CN108615104A - A kind of constructing tunnel quality tracing system and method - Google Patents

A kind of constructing tunnel quality tracing system and method Download PDF

Info

Publication number
CN108615104A
CN108615104A CN201810268518.1A CN201810268518A CN108615104A CN 108615104 A CN108615104 A CN 108615104A CN 201810268518 A CN201810268518 A CN 201810268518A CN 108615104 A CN108615104 A CN 108615104A
Authority
CN
China
Prior art keywords
information
concrete
tunnel
monitoring module
concreting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810268518.1A
Other languages
Chinese (zh)
Inventor
王元全
程科
於跃成
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201810268518.1A priority Critical patent/CN108615104A/en
Publication of CN108615104A publication Critical patent/CN108615104A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0639Performance analysis of employees; Performance analysis of enterprise or organisation operations
    • G06Q10/06395Quality analysis or management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Abstract

The invention discloses a kind of constructing tunnel quality tracing systems and method, this method to include:Acquisition is per the information of a collection of raw material, the information of tunnel excavation, the information of concrete production, acquire transport concrete and steel, tunnel, imperial frame, concreting information, and the temperature information in acquisition concreting process;It receives and stores the information of raw material, the production and transportation information of concrete, steel transit information, concreting information and concrete temperature information and transmits the information to monitoring client;The information received described in monitoring client real-time display.Present system is for realizing above-mentioned monitoring method.The present invention is in constructing tunnel work progress, the comprehensive management of data and analysis, reaches comprehensive management and control and fine-grained management to constructing tunnel quality, realizes that constructing tunnel whole process quality can trace.

