CN108609454A - A kind of segmented setting out method of elevator installation - Google Patents
A kind of segmented setting out method of elevator installation Download PDFInfo
- Publication number
- CN108609454A CN108609454A CN201810450066.9A CN201810450066A CN108609454A CN 108609454 A CN108609454 A CN 108609454A CN 201810450066 A CN201810450066 A CN 201810450066A CN 108609454 A CN108609454 A CN 108609454A
- Authority
- CN
- China
- Prior art keywords
- model
- stage
- transect
- line
- layer doorway
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66B—ELEVATORS; ESCALATORS OR MOVING WALKWAYS
- B66B7/00—Other common features of elevators
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66B—ELEVATORS; ESCALATORS OR MOVING WALKWAYS
- B66B11/00—Main component parts of lifts in, or associated with, buildings or other structures
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66B—ELEVATORS; ESCALATORS OR MOVING WALKWAYS
- B66B19/00—Mining-hoist operation
- B66B19/002—Mining-hoist operation installing or exchanging guide rails
Landscapes
- Engineering & Computer Science (AREA)
- Civil Engineering (AREA)
- Mechanical Engineering (AREA)
- Structural Engineering (AREA)
- Lift-Guide Devices, And Elevator Ropes And Cables (AREA)
Abstract
The invention discloses a kind of segmented setting out method of elevator installation, the lower half portion hoistway of the elevator is completed, insulating course is set in hoistway, first stage loading frame is arranged on the insulating course of hoistway, the pit in hoistway is arranged in lower sample rack, using interim model as second stage layer doorway model, and in interim model both ends hanging layer doorway line-transect, installation second stage layer doorway model behind before and after the model of second stage layer doorway and left and right position is determined by layer doorway line-transect, dismantle interim model, and the installation site of second stage upper rail model is determined according to second stage layer doorway model, setting-out process is completed with this repetitive operation.The present invention installs elevator using the setting out method of segmented, elevator installation work can be made to begin to carry out when hoistway does not build completion, it is matched with civil engineering, hence it is evident that the installation integral cycle for shortening elevator completes civil construction to ensure within the normal duration.
Description
Technical field
The present invention relates to the segmented setting out method that elevator mounting engineering technical field more particularly to a kind of elevator are installed.
Specifically, when hoistway does not build completion, elevator installation work is divided into two sections or more and is installed.
Background technology
With the high speed development of China's economic, urban development is also getting faster, and Re-search on Urbanization process also can further add
Soon.When urban population constantly expands, and economy continues to develop, soil will be especially nervous, and therefore, domestic skyscraper will be a large amount of
It emerges in large numbers, emerging in large numbers for skyscraper means that elevator will enter Rapid development stage.It comes in and goes out in order to facilitate civic, skyscraper will
Express elevator is installed with meet demand.
Due to the quickening that work section gathers, the speed of civil engineering construction is also getting faster, and the installation progress of elevator also will constantly add
Soon.But since the civil construction part of project construction is there is more uncertain factor, when the case where construction speed lags
There is generation, cause the construction period in project later stage at full stretch, very big influence especially is produced on our elevator installation progresses.
Once civil engineering working-day claims, the transfer of elevator shaft just postpones, and client is in order to promote project process at this time, and civil engineering is damaged before making up
The time is lost, often may require that elevator company installs Fire lift with the shortest time, so as to as rapid vertical transport and communications
Tool, while in order to across construction elevator and close outer eaves hole offer condition outside premature removal.And the elevator that client provides at this time
Installation period is seriously to be less than normal installation period;It such as presses the normal duration to install, can not possibly substantially complete.
The traditional mounting means of elevator is installed for whole segmentation, setting out method:Elevator shaft is just opened after the completion of all building
Begin to carry out setting-out, loading setting is arranged in computer room or well headroom, lower sample in pit.In order to meet customer requirement, accelerate installation
The method of the integral cycle of elevator, segmented installation elevator is just come into being, and when civil engineering is built, elevator section construction can be protected
Card elevator is constructed after civil engineering reach a certain height.
Invention content
In order to solve the problems, such as that the traditional mounting means integral cycle length of elevator, the present invention provide a kind of point of elevator installation
Segmentation setting out method, with it is simple, of low cost, convenient for disassembly and assembly, safe, be easy implement, it is adaptable, convenient effectively
The features such as.
The purpose of the present invention will be achieved through the following technical solutions:A kind of segmented setting out method of elevator installation, it is described
The lower half portion hoistway of elevator is completed, and insulating course is arranged in hoistway, and the insulating course in hoistway is arranged in first stage loading frame
On, the pit in hoistway is arranged in lower sample rack, using interim model as second stage layer doorway model, and at interim model both ends
Layer doorway line-transect is hung, is determined by layer doorway line-transect and installs the behind before and after the model of second stage layer doorway and left and right position
Two-stage layer doorway model, dismantles interim model, and determine second stage upper rail model according to second stage layer doorway model
Installation site, with this repetitive operation complete setting-out process.
Preferably, the segmented setting out method of described a kind of elevator installation, before the model of second stage layer doorway
Afterwards position by measure the distance between two groups of second stage layer doorway line-transects and first stage layer doorway line-transect it is whether equal come
It determines, when the distance between two groups of second stage layer doorway line-transects and first stage layer doorway line-transect is equal, interim sample at this time
The front and back relative position of plate is second stage layer doorway model front-rear direction position.
Preferably, the segmented setting out method of described a kind of elevator installation, second stage layer doorway line-transect and the
The distance between one phase layer doorway line-transect measures once every 8~12 meters, ensures interim model and first stage layer door with this
Mouth model is parallel.
Preferably, a kind of segmented setting out method of elevator installation, second stage layer doorway line-transect are in
Vertical state, by overlapping a right-angle side of square with interim model, another right-angle side of square is close to second stage
Layer doorway line-transect, when another right-angle side of square is overlapped with second stage layer doorway line-transect at the line-transect of second stage layer doorway
In vertical state, otherwise, constantly adjusts second stage layer doorway line-transect and second stage layer doorway line-transect is made to be in vertical state.
Preferably, the segmented setting out method of a kind of elevator installation, a left side for second stage layer doorway model
Right position is determined by moving left and right interim model, after moving left and right interim model, second stage layer doorway line-transect and
One phase layer doorway line-transect coincides together, and interim model position is the installation position of second stage layer doorway model at this time
It sets.
Preferably, the segmented setting out method of a kind of elevator installation, the distance that the interim model moves left and right
Equal to the distance between second stage layer doorway line-transect and first stage layer doorway line-transect, second stage layer doorway sample is verified repeatedly
Interim model is moved left and right after the distance between line and first stage layer doorway line-transect, when second stage layer doorway line-transect and first
When phase layer doorway line-transect coincides together, interim model position is the installation site of second stage layer doorway model.
Preferably, the segmented setting out method of a kind of elevator installation, the installation of second stage layer doorway model
After determination, by way of evening up line, it is ensured that the installation parallel with second stage layer doorway model of second stage upper rail model.
Preferably, the segmented setting out method of a kind of elevator installation, the installation of second stage layer doorway model
Afterwards, by measuring the mounting distance between second stage upper rail model and second stage layer doorway model, second stage is determined
The left and right position of upper rail model.
Preferably, the segmented setting out method of a kind of elevator installation, the installation of second stage layer doorway model
Afterwards, whether equal by detecting the distance of center to the second stage upper rail model left and right ends of second stage layer doorway model
To determine the front and back position of second stage upper rail model.
Preferably, the segmented setting out method of described a kind of elevator installation, installation is complete for model in the second stage
Afterwards, the secondary rail line-transect of model hanging on the secondary rail of second stage, when the secondary rail line-transect of second stage and the secondary rail sample of first stage
When line overlaps, confirm that model installation is errorless in second stage.
Compared with prior art, the invention has the advantages that:The present invention is installed using the setting out method of segmented
Elevator can make elevator installation work begin to carry out when hoistway does not build completion, be matched with civil engineering, hence it is evident that shorten electricity
The installation integral cycle of ladder, civil construction is completed to ensure within the normal duration.
Description of the drawings
In order to more clearly explain the embodiment of the invention or the technical proposal in the existing technology, to embodiment or will show below
There is attached drawing needed in technology description to be briefly described, it should be apparent that, the accompanying drawings in the following description is only this
One embodiment of invention without having to pay creative labor, may be used also for those of ordinary skill in the art
With obtain other attached drawings according to these attached drawings.
Fig. 1 is a kind of structural schematic diagram of the segmented setting out method of elevator installation;
Fig. 2 is a kind of side view of the segmented setting out method of elevator installation;
Fig. 3 is a kind of vertical view of the segmented setting out method of elevator installation;
Fig. 4 is second stage upper rail model installation diagram in the segmented setting out method that a kind of elevator is installed;
Fig. 5 is sample rack installation is complete figure in a kind of second stage of the segmented setting out method of the elevator installation.
In figure:1. interim model;2. sample rack in second stage;3. second stage layer doorway line-transect;4. first stage loading
Frame;5. first stage layer doorway line-transect;6. second stage layer doorway model;7. second stage upper rail model;8. lower sample rack.
Specific implementation mode
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete
Site preparation describes, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on
Embodiment in the present invention, those of ordinary skill in the art are obtained every other without creative efforts
Embodiment shall fall within the protection scope of the present invention.
Shown in Fig. 1 to Fig. 5, a kind of segmented setting out method of elevator installation, the lower half portion hoistway of the elevator is
It completes, insulating course is set in hoistway, and on the first stage 4. sample rack is arranged on the insulating course of hoistway, 8. lower sample rack is arranged in well
1. 6. the pit in road is used as second stage layer doorway model using interim model, and 1. layer doorway is hung at both ends in interim model
Line-transect installs second stage layer before and after determining second stage layer doorway model 6. by layer doorway line-transect and behind left and right position
6. 1. doorway model, dismantles interim model, and 6. determine second stage upper rail model 7. according to second stage layer doorway model
Installation site, with this repetitive operation complete setting-out process.
The front and back position of second stage layer doorway model 6. by measure two groups of second stage layer doorway line-transects 3. with
First stage layer doorway line-transect the distance between 5. whether it is equal determine, when two groups of second stage layer doorway line-transects are 3. with first
Phase layer doorway line-transect the distance between 5. equal (A1=A1 ') when, the front and back relative position of interim model 1. is at this time
Two-stage layer doorway model 6. front-rear direction position.Second stage layer doorway line-transect 3. with first stage layer doorway line-transect 5.
The distance between measure primary (A1=A1 '=A2=A2 ') every 8~12 meters, with this ensure interim model 1. with the first stage
Layer doorway model is parallel.
3. second stage layer doorway line-transect is in vertical state, by by a right-angle side of square and interim model
1. overlap, another right-angle side of square close to second stage layer doorway line-transect 3., when another right-angle side of square and second
When phase layer doorway line-transect overlaps 3. 3. otherwise second stage layer doorway line-transect constantly adjusts second stage in vertical state
3. layer doorway line-transect makes second stage layer doorway line-transect 3. be in vertical state.
The left and right position of second stage layer doorway model 6. is determined by moving left and right interim model 1., when left and right
After moving interim model 1., 3. 5. second stage layer doorway line-transect coincides together with first stage layer doorway line-transect, face at this time
When model 1. position is the installation site of second stage layer doorway model 6..The interim model 1. move left and right away from
From equal to second stage layer doorway line-transect 3. with first stage layer doorway line-transect the distance between 5., verify second stage layer repeatedly
Doorway line-transect 3. with first stage layer doorway line-transect the distance between 5. after move left and right interim model 1., when second stage layer door
When mouth line-transect coincides together with first stage layer doorway line-transect 3. 5., 1. position is second stage layer door to interim model
The installation site of mouth model 6..
6. second stage layer doorway model installs determination after, by way of evening up line, it is ensured that in second stage
Guide rail model 7. with the 6. parallel installation of second stage layer doorway model.6. second stage layer doorway model is installed after, pass through
Measure second stage upper rail model 7. with second stage layer doorway model 6. between mounting distance, determine and led in second stage
The left and right position of rail model 7..6. second stage layer doorway model is installed after, by detecting second stage layer doorway model
6. the distances of center to second stage upper rail model 7. left and right ends whether equal determine second stage upper rail model
7. front and back position.Model is after 6. installation is complete in the second stage, the secondary rail sample of model hanging on the secondary rail of second stage
Line confirms model peace in second stage when the secondary rail line-transect of second stage is overlapped with the secondary rail line-transect of first stage (B=B ')
It fills errorless.
The above is merely preferred embodiments of the present invention, be not intended to limit the invention, it is all in spirit herein and
Within principle, any modification, equivalent replacement, improvement and so on should all be included in the protection scope of the present invention.
Claims (10)
1. a kind of segmented setting out method of elevator installation, the lower half portion hoistway of the elevator are completed, it is characterised in that:
Insulating course is set in hoistway, and first stage loading frame is arranged on the insulating course of hoistway, and the pit in hoistway is arranged in lower sample rack, adopts
It uses interim model as second stage layer doorway model, and in interim model both ends hanging layer doorway line-transect, passes through layer doorway sample
Line determines installation second stage layer doorway model behind the front and back and left and right position of second stage layer doorway model, dismantles interim sample
Plate, and determine according to second stage layer doorway model the installation site of second stage upper rail model, it is completed with this repetitive operation
Setting-out process.
2. a kind of segmented setting out method of elevator installation according to claim 1, it is characterised in that:The second stage
The front and back position of layer doorway model is by measuring between two groups of second stage layer doorway line-transects and first stage layer doorway line-transect
Whether distance is equal to determine, when the distance between two groups of second stage layer doorway line-transects and first stage layer doorway line-transect are equal
When, the front and back relative position of interim model is second stage layer doorway model front-rear direction position at this time.
3. a kind of segmented setting out method of elevator installation according to claim 2, it is characterised in that:The second stage
The distance between layer doorway line-transect and first stage layer doorway line-transect measure once every 8~12 meters, ensure interim model with this
It is parallel with first stage layer doorway model.
4. a kind of segmented setting out method of elevator installation according to claim 1, it is characterised in that:The second stage
Layer doorway line-transect is in vertical state, by the way that a right-angle side of square is overlapped with interim model, another right angle of square
While close to second stage layer doorway line-transect, the second-order when another right-angle side of square is overlapped with second stage layer doorway line-transect
Section layer doorway line-transect is in vertical state, otherwise, constantly adjusts second stage layer doorway line-transect and makes second stage layer doorway sample
Line is in vertical state.
5. a kind of segmented setting out method of elevator installation according to claim 1, it is characterised in that:The second stage
The left and right position of layer doorway model is determined by moving left and right interim model, after moving left and right interim model, second stage
Layer doorway line-transect coincides together with first stage layer doorway line-transect, and interim model position is second stage layer door at this time
The installation site of mouth model.
6. a kind of segmented setting out method of elevator installation according to claim 5, it is characterised in that:The interim model
The distance moved left and right is equal to the distance between second stage layer doorway line-transect and first stage layer doorway line-transect, verifies the repeatedly
Interim model is moved left and right after the distance between two-stage layer doorway line-transect and first stage layer doorway line-transect, when second stage layer
When doorway line-transect coincides together with first stage layer doorway line-transect, interim model position is second stage layer doorway sample
The installation site of plate.
7. a kind of segmented setting out method of elevator installation according to claim 1, it is characterised in that:The second stage
After the model installation of layer doorway determines, by way of evening up line, it is ensured that second stage upper rail model and second stage layer door
The parallel installation of mouth model.
8. a kind of segmented setting out method of elevator installation according to claim 1, it is characterised in that:The second stage
After the model installation of layer doorway, by measuring the locating distance between second stage upper rail model and second stage layer doorway model
From determining the left and right position of second stage upper rail model.
9. a kind of segmented setting out method of elevator installation according to claim 1, it is characterised in that:The second stage
After the model installation of layer doorway, by the center to second stage upper rail model left and right ends for detecting second stage layer doorway model
Distance whether equal determine the front and back position of second stage upper rail model.
10. a kind of segmented setting out method of elevator installation according to claim 1, it is characterised in that:The second-order
Model is after installation is complete in section, the secondary rail line-transect of model hanging on the secondary rail of second stage, when second stage secondary rail line-transect with
When the secondary rail line-transect of first stage overlaps, confirm that model installation is errorless in second stage.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810450066.9A CN108609454B (en) | 2018-05-11 | 2018-05-11 | A kind of segmented setting out method of elevator installation |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810450066.9A CN108609454B (en) | 2018-05-11 | 2018-05-11 | A kind of segmented setting out method of elevator installation |
Publications (2)
Publication Number | Publication Date |
---|---|
CN108609454A true CN108609454A (en) | 2018-10-02 |
CN108609454B CN108609454B (en) | 2019-09-27 |
Family
ID=63662877
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810450066.9A Active CN108609454B (en) | 2018-05-11 | 2018-05-11 | A kind of segmented setting out method of elevator installation |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108609454B (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109339399A (en) * | 2018-11-23 | 2019-02-15 | 宝钢钢构有限公司 | A kind of section construction method of steel construction in elevator shaft |
CN111472547A (en) * | 2020-04-01 | 2020-07-31 | 日立电梯(中国)有限公司 | Lofting method for scaffold-free elevator |
WO2021057193A1 (en) * | 2019-09-28 | 2021-04-01 | 中建三局集团有限公司 | Skyscraper firefighting elevator scaffolding-less segmented installation and construction method |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2000073485A (en) * | 1998-09-02 | 2000-03-07 | Misawa Homes Co Ltd | Mounting structure for elevator for building |
JP2002188212A (en) * | 2000-12-19 | 2002-07-05 | Toa:Kk | Prefabricating device for elevator-mounted building |
CN104340813A (en) * | 2014-10-30 | 2015-02-11 | 中国建筑股份有限公司 | Construction method of elevator mounting |
CN105366494A (en) * | 2015-11-11 | 2016-03-02 | 四川汇辰精密机械有限公司 | Elevator mounting process |
-
2018
- 2018-05-11 CN CN201810450066.9A patent/CN108609454B/en active Active
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2000073485A (en) * | 1998-09-02 | 2000-03-07 | Misawa Homes Co Ltd | Mounting structure for elevator for building |
JP2002188212A (en) * | 2000-12-19 | 2002-07-05 | Toa:Kk | Prefabricating device for elevator-mounted building |
CN104340813A (en) * | 2014-10-30 | 2015-02-11 | 中国建筑股份有限公司 | Construction method of elevator mounting |
CN105366494A (en) * | 2015-11-11 | 2016-03-02 | 四川汇辰精密机械有限公司 | Elevator mounting process |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109339399A (en) * | 2018-11-23 | 2019-02-15 | 宝钢钢构有限公司 | A kind of section construction method of steel construction in elevator shaft |
CN109339399B (en) * | 2018-11-23 | 2023-08-25 | 宝钢钢构有限公司 | Sectional construction method of steel structure in elevator hoistway |
WO2021057193A1 (en) * | 2019-09-28 | 2021-04-01 | 中建三局集团有限公司 | Skyscraper firefighting elevator scaffolding-less segmented installation and construction method |
CN111472547A (en) * | 2020-04-01 | 2020-07-31 | 日立电梯(中国)有限公司 | Lofting method for scaffold-free elevator |
Also Published As
Publication number | Publication date |
---|---|
CN108609454B (en) | 2019-09-27 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108609454B (en) | A kind of segmented setting out method of elevator installation | |
CN103046933B (en) | Shield station-crossing tunneling and station parallel construction method | |
CN108999281A (en) | A kind of novel precast concrete bean column node and its construction method | |
CN104594201A (en) | Method for erecting pier top steel beam through single-side pier-side bracket | |
CN104631819A (en) | Template system of arc-shaped facade arch-shaped concrete door beam and erection method of template system | |
CN110359485A (en) | A kind of pre-buried trough fixation device of steel form and its construction method | |
CN206408951U (en) | A kind of architectural industrialization project conversion layer position level ladder muscle | |
CN109440987A (en) | A kind of construction method of the element type curtain wall of super high-rise building | |
CN106337687A (en) | Convenient segmented support method for mine slant chute | |
CN103775091B (en) | For Subarea detecting method and the device of graded crossing constructing tunnel | |
CN207110029U (en) | A kind of assembled house | |
Zhang et al. | Development and application of mechanized matching equipment for high-speed railway tunnel construction | |
CN105386447A (en) | Construction method for replacement support of post-cast strip in construction site | |
CN210685982U (en) | Automatic monitoring system for deformation of subway crossing building | |
CN111472839B (en) | Comprehensive seepage control-based quantitative calculation method for water discharge of water-rich tunnel construction | |
CN107190989A (en) | Shaped steel partition plate external wall construction method | |
CN206468003U (en) | A kind of Xin Jiamo guard bar structures | |
CN208250928U (en) | A kind of steel and wood composite template | |
CN206458067U (en) | Operation platform in high-rise building elevator | |
CN202914109U (en) | Integral type lining system of light-section cable tunnel | |
CN105257005A (en) | Method for segmenting steel-structured transfer truss and segmented steel-structured transfer truss | |
CN204492177U (en) | A kind of template system of arc facade arch concrete door beam | |
CN204384738U (en) | Poured band of outer wall of basement cement concrete draw-in groove construction hoisting equipment | |
CN208870182U (en) | A kind of novel precast concrete bean column node | |
CN206625850U (en) | Tunnel concrete liner Simple steel scaffold |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |