordinate method , if there is a deviation, adjust it until it meets the requirements;

3)、混凝土浇筑过程中,在墩身模板4条长边上各布设2个平面位置监控点,随时监控,发现问题及时采取措施纠偏; 3) During the concrete pouring process, 2 plane position monitoring points are arranged on each of the 4 long sides of the pier body formwork to monitor at any time and take timely measures to correct deviations when problems are found;

4)、循环进行上述步骤1)~3); 4), cycle through the above steps 1) to 3);

5)、墩顶最后一个节段施工前,高程测量采用三角高程及水准高程钢尺传递两种方法同时进行,校核无误后方可施工; 5) Before the construction of the last section of the pier top, the elevation measurement shall be carried out simultaneously by two methods of triangular elevation and horizontal elevation steel ruler transmission, and the construction can only be carried out after the verification is correct;

6)、高程测量包括桥墩沉降和桥墩竖向变形 6) Elevation measurement includes pier settlement and vertical deformation of pier

   (1)桥墩沉降观测包括水准基点的引测与测量方法 (1) The settlement observation of bridge piers includes the introduction and measurement methods of benchmark points

沉降观测点采用预埋钢质测点桩,沉降测点布设方法:每个承台设4个沉降观测点,Φ20钢筋头测点伸出承台顶3cm,承台端部加工磨圆并涂上红油漆,或将预埋钢筋弯出承台; The settlement observation point adopts pre-buried steel measuring point piles, and the layout method of the settlement measuring point: set up 4 settlement observation points for each cap, the Φ20 steel bar head measuring point protrudes 3cm from the top of the cap, and the end of the cap is rounded and painted Red paint, or bend the pre-embedded steel bar out of the cap;

①水准基点的引测  ① Leading test of benchmark point

沉降观测点引用的水准基点,初期采用应急测量网水准点,点间距为200m,在全线控制网建立后,改为精测网高程水准点,点间距为150~180m,并将引用应急测量网水准基点得到的沉降观测结果归算到精测网高程系统之中;沉降观测从最近的水准基点引测,引测前对引用水准基点进行检核,检核采用复测方式进行,将前后相邻水准基点之间的高差值与原高差值进行对比,当检测的高差值与原高差值满足时,即引测水准基点处于稳固状态;否则进一步复测; The benchmarking points quoted by the settlement observation points initially adopt the benchmarking points of the emergency surveying network with a point spacing of 200m. The settlement observation results obtained from the benchmark point are attributed to the elevation system of the Jingwei network; the settlement observation is measured from the nearest benchmark point, and the quoted benchmark point is checked before the survey. The height difference between adjacent benchmark points is compared with the original height difference. When the detected height difference and the original height difference are satisfied, the benchmarking point is in a stable state; otherwise, further retesting;

②测量方法 ②Measurement method

沉降观测采用从邻近水准点测至沉降观测点,再闭合至邻近另一水准基点的符合水准路线法,也根据需要采用从邻近水准基点直接测至沉降观测点、并进行往返测的支路线法;桥墩监测基点为标准水准点,监测时通过测得各测点与水准点(基点)在t(2)时间的高程差ΔH,可计算得到各监测点在t(2)时间的标准高程ht(2),然后与上次t(1)时间测得的高程ht(1)进行比较,差值Δht(1,2)即为该测点的在t(1)~t(2) 时间段的沉降值,即: The subsidence observation adopts the conforming leveling route method of measuring from the adjacent benchmarking point to the settlement observation point, and then closes to another benchmarking point adjacent to it, and also adopts the branch line method of directly measuring from the adjacent benchmarking point to the settlement observation point and making round-trip measurements as required ; The monitoring base point of the bridge pier is the standard benchmarking point. By measuring the elevation difference ΔH between each measuring point and the benchmarking point (base point) at time t(2) during monitoring, the standard height ht of each monitoring point at time t(2) can be calculated (2), and then compared with the height ht(1) measured at the last t(1) time, the difference Δht(1, 2) is the time period of the measuring point during t(1)~t(2) The settlement value of , namely:

Δht(1,2)=ht(2)-ht(1) Δht(1,2)=ht(2)-ht(1)

(2)桥墩竖向变形 (2) Vertical deformation of bridge piers

由于1.6次抛物线特大桥墩墩身的高度,施工过程中要考虑桥墩因混凝土弹性压缩、收缩徐变等引起的竖向变形,通过对材料力学性能的测试,确定混凝土的弹性模量和收缩徐变系数,经过有限元计算,并计入施工中的基础沉降,最终确定桥墩的预抛高值。 Due to the height of the pier body of the 1.6-degree parabolic extra-large bridge, the vertical deformation of the pier due to the elastic compression and shrinkage of the concrete should be considered during the construction process. The elastic modulus and shrinkage of the concrete should be determined by testing the mechanical properties of the material. The coefficient is calculated by finite element and included in the foundation settlement during construction to finally determine the pre-throwing height of the bridge pier.

在本发明中,高程预抛高值为桥墩沉降值和桥墩竖向变形之和。 In the present invention, the elevation pre-throwing height value is the sum of the settlement value of the pier and the vertical deformation of the pier.

有益效果Beneficial effect

本发明所需的机械工具为常规工具、其操作工艺简便;且桥墩测量速度快,控制精度准确;针对特大桥墩墩身线形控制的观测,为控制高程预抛高值提供参考依据,同时有效控制墩身线形,提高工程安全系数,控制成本低,工效高。 The mechanical tools required by the present invention are conventional tools, and the operation process is simple; and the measurement speed of the bridge pier is fast, and the control accuracy is accurate; aiming at the observation of the line shape control of the super large bridge pier body, it provides a reference for controlling the elevation pre-throwing height value, and at the same time effectively controls The linear shape of the pier body improves the safety factor of the project, with low control cost and high work efficiency.

附图说明 Description of drawings

图1为本发明中平面控制网布设与主墩相对位置示意图。 Fig. 1 is a schematic diagram of the layout of the planar control network and the relative position of the main pier in the present invention.

图2为本发明中墩身断面放样及复合控制点示意图。 Fig. 2 is a schematic diagram of pier body section stakeout and compound control points in the present invention.

图3为本发明中桥墩沉降观测点布置正视图。 Fig. 3 is a front view of the arrangement of observation points for settlement of bridge piers in the present invention.

图4为本发明中桥墩沉降观测点布置俯视图。 Fig. 4 is a top view of the arrangement of observation points for settlement of bridge piers in the present invention.

其中,图1中A、B、1、2分别表示平面控制点,表示与主墩的相对位置,用来控制主墩上模板平面位置与高程;图4中1、2、3、4表示桥墩沉降观测点。 Among them, A, B, 1, and 2 in Figure 1 represent the plane control points, which represent the relative position to the main pier, and are used to control the plane position and elevation of the formwork on the main pier; 1, 2, 3, and 4 in Figure 4 represent the bridge pier Subsidence observation point.

具体实施方式 Detailed ways

以下结合附图和实施例对本发明作进一步详细说明。 The present invention will be described in further detail below in conjunction with the accompanying drawings and embodiments.

参见图1、图2、图3、图4的一种1.6次抛物线型特大桥墩测量及墩身线形控制方法,其中,桥墩测量采用控制网测量,控制网为四边形结构,控制网处设置有控制点,且控制网包括平面控制网和高程控制网,平面控制网按四等控制网布设,设置有4个控制点,高程控制网按五等高程控制网布设,桥墩的基线边与全线控制网联测,可有效保证主桥控制测量,测量速度快,控制精度准确;墩身为抛物线型空心结构,其墩身线形控制方法具体施工步骤如下: Refer to Fig. 1, Fig. 2, Fig. 3 and Fig. 4 for a 1.6-degree parabolic super large bridge pier measurement and pier body alignment control method, wherein the pier measurement adopts the control network measurement, the control network is a quadrilateral structure, and the control network is equipped with control points, and the control network includes plane control network and elevation control network. The joint measurement can effectively ensure the control measurement of the main bridge, the measurement speed is fast, and the control accuracy is accurate; the pier body is a parabolic hollow structure, and the specific construction steps of the pier body alignment control method are as follows:

1)、在一节段混凝土浇筑完成后,采用三角高程法测出混凝土顶面高程,根据实测标高,绘出该标高处断面图,并采用全站仪按坐标法,将轮廓线放样到混凝土顶面上,作为支立上一节段模板的控制基线; 1) After a section of concrete pouring is completed, use the triangular elevation method to measure the elevation of the concrete top surface, draw a cross-sectional view at the elevation according to the actual measurement elevation, and use the total station to set out the contour line to the concrete according to the coordinate method On the top surface, it serves as the control baseline for supporting the formwork of the previous segment;

2)、上一节段模板支立完成后,采用三角高程法测出模板顶面高程,并绘出模板顶处桥墩横断面图,然后采用全站仪按坐标法,逐点校核模板位置,如有偏差,进行调整,直到符合要求为止; 2) After the formwork support of the previous section is completed, use the triangular elevation method to measure the elevation of the top surface of the formwork, and draw the cross-sectional view of the pier at the top of the formwork, and then use the total station to check the position of the formwork point by point according to the coordinate method , if there is a deviation, adjust it until it meets the requirements;

3)、混凝土浇筑过程中,在墩身模板4条长边上各布设2个平面位置监控点,随时监控,发现问题及时采取措施纠偏; 3) During the concrete pouring process, 2 plane position monitoring points are arranged on each of the 4 long sides of the pier body formwork to monitor at any time and take timely measures to correct deviations when problems are found;

4)、循环进行上述步骤1)~3); 4), cycle through the above steps 1) to 3);

5)、墩顶最后一个节段施工前,高程测量采用三角高程及水准高程钢尺传递两种方法同时进行,校核无误后方可施工; 5) Before the construction of the last section of the pier top, the elevation measurement shall be carried out simultaneously by two methods of triangular elevation and horizontal elevation steel ruler transmission, and the construction can only be carried out after the verification is correct;

6)、高程测量包括桥墩沉降和桥墩竖向变形 6) Elevation measurement includes pier settlement and vertical deformation of pier

   (1)桥墩沉降观测包括水准基点的引测与测量方法 (1) The settlement observation of bridge piers includes the introduction and measurement methods of benchmark points

沉降观测点采用预埋钢质测点桩,沉降测点布设方法:每个承台设4个沉降观测点,Φ20钢筋头测点伸出承台顶3cm,承台端部加工磨圆并涂上红油漆,或将预埋钢筋弯出承台; The settlement observation point adopts pre-buried steel measuring point piles, and the layout method of the settlement measuring point: set up 4 settlement observation points for each cap, the Φ20 steel bar head measuring point protrudes 3cm from the top of the cap, and the end of the cap is rounded and painted Red paint, or bend the pre-embedded steel bar out of the cap;

①水准基点的引测 ①Introduction of benchmarking points

沉降观测点引用的水准基点,初期采用应急测量网水准点(二等水准点,点间距200m),全线控制网建立后,改为精测网高程水准点(二等水准点,点间距160m),并将引用应急测量网水准基点得到的沉降观测结果归算到精测网高程系统之中; The benchmarking points quoted by the settlement observation points are the emergency surveying network benchmarking points (second-class benchmarking points, point spacing 200m) at the initial stage, and after the establishment of the whole line control network, they are changed to the precise surveying network elevation benchmarking points (second-class benchmarking points, point spacing 160m) , and the settlement observation results obtained by citing the benchmark points of the emergency survey network are attributed to the elevation system of the fine survey network;

