CN108589815B - Blow off pipe is laid and is used ditching equipment - Google Patents

Blow off pipe is laid and is used ditching equipment Download PDF

Info

Publication number
CN108589815B
CN108589815B CN201810380914.3A CN201810380914A CN108589815B CN 108589815 B CN108589815 B CN 108589815B CN 201810380914 A CN201810380914 A CN 201810380914A CN 108589815 B CN108589815 B CN 108589815B
Authority
CN
China
Prior art keywords
frame
belt pulley
rotating shaft
frame body
trenching
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201810380914.3A
Other languages
Chinese (zh)
Other versions
CN108589815A (en
Inventor
吴华斌
吴玲玲
李逍
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiaxing City Xun Cheng Information Technology Co. Ltds
Original Assignee
Jiaxing City Xun Cheng Information Technology Co Ltds
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiaxing City Xun Cheng Information Technology Co Ltds filed Critical Jiaxing City Xun Cheng Information Technology Co Ltds
Priority to CN201810380914.3A priority Critical patent/CN108589815B/en
Publication of CN108589815A publication Critical patent/CN108589815A/en
Application granted granted Critical
Publication of CN108589815B publication Critical patent/CN108589815B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F5/00Dredgers or soil-shifting machines for special purposes
    • E02F5/02Dredgers or soil-shifting machines for special purposes for digging trenches or ditches
    • E02F5/08Dredgers or soil-shifting machines for special purposes for digging trenches or ditches with digging wheels turning round an axis

Abstract

The invention relates to trenching equipment, in particular to trenching equipment for laying a sewage discharge pipe. The invention aims to solve the technical problem of providing the trenching equipment for laying the sewage discharge pipe, which has high trenching speed and uniform trenching depth. The invention provides trenching equipment for laying a drain pipe, which comprises a frame, a push handle, a slide rail, a slide block, a frame body, a cylinder, a first bearing seat, a first rotating shaft and the like; the pushing hands are installed at the top outside the frame, two slide rails are installed on the front side and the rear side in the frame, slide blocks are arranged on the inner side faces of the slide rails in an all-sliding mode, a frame body is installed between the front slide block and the rear slide block, and two cylinders are installed at the top in the frame. The first motor is used for driving, so that the roller can be driven to rotate, the scraping blade can be driven to rotate, an operator can push the rotary trencher to dig a trench on the ground, and the small trench is dug by the scraper first, so that the trenching efficiency can be improved, and the effects of high trenching speed and uniform depth of the dug trench are achieved.

Description

Blow off pipe is laid and is used ditching equipment
Technical Field
The invention relates to trenching equipment, in particular to trenching equipment for laying a sewage discharge pipe.
Background
Sewage treatment: the sewage is purified to reach the water quality requirement of draining a certain water body or reusing the water body. Sewage treatment is widely applied to various fields such as buildings, agriculture, traffic, energy, petrifaction, environmental protection, urban landscape, medical treatment, catering and the like, and is increasingly used in daily life of common people.
When handling sewage, need lay the blow off pipe, need subaerial ditching when laying the blow off pipe, the ditching speed is slow during artifical ditching, the ditch depth of digging out is inhomogeneous, consequently needs urgent need to develop a quick, the ditch depth of digging out of ditch of digging out and lays and use ditching equipment.
Disclosure of Invention
(1) Technical problem to be solved
The invention aims to overcome the defects of low trenching speed and uneven excavated depth of a trench during manual trenching, and provides trenching equipment for laying a sewage discharge pipe, which has high trenching speed and uniform excavated depth of the trench.
(2) Technical scheme
In order to solve the technical problem, the invention provides trenching equipment for laying a sewage pipe, which comprises a frame, a pushing handle, slide rails, slide blocks, a frame body, air cylinders, first bearing seats, first rotating shafts, rollers, scraping sheets, universal wheels, a first belt pulley, a first motor, a second rotating shaft, a second belt pulley and a first flat belt, wherein the pushing handle is arranged at the top outside the frame, the front side and the rear side in the frame are respectively provided with two slide rails, the inner side surfaces of the slide rails are respectively provided with the slide blocks in a sliding manner, the frame body is arranged between the front slide block and the rear slide block, the top in the frame is provided with two air cylinders, the bottom ends of telescopic rods of the two air cylinders are connected with the top outside the frame body, the first bearing seats are respectively arranged at the middle parts of the front side and the rear side of the frame in an embedded manner, the first rotating shafts are connected with bearings in the first, a first belt pulley is installed behind the first rotating shaft, a first opening is formed in the middle of the top of the frame body, a first motor is installed behind the top of the outer portion of the frame body, a second rotating shaft is connected to an output shaft of the first motor through a coupler, a second belt pulley is installed at the rear end of the second rotating shaft, and a first flat belt is connected between the first belt pulley and the second belt pulley.
Preferably, the belt conveyor further comprises mounting rods, second bearing seats, a third rotating shaft, a cylinder, a scraper, a third belt pulley, a fourth belt pulley and a second flat belt, wherein the two mounting rods are mounted at the lower part of the left side face of the frame body, the second bearing seats are mounted at the tail ends of the two mounting rods in an embedded mode, bearings in the two second bearing seats are connected with the third rotating shaft, the cylinder is mounted in the middle of the third rotating shaft and located between the two mounting rods, the scraper is connected to the circumferential direction of the cylinder, the third belt pulley is mounted at the rear end of the third rotating shaft, a second opening is formed in the lower part of the left side of the frame body, the fourth belt pulley is mounted in front of the first rotating shaft.
Preferably, the frame further comprises transverse plates, guide rods, first springs and arc-shaped rubber pads, the transverse plates are mounted on the left side and the right side of the bottom in the frame, sliding holes are formed in the tops of the two transverse plates, the guide rods are arranged in the sliding holes in a sliding mode, the first springs are connected between the bottoms of the guide rods and the sliding holes, and the arc-shaped rubber pads are mounted at the top ends of the guide rods.
Preferably, still including mounting panel, sleeve, movable rod, arc and second spring, the mounting panel is installed to the outer left surface lower part of frame, and the sleeve is installed to mounting panel bottom left, and the sleeve internal sliding formula is equipped with the movable rod, is connected with the second spring between top in movable rod top and the sleeve, and the arc is installed to the movable rod bottom.
The working principle is as follows: when the invention is used, an operator pushes the invention to a designated place through a pushing hand, the operator starts the first motor to rotate again, the first motor can drive the second rotating shaft to rotate, the second rotating shaft can drive the second belt pulley to rotate, the second belt pulley can drive the first belt pulley to rotate through the first flat belt, the first belt pulley can drive the first rotating shaft to rotate, the first rotating shaft can drive the roller to rotate, the roller can drive the scraping blade to rotate, the operator starts the cylinder to extend again, the air cylinder can drive the frame body to move downwards, the sliding rail and the sliding block play a guiding role, the frame body can drive the scraping blade to move downwards, so that the scraping blade can dig a trench on the soil, the operator can push the invention through the universal wheel while digging the trench, the operator can move while digging the trench, after the trench digging is finished, the operator stops the first motor, the operator starts the air cylinder to shorten again, the air cylinder can drive the frame body to move upwards, so that the scraping sheet can be driven to move upwards, after the scraping sheet is separated from the ground, an operator can hold the push handle, and the universal wheel can push the scraper away.
Because still including the installation pole, the second bearing frame, the third pivot, the drum, the scraper, the third belt pulley, fourth belt pulley and the flat belt of second, two installation poles are installed to framework left surface lower part, the second bearing frame is installed to two installation pole end homogeneous embedding, the bearing in two second bearing frames is connected with the third pivot, third pivot mid-mounting has the drum, the drum is located between two installation poles, the circumference of drum is connected with the scraper, the third belt pulley is installed to third pivot rear end, framework left side lower part is opened there is the second opening, the fourth belt pulley is installed in first pivot the place ahead, be connected with the flat belt of second between third belt pulley and the fourth belt pulley. Therefore, the first rotating shaft rotates to drive the fourth belt pulley to rotate, the fourth belt pulley drives the third belt pulley to rotate through the second flat belt, the third belt pulley can drive the third rotating shaft to rotate, the third rotating shaft can drive the cylinder to rotate, the cylinder can drive the scraper to rotate, and the scraper can dig out small grooves in the ground, so that the ditching efficiency can be improved.
Because still including diaphragm, guide arm, first spring, arc rubber pad, the diaphragm is all installed to both sides about the bottom in the frame, and two diaphragm tops all open there is the slide opening, and the guide arm that all is equipped with of equal slidingtype in the slide opening is connected with first spring between guide arm bottom and the slide opening, and the arc rubber pad is installed on the guide arm top. Therefore, when the sliding block moves downwards, the sliding block can not be separated from the sliding rail under the buffer action of the first spring and the guide rod after contacting the arc-shaped rubber pad.
Because still including mounting panel, sleeve, movable rod, arc and second spring, the mounting panel is installed to the outer left surface lower part of frame, and the sleeve is installed to mounting panel bottom left, and the sleeve internal sliding formula is equipped with the movable rod, is connected with the second spring between top in movable rod top and the sleeve, and the arc is installed to the movable rod bottom. Therefore, when the movable plate moves, the arc-shaped plate can be always contacted with the ground under the action of the movable rod and the second spring, so that sundries such as stones in front can be pushed away, and the normal work of the movable plate can not be influenced.
(3) Advantageous effects
The first motor is used for driving, so that the roller can be driven to rotate, the scraping blade can be driven to rotate, an operator can push the rotary trencher to dig a trench on the ground, and the small trench is dug by the scraper first, so that the trenching efficiency can be improved, and the effects of high trenching speed and uniform depth of the dug trench are achieved.
Drawings
Fig. 1 is a first front view structure diagram of the present invention.
Fig. 2 is a second front view structure diagram of the present invention.
Fig. 3 is a left side view structural diagram of the present invention.
Fig. 4 is an enlarged schematic view of part a of the present invention.
Fig. 5 is a third schematic view of the present invention.
The labels in the figures are: 1-frame, 2-pushing handle, 3-sliding rail, 4-sliding block, 5-frame, 6-cylinder, 7-first bearing seat, 8-first rotating shaft, 9-roller, 10-scraping blade, 11-universal wheel, 12-first belt pulley, 13-first opening, 14-first motor, 15-second rotating shaft, 16-second belt pulley, 17-first flat belt, 18-mounting rod, 19-second bearing seat, 20-third rotating shaft, 21-cylinder, 22-scraping blade, 23-third belt pulley, 24-fourth belt pulley, 25-second opening, 26-second flat belt, 27-transverse plate, 28-sliding hole, 29-guide rod, 30-first spring, 31-arc rubber pad, 32-mounting plate, 33-sleeve, 34-movable rod, 35-arc plate and 36-second spring.
Detailed Description
The invention is further described below with reference to the figures and examples.
Example 1
A ditching device for laying a sewage draining pipe is shown in figures 1-5 and comprises a frame 1, a pushing handle 2, a sliding rail 3, a sliding block 4, a frame body 5, a cylinder 6, a first bearing seat 7, a first rotating shaft 8, a roller 9, a scraping blade 10, a universal wheel 11, a first belt pulley 12, a first motor 14, a second rotating shaft 15, a second belt pulley 16 and a first flat belt 17, wherein the pushing handle 2 is arranged at the outer top of the frame 1, two sliding rails 3 are respectively arranged at the front side and the rear side in the frame 1, the sliding block 4 is arranged at the inner side surface of each sliding rail 3 in a sliding way, the frame body 5 is arranged between the front sliding block 4 and the rear sliding block 4, the two cylinders 6 are arranged at the inner top of the frame 1, the bottom ends of telescopic rods of the two cylinders 6 are connected with the outer top of the frame body 5, the first bearing seats 7 are respectively arranged at the middle parts of the front side and, the doctor-bar 10 is installed to the even interval of circumference of cylinder 9, the universal wheel 11 is installed to the even interval in frame 1 bottom, first belt pulley 12 is installed to first pivot 8 rear, it has first opening 13 to open in the middle of 5 tops of framework, first motor 14 is installed at the outer top rear of framework 5, there is second pivot 15 through the coupling joint on first motor 14's the output shaft, second belt pulley 16 is installed to 15 rear ends of second pivot, be connected with first flat belt 17 between first belt pulley 12 and the second belt pulley 16.
Example 2
A ditching device for laying a sewage draining pipe is shown in figures 1-5 and comprises a frame 1, a pushing handle 2, a sliding rail 3, a sliding block 4, a frame body 5, a cylinder 6, a first bearing seat 7, a first rotating shaft 8, a roller 9, a scraping blade 10, a universal wheel 11, a first belt pulley 12, a first motor 14, a second rotating shaft 15, a second belt pulley 16 and a first flat belt 17, wherein the pushing handle 2 is arranged at the outer top of the frame 1, two sliding rails 3 are respectively arranged at the front side and the rear side in the frame 1, the sliding block 4 is arranged at the inner side surface of each sliding rail 3 in a sliding way, the frame body 5 is arranged between the front sliding block 4 and the rear sliding block 4, the two cylinders 6 are arranged at the inner top of the frame 1, the bottom ends of telescopic rods of the two cylinders 6 are connected with the outer top of the frame body 5, the first bearing seats 7 are respectively arranged at the middle parts of the front side and, the doctor-bar 10 is installed to the even interval of circumference of cylinder 9, the universal wheel 11 is installed to the even interval in frame 1 bottom, first belt pulley 12 is installed to first pivot 8 rear, it has first opening 13 to open in the middle of 5 tops of framework, first motor 14 is installed at the outer top rear of framework 5, there is second pivot 15 through the coupling joint on first motor 14's the output shaft, second belt pulley 16 is installed to 15 rear ends of second pivot, be connected with first flat belt 17 between first belt pulley 12 and the second belt pulley 16.
Still including installation pole 18, second bearing frame 19, third pivot 20, drum 21, scraper 22, third belt pulley 23, fourth belt pulley 24 and the flat belt 26 of second, two installation poles 18 are installed to 5 left surface lower parts of framework, the equal embedded second bearing frame 19 of installing in two installation pole 18 terminal, the bearing in two second bearing frames 19 is connected with third pivot 20, third pivot 20 mid-mounting has drum 21, drum 21 is located between two installation poles 18, the circumference of drum 21 is connected with scraper 22, third belt pulley 23 is installed to 20 rear ends of third pivot, framework 5 left side lower part is opened there is the second opening 25, fourth belt pulley 24 is installed in 8 the place ahead of first pivot, be connected with the flat belt 26 of second between third belt pulley 23 and the fourth belt pulley 24.
Example 3
A ditching device for laying a sewage draining pipe is shown in figures 1-5 and comprises a frame 1, a pushing handle 2, a sliding rail 3, a sliding block 4, a frame body 5, a cylinder 6, a first bearing seat 7, a first rotating shaft 8, a roller 9, a scraping blade 10, a universal wheel 11, a first belt pulley 12, a first motor 14, a second rotating shaft 15, a second belt pulley 16 and a first flat belt 17, wherein the pushing handle 2 is arranged at the outer top of the frame 1, two sliding rails 3 are respectively arranged at the front side and the rear side in the frame 1, the sliding block 4 is arranged at the inner side surface of each sliding rail 3 in a sliding way, the frame body 5 is arranged between the front sliding block 4 and the rear sliding block 4, the two cylinders 6 are arranged at the inner top of the frame 1, the bottom ends of telescopic rods of the two cylinders 6 are connected with the outer top of the frame body 5, the first bearing seats 7 are respectively arranged at the middle parts of the front side and, the doctor-bar 10 is installed to the even interval of circumference of cylinder 9, the universal wheel 11 is installed to the even interval in frame 1 bottom, first belt pulley 12 is installed to first pivot 8 rear, it has first opening 13 to open in the middle of 5 tops of framework, first motor 14 is installed at the outer top rear of framework 5, there is second pivot 15 through the coupling joint on first motor 14's the output shaft, second belt pulley 16 is installed to 15 rear ends of second pivot, be connected with first flat belt 17 between first belt pulley 12 and the second belt pulley 16.