Description

A kind of constructing tunnel quality tracing system and method
Technical field
The present invention relates to constructing tunnel quality tracing system and methods, belong to construction field.
Background technology
Currently, in Tunnel Project work progress, since engineering product is not reproducible, construction technology stability is poor, Complex process, process data collection capacity are big, lack effective management means in industry always to the technique in construction production process Data are effectively managed, and are caused work progress process data to be difficult to keep integrality, accuracy, real-time and consistency, are applied The significant data of work process cannot recall and effectively analyze, and effectively can not control and manage construction technological process, can not be formed The sustained improvement and optimization of technological process are supported in effective knowledge accumulation.
Invention content
Goal of the invention:In order to overcome the deficiencies in the prior art, the present invention to provide a kind of constructing tunnel quality tracing System and method realizes that during constructing tunnel, the comprehensive management of data and analysis reach to the comprehensive of constructing tunnel quality Management and control and fine-grained management realize that constructing tunnel whole process quality can trace.
Technical solution:To achieve the above object, constructing tunnel quality tracing system of the invention, including raw material data are adopted Collect module, concrete production monitoring module, the super deficient monitoring module in tunnel, concrete transportation monitoring module, the monitoring of steel transport vehicle In module, concreting process monitoring module, concrete temperature monitoring module, concreting process imperial frame monitoring module and Data center module, data center module receive raw material data acquisition module, concrete production monitoring module, the super deficient prison in tunnel Control module, concrete transportation monitoring module, steel transport vehicle monitoring module, concreting process monitoring module, coagulation soil temperature The information of imperial frame monitoring module in monitoring module, concreting process is spent, all information are transmitted to prison by data center module Control end.
Preferably, the raw material data acquisition module, the information for acquiring every a collection of raw material, the raw material Information include:The information of steel, cement, sandstone aggregate, flyash and additive;Concrete production monitoring module, for adopting Collect the creation data of concrete, the creation data of the concrete includes:The production time of concrete, Fang Liang, machine outlet, design Match ratio and practical match ratio.
Preferably, the super deficient monitoring module in tunnel, the creation data for acquiring tunnel excavation;Concrete transportation is supervised Module is controlled, the data of the data for acquiring cable machine transport concrete, the transport concrete include:Big truck position, horizontal speed Degree, small truck position, vertical speed and load.
Preferably, the steel transport vehicle monitoring module, for acquiring the information being transported into tunnel comprising:It is contained Steel specs, manufacturer and address;Concreting process monitoring module, for acquiring the concreting each poured letter Breath, the concreting information poured include:Pour progress, resource input, unusual condition and temperature data.
Preferably, the concrete temperature monitoring module, for acquiring the temperature data in concreting process;It is mixed Imperial frame monitoring module in solidifying soil casting process, for monitoring imperial frame deformation.
A method of such as above-mentioned constructing tunnel quality tracing system, include the following steps:
(1) information of the acquisition per a collection of raw material, the raw material information include:Steel, cement, sandstone aggregate, fine coal The information of ash and additive;
(2) information of concrete production is acquired, the concrete production information includes:Production time of concrete, Fang Liang, Machine outlet, design mixture proportion and practical match ratio;
(3) information of cable machine transport concrete is acquired, the cable machine transport concrete information includes:Big truck position, level Speed, small truck position, vertical speed and load;
(4) information of steel transport vehicle is acquired, the steel transport vehicle information includes:Contained steel specs, manufacturer The address and;
(5) information of tunnel excavation is acquired;
(6) information of tunnel dragon frame structure is acquired, the tunnel dragon frame structural information includes:Imperial frame steel density, imperial frame Type shape and size;
(7) information of concreting in tunnel is acquired, concreting information includes in the tunnel:Pour progress, Resource input, unusual condition and temperature data;
(8) temperature information in concreting process is acquired;
(9) information of imperial frame deformation in concreting process is acquired;
(10) information of raw material, the production information of concrete, concrete transportation information, steel transport letter are received and stored Breath, tunnel excavation information, tunnel dragon frame structural information, concreting information and concrete temperature information and imperial frame modification letter Breath, and monitoring client is transmitted the information to, the information received described in monitoring client real-time display.
Advantageous effect:The method of the constructing tunnel quality tracing system of the present invention acquires tunnel concrete and steel in real time Raw material, production, transport, excavate, pour, imperial frame modification, it is temperature controlled during data, pass through and analyze the above process The data of the quality of middle constructing tunnel process understand the quality of construction technology links, to finally control entire tunnel The construction quality of construction.
Description of the drawings
Fig. 1 is the flow chart of the present invention.
Specific implementation mode
The present invention is further described below in conjunction with the accompanying drawings.
The present invention encodes certain tunnel entity structure object progress WBS and self-editing by hierarchical structures such as tunnel construction sections-tunnel blocks Code.WBS coded representation works hierarchical relationships, using 4 level-ones, higher level is encoded to the prefix of subordinate's coding;Own coding according to Service management needs, and the prefix of subordinate's coding can be encoded to self-defining, principle top-ranking.
Constructing tunnel quality tracing object entity and its coding scheme purchase through tunnel material material, produce, transporting always, It excavates, imperial frame structure, pour, temperature and imperial frame modification control overall process, ensure that tunnel different structure part, different phase Monitoring data be able to comprehensive, complete management and analysis, to ensure that the quality of tunnel structure object.Therefore, the present invention adopts With WBS work breakdown structure (WBS) technologies, tunnel is decomposed into several tunnel blocks.To the real time monitoring of the quality of each tunnel block, Reach quality control requirement;Each tunnel block for meeting quality control requirement is finally configured to one and meets quality management It is required that tunnel, that is, realize comprehensive real time monitoring of constructing tunnel quality.
Constructing tunnel quality tracing system, including:Raw material data acquisition module, concrete production monitoring module, coagulation Native transport monitoring module, concreting process monitoring module, concrete temperature monitoring module, steel transport monitoring module, tunnel Excavate monitoring module, imperial frame modification monitoring module and data center module in road.
As shown in Figure 1, a kind of constructing tunnel quality tracing method, includes the following steps:
Step S101:Information of the acquisition per a collection of raw material, the raw material information include:Steel, cement, sandstone bone The information of material, flyash and additive;
Step S102:The information of concrete production is acquired, the concrete production information includes:When the production of concrete Between, Fang Liang, machine outlet, design mixture proportion and practical match ratio;
Step S103:The information of cable machine transport concrete is acquired, the cable machine transport concrete information includes:Big parking stall Set, horizontal velocity, small truck position, vertical speed and load;
Step S104:The information of steel transport vehicle is acquired, the steel transport vehicle information includes:Contained steel specs, life Produce producer and address;
Step S105:Acquire the information of tunnel excavation;
Step S106:The information of tunnel dragon frame structure is acquired, the tunnel dragon frame structural information includes:Imperial frame steel are close Degree, imperial frame type shape and size;
Step S107:The information of concreting in tunnel is acquired, concreting information includes in the tunnel:It pours Progress, resource input, unusual condition and temperature data;
Step S108:Acquire the temperature information in concreting process;
Step S109:Acquire the information of imperial frame modification in concreting process;
Step S1010:Receive and store the information of raw material, the production information of concrete, concrete transportation information, steel Transit information, tunnel excavation information, tunnel dragon frame structural information, concreting information and concrete temperature information and imperial frame become Type information, and monitoring client is transmitted the information to, the information received described in monitoring client real-time display.
A kind of constructing tunnel quality tracing system, comprises the following modules:
Raw material data acquisition module, the information for acquiring every a collection of raw material, the information of the raw material include:Steel The information of material, cement, sandstone aggregate, flyash and additive;
The creation data of concrete production monitoring module, the creation data for acquiring concrete, the concrete includes: Production time, Fang Liang, machine outlet, design mixture proportion and the practical match ratio of concrete;
The super deficient monitoring module in tunnel, the creation data for acquiring tunnel excavation;
Concrete transportation monitoring module, the data for acquiring cable machine transport concrete, the data of the transport concrete Including:Big truck position, horizontal velocity, small truck position, vertical speed and load;
Steel transport vehicle monitoring module, for acquiring the information being transported into tunnel comprising:Contained steel specs, production Producer and address;
Concreting process monitoring module, for acquiring the concreting information each poured, it is described pour it is mixed Solidifying soil pours information:Pour progress, resource input, unusual condition and temperature data;
Concrete temperature monitoring module, for acquiring the temperature data in concreting process;
Imperial frame monitoring module in concreting process;And
Data center module, receive and store the information of raw material, the production information of concrete, concrete transportation information, Steel transit information, tunnel excavation information, tunnel dragon frame structural information, concreting information and concrete temperature information and dragon Frame modification information, and transmit the information to monitoring client;
Monitoring client display is connect with the data center module, the information for being received described in real-time display.

Claims (6)

1. a kind of constructing tunnel quality tracing system, it is characterised in that:It is supervised including raw material data acquisition module, concrete production Control module, the super deficient monitoring module in tunnel, concrete transportation monitoring module, steel transport vehicle monitoring module, concreting process Imperial frame monitoring module and data center module in monitoring module, concrete temperature monitoring module, concreting process, in data Core module receives raw material data acquisition module, concrete production monitoring module, the super deficient monitoring module in tunnel, concrete transportation prison Control module, steel transport vehicle monitoring module, concreting process monitoring module, concrete temperature monitoring module, concrete pour All information are transmitted to monitoring client by the information of imperial frame monitoring module, data center module during building.
2. constructing tunnel quality tracing system according to claim 1, it is characterised in that:The raw material data acquires mould Block, the information for acquiring every a collection of raw material, the information of the raw material include:Steel, cement, sandstone aggregate, flyash With the information of additive;Concrete production monitoring module, the creation data for acquiring concrete, the production number of the concrete According to including:Production time, Fang Liang, machine outlet, design mixture proportion and the practical match ratio of concrete.
3. constructing tunnel quality tracing system according to claim 1, it is characterised in that:The super deficient monitoring mould in tunnel Block, the creation data for acquiring tunnel excavation;Concrete transportation monitoring module, the number for acquiring cable machine transport concrete According to the data of the transport concrete include:Big truck position, horizontal velocity, small truck position, vertical speed and load.
4. constructing tunnel quality tracing system according to claim 1, it is characterised in that:The steel transport vehicle monitors mould Block, for acquiring the information being transported into tunnel comprising:Contained steel specs, manufacturer and address;Concreting process Monitoring module, for acquiring the concreting information each poured, the concreting information poured includes:Pour into Degree, resource input, unusual condition and temperature data.
5. constructing tunnel quality tracing system according to claim 1, it is characterised in that:The concrete temperature monitors mould Block, for acquiring the temperature data in concreting process;Imperial frame monitoring module in concreting process, for monitoring dragon Frame deformation.
6. a kind of method of such as constructing tunnel quality tracing system described in any one of claim 1 to 5, which is characterized in that packet Include following steps:
(1) information of the acquisition per a collection of raw material, the raw material information include:Steel, cement, sandstone aggregate, flyash and The information of additive;
(2) information of concrete production is acquired, the concrete production information includes:The production time of concrete, goes out machine at Fang Liang Mouth, design mixture proportion and practical match ratio;
(3) information of cable machine transport concrete is acquired, the cable machine transport concrete information includes:Big truck position, horizontal velocity, Small truck position, vertical speed and load;
(4) information of steel transport vehicle is acquired, the steel transport vehicle information includes:Contained steel specs, manufacturer and ground Location;
(5) information of tunnel excavation is acquired;
(6) information of tunnel dragon frame structure is acquired, the tunnel dragon frame structural information includes:Imperial frame steel density, imperial frame type shape And size;
(7) information of concreting in tunnel is acquired, concreting information includes in the tunnel:Pour progress, resource Input, unusual condition and temperature data;
(8) temperature information in concreting process is acquired;
(9) information of imperial frame deformation in concreting process is acquired;
(10) receive and store the information of raw material, the production information of concrete, concrete transportation information, steel transit information, Tunnel excavation information, tunnel dragon frame structural information, concreting information and concrete temperature information and imperial frame modification information, and Transmit the information to monitoring client, the information received described in monitoring client real-time display.
CN201810268518.1A 2018-03-29 2018-03-29 A kind of constructing tunnel quality tracing system and method Pending CN108615104A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810268518.1A CN108615104A (en) 2018-03-29 2018-03-29 A kind of constructing tunnel quality tracing system and method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810268518.1A CN108615104A (en) 2018-03-29 2018-03-29 A kind of constructing tunnel quality tracing system and method

Publications (1)

Publication Number Publication Date
CN108615104A true CN108615104A (en) 2018-10-02

Family

ID=63659366

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810268518.1A Pending CN108615104A (en) 2018-03-29 2018-03-29 A kind of constructing tunnel quality tracing system and method

Country Status (1)

Country Link
CN (1) CN108615104A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111694554A (en) * 2020-06-15 2020-09-22 中铁隧道集团三处有限公司 Visual subway construction quality tracing system and control method thereof
CN113585269A (en) * 2021-09-27 2021-11-02 国能大渡河大数据服务有限公司 Construction safety monitoring method and system for hydropower engineering
JP7423286B2 (en) 2019-12-03 2024-01-29 清水建設株式会社 Concrete construction management device

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP7423286B2 (en) 2019-12-03 2024-01-29 清水建設株式会社 Concrete construction management device
CN111694554A (en) * 2020-06-15 2020-09-22 中铁隧道集团三处有限公司 Visual subway construction quality tracing system and control method thereof
CN113585269A (en) * 2021-09-27 2021-11-02 国能大渡河大数据服务有限公司 Construction safety monitoring method and system for hydropower engineering
CN113585269B (en) * 2021-09-27 2021-12-17 国能大渡河大数据服务有限公司 Construction safety monitoring method and system for hydropower engineering

Similar Documents

Publication Publication Date Title
CN108615104A (en) A kind of constructing tunnel quality tracing system and method
CN103901869B (en) The quality control method of concrete construction
WO2022028038A1 (en) Novel embankment construction method using calcareous sand concrete
CN109581980B (en) Underground mine intelligent mining equipment scheduling system and method
CN102199019A (en) Brick-concrete building garbage road base material and production device and production method thereof
CN103064394A (en) Concrete dam construction quality real-time monitoring method and system
CN103331817A (en) 3D (Three-dimensional) printing method of engineering structure
CN108101456A (en) A kind of big water absorption rate coarse aggregate high-performance marine concrete and its construction
CN106991214A (en) The informatization management method of high speed railway prefabricating Liang Chang based on BIM
CN110488782A (en) Cement concrete batching plant back court intelligent monitor system based on BIM platform
CN107066752A (en) Existing coil holder beam simulative construction method is closed on using the DJ180 Bridge Erectors of BIM technology
CN102873072A (en) Mobile production system capable of demolishing buildings selectively on site and recycling construction waste
CN101125440A (en) Pretensioned beam whole opening prefabricated construction method
CN103896539B (en) Prefabricated sial base green cement concrete bidirectional hole hollow template and manufacture method thereof
CN109518544A (en) A kind of subway precast track plate railway roadbed laying method
CN201704603U (en) Pavement paver capable of constructing across central dividing strip
CN113235451A (en) Construction method of mass concrete
CN112613109A (en) Construction progress and cost management method and device of railway BIM system based on web real-time modeling
CN102324061B (en) Pump-truck and agitating-truck combined-operation dispatching system, method thereof
CN204530499U (en) For the automatic travelling device of highway bridge prefabrication beam slab concrete distributing
CN203031746U (en) Tubular pile concrete feeding system
CN109655853A (en) One kind being used for pavement construction procedure quality dynamic managing and control system
CN114841594A (en) Construction project site concrete section excess management method and system
CN113445381A (en) Construction method for cement gypsum composite stable steel slag base layer
CN208235267U (en) A kind of concrete casting device for both sides of the road subgrade construction

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20181002

WD01 Invention patent application deemed withdrawn after publication