沉降观测从最近的水准基点引测,引测前对引用水准基点进行检核,检核采用复测方式进行,将前后相邻水准基点之间的高差值与原高差值进行对比,当检测的高差值与原高差值满足(L为两相邻水准基点间的距离,单位为km)时,即引测水准基点处于稳固状态;否则进一步复测; The settlement observation is conducted from the nearest benchmark point, and the reference benchmark point is checked before the survey. The check is carried out by re-testing, and the height difference between the adjacent benchmark points is compared with the original height difference value. When the detected height difference and the original height difference meet (L is the distance between two adjacent benchmark points, the unit is km), that is, the lead survey benchmark point is in a stable state; otherwise, further retest;

②测量方法 ②Measurement method

沉降观测采用从邻近水准点测至沉降观测点,再闭合至邻近另一水准基点的符合水准路线法,也根据需要采用从邻近水准基点直接测至沉降观测点、并进行往返测的支路线法;桥墩监测基点为标准水准点(高程已知),监测时通过测得各测点与水准点(基点)在t(2)时间的高程差ΔH,可计算得到各监测点在t(2)时间的标准高程ht(2),然后与上次t(1)时间测得的高程ht(1)进行比较,差值Δht(1,2)即为该测点的在t(1)~t(2) 时间段的沉降值,即: The subsidence observation adopts the conforming leveling route method of measuring from the adjacent benchmarking point to the settlement observation point, and then closes to another benchmarking point adjacent to it, and also adopts the branch line method of directly measuring from the adjacent benchmarking point to the settlement observation point and making round-trip measurements as required ;The monitoring base point of the bridge pier is the standard benchmarking point (the elevation is known). During monitoring, by measuring the elevation difference ΔH between each measuring point and the benchmarking point (base point) at time t(2), it can be calculated that each monitoring point is at t(2) The standard height ht(2) at time, and then compared with the height ht(1) measured at the last time t(1), the difference Δht(1, 2) is the height of the measuring point between t(1)~t (2) The settlement value of the time period, namely:

Δht(1,2)=ht(2)-ht(1) Δht(1,2)=ht(2)-ht(1)

(2)桥墩竖向变形 (2) Vertical deformation of bridge piers

由于1.6次抛物线特大桥墩墩身的高度,施工过程中要考虑桥墩因混凝土弹性压缩、收缩徐变等引起的竖向变形,通过对材料力学性能的测试,确定混凝土的弹性模量和收缩徐变系数,经过有限元计算,并计入施工中的基础沉降,最终确定桥墩的预抛高值。 Due to the height of the pier body of the 1.6-degree parabolic extra-large bridge, the vertical deformation of the pier due to the elastic compression and shrinkage of the concrete should be considered during the construction process. The elastic modulus and shrinkage of the concrete should be determined by testing the mechanical properties of the material. The coefficient is calculated by finite element and included in the foundation settlement during construction to finally determine the pre-throwing height of the bridge pier.

在本实施例中,控制网的控制点设置在施工现场外,且采用混凝土埋设,桩顶埋设刻有“+”的钢筋头;控制点每隔2个月复测一次,放样时经常检查和校核。 In this embodiment, the control points of the control network are set outside the construction site, and are buried in concrete, and the top of the pile is buried with a "+" steel bar head; the control points are retested every 2 months, and they are often checked and proofreading.

以上显示和描述了本发明的基本原理和主要特征和本发明的优点。本行业的技术人员应该了解,本发明不受上述实施例的限制,上述实施例和说明书中描述的只是说明本发明的原理,在不脱离本发明精神和范围的前提下,本发明还会有各种变化和改进,这些变化和改进都落入要求保护的本发明范围内。本发明要求保护范围由所附的权利要求书及其等效物界定。 The basic principles and main features of the present invention and the advantages of the present invention have been shown and described above. Those skilled in the industry should understand that the present invention is not limited by the above-mentioned embodiments. What are described in the above-mentioned embodiments and the description only illustrate the principle of the present invention. Without departing from the spirit and scope of the present invention, the present invention will also have Variations and improvements are possible, which fall within the scope of the claimed invention. The protection scope of the present invention is defined by the appended claims and their equivalents.