Still including installation pole 18, second bearing frame 19, third pivot 20, drum 21, scraper 22, third belt pulley 23, fourth belt pulley 24 and the flat belt 26 of second, two installation poles 18 are installed to 5 left surface lower parts of framework, the equal embedded second bearing frame 19 of installing in two installation pole 18 terminal, the bearing in two second bearing frames 19 is connected with third pivot 20, third pivot 20 mid-mounting has drum 21, drum 21 is located between two installation poles 18, the circumference of drum 21 is connected with scraper 22, third belt pulley 23 is installed to 20 rear ends of third pivot, framework 5 left side lower part is opened there is the second opening 25, fourth belt pulley 24 is installed in 8 the place ahead of first pivot, be connected with the flat belt 26 of second between third belt pulley 23 and the fourth belt pulley 24.
The frame comprises a frame body 1 and is characterized by further comprising transverse plates 27, guide rods 29, first springs 30 and arc-shaped rubber pads 31, the transverse plates 27 are mounted on the left side and the right side of the bottom in the frame body 1, sliding holes 28 are formed in the tops of the two transverse plates 27, the guide rods 29 are arranged in the sliding holes 28 in a sliding mode, the first springs 30 are connected between the bottoms of the guide rods 29 and the sliding holes 28, and the arc-shaped rubber pads 31 are mounted at the top ends of the guide rods.
Example 4
A ditching device for laying a sewage draining pipe is shown in figures 1-5 and comprises a frame 1, a pushing handle 2, a sliding rail 3, a sliding block 4, a frame body 5, a cylinder 6, a first bearing seat 7, a first rotating shaft 8, a roller 9, a scraping blade 10, a universal wheel 11, a first belt pulley 12, a first motor 14, a second rotating shaft 15, a second belt pulley 16 and a first flat belt 17, wherein the pushing handle 2 is arranged at the outer top of the frame 1, two sliding rails 3 are respectively arranged at the front side and the rear side in the frame 1, the sliding block 4 is arranged at the inner side surface of each sliding rail 3 in a sliding way, the frame body 5 is arranged between the front sliding block 4 and the rear sliding block 4, the two cylinders 6 are arranged at the inner top of the frame 1, the bottom ends of telescopic rods of the two cylinders 6 are connected with the outer top of the frame body 5, the first bearing seats 7 are respectively arranged at the middle parts of the front side and, the doctor-bar 10 is installed to the even interval of circumference of cylinder 9, the universal wheel 11 is installed to the even interval in frame 1 bottom, first belt pulley 12 is installed to first pivot 8 rear, it has first opening 13 to open in the middle of 5 tops of framework, first motor 14 is installed at the outer top rear of framework 5, there is second pivot 15 through the coupling joint on first motor 14's the output shaft, second belt pulley 16 is installed to 15 rear ends of second pivot, be connected with first flat belt 17 between first belt pulley 12 and the second belt pulley 16.
Still including installation pole 18, second bearing frame 19, third pivot 20, drum 21, scraper 22, third belt pulley 23, fourth belt pulley 24 and the flat belt 26 of second, two installation poles 18 are installed to 5 left surface lower parts of framework, the equal embedded second bearing frame 19 of installing in two installation pole 18 terminal, the bearing in two second bearing frames 19 is connected with third pivot 20, third pivot 20 mid-mounting has drum 21, drum 21 is located between two installation poles 18, the circumference of drum 21 is connected with scraper 22, third belt pulley 23 is installed to 20 rear ends of third pivot, framework 5 left side lower part is opened there is the second opening 25, fourth belt pulley 24 is installed in 8 the place ahead of first pivot, be connected with the flat belt 26 of second between third belt pulley 23 and the fourth belt pulley 24.
The frame comprises a frame body 1 and is characterized by further comprising transverse plates 27, guide rods 29, first springs 30 and arc-shaped rubber pads 31, the transverse plates 27 are mounted on the left side and the right side of the bottom in the frame body 1, sliding holes 28 are formed in the tops of the two transverse plates 27, the guide rods 29 are arranged in the sliding holes 28 in a sliding mode, the first springs 30 are connected between the bottoms of the guide rods 29 and the sliding holes 28, and the arc-shaped rubber pads 31 are mounted at the top ends of the guide rods.
Still including mounting panel 32, sleeve 33, movable rod 34, arc 35 and second spring 36, mounting panel 32 is installed to the outer left surface lower part of frame 1, and sleeve 33 is installed to mounting panel 32 bottom left, and sleeve 33 internal sliding formula is equipped with movable rod 34, is connected with second spring 36 between the top in movable rod 34 top and the sleeve 33, and arc 35 is installed to movable rod 34 bottom.
The working principle is as follows: when the invention is used, an operator pushes the invention to a designated place through the push handle 2, the operator starts the first motor 14 to rotate, the first motor 14 can drive the second rotating shaft 15 to rotate, the second rotating shaft 15 can drive the second belt pulley 16 to rotate, the second belt pulley 16 can drive the first belt pulley 12 to rotate through the first flat belt 17, the first belt pulley 12 can drive the first rotating shaft 8 to rotate, the first rotating shaft 8 can drive the roller 9 to rotate, the roller 9 can drive the scraping blade 10 to rotate, the operator starts the air cylinder 6 to extend, the air cylinder 6 can drive the frame body 5 to move downwards, the slide rail 3 and the slide block 4 play a role in guiding, the frame body 5 can drive the scraping blade 10 to move downwards, so that the scraping blade 10 can dig a trench on the ground, and the operator can push the invention through the universal wheel 11 while digging the trench, so as to move while digging, after trenching is finished, an operator turns off the first motor 14, the operator starts the air cylinder 6 again to shorten, the air cylinder 6 can drive the frame body 5 to move upwards, so that the scraping blade 10 can be driven to move upwards, and after the scraping blade 10 is separated from the ground, the operator can hold the push handle 2 and push the invention away through the universal wheel 11.
Because still including installation pole 18, second bearing frame 19, third pivot 20, drum 21, scraper 22, third belt pulley 23, fourth belt pulley 24 and the flat belt 26 of second, two installation poles 18 are installed to framework 5 left surface lower part, the equal embedded second bearing frame 19 of installing of two installation pole 18 terminal, the bearing in two second bearing frames 19 is connected with third pivot 20, drum 21 is installed to third pivot 20 mid-mounting, drum 21 is located between two installation poles 18, the circumference of drum 21 is connected with scraper 22, third belt pulley 23 is installed to third pivot 20 rear end, framework 5 left side lower part is opened there is the second opening 25, fourth belt pulley 24 is installed in first pivot 8 the place ahead, be connected with the flat belt 26 of second between third belt pulley 23 and the fourth belt pulley 24. Therefore, the first rotating shaft 8 rotates to drive the fourth belt pulley 24 to rotate, the fourth belt pulley 24 drives the third belt pulley 23 to rotate through the second flat belt 26, the third belt pulley 23 can drive the third rotating shaft 20 to rotate, the third rotating shaft 20 can drive the cylinder 21 to rotate, the cylinder 21 can drive the scraper 22 to rotate, and the scraper 22 can dig a small groove in the ground, so that the trenching efficiency can be improved.
Because still including diaphragm 27, guide arm 29, first spring 30, arc rubber pad 31, both sides are all installed with diaphragm 27 about the bottom in frame 1, and both open at two diaphragm 27 tops have slide opening 28, and the guide arm 29 is equipped with to the even slidingtype in the slide opening 28, is connected with first spring 30 between guide arm 29 bottom and the slide opening 28, and arc rubber pad 31 is installed at guide arm 29 top. Therefore, when the sliding block 4 moves downwards, the sliding block 4 can not be separated from the sliding rail 3 under the buffering action of the first spring 30 and the guide rod 29 after the sliding block 4 touches the arc-shaped rubber pad 31.
Because still including mounting panel 32, sleeve 33, movable rod 34, arc 35 and second spring 36, mounting panel 32 is installed to the outer left surface lower part of frame 1, and sleeve 33 is installed to mounting panel 32 bottom left, and sleeve 33 internal sliding is equipped with movable rod 34, is connected with second spring 36 between the top of movable rod 34 and the interior top of sleeve 33, and arc 35 is installed to movable rod 34 bottom. Therefore, when the invention moves, the arc-shaped plate 35 can be always contacted with the ground under the action of the movable rod 34 and the second spring 36, so that sundries such as stones in front can be pushed away, and the normal work of the invention is not influenced.
The above examples are merely representative of preferred embodiments of the present invention, and the description thereof is more specific and detailed, but not to be construed as limiting the scope of the present invention. It should be noted that, for those skilled in the art, various changes, modifications and substitutions can be made without departing from the spirit of the present invention, and these are all within the scope of the present invention. Therefore, the protection scope of the present patent shall be subject to the appended claims.

Claims (1)

1. A ditching device for laying a sewage draining pipe is characterized by comprising a frame (1), a push handle (2), slide rails (3), slide blocks (4), a frame body (5), air cylinders (6), a first bearing seat (7), a first rotating shaft (8), a roller (9), a scraping blade (10), a universal wheel (11), a first belt pulley (12), a first motor (14), a second rotating shaft (15), a second belt pulley (16) and a first flat belt (17), wherein the push handle (2) is arranged at the outer top of the frame (1), the front side and the rear side of the inner side of the frame (1) are respectively provided with two slide rails (3), the inner side surfaces of the slide rails (3) are respectively provided with the slide blocks (4) in a sliding manner, the frame body (5) is arranged between the front slide blocks and the rear slide blocks (4), the inner top of the frame (1) is provided with the two air cylinders (6), the bottom ends of telescopic, the middle parts of the front side and the rear side of the frame body (5) are provided with first bearing seats (7) in an embedded mode, bearings in the two first bearing seats (7) are connected with first rotating shafts (8), the middle parts of the first rotating shafts (8) are provided with rollers (9), scrapers (10) are uniformly arranged at intervals in the circumferential direction of the rollers (9), universal wheels (11) are uniformly arranged at intervals at the bottom of the frame body (1), first belt pulleys (12) are arranged behind the first rotating shafts (8), a first opening (13) is formed in the middle of the top of the frame body (5), a first motor (14) is arranged behind the outer top of the frame body (5), an output shaft of the first motor (14) is connected with second rotating shafts (15) through a coupler, a second belt pulley (16) is arranged at the rear end of each second rotating shaft (15), and a first flat belt (17) is connected between the first belt pulley; also comprises a mounting rod (18), a second bearing block (19), a third rotating shaft (20), a cylinder (21), a scraper (22), a third belt pulley (23), a fourth belt pulley (24) and a second flat belt (26), two mounting rods (18) are mounted on the lower portion of the left side face of the frame body (5), second bearing blocks (19) are mounted at the tail ends of the two mounting rods (18) in an embedded mode, bearings in the two second bearing blocks (19) are connected with a third rotating shaft (20), a cylinder (21) is mounted in the middle of the third rotating shaft (20), the cylinder (21) is located between the two mounting rods (18), scrapers (22) are connected to the circumference of the cylinder (21), a third belt pulley (23) is mounted at the rear end of the third rotating shaft (20), a second opening (25) is formed in the lower portion of the left side of the frame body (5), a fourth belt pulley (24) is mounted in front of the first rotating shaft (8), and a second flat belt (26) is connected between the third belt pulley (; the frame is characterized by further comprising transverse plates (27), guide rods (29), first springs (30) and arc-shaped rubber pads (31), wherein the transverse plates (27) are mounted on the left side and the right side of the bottom in the frame (1), sliding holes (28) are formed in the tops of the two transverse plates (27), the guide rods (29) are arranged in the sliding holes (28) in a sliding mode, the first springs (30) are connected between the bottoms of the guide rods (29) and the sliding holes (28), and the arc-shaped rubber pads (31) are mounted at the top ends of the guide rods (29); still including mounting panel (32), sleeve (33), movable rod (34), arc (35) and second spring (36), mounting panel (32) are installed to the outer left surface lower part of frame (1), sleeve (33) are installed to mounting panel (32) bottom left, sleeve (33) are equipped with movable rod (34) of sliding type in sleeve (33), be connected with second spring (36) between top in movable rod (34) top and sleeve (33), arc (35) are installed to movable rod (34) bottom.
CN201810380914.3A 2018-04-25 2018-04-25 Blow off pipe is laid and is used ditching equipment Active CN108589815B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810380914.3A CN108589815B (en) 2018-04-25 2018-04-25 Blow off pipe is laid and is used ditching equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810380914.3A CN108589815B (en) 2018-04-25 2018-04-25 Blow off pipe is laid and is used ditching equipment

Publications (2)

Publication Number Publication Date
CN108589815A CN108589815A (en) 2018-09-28
CN108589815B true CN108589815B (en) 2020-10-13

Family

ID=63609723

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810380914.3A Active CN108589815B (en) 2018-04-25 2018-04-25 Blow off pipe is laid and is used ditching equipment

Country Status (1)

Country Link
CN (1) CN108589815B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110499797A (en) * 2019-09-02 2019-11-26 邢旭英 A kind of profile groove for agricultural irrigation is built canals device

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4825569A (en) * 1988-05-17 1989-05-02 Porter Roger D Trench digging, cable laying and trench filling apparatus
DE202008016851U1 (en) * 2008-12-22 2009-03-12 Franz, Roman Device for introducing a ground hole in the ground
CN206212617U (en) * 2016-11-15 2017-06-06 杨建锋 One kind plantation efficient digging apparatus of tangerine orange
CN206438496U (en) * 2017-02-08 2017-08-25 长兴佳源园林建设有限公司 A kind of ramming machine for building
CN206768768U (en) * 2017-03-25 2017-12-19 于树霞 A kind of drain pipe for farmlands
CN107869157A (en) * 2017-11-17 2018-04-03 南昌首诺科技有限公司 A kind of mud-stone flow disaster cleaning equipment

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4825569A (en) * 1988-05-17 1989-05-02 Porter Roger D Trench digging, cable laying and trench filling apparatus
DE202008016851U1 (en) * 2008-12-22 2009-03-12 Franz, Roman Device for introducing a ground hole in the ground
CN206212617U (en) * 2016-11-15 2017-06-06 杨建锋 One kind plantation efficient digging apparatus of tangerine orange
CN206438496U (en) * 2017-02-08 2017-08-25 长兴佳源园林建设有限公司 A kind of ramming machine for building
CN206768768U (en) * 2017-03-25 2017-12-19 于树霞 A kind of drain pipe for farmlands
CN107869157A (en) * 2017-11-17 2018-04-03 南昌首诺科技有限公司 A kind of mud-stone flow disaster cleaning equipment

Also Published As

Publication number Publication date
CN108589815A (en) 2018-09-28

Similar Documents

Publication Publication Date Title
CN108589815B (en) Blow off pipe is laid and is used ditching equipment
CN211285754U (en) Ditching device is used in gardens construction
CN214530850U (en) Chain communication pipeline ditching machine
CN104032784A (en) Bulldozer with vibration function for civil engineering
CN114232779B (en) Self-cleaning sewage discharging device for drainage pipeline
CN213508651U (en) Dredging equipment for agricultural irrigation ditch
CN105735394A (en) Self-propelled amphibious river cleaning dredging machine
CN211080355U (en) Chain type ditcher for farmland building
CN108988213B (en) Temporary cable laying device for construction site
CN211006818U (en) Crawler-type ditcher
CN209494038U (en) A kind of no-dig technique pipeline pipe dredging device
CN113047359A (en) A portable irrigation canals and ditches excavating gear for moving people engineering construction
CN206323767U (en) A kind of garden layout furrow making dveice
CN101982619B (en) Continuous cable and pipeline trencher
CN205443889U (en) Highway ditching machine
CN220186205U (en) Pipeline repair formwork device
CN206928357U (en) A kind of irrigation canals and ditches sewage disposal apparatus of high-efficiency environment friendly
CN214728690U (en) Mud scraping device of road roller
CN109005776A (en) A kind of ditcher
CN217266800U (en) Municipal administration road construction is with soil matrix unevenness device of strickleing off
CN208908565U (en) A kind of ditcher
CN219643455U (en) Calandria construction protector
CN110528373A (en) A kind of clearing apparatus for milling
CN216143270U (en) High-efficient pipeline laying equipment
CN114524396B (en) Municipal drainage grating plate prying dredging device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20200909

Address after: 314031 room 318, 1663 Hong Gao Road, Xiuzhou District, Jiaxing, Zhejiang.

Applicant after: Jiaxing City Xun Cheng Information Technology Co. Ltds

Address before: 510000 Whampoa West Road, Guangdong, Guangzhou, No. 601, No.

Applicant before: Wu Huabin

GR01 Patent grant