CN108609454A - A kind of segmented setting out method of elevator installation - Google Patents

A kind of segmented setting out method of elevator installation Download PDF

Info

Publication number
CN108609454A
CN108609454A CN201810450066.9A CN201810450066A CN108609454A CN 108609454 A CN108609454 A CN 108609454A CN 201810450066 A CN201810450066 A CN 201810450066A CN 108609454 A CN108609454 A CN 108609454A
Authority
CN
China
Prior art keywords
model
stage
transect
line
layer doorway
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810450066.9A
Other languages
Chinese (zh)
Other versions
CN108609454B (en
Inventor
吴子坚
黄照明
黄伟栊
萧粤柏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hitachi Elevator China Co Ltd
Original Assignee
Hitachi Elevator China Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hitachi Elevator China Co Ltd filed Critical Hitachi Elevator China Co Ltd
Priority to CN201810450066.9A priority Critical patent/CN108609454B/en
Publication of CN108609454A publication Critical patent/CN108609454A/en
Application granted granted Critical
Publication of CN108609454B publication Critical patent/CN108609454B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66BELEVATORS; ESCALATORS OR MOVING WALKWAYS
    • B66B7/00Other common features of elevators
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66BELEVATORS; ESCALATORS OR MOVING WALKWAYS
    • B66B11/00Main component parts of lifts in, or associated with, buildings or other structures
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66BELEVATORS; ESCALATORS OR MOVING WALKWAYS
    • B66B19/00Mining-hoist operation
    • B66B19/002Mining-hoist operation installing or exchanging guide rails

Landscapes

  • Engineering & Computer Science (AREA)
  • Civil Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Structural Engineering (AREA)
  • Lift-Guide Devices, And Elevator Ropes And Cables (AREA)

Abstract

The invention discloses a kind of segmented setting out method of elevator installation, the lower half portion hoistway of the elevator is completed, insulating course is set in hoistway, first stage loading frame is arranged on the insulating course of hoistway, the pit in hoistway is arranged in lower sample rack, using interim model as second stage layer doorway model, and in interim model both ends hanging layer doorway line-transect, installation second stage layer doorway model behind before and after the model of second stage layer doorway and left and right position is determined by layer doorway line-transect, dismantle interim model, and the installation site of second stage upper rail model is determined according to second stage layer doorway model, setting-out process is completed with this repetitive operation.The present invention installs elevator using the setting out method of segmented, elevator installation work can be made to begin to carry out when hoistway does not build completion, it is matched with civil engineering, hence it is evident that the installation integral cycle for shortening elevator completes civil construction to ensure within the normal duration.

Description

A kind of segmented setting out method of elevator installation
Technical field
The present invention relates to the segmented setting out method that elevator mounting engineering technical field more particularly to a kind of elevator are installed. Specifically, when hoistway does not build completion, elevator installation work is divided into two sections or more and is installed.
Background technology
With the high speed development of China's economic, urban development is also getting faster, and Re-search on Urbanization process also can further add Soon.When urban population constantly expands, and economy continues to develop, soil will be especially nervous, and therefore, domestic skyscraper will be a large amount of It emerges in large numbers, emerging in large numbers for skyscraper means that elevator will enter Rapid development stage.It comes in and goes out in order to facilitate civic, skyscraper will Express elevator is installed with meet demand.
Due to the quickening that work section gathers, the speed of civil engineering construction is also getting faster, and the installation progress of elevator also will constantly add Soon.But since the civil construction part of project construction is there is more uncertain factor, when the case where construction speed lags There is generation, cause the construction period in project later stage at full stretch, very big influence especially is produced on our elevator installation progresses. Once civil engineering working-day claims, the transfer of elevator shaft just postpones, and client is in order to promote project process at this time, and civil engineering is damaged before making up The time is lost, often may require that elevator company installs Fire lift with the shortest time, so as to as rapid vertical transport and communications Tool, while in order to across construction elevator and close outer eaves hole offer condition outside premature removal.And the elevator that client provides at this time Installation period is seriously to be less than normal installation period;It such as presses the normal duration to install, can not possibly substantially complete.
The traditional mounting means of elevator is installed for whole segmentation, setting out method:Elevator shaft is just opened after the completion of all building Begin to carry out setting-out, loading setting is arranged in computer room or well headroom, lower sample in pit.In order to meet customer requirement, accelerate installation The method of the integral cycle of elevator, segmented installation elevator is just come into being, and when civil engineering is built, elevator section construction can be protected Card elevator is constructed after civil engineering reach a certain height.
Invention content
In order to solve the problems, such as that the traditional mounting means integral cycle length of elevator, the present invention provide a kind of point of elevator installation Segmentation setting out method, with it is simple, of low cost, convenient for disassembly and assembly, safe, be easy implement, it is adaptable, convenient effectively The features such as.
The purpose of the present invention will be achieved through the following technical solutions:A kind of segmented setting out method of elevator installation, it is described The lower half portion hoistway of elevator is completed, and insulating course is arranged in hoistway, and the insulating course in hoistway is arranged in first stage loading frame On, the pit in hoistway is arranged in lower sample rack, using interim model as second stage layer doorway model, and at interim model both ends Layer doorway line-transect is hung, is determined by layer doorway line-transect and installs the behind before and after the model of second stage layer doorway and left and right position Two-stage layer doorway model, dismantles interim model, and determine second stage upper rail model according to second stage layer doorway model Installation site, with this repetitive operation complete setting-out process.
Preferably, the segmented setting out method of described a kind of elevator installation, before the model of second stage layer doorway Afterwards position by measure the distance between two groups of second stage layer doorway line-transects and first stage layer doorway line-transect it is whether equal come It determines, when the distance between two groups of second stage layer doorway line-transects and first stage layer doorway line-transect is equal, interim sample at this time The front and back relative position of plate is second stage layer doorway model front-rear direction position.
Preferably, the segmented setting out method of described a kind of elevator installation, second stage layer doorway line-transect and the The distance between one phase layer doorway line-transect measures once every 8~12 meters, ensures interim model and first stage layer door with this Mouth model is parallel.
Preferably, a kind of segmented setting out method of elevator installation, second stage layer doorway line-transect are in Vertical state, by overlapping a right-angle side of square with interim model, another right-angle side of square is close to second stage Layer doorway line-transect, when another right-angle side of square is overlapped with second stage layer doorway line-transect at the line-transect of second stage layer doorway In vertical state, otherwise, constantly adjusts second stage layer doorway line-transect and second stage layer doorway line-transect is made to be in vertical state.
Preferably, the segmented setting out method of a kind of elevator installation, a left side for second stage layer doorway model Right position is determined by moving left and right interim model, after moving left and right interim model, second stage layer doorway line-transect and One phase layer doorway line-transect coincides together, and interim model position is the installation position of second stage layer doorway model at this time It sets.
Preferably, the segmented setting out method of a kind of elevator installation, the distance that the interim model moves left and right Equal to the distance between second stage layer doorway line-transect and first stage layer doorway line-transect, second stage layer doorway sample is verified repeatedly Interim model is moved left and right after the distance between line and first stage layer doorway line-transect, when second stage layer doorway line-transect and first When phase layer doorway line-transect coincides together, interim model position is the installation site of second stage layer doorway model.
Preferably, the segmented setting out method of a kind of elevator installation, the installation of second stage layer doorway model After determination, by way of evening up line, it is ensured that the installation parallel with second stage layer doorway model of second stage upper rail model.
Preferably, the segmented setting out method of a kind of elevator installation, the installation of second stage layer doorway model Afterwards, by measuring the mounting distance between second stage upper rail model and second stage layer doorway model, second stage is determined The left and right position of upper rail model.
Preferably, the segmented setting out method of a kind of elevator installation, the installation of second stage layer doorway model Afterwards, whether equal by detecting the distance of center to the second stage upper rail model left and right ends of second stage layer doorway model To determine the front and back position of second stage upper rail model.
Preferably, the segmented setting out method of described a kind of elevator installation, installation is complete for model in the second stage Afterwards, the secondary rail line-transect of model hanging on the secondary rail of second stage, when the secondary rail line-transect of second stage and the secondary rail sample of first stage When line overlaps, confirm that model installation is errorless in second stage.
Compared with prior art, the invention has the advantages that:The present invention is installed using the setting out method of segmented Elevator can make elevator installation work begin to carry out when hoistway does not build completion, be matched with civil engineering, hence it is evident that shorten electricity The installation integral cycle of ladder, civil construction is completed to ensure within the normal duration.
Description of the drawings
In order to more clearly explain the embodiment of the invention or the technical proposal in the existing technology, to embodiment or will show below There is attached drawing needed in technology description to be briefly described, it should be apparent that, the accompanying drawings in the following description is only this One embodiment of invention without having to pay creative labor, may be used also for those of ordinary skill in the art With obtain other attached drawings according to these attached drawings.
Fig. 1 is a kind of structural schematic diagram of the segmented setting out method of elevator installation;
Fig. 2 is a kind of side view of the segmented setting out method of elevator installation;
Fig. 3 is a kind of vertical view of the segmented setting out method of elevator installation;
Fig. 4 is second stage upper rail model installation diagram in the segmented setting out method that a kind of elevator is installed;
Fig. 5 is sample rack installation is complete figure in a kind of second stage of the segmented setting out method of the elevator installation.
In figure:1. interim model;2. sample rack in second stage;3. second stage layer doorway line-transect;4. first stage loading Frame;5. first stage layer doorway line-transect;6. second stage layer doorway model;7. second stage upper rail model;8. lower sample rack.
Specific implementation mode
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation describes, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, those of ordinary skill in the art are obtained every other without creative efforts Embodiment shall fall within the protection scope of the present invention.
Shown in Fig. 1 to Fig. 5, a kind of segmented setting out method of elevator installation, the lower half portion hoistway of the elevator is It completes, insulating course is set in hoistway, and on the first stage 4. sample rack is arranged on the insulating course of hoistway, 8. lower sample rack is arranged in well 1. 6. the pit in road is used as second stage layer doorway model using interim model, and 1. layer doorway is hung at both ends in interim model Line-transect installs second stage layer before and after determining second stage layer doorway model 6. by layer doorway line-transect and behind left and right position 6. 1. doorway model, dismantles interim model, and 6. determine second stage upper rail model 7. according to second stage layer doorway model Installation site, with this repetitive operation complete setting-out process.
The front and back position of second stage layer doorway model 6. by measure two groups of second stage layer doorway line-transects 3. with First stage layer doorway line-transect the distance between 5. whether it is equal determine, when two groups of second stage layer doorway line-transects are 3. with first Phase layer doorway line-transect the distance between 5. equal (A1=A1 ') when, the front and back relative position of interim model 1. is at this time Two-stage layer doorway model 6. front-rear direction position.Second stage layer doorway line-transect 3. with first stage layer doorway line-transect 5. The distance between measure primary (A1=A1 '=A2=A2 ') every 8~12 meters, with this ensure interim model 1. with the first stage Layer doorway model is parallel.
3. second stage layer doorway line-transect is in vertical state, by by a right-angle side of square and interim model 1. overlap, another right-angle side of square close to second stage layer doorway line-transect 3., when another right-angle side of square and second When phase layer doorway line-transect overlaps 3. 3. otherwise second stage layer doorway line-transect constantly adjusts second stage in vertical state 3. layer doorway line-transect makes second stage layer doorway line-transect 3. be in vertical state.
The left and right position of second stage layer doorway model 6. is determined by moving left and right interim model 1., when left and right After moving interim model 1., 3. 5. second stage layer doorway line-transect coincides together with first stage layer doorway line-transect, face at this time When model 1. position is the installation site of second stage layer doorway model 6..The interim model 1. move left and right away from From equal to second stage layer doorway line-transect 3. with first stage layer doorway line-transect the distance between 5., verify second stage layer repeatedly Doorway line-transect 3. with first stage layer doorway line-transect the distance between 5. after move left and right interim model 1., when second stage layer door When mouth line-transect coincides together with first stage layer doorway line-transect 3. 5., 1. position is second stage layer door to interim model The installation site of mouth model 6..
6. second stage layer doorway model installs determination after, by way of evening up line, it is ensured that in second stage Guide rail model 7. with the 6. parallel installation of second stage layer doorway model.6. second stage layer doorway model is installed after, pass through Measure second stage upper rail model 7. with second stage layer doorway model 6. between mounting distance, determine and led in second stage The left and right position of rail model 7..6. second stage layer doorway model is installed after, by detecting second stage layer doorway model 6. the distances of center to second stage upper rail model 7. left and right ends whether equal determine second stage upper rail model 7. front and back position.Model is after 6. installation is complete in the second stage, the secondary rail sample of model hanging on the secondary rail of second stage Line confirms model peace in second stage when the secondary rail line-transect of second stage is overlapped with the secondary rail line-transect of first stage (B=B ') It fills errorless.
The above is merely preferred embodiments of the present invention, be not intended to limit the invention, it is all in spirit herein and Within principle, any modification, equivalent replacement, improvement and so on should all be included in the protection scope of the present invention.

Claims (10)

1. a kind of segmented setting out method of elevator installation, the lower half portion hoistway of the elevator are completed, it is characterised in that: Insulating course is set in hoistway, and first stage loading frame is arranged on the insulating course of hoistway, and the pit in hoistway is arranged in lower sample rack, adopts It uses interim model as second stage layer doorway model, and in interim model both ends hanging layer doorway line-transect, passes through layer doorway sample Line determines installation second stage layer doorway model behind the front and back and left and right position of second stage layer doorway model, dismantles interim sample Plate, and determine according to second stage layer doorway model the installation site of second stage upper rail model, it is completed with this repetitive operation Setting-out process.
2. a kind of segmented setting out method of elevator installation according to claim 1, it is characterised in that:The second stage The front and back position of layer doorway model is by measuring between two groups of second stage layer doorway line-transects and first stage layer doorway line-transect Whether distance is equal to determine, when the distance between two groups of second stage layer doorway line-transects and first stage layer doorway line-transect are equal When, the front and back relative position of interim model is second stage layer doorway model front-rear direction position at this time.
3. a kind of segmented setting out method of elevator installation according to claim 2, it is characterised in that:The second stage The distance between layer doorway line-transect and first stage layer doorway line-transect measure once every 8~12 meters, ensure interim model with this It is parallel with first stage layer doorway model.
4. a kind of segmented setting out method of elevator installation according to claim 1, it is characterised in that:The second stage Layer doorway line-transect is in vertical state, by the way that a right-angle side of square is overlapped with interim model, another right angle of square While close to second stage layer doorway line-transect, the second-order when another right-angle side of square is overlapped with second stage layer doorway line-transect Section layer doorway line-transect is in vertical state, otherwise, constantly adjusts second stage layer doorway line-transect and makes second stage layer doorway sample Line is in vertical state.
5. a kind of segmented setting out method of elevator installation according to claim 1, it is characterised in that:The second stage The left and right position of layer doorway model is determined by moving left and right interim model, after moving left and right interim model, second stage Layer doorway line-transect coincides together with first stage layer doorway line-transect, and interim model position is second stage layer door at this time The installation site of mouth model.
6. a kind of segmented setting out method of elevator installation according to claim 5, it is characterised in that:The interim model The distance moved left and right is equal to the distance between second stage layer doorway line-transect and first stage layer doorway line-transect, verifies the repeatedly Interim model is moved left and right after the distance between two-stage layer doorway line-transect and first stage layer doorway line-transect, when second stage layer When doorway line-transect coincides together with first stage layer doorway line-transect, interim model position is second stage layer doorway sample The installation site of plate.
7. a kind of segmented setting out method of elevator installation according to claim 1, it is characterised in that:The second stage After the model installation of layer doorway determines, by way of evening up line, it is ensured that second stage upper rail model and second stage layer door The parallel installation of mouth model.
8. a kind of segmented setting out method of elevator installation according to claim 1, it is characterised in that:The second stage After the model installation of layer doorway, by measuring the locating distance between second stage upper rail model and second stage layer doorway model From determining the left and right position of second stage upper rail model.
9. a kind of segmented setting out method of elevator installation according to claim 1, it is characterised in that:The second stage After the model installation of layer doorway, by the center to second stage upper rail model left and right ends for detecting second stage layer doorway model Distance whether equal determine the front and back position of second stage upper rail model.
10. a kind of segmented setting out method of elevator installation according to claim 1, it is characterised in that:The second-order Model is after installation is complete in section, the secondary rail line-transect of model hanging on the secondary rail of second stage, when second stage secondary rail line-transect with When the secondary rail line-transect of first stage overlaps, confirm that model installation is errorless in second stage.
CN201810450066.9A 2018-05-11 2018-05-11 A kind of segmented setting out method of elevator installation Active CN108609454B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810450066.9A CN108609454B (en) 2018-05-11 2018-05-11 A kind of segmented setting out method of elevator installation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810450066.9A CN108609454B (en) 2018-05-11 2018-05-11 A kind of segmented setting out method of elevator installation

Publications (2)

Publication Number Publication Date
CN108609454A true CN108609454A (en) 2018-10-02
CN108609454B CN108609454B (en) 2019-09-27

