CN108589815A - A kind of blow-off pipe laying ditching equipment - Google Patents
A kind of blow-off pipe laying ditching equipment Download PDFInfo
- Publication number
- CN108589815A CN108589815A CN201810380914.3A CN201810380914A CN108589815A CN 108589815 A CN108589815 A CN 108589815A CN 201810380914 A CN201810380914 A CN 201810380914A CN 108589815 A CN108589815 A CN 108589815A
- Authority
- CN
- China
- Prior art keywords
- belt pulley
- shaft
- frame
- framework
- cylinder
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02F—DREDGING; SOIL-SHIFTING
- E02F5/00—Dredgers or soil-shifting machines for special purposes
- E02F5/02—Dredgers or soil-shifting machines for special purposes for digging trenches or ditches
- E02F5/08—Dredgers or soil-shifting machines for special purposes for digging trenches or ditches with digging wheels turning round an axis
Abstract
The present invention relates to a kind of ditching equipment more particularly to a kind of blow-off pipe to be laid with ditching equipment.The more uniform blow-off pipe laying ditching equipment of the ditch depth that the technical problem to be solved in the present invention is to provide a kind of ditching speed soon, digs out.The present invention provides such a blow-off pipe laying ditching equipment, include frame, pushing hands, sliding rail, sliding block, framework, cylinder, first bearing seat, first rotating shaft etc.;The outer top of frame is equipped with pushing hands, and front and rear sides are respectively mounted there are two sliding rail in frame, and the equal slidingtype of sliding rail medial surface is equipped with sliding block, framework is equipped between front and back sliding block, there are two cylinders for the installation of frame inner top.The present invention is used as driving by first motor, it is rotated so as to driving drum, so as to drive scraping blade to rotate, operating personnel push the present invention again, so as to carry out ditching on the ground, sulculus is first also dug out by scraper, to which the efficiency of ditching can be improved, to reach the more uniform effect of the ditch depth that ditching speed is fast, digs out.
Description
Technical field
The present invention relates to a kind of ditching equipment more particularly to a kind of blow-off pipe to be laid with ditching equipment.
Background technology
Sewage disposal:The mistake that it is purified for the water quality requirement for making sewage reach a certain water body of draining or reusing
Journey.It is each that sewage disposal is widely used in building, agricultural, traffic, the energy, petrochemical industry, environmental protection, urban landscape, medical treatment, food and drink etc.
The daily life of common people is also come into field more and more.
It when handling sewage, needs to be laid with blow-off pipe, needs ditching on the ground, excavated by manual work when being laid with blow-off pipe
The ditch depth that ditching speed is slow when ditch, digs out is uneven, therefore there is an urgent need for research and develop a kind of ditching speed is fast, digs out the ditch depth more
Uniform blow-off pipe, which is laid with, uses ditching equipment.
Invention content
(1) technical problems to be solved
The non-uniform disadvantage of the ditch depth that ditching speed is slow when the present invention is in order to overcome artificial ditching, digs out, the present invention want
The technical issues of solution, is to provide the more uniform blow-off pipe laying of the ditch depth that a kind of ditching speed is fast, digs out and is set with ditching
It is standby.
(2) technical solution
In order to solve the above technical problem, the present invention provides such a blow-off pipe laying ditching equipment, include
Frame, pushing hands, sliding rail, sliding block, framework, cylinder, first bearing seat, first rotating shaft, roller, scraping blade, universal wheel, the first belt
Wheel, first motor, the second shaft, the second belt pulley and the first flat belt, the outer top of frame are equipped with pushing hands, front and back two in frame
Side is respectively mounted there are two sliding rail, and the equal slidingtype of sliding rail medial surface is equipped with sliding block, is equipped with framework between front and back sliding block, in frame
There are two cylinders for top installation, and the telescopic rod bottom end of two cylinders is connect with the outer top of framework, embedded in the middle part of framework front and rear sides
Formula is equipped with first bearing seat, and the bearing in two first bearing seats is connected with first rotating shaft, rolling is equipped in the middle part of first rotating shaft
Cylinder, the circumferential direction of roller is evenly spaced to be equipped with scraping blade, and base of frame is evenly spaced to be equipped with universal wheel, first rotating shaft rear
First belt pulley is installed, framework top center is provided with the first opening, and the outer top rear of framework is equipped with first motor, the first electricity
The second shaft is connected with by shaft coupling on the output shaft of machine, the second shaft rear end is equipped with the second belt pulley, the first belt pulley
The first flat belt is connected between the second belt pulley.
Preferably, further include having mounting rod, second bearing seat, third shaft, cylinder, scraper, third belt pulley, the 4th skin
Belt wheel and the second flat belt, there are two mounting rods for the installation of framework left side lower part, and two mounting rod ends are Embedded to be equipped with
Second bearing seat, the bearing in two second bearing seats are connected with third shaft, are equipped with cylinder in the middle part of third shaft, cylinder is located at
Between two mounting rods, the circumferential direction of cylinder is connected with scraper, and third shaft rear end is equipped with third belt pulley, and framework left lower is opened
There is the second opening, the 4th belt pulley is installed in front of first rotating shaft, second is connected between third belt pulley and the 4th belt pulley
Flat belt.
Preferably, further include having transverse slat, guide rod, the first spring, arc rubber pad, two sides of bottom or so are respectively mounted in frame
There is a transverse slat, be provided with slide opening at the top of two transverse slats, slidingtype is equipped with guide rod in slide opening, is connected between guide rod bottom and slide opening
First spring, guide rod top are equipped with arc rubber pad.
Preferably, further include having mounting plate, sleeve, motion bar, arc panel and second spring, the outer left side lower part peace of frame
Equipped with mounting plate, mounting plate bottom left is equipped with sleeve, and sleeve inner sliding type is equipped with motion bar, motion bar top and sleeve
Second spring is connected between inner top, motion bar bottom end is equipped with arc panel.
Operation principle:When using the present invention, operating personnel first pass through pushing hands and push away the present invention toward specified place, operator
Member restarts first motor rotation, and first motor can drive the second shaft to rotate, and the second shaft can drive the second belt
Wheel rotation, the second belt pulley can drive the rotation of the first belt pulley, the first belt pulley that can drive first by the first flat belt
Shaft rotates, and first rotating shaft can drive roller to rotate, and roller can drive scraping blade to rotate, and operating personnel restart cylinder and stretch
Long, cylinder can drive framework to move down, and sliding rail and sliding block play the guiding role, and framework can drive scraping blade to move down, from
And may make that scraping blade carries out ditching to soil, while ditching, operating personnel can also push the present invention by universal wheel, to
It can be moved in ditching, after waiting for ditching, operating personnel close first motor, and operating personnel restart cylinder shortening, cylinder
Framework can be driven up to move, so as to drive scraping blade up to move, after scraping blade and surface separation, operating personnel can hold
Firmly pushing hands is pushed the present invention by universal wheel.
Because further including having mounting rod, second bearing seat, third shaft, cylinder, scraper, third belt pulley, the 4th belt
Wheel and the second flat belt, for the installation of framework left side lower part there are two mounting rod, two mounting rod ends are Embedded to be equipped with the
Two bearing bracket, the bearing in two second bearing seats are connected with third shaft, and cylinder is equipped in the middle part of third shaft, and cylinder is located at two
Between mounting rod, the circumferential direction of cylinder is connected with scraper, and third shaft rear end is equipped with third belt pulley, and framework left lower is provided with
Second opening, first rotating shaft front are equipped with the 4th belt pulley, and it is flat to be connected with second between third belt pulley and the 4th belt pulley
Belt.So first rotating shaft rotation drives the rotation of the 4th belt pulley, the 4th belt pulley to drive third belt by the second flat belt
Wheel rotation, third belt pulley can drive third shaft to rotate, and third shaft can drive cylinder to rotate, and cylinder can drive and scrape
Knife rotates, and ground can be dug out sulculus by scraper, to which the efficiency of ditching can be improved.
Because further including having transverse slat, guide rod, the first spring, arc rubber pad, two sides of bottom or so are mounted in frame
Transverse slat, is provided with slide opening at the top of two transverse slats, and slidingtype is equipped with guide rod in slide opening, and the is connected between guide rod bottom and slide opening
One spring, guide rod top are equipped with arc rubber pad.So when sliding block moves down, when sliding block touches arc rubber pad
Afterwards, under the cushioning effect of the first spring and guide rod, you can so that sliding block is without departing from sliding rail.
Because further including having mounting plate, sleeve, motion bar, arc panel and second spring, the outer left side lower part installation of frame
Have a mounting plate, mounting plate bottom left is equipped with sleeve, and sleeve inner sliding type is equipped with motion bar, motion bar top in sleeve
Second spring is connected between top, motion bar bottom end is equipped with arc panel.So working as the present invention when moving, arc panel is in work
Under the action of lever and second spring, you can contacted always with ground, so as to push the sundries such as the stone in front, to not
It can influence the normal work of the present invention.
(3) advantageous effect
The present invention is used as driving by first motor, is rotated so as to driving drum, so as to drive scraping blade to rotate, operation
Personnel push the present invention again, so as to carry out ditching on the ground, also sulculus are first dug out by scraper, to which ditching can be improved
Efficiency, to reach the more uniform effect of the ditch depth that ditching speed is fast, digs out.
Description of the drawings
Fig. 1 is the first main structure diagram of the present invention.
Fig. 2 is second of main structure diagram of the present invention.
Fig. 3 is the left view structural representation of the present invention.
Fig. 4 is the enlarged diagram of the part A of the present invention.
Fig. 5 is the third main structure diagram of the present invention.
Label in attached drawing be:1- frames, 2- pushing hands, 3- sliding rails, 4- sliding blocks, 5- frameworks, 6- cylinders, 7- first bearings
Seat, 8- first rotating shafts, 9- rollers, 10- scraping blades, 11- universal wheels, the first belt pulleys of 12-, 13- first are open, 14- first motors,
The second shafts of 15-, the second belt pulleys of 16-, the first flat belts of 17-, 18- mounting rods, 19- second bearing seats, 20- third shafts,
21- cylinders, 22- scrapers, 23- third belt pulleys, the 4th belt pulleys of 24-, 25- second are open, the second flat belts of 26-, and 27- is horizontal
Plate, 28- slide openings, 29- guide rods, the first springs of 30-, 31- arc rubber pads, 32- mounting plates, 33- sleeves, 34- motion bars, 35-
Arc panel, 36- second springs.
Specific implementation mode
The present invention is further illustrated with reference to the accompanying drawings and examples.
Embodiment 1
It includes as shown in Figs. 1-5 frame 1, pushing hands 2, sliding rail 3, sliding block 4, frame that a kind of blow-off pipe, which is laid with ditching equipment,
Body 5, cylinder 6, first bearing seat 7, first rotating shaft 8, roller 9, scraping blade 10, universal wheel 11, the first belt pulley 12, first motor
14, the second shaft 15, the second belt pulley 16 and the first flat belt 17, the outer top of frame 1 are equipped with pushing hands 2, front and back two in frame 1
Side is respectively mounted there are two sliding rail 3, and the equal slidingtype of 3 medial surface of sliding rail is equipped with sliding block 4, framework 5 is equipped between front and back sliding block 4,
There are two cylinder 6, the telescopic rod bottom ends of two cylinders 6 to be connect with the outer top of framework 5 for the installation of 1 inner top of frame, 5 front and rear sides of framework
Middle part is Embedded to be equipped with first bearing seat 7, and the bearing in two first bearing seats 7 is connected with first rotating shaft 8, first rotating shaft
8 middle parts are equipped with roller 9, and the circumferential direction of roller 9 is evenly spaced to be equipped with scraping blade 10, and 1 bottom of frame is evenly spaced to be equipped with
Universal wheel 11,8 rear of first rotating shaft are equipped with the first belt pulley 12, and 5 top center of framework is provided with the first opening 13, outside framework 5
Top rear is equipped with first motor 14, and the second shaft 15 is connected with by shaft coupling on the output shaft of first motor 14, and second
15 rear end of shaft is equipped with the second belt pulley 16, and the first flat belt is connected between the first belt pulley 12 and the second belt pulley 16
17。
Embodiment 2
It includes as shown in Figs. 1-5 frame 1, pushing hands 2, sliding rail 3, sliding block 4, frame that a kind of blow-off pipe, which is laid with ditching equipment,
Body 5, cylinder 6, first bearing seat 7, first rotating shaft 8, roller 9, scraping blade 10, universal wheel 11, the first belt pulley 12, first motor
14, the second shaft 15, the second belt pulley 16 and the first flat belt 17, the outer top of frame 1 are equipped with pushing hands 2, front and back two in frame 1
Side is respectively mounted there are two sliding rail 3, and the equal slidingtype of 3 medial surface of sliding rail is equipped with sliding block 4, framework 5 is equipped between front and back sliding block 4,
There are two cylinder 6, the telescopic rod bottom ends of two cylinders 6 to be connect with the outer top of framework 5 for the installation of 1 inner top of frame, 5 front and rear sides of framework
Middle part is Embedded to be equipped with first bearing seat 7, and the bearing in two first bearing seats 7 is connected with first rotating shaft 8, first rotating shaft
8 middle parts are equipped with roller 9, and the circumferential direction of roller 9 is evenly spaced to be equipped with scraping blade 10, and 1 bottom of frame is evenly spaced to be equipped with
Universal wheel 11,8 rear of first rotating shaft are equipped with the first belt pulley 12, and 5 top center of framework is provided with the first opening 13, outside framework 5
Top rear is equipped with first motor 14, and the second shaft 15 is connected with by shaft coupling on the output shaft of first motor 14, and second
15 rear end of shaft is equipped with the second belt pulley 16, and the first flat belt is connected between the first belt pulley 12 and the second belt pulley 16
17。
Further include have mounting rod 18, second bearing seat 19, third shaft 20, cylinder 21, scraper 22, third belt pulley 23,
4th belt pulley 24 and the second flat belt 26, for the installation of 5 left side lower part of framework there are two mounting rod 18, two mounting rods, 18 end is equal
Embedded to be equipped with second bearing seat 19, the bearing in two second bearing seats 19 is connected with third shaft 20, third shaft 20
Middle part is equipped with cylinder 21, and for cylinder 21 between two mounting rods 18, the circumferential direction of cylinder 21 is connected with scraper 22, third shaft 20
Rear end is equipped with third belt pulley 23, and 5 left lower of framework is provided with the second opening 25, and 8 front of first rotating shaft is equipped with the 4th skin
Belt wheel 24 is connected with the second flat belt 26 between third belt pulley 23 and the 4th belt pulley 24.
Embodiment 3
It includes as shown in Figs. 1-5 frame 1, pushing hands 2, sliding rail 3, sliding block 4, frame that a kind of blow-off pipe, which is laid with ditching equipment,
Body 5, cylinder 6, first bearing seat 7, first rotating shaft 8, roller 9, scraping blade 10, universal wheel 11, the first belt pulley 12, first motor
14, the second shaft 15, the second belt pulley 16 and the first flat belt 17, the outer top of frame 1 are equipped with pushing hands 2, front and back two in frame 1
Side is respectively mounted there are two sliding rail 3, and the equal slidingtype of 3 medial surface of sliding rail is equipped with sliding block 4, framework 5 is equipped between front and back sliding block 4,
There are two cylinder 6, the telescopic rod bottom ends of two cylinders 6 to be connect with the outer top of framework 5 for the installation of 1 inner top of frame, 5 front and rear sides of framework
Middle part is Embedded to be equipped with first bearing seat 7, and the bearing in two first bearing seats 7 is connected with first rotating shaft 8, first rotating shaft
8 middle parts are equipped with roller 9, and the circumferential direction of roller 9 is evenly spaced to be equipped with scraping blade 10, and 1 bottom of frame is evenly spaced to be equipped with
Universal wheel 11,8 rear of first rotating shaft are equipped with the first belt pulley 12, and 5 top center of framework is provided with the first opening 13, outside framework 5
Top rear is equipped with first motor 14, and the second shaft 15 is connected with by shaft coupling on the output shaft of first motor 14, and second
15 rear end of shaft is equipped with the second belt pulley 16, and the first flat belt is connected between the first belt pulley 12 and the second belt pulley 16
17。
Further include have mounting rod 18, second bearing seat 19, third shaft 20, cylinder 21, scraper 22, third belt pulley 23,
4th belt pulley 24 and the second flat belt 26, for the installation of 5 left side lower part of framework there are two mounting rod 18, two mounting rods, 18 end is equal
Embedded to be equipped with second bearing seat 19, the bearing in two second bearing seats 19 is connected with third shaft 20, third shaft 20
Middle part is equipped with cylinder 21, and for cylinder 21 between two mounting rods 18, the circumferential direction of cylinder 21 is connected with scraper 22, third shaft 20
Rear end is equipped with third belt pulley 23, and 5 left lower of framework is provided with the second opening 25, and 8 front of first rotating shaft is equipped with the 4th skin
Belt wheel 24 is connected with the second flat belt 26 between third belt pulley 23 and the 4th belt pulley 24.
Further include having transverse slat 27, guide rod 29, the first spring 30, arc rubber pad 31, two Fang Junan of bottom or so in frame 1
Equipped with transverse slat 27, the top of two transverse slat 27 is provided with slide opening 28, and slidingtype is equipped with guide rod 29 in slide opening 28,29 bottom of guide rod with
The first spring 30 is connected between slide opening 28,29 top of guide rod is equipped with arc rubber pad 31.
Embodiment 4
It includes as shown in Figs. 1-5 frame 1, pushing hands 2, sliding rail 3, sliding block 4, frame that a kind of blow-off pipe, which is laid with ditching equipment,
Body 5, cylinder 6, first bearing seat 7, first rotating shaft 8, roller 9, scraping blade 10, universal wheel 11, the first belt pulley 12, first motor
14, the second shaft 15, the second belt pulley 16 and the first flat belt 17, the outer top of frame 1 are equipped with pushing hands 2, front and back two in frame 1
Side is respectively mounted there are two sliding rail 3, and the equal slidingtype of 3 medial surface of sliding rail is equipped with sliding block 4, framework 5 is equipped between front and back sliding block 4,
There are two cylinder 6, the telescopic rod bottom ends of two cylinders 6 to be connect with the outer top of framework 5 for the installation of 1 inner top of frame, 5 front and rear sides of framework
Middle part is Embedded to be equipped with first bearing seat 7, and the bearing in two first bearing seats 7 is connected with first rotating shaft 8, first rotating shaft
8 middle parts are equipped with roller 9, and the circumferential direction of roller 9 is evenly spaced to be equipped with scraping blade 10, and 1 bottom of frame is evenly spaced to be equipped with
Universal wheel 11,8 rear of first rotating shaft are equipped with the first belt pulley 12, and 5 top center of framework is provided with the first opening 13, outside framework 5
Top rear is equipped with first motor 14, and the second shaft 15 is connected with by shaft coupling on the output shaft of first motor 14, and second
15 rear end of shaft is equipped with the second belt pulley 16, and the first flat belt is connected between the first belt pulley 12 and the second belt pulley 16
17。
Further include have mounting rod 18, second bearing seat 19, third shaft 20, cylinder 21, scraper 22, third belt pulley 23,
4th belt pulley 24 and the second flat belt 26, for the installation of 5 left side lower part of framework there are two mounting rod 18, two mounting rods, 18 end is equal
Embedded to be equipped with second bearing seat 19, the bearing in two second bearing seats 19 is connected with third shaft 20, third shaft 20
Middle part is equipped with cylinder 21, and for cylinder 21 between two mounting rods 18, the circumferential direction of cylinder 21 is connected with scraper 22, third shaft 20
Rear end is equipped with third belt pulley 23, and 5 left lower of framework is provided with the second opening 25, and 8 front of first rotating shaft is equipped with the 4th skin
Belt wheel 24 is connected with the second flat belt 26 between third belt pulley 23 and the 4th belt pulley 24.
Further include having transverse slat 27, guide rod 29, the first spring 30, arc rubber pad 31, two Fang Junan of bottom or so in frame 1
Equipped with transverse slat 27, the top of two transverse slat 27 is provided with slide opening 28, and slidingtype is equipped with guide rod 29 in slide opening 28,29 bottom of guide rod with
The first spring 30 is connected between slide opening 28,29 top of guide rod is equipped with arc rubber pad 31.
Further include having mounting plate 32, sleeve 33, motion bar 34, arc panel 35 and second spring 36, under 1 outer left side of frame
Portion is equipped with mounting plate 32, and 32 bottom left of mounting plate is equipped with sleeve 33, and 33 inner sliding type of sleeve is equipped with motion bar 34, lives
Second spring 36 is connected between 33 inner top of 34 top of lever and sleeve, 34 bottom end of motion bar is equipped with arc panel 35.
Operation principle:When using the present invention, operating personnel first pass through pushing hands 2 and push away the present invention toward specified place, operation
Personnel restart the rotation of first motor 14, and first motor 14 can drive the second shaft 15 to rotate, and the second shaft 15 can band
Dynamic second belt pulley 16 rotation, the second belt pulley 16 can drive the first belt pulley 12 to rotate by the first flat belt 17, and first
Belt pulley 12 can drive first rotating shaft 8 to rotate, and first rotating shaft 8 can drive roller 9 to rotate, and roller 9 can drive scraping blade 10
Rotation, operating personnel restart the elongation of cylinder 6, and cylinder 6 can drive framework 5 to move down, and sliding rail 3 and sliding block 4 play guiding and make
With, framework 5 can drive scraping blade 10 to move down, to may make scraping blade 10 to carry out ditching to soil, while ditching, and behaviour
Make personnel can also push the present invention by universal wheel 11, and so as to be moved in ditching, after waiting for ditching, operating personnel close
First motor 14, operating personnel restart the shortening of cylinder 6, and cylinder 6 can drive framework 5 up to move, so as to drive scraping blade
10 up move, and after scraping blade 10 and surface separation, operating personnel can hold pushing hands 2, be pushed away the present invention by universal wheel 11
It walks.