Claims (4)

1. the especially big bridge pier of 6 parabolic types is measured and the pier shaft linear control method, comprise bridge pier measurement and pier shaft linear control method, it is characterized in that, bridge pier is measured and is adopted the control net to measure, and the control net is quadrilateral structure, and control net place is provided with the reference mark, and the control net comprises horizontal control network and vertical control network, horizontal control network is established by fourth class control screen cloth, and vertical control network is established by five contour process control screen cloths, and the net translocation is controlled with all fronts in the baseline limit of bridge pier; Pier shaft is the parabolic type hollow-core construction, its linear control method comprises hollow pier centralized positioning measurement, the measurement of higher degree and hollow pier squareness measurement, by measuring hollow pier center, elevation and hollow pier verticality, throw high value in advance for the control elevation reference frame is provided.
2. the especially big bridge pier of a kind of 1.6 parabolic types according to claim 1 is measured and the pier shaft linear control method, it is characterized in that, the reference mark of control net is arranged on outside the working-yard, and adopts concrete to bury underground, and the steel bar end that is carved with "+" is buried on the stake top underground; The reference mark every 2 months repetition measurements once, running check and check during setting-out.
3. the especially big bridge pier of a kind of 1.6 parabolic types according to claim 1 is measured and the pier shaft linear control method, it is characterized in that the linear control concrete steps of pier shaft are as follows:
1), after a sections concreting is finished, adopt the triangulated height method to measure the top of concrete elevation, according to the actual measurement absolute altitude, draw this absolute altitude place sectional drawing, and adopt total powerstation to press coordinate method, with the outline line setting-out to top of concrete, as the control baseline of the last sections template of Zhi Li;
2), after a last sections formwork support arrangement finishes, adopt the triangulated height method to measure the template elevation of top surface, and draw place, template top bridge pier cross-sectional view, adopt total powerstation to press coordinate method then, template position is checked in pointwise, if any deviation, adjust, till meeting the requirements;
3), in the concreting process, on 4 long limits of pier shaft template, respectively lay control point, 2 planimetric positions, monitoring at any time, the correction of in time taking measures of pinpointing the problems;
4), above-mentioned steps 1 is carried out in circulation)~3);
5), before the construction of last sections of Dun Ding, the measurement of higher degree adopts triangulated height and two kinds of methods of level elevation steel ruler transmission to carry out simultaneously, checks and can construct after errorless;
6), the measurement of higher degree comprises bridge pier sedimentation and bridge pier vertical deformation
(1) the bridge pier settlement observation comprises that drawing of leveling base survey and measuring method
Settlement observation point adopts the stake of pre-buried steel measuring point, sedimentation measuring point distribution method: each cushion cap is established 4 settlement observation points, and Φ 20 steel bar end measuring points stretch out cushion cap top 3cm, and cushion cap end processing rounding is also coated red paint, or embedded bar is bent cushion cap;
1. leveling base draws survey
The leveling base that settlement observation point is quoted, initial stage is adopted emergence measuring net leveling point, dot spacing is 200m, after the control net is set up completely, change accurate measurement net height journey leveling point into, dot spacing is 150~180m, and will quote settlement observation reduction as a result that emergence measuring net leveling base obtains among accurate measurement net height journey system; Settlement observation is drawn survey from nearest leveling base, check quoting leveling base before drawing survey, check and adopt the repetition measurement mode to carry out, high difference between the adjacent leveling base in front and back and former high difference are compared, when the high difference that detects and former high difference satisfy, namely draw the survey leveling base and be in steady status; Otherwise further repetition measurement;
2. measuring method
Settlement observation is adopted from contiguous leveling point and is surveyed to settlement observation point, is closed to the contact level route method of contiguous another leveling base again, also adopts as required from contiguous leveling base and directly surveys to settlement observation point and come and go the branch road collimation method of survey; Bridge pier monitoring basic point be standard water on schedule, during monitoring by recording each measuring point and leveling point (basic point) the difference of elevation Δ H in t (2) time, can calculate the standard elevation ht(2 of each monitoring point in t (2) time), the elevation ht(1 that records with t (1) time last time then) compares, difference DELTA ht(1,2) be the sedimentation value in t (1)~t (2) time period of this measuring point, that is:
Δht(1,2)=ht(2)-ht(1)
(2) bridge pier vertical deformation
Because the height of 1.6 especially big bridge pier pier shafts of para-curve, to consider the vertical deformation that bridge pier causes because of concrete elastic compression, shrinkage and creep etc. in the work progress, by the test to material mechanical performance, determine concrete elastic modulus and shrinkage and creep coefficient, through FEM (finite element) calculation, and count foundation settlement in the construction, finally determine high value of pre-throwings of bridge pier.
4. measure and the pier shaft linear control method according to claim 1 or the especially big bridge pier of 3 described a kind of 1.6 parabolic types, it is characterized in that, it is bridge pier sedimentation value and bridge pier vertical deformation sum that elevation is thrown high value in advance.
CN201310281791.5A 2013-07-05 2013-07-05 1.6-degree parabolic extralarge pier measuring and pier body linear control method Expired - Fee Related CN103344214B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310281791.5A CN103344214B (en) 2013-07-05 2013-07-05 1.6-degree parabolic extralarge pier measuring and pier body linear control method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310281791.5A CN103344214B (en) 2013-07-05 2013-07-05 1.6-degree parabolic extralarge pier measuring and pier body linear control method

Publications (2)

Publication Number Publication Date
CN103344214A true CN103344214A (en) 2013-10-09
CN103344214B CN103344214B (en) 2015-06-24

Family

ID=49279030

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310281791.5A Expired - Fee Related CN103344214B (en) 2013-07-05 2013-07-05 1.6-degree parabolic extralarge pier measuring and pier body linear control method

Country Status (1)

Country Link
CN (1) CN103344214B (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107504962A (en) * 2017-06-29 2017-12-22 中交航局第四工程有限公司 A kind of method using laser plummet apparatus control bridge deck-molding pier stud perpendicularity
CN108759775A (en) * 2018-03-14 2018-11-06 江苏恒久钢构有限公司 A kind of method for building up of vertical control network
CN110332920A (en) * 2019-07-08 2019-10-15 中铁第四勘察设计院集团有限公司 A kind of undercrossing tunnel bridge deformation monitoring system, method and storage medium
CN115406604A (en) * 2022-09-21 2022-11-29 中建八局浙江建设有限公司 Steel box girder mid-span line shape and stress monitoring method
CN116136403A (en) * 2023-04-14 2023-05-19 中交一航局第一工程有限公司 Construction measurement method for offshore installation of large prefabricated pier
CN116164697A (en) * 2022-12-14 2023-05-26 北玻院(滕州)复合材料有限公司 Method and device for measuring profile deformation of wind power blade die

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2180430C1 (en) * 2000-06-26 2002-03-10 Марийский государственный технический университет Method of control over stability of reference points
KR20100048675A (en) * 2008-10-31 2010-05-11 현대건설주식회사 Measuring method and apparatus of bridge displacement by measure of strain
CN102288156A (en) * 2011-07-20 2011-12-21 中铁四局集团第一工程有限公司 Second-class bench mark on-bridge measurement method

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2180430C1 (en) * 2000-06-26 2002-03-10 Марийский государственный технический университет Method of control over stability of reference points
KR20100048675A (en) * 2008-10-31 2010-05-11 현대건설주식회사 Measuring method and apparatus of bridge displacement by measure of strain
CN102288156A (en) * 2011-07-20 2011-12-21 中铁四局集团第一工程有限公司 Second-class bench mark on-bridge measurement method

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107504962A (en) * 2017-06-29 2017-12-22 中交航局第四工程有限公司 A kind of method using laser plummet apparatus control bridge deck-molding pier stud perpendicularity
CN108759775A (en) * 2018-03-14 2018-11-06 江苏恒久钢构有限公司 A kind of method for building up of vertical control network
CN110332920A (en) * 2019-07-08 2019-10-15 中铁第四勘察设计院集团有限公司 A kind of undercrossing tunnel bridge deformation monitoring system, method and storage medium
CN110332920B (en) * 2019-07-08 2024-04-02 中铁第四勘察设计院集团有限公司 System, method and storage medium for monitoring deformation of underpass railway bridge
CN115406604A (en) * 2022-09-21 2022-11-29 中建八局浙江建设有限公司 Steel box girder mid-span line shape and stress monitoring method
CN116164697A (en) * 2022-12-14 2023-05-26 北玻院(滕州)复合材料有限公司 Method and device for measuring profile deformation of wind power blade die
WO2024125088A1 (en) * 2022-12-14 2024-06-20 北玻院 (滕州)复合材料有限公司 Method and apparatus for measuring deformation of molded surface of wind power blade mold
CN116136403A (en) * 2023-04-14 2023-05-19 中交一航局第一工程有限公司 Construction measurement method for offshore installation of large prefabricated pier

Also Published As

Publication number Publication date
CN103344214B (en) 2015-06-24

Similar Documents

Publication Publication Date Title
CN103344214B (en) 1.6-degree parabolic extralarge pier measuring and pier body linear control method
CN102147252B (en) Method for measuring strut positions of contact network of special railway line for passenger traffic
CN103913145B (en) A kind of crack openings double-deformation monitoring of structures and measuring method
CN109515252B (en) Trackless measurement construction method for subway contact network
CN104634267B (en) A kind of overhead and gantry cranes camber measuring method
CN109839315A (en) Simulate the two-way sliding physical model case and Cross-fault leveling tunnel mechanics performance testing method in Cross-fault leveling tunnel
CN103558044A (en) Indoor model testing apparatus for analyzing influences of shield tunnel grouting construction on adjacent pile foundations
CN205718762U (en) A kind of stake holes measuring instrument
CN114046770A (en) A method of observation and measurement of marine subsidence
CN103411584B (en) Method and device for inspection measurement of fan-shaped section base of continuous casting machine
CN102966041A (en) Spatial stay-cable positioning method of multispan continuous S-shaped landscape bridge
CN102288156A (en) Second-class bench mark on-bridge measurement method
CN104674860B (en) Wire holing through survey method in seabed tunnel
CN206670617U (en) Settlement monitoring device is used in a kind of Underground Engineering Excavation construction
CN102966254B (en) Arrangement method for measuring tower used for construction of stub matching method
CN102995562B (en) High-accuracy control method of construction of large temporary steel structure slideway platform of steel truss girder
CN100554882C (en) Quick and easy setting-out method of construction engineering foundation pit
CN102493665B (en) Location installing method of sector embedded part
CN103422487B (en) Method for measuring settlement deformation by utilizing inclinometer and angle-adjustable converter
CN111041996A (en) Construction method for installing stay cable and cable pipe by axial method
CN203502020U (en) Centering, height fixing and leveling base device
CN206876177U (en) The fast-positioning device of Metro Tunnel circuit measuring point point position
CN108489455B (en) Method for measuring internal structure of sewage open caisson
CN206208430U (en) A kind of tension measuring device and system
CN107270881B (en) A kind of efficient setting out method in tunnel body for wind inner mold surface construction control point

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150624

Termination date: 20180705