CN108590227A - A kind of Core Walls Structure express passway that people's goods is dual-purpose - Google Patents
A kind of Core Walls Structure express passway that people's goods is dual-purpose Download PDFInfo
- Publication number
- CN108590227A CN108590227A CN201810731139.1A CN201810731139A CN108590227A CN 108590227 A CN108590227 A CN 108590227A CN 201810731139 A CN201810731139 A CN 201810731139A CN 108590227 A CN108590227 A CN 108590227A
- Authority
- CN
- China
- Prior art keywords
- people
- core walls
- walls structure
- dual
- aisle
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 47
- 239000010959 steel Substances 0.000 claims abstract description 47
- 230000008878 coupling Effects 0.000 claims abstract description 20
- 238000010168 coupling process Methods 0.000 claims abstract description 20
- 238000005859 coupling reaction Methods 0.000 claims abstract description 20
- 238000009434 installation Methods 0.000 claims description 7
- 230000001681 protective effect Effects 0.000 claims description 5
- 238000006243 chemical reaction Methods 0.000 claims description 3
- 239000000725 suspension Substances 0.000 claims description 3
- 240000007594 Oryza sativa Species 0.000 claims description 2
- 235000007164 Oryza sativa Nutrition 0.000 claims description 2
- 235000009566 rice Nutrition 0.000 claims description 2
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims 2
- 230000007123 defense Effects 0.000 claims 1
- 238000010276 construction Methods 0.000 abstract description 17
- 241000282326 Felis catus Species 0.000 description 3
- 238000010586 diagram Methods 0.000 description 2
- 238000005516 engineering process Methods 0.000 description 2
- 239000000463 material Substances 0.000 description 2
- 238000000465 moulding Methods 0.000 description 2
- 238000004873 anchoring Methods 0.000 description 1
- 230000009194 climbing Effects 0.000 description 1
- 239000002131 composite material Substances 0.000 description 1
- 210000001699 lower leg Anatomy 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 238000000034 method Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 230000002787 reinforcement Effects 0.000 description 1
- 238000007493 shaping process Methods 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G27/00—Temporary arrangements for giving access from one level to another for men or vehicles, e.g. steps, ramps
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/32—Safety or protective measures for persons during the construction of buildings
- E04G21/3204—Safety or protective measures for persons during the construction of buildings against falling down
Abstract
The present invention proposes a kind of Core Walls Structure express passway that people's goods is dual-purpose, including:Aisle platform, it is disposed in proximity in the Core Walls Structure coupling beam of people's Cargo Lift side, the horizontal girder steel of aisle platform one end is anchored in Core Walls Structure coupling beam, the horizontal girder steel of the other end overhangs to people's Cargo Lift ladder cage doorway, the overhanging is that the horizontal girder steel of the aisle platform is connected and fixed on by steel wire rope in upper track coupling beam, wherein, foot guard plate, guardrail and edge protection are provided on the aisle platform.The dual-purpose Core Walls Structure express passway of people's goods proposed by the present invention, it is about 300Kg that people's Cargo Lift, which overhangs aisle platform weight, simple and light easy for construction.The time required to greatly reducing personnel's lower work face in actual use, the safety of construction equipment is carried when greatly improving worker or more vertical channel.Aisle platform safety is firm in actual use, and is additionally arranged at the bottom limit measure in aisle while also playing the measure of protection finished product.
Description
Technical field
The invention belongs to architectural engineering construction technique fields, relate generally to the technical measures in Super High work progress, tool
Body is a kind of Core Walls Structure express passway that people's goods is dual-purpose.
Background technology
Outline border Construction of Steel Structure vertical channel mainly has the plug-in steel of outline border to climb in existing Construction Technology of Super Tall Buildingin measure
Ladder, Core Walls Structure lateral crus hand or shaping operation platform vertical channel.Its main working measure is:Plug-in steel cat ladder mainly uses side
Pipe or reinforcement fabrication molding, generally in place with steel column lifting installation, disadvantage is single cat ladder limited height, because it is dangerous high
Degree may be only configured in outline border story height or 5 meters, the outer operating platform vertical channel of Core Walls Structure mainly set up using scaffold tubes or
Square tube make molding, generally set up after the completion of outline border steel girder erection or this turned over, disadvantage be because material utilization amount is larger can not
Every layer of setting of energy, it is relatively time-consuming laborious above and below personnel in the case of height difference is excessively high.
Invention content
Because pioneer Construction of Steel Structure of the steel construction in construction of super highrise building need to surpass civil construction multilayer, and because of superelevation
People's Cargo Lift is only to steel platform operating surface at the top of Core Walls Structure in layer core wall structure diversity Core Walls Structure, to solve Construction of Steel Structure
Personnel in the safety of outline border working face vertical channel, reliability and economy by means of people's Cargo Lift in Core Walls Structure, in steel construction
Construction working face setting people's Cargo Lift overhangs aisle platform and facilitates worker or more.
In order to achieve the above object, the present invention proposes a kind of Core Walls Structure express passway that people's goods is dual-purpose, including:
Aisle platform is disposed in proximity in the Core Walls Structure coupling beam of people's Cargo Lift side, the level of aisle platform one end
Girder steel is anchored in Core Walls Structure coupling beam, and the horizontal girder steel of the other end overhangs to people's Cargo Lift ladder cage doorway, and the overhanging is walked for described in
The horizontal girder steel of road platform is connected and fixed on by steel wire rope in upper track coupling beam,
Wherein, foot guard plate, guardrail and edge protection are provided on the aisle platform.
Further, the horizontal girder steel of the aisle platform is fixedly connected by embedded part with Core Walls Structure coupling beam.
Further, the girder of the aisle platform and secondary beam are made using No. 14 channel steels.
Further, the guardrail and edge protection are made of 25mm square tubes.
Further, the edge protection is provided with protective door.
Further, the edge protection and the height of protective door are 1.8 meters.
Further, the height of the guardrail is 1.2 meters.
Further, the cantilever span of the horizontal girder steel of the aisle platform is 1.76m, and the anchoring in Core Walls Structure coupling beam is grown
Degree is 0.76m, and it is 0.70m to overhang the horizontal girder steel spacing i.e. width of aisle platform.
Further, the overhanging of the aisle platform is to be connected in upper track coupling beam by unloading first, flower basket bolt and steel wire rope
Anchor point, then under tower crane hook conversion suspension centre, aisle platform is pushed into installation site, is welded and fixed after dropping place, gets rid of the tight gaily decorated basket
Bolt.
Further, steel mesh piece is completely spread on the aisle platform.
The dual-purpose Core Walls Structure express passway of people's goods proposed by the present invention, it is about 300Kg that people's Cargo Lift, which overhangs aisle platform weight,
It is simple and light easy for construction.The time required to greatly reducing personnel's lower work face in actual use, it is greatly improved
Worker up and down vertical channel when carry the safety of construction equipment.Aisle platform safety is firm in actual use, and
It is additionally arranged at the bottom limit measure in aisle while also playing the measure of protection finished product.
Description of the drawings
Fig. 1 show the dual-purpose Core Walls Structure express passway structural schematic diagram of people's goods of present pre-ferred embodiments.
It is the dual-purpose Core Walls Structure express passway floor plan of people's goods shown in Fig. 2.
It is the dual-purpose Core Walls Structure express passway edge protection elevation of people's goods shown in Fig. 3.
Specific implementation mode
The specific implementation mode of the present invention is provided below in conjunction with attached drawing, but the present invention is not limited to the following embodiments and the accompanying drawings.Root
According to following explanation and claims, advantages and features of the invention will become apparent from.It should be noted that attached drawing be all made of it is very simple
The form of change and use non-accurate ratio, be only used for conveniently, lucidly aid in illustrating the embodiment of the present invention purpose.
It please refers to Fig.1 and Fig. 2, Fig. 1 show the dual-purpose Core Walls Structure express passway knots of people's goods of present pre-ferred embodiments
Structure schematic diagram.It is the dual-purpose Core Walls Structure express passway floor plan of people's goods shown in Fig. 2.The present invention proposes that a kind of people's goods is dual-purpose
Core Walls Structure express passway, including:
Aisle platform 10 is disposed in proximity in people's Cargo Lift side Core Walls Structure coupling beam 100, described 10 one end of aisle platform
Horizontal girder steel 20 be anchored in Core Walls Structure coupling beam 100, the horizontal girder steel 20 of the other end overhangs to people's Cargo Lift ladder cage doorway, described
Overhanging is that the horizontal girder steel 20 of the aisle platform is connected and fixed on by steel wire rope 200 in upper track coupling beam 300, wherein described
Foot guard plate 400, guardrail 500 and edge protection 600 are provided on aisle platform 10.
Main installation steps are that people's Cargo Lift aisle platform is hung to the required work surface installed, installation insurance using tower crane
Rope, is welded and fixed, and is listed and comes into operation after acceptance(check).
According to present pre-ferred embodiments, the horizontal girder steel 20 of the aisle platform 10 is connected by embedded part 700 and Core Walls Structure
Beam 100 is fixedly connected.
The girder and secondary beam of the aisle platform 10 are made using No. 14 channel steels.The guardrail 500 and edge protection 600 are adopted
It is made of 25mm square tubes.Safety rope uses Φ 16mm 6x37+FC-1670MPa steel wire ropes, 2t bow shackles, 1.6t OO type spiral shells
Spinner.
Referring to FIG. 3, being the dual-purpose Core Walls Structure express passway edge protection elevation of people's goods shown in Fig. 3.The aisle is flat
Completely spread steel mesh piece on platform, the edge protection 600 is provided with protective door 700, and the height of the edge protection and protective door is 1.8
The height of rice, the guardrail is 1.2 meters.
The cantilever span of the horizontal girder steel of the aisle platform is 1.76m, and the anchorage length in Core Walls Structure coupling beam is
0.76m, it is 0.70m to overhang the horizontal girder steel spacing i.e. width of aisle platform.Allowable bearing evenly load 1.50kN/m2, most
Raft putting material load 0.50kN.Through design checking, people's Cargo Lift overhanging aisle platform meets stability requirement, safety rope and embedded part
Meet requirement for bearing capacity.
Main installation steps are that people's Cargo Lift aisle platform is hung to the required work surface installed using tower crane, and the aisle is flat
The overhanging of platform is by unloading the anchor point in first, flower basket bolt and steel wire rope connection upper track coupling beam, then hooking conversion under tower crane and hang
Aisle platform is pushed into installation site, is welded and fixed after dropping place, gets rid of tight flower basket bolt by point.When turning over again, first connected using tower crane
Suspension centre is connect, subsequent gas cutting cuts off aisle platform and embedded part tie point, and loose flower basket bolt and steel wire rope tower crane are hooked up and turned over.
In actual use, people's Cargo Lift overhangs aisle platform significant increase construction efficiency.Site operation personnel indicate
This measure brings great convenience for upper and lower work surface, and personnel need not use in carrying tool climbing composite steel cat ladder
Work surface only needs 5 minutes up and down after this aisle platform, while it is hidden to decrease the safety such as falling object from high altitude and personnel's high falling
Suffer from.
In conclusion the Core Walls Structure express passway that people's goods proposed by the present invention is dual-purpose, people's Cargo Lift overhangs aisle platform weight
About 300Kg, it is simple and light easy for construction.Personnel's lower work face is greatly reduced in actual use to be taken
Between, the safety of construction equipment is carried when greatly improving worker or more vertical channel.Aisle platform in actual use
Safety and firmness, and be additionally arranged at the bottom limit measure in aisle while also playing the measure of protection finished product.
Although the present invention has been disclosed as a preferred embodiment, however, it is not to limit the invention.Skill belonging to the present invention
Has usually intellectual in art field, without departing from the spirit and scope of the present invention, when can be used for a variety of modifications and variations.Cause
This, the scope of protection of the present invention is defined by those of the claims.
Claims (10)
1. a kind of Core Walls Structure express passway that people's goods is dual-purpose, which is characterized in that including:
Aisle platform is disposed in proximity in the Core Walls Structure coupling beam of people's Cargo Lift side, the horizontal girder steel of aisle platform one end
It is anchored in Core Walls Structure coupling beam, the horizontal girder steel of the other end overhangs to people's Cargo Lift ladder cage doorway, and the overhanging is that the aisle is flat
The horizontal girder steel of platform is connected and fixed on by steel wire rope in upper track coupling beam,
Wherein, foot guard plate, guardrail and edge protection are provided on the aisle platform.
2. the dual-purpose Core Walls Structure express passway of people's goods according to claim 1, which is characterized in that the water of the aisle platform
Flat girder steel is fixedly connected by embedded part with Core Walls Structure coupling beam.
3. the dual-purpose Core Walls Structure express passway of people's goods according to claim 1, which is characterized in that the master of the aisle platform
Beam and secondary beam are made using No. 14 channel steels.
4. the dual-purpose Core Walls Structure express passway of people's goods according to claim 1, which is characterized in that the guardrail and face frontier defense
Shield is made of 25mm square tubes.
5. the dual-purpose Core Walls Structure express passway of people's goods according to claim 1, which is characterized in that the edge protection setting
There is protective door.
6. the dual-purpose Core Walls Structure express passway of people's goods according to claim 5, which is characterized in that the edge protection and anti-
The height for protecting door is 1.8 meters.
7. the dual-purpose Core Walls Structure express passway of people's goods according to claim 1, which is characterized in that the height of the guardrail is
1.2 rice.
8. the dual-purpose Core Walls Structure express passway of people's goods according to claim 1, which is characterized in that the water of the aisle platform
The cantilever span of flat girder steel is 1.76m, and the anchorage length in Core Walls Structure coupling beam is 0.76m, overhangs horizontal girder steel spacing i.e. aisle
The width of platform is 0.70m.
9. the dual-purpose Core Walls Structure express passway of people's goods according to claim 1, which is characterized in that the aisle platform hangs
It chooses by unloading the anchor point in first, flower basket bolt and steel wire rope connection upper track coupling beam, conversion suspension centre then to be hooked under tower crane, will be walked
Road platform is pushed into installation site, is welded and fixed after dropping place, gets rid of tight flower basket bolt.
10. the dual-purpose Core Walls Structure express passway of people's goods according to claim 1, which is characterized in that on the aisle platform
Completely spread steel mesh piece.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810731139.1A CN108590227A (en) | 2018-07-05 | 2018-07-05 | A kind of Core Walls Structure express passway that people's goods is dual-purpose |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810731139.1A CN108590227A (en) | 2018-07-05 | 2018-07-05 | A kind of Core Walls Structure express passway that people's goods is dual-purpose |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108590227A true CN108590227A (en) | 2018-09-28 |
Family
ID=63614958
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810731139.1A Pending CN108590227A (en) | 2018-07-05 | 2018-07-05 | A kind of Core Walls Structure express passway that people's goods is dual-purpose |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108590227A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110965808A (en) * | 2019-11-26 | 2020-04-07 | 上海二十冶建设有限公司 | Construction method of externally hung stair and packway of fabricated building |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
FR2671575A1 (en) * | 1991-01-10 | 1992-07-17 | Roussel Daniel | Guard rail for shuttering boards (wall forms) |
CN202125079U (en) * | 2011-06-01 | 2012-01-25 | 山东宁建建设集团有限公司 | Construction-elevator overhanging type discharging platform device |
CN103174303A (en) * | 2011-12-23 | 2013-06-26 | 五冶集团上海有限公司 | Movable overhung unloading platform and manufacture and installation method thereof |
CN204001751U (en) * | 2014-06-11 | 2014-12-10 | 中建钢构有限公司 | Super high steel structure construction overhanging unloading platform |
CN105401733A (en) * | 2015-12-03 | 2016-03-16 | 上海建工一建集团有限公司 | Channel connecting core barrel with peripheral steel structure and construction method for channel |
CN208564047U (en) * | 2018-07-05 | 2019-03-01 | 上海市机械施工集团有限公司 | A kind of people's Cargo Lift overhanging aisle platform |
-
2018
- 2018-07-05 CN CN201810731139.1A patent/CN108590227A/en active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
FR2671575A1 (en) * | 1991-01-10 | 1992-07-17 | Roussel Daniel | Guard rail for shuttering boards (wall forms) |
CN202125079U (en) * | 2011-06-01 | 2012-01-25 | 山东宁建建设集团有限公司 | Construction-elevator overhanging type discharging platform device |
CN103174303A (en) * | 2011-12-23 | 2013-06-26 | 五冶集团上海有限公司 | Movable overhung unloading platform and manufacture and installation method thereof |
CN204001751U (en) * | 2014-06-11 | 2014-12-10 | 中建钢构有限公司 | Super high steel structure construction overhanging unloading platform |
CN105401733A (en) * | 2015-12-03 | 2016-03-16 | 上海建工一建集团有限公司 | Channel connecting core barrel with peripheral steel structure and construction method for channel |
CN208564047U (en) * | 2018-07-05 | 2019-03-01 | 上海市机械施工集团有限公司 | A kind of people's Cargo Lift overhanging aisle platform |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110965808A (en) * | 2019-11-26 | 2020-04-07 | 上海二十冶建设有限公司 | Construction method of externally hung stair and packway of fabricated building |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103603504B (en) | The dynamo-electric heavy caliber standpipe of super highrise building is with the method for main body progress lifting construction | |
CN207144449U (en) | A kind of hoistway operation platform | |
CN102535845A (en) | Construction method of bearing frame of corridor structure | |
CN105908960B (en) | Scaffold for large space construction | |
CN205955237U (en) | Plug -type platform of unloading of encorbelmenting | |
CN107700719A (en) | A kind of hanging method of high-rise building glass curtain wall | |
CN203487803U (en) | Safety protection structure for elevator shaft construction | |
CN104652813A (en) | Tower crane construction technology used for super high-rise building steel structure | |
CN201826542U (en) | Self-climbing protective screening | |
CN208564047U (en) | A kind of people's Cargo Lift overhanging aisle platform | |
CN209723438U (en) | A kind of novel coagulation body precast stair plate | |
CN202990427U (en) | Climbing discharging platform | |
CN106150057A (en) | A kind of split blade type hydraulic pressure lift climbing frame | |
CN108590227A (en) | A kind of Core Walls Structure express passway that people's goods is dual-purpose | |
CN101818563B (en) | Jack-up integral lifting mobile platform and using method | |
CN113062584A (en) | Multipoint elevator shaft construction lifting platform and construction method | |
CN209011528U (en) | A kind of all steel attachment type raise scaffold | |
CN106193621A (en) | Fabricated construction superimposed sheet string hangs construction method | |
CN216810895U (en) | Elevator shaft operation platform | |
CN203654754U (en) | Double-layered overhanging type discharging platform | |
CN203547125U (en) | Column type overall steel platform hydraulic creeping formwork | |
CN214828568U (en) | Tower crane pedestrian passageway capable of being integrally lifted along with climbing frame | |
CN205894715U (en) | Light steel structure is semi -automatic under enclosed construction constructs from hoisting machine that climbs | |
CN205134921U (en) | Building outer wall concrete constructional column hangs construction platform | |
CN201495786U (en) | Lifting type insulation and protective device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WD01 | Invention patent application deemed withdrawn after publication | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20180928 |