Family

ID=63662877

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810450066.9A Active CN108609454B (en) 2018-05-11 2018-05-11 A kind of segmented setting out method of elevator installation

Country Status (1)

Country Link
CN (1) CN108609454B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109339399A (en) * 2018-11-23 2019-02-15 宝钢钢构有限公司 A kind of section construction method of steel construction in elevator shaft
CN111472547A (en) * 2020-04-01 2020-07-31 日立电梯(中国)有限公司 Lofting method for scaffold-free elevator
WO2021057193A1 (en) * 2019-09-28 2021-04-01 中建三局集团有限公司 Skyscraper firefighting elevator scaffolding-less segmented installation and construction method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000073485A (en) * 1998-09-02 2000-03-07 Misawa Homes Co Ltd Mounting structure for elevator for building
JP2002188212A (en) * 2000-12-19 2002-07-05 Toa:Kk Prefabricating device for elevator-mounted building
CN104340813A (en) * 2014-10-30 2015-02-11 中国建筑股份有限公司 Construction method of elevator mounting
CN105366494A (en) * 2015-11-11 2016-03-02 四川汇辰精密机械有限公司 Elevator mounting process

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000073485A (en) * 1998-09-02 2000-03-07 Misawa Homes Co Ltd Mounting structure for elevator for building
JP2002188212A (en) * 2000-12-19 2002-07-05 Toa:Kk Prefabricating device for elevator-mounted building
CN104340813A (en) * 2014-10-30 2015-02-11 中国建筑股份有限公司 Construction method of elevator mounting
CN105366494A (en) * 2015-11-11 2016-03-02 四川汇辰精密机械有限公司 Elevator mounting process

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109339399A (en) * 2018-11-23 2019-02-15 宝钢钢构有限公司 A kind of section construction method of steel construction in elevator shaft
CN109339399B (en) * 2018-11-23 2023-08-25 宝钢钢构有限公司 Sectional construction method of steel structure in elevator hoistway
WO2021057193A1 (en) * 2019-09-28 2021-04-01 中建三局集团有限公司 Skyscraper firefighting elevator scaffolding-less segmented installation and construction method
CN111472547A (en) * 2020-04-01 2020-07-31 日立电梯(中国)有限公司 Lofting method for scaffold-free elevator

Also Published As

Publication number Publication date
CN108609454B (en) 2019-09-27

Similar Documents

Publication Publication Date Title
CN108609454B (en) A kind of segmented setting out method of elevator installation
CN103046933B (en) Shield station-crossing tunneling and station parallel construction method
CN108999281A (en) A kind of novel precast concrete bean column node and its construction method
CN104594201A (en) Method for erecting pier top steel beam through single-side pier-side bracket
CN104631819A (en) Template system of arc-shaped facade arch-shaped concrete door beam and erection method of template system
CN110359485A (en) A kind of pre-buried trough fixation device of steel form and its construction method
CN206408951U (en) A kind of architectural industrialization project conversion layer position level ladder muscle
CN109440987A (en) A kind of construction method of the element type curtain wall of super high-rise building
CN106337687A (en) Convenient segmented support method for mine slant chute
CN103775091B (en) For Subarea detecting method and the device of graded crossing constructing tunnel
CN207110029U (en) A kind of assembled house
Zhang et al. Development and application of mechanized matching equipment for high-speed railway tunnel construction
CN105386447A (en) Construction method for replacement support of post-cast strip in construction site
CN210685982U (en) Automatic monitoring system for deformation of subway crossing building
CN111472839B (en) Comprehensive seepage control-based quantitative calculation method for water discharge of water-rich tunnel construction
CN107190989A (en) Shaped steel partition plate external wall construction method
CN206468003U (en) A kind of Xin Jiamo guard bar structures
CN208250928U (en) A kind of steel and wood composite template
CN206458067U (en) Operation platform in high-rise building elevator
CN202914109U (en) Integral type lining system of light-section cable tunnel
CN105257005A (en) Method for segmenting steel-structured transfer truss and segmented steel-structured transfer truss
CN204492177U (en) A kind of template system of arc facade arch concrete door beam
CN204384738U (en) Poured band of outer wall of basement cement concrete draw-in groove construction hoisting equipment
CN208870182U (en) A kind of novel precast concrete bean column node
CN206625850U (en) Tunnel concrete liner Simple steel scaffold

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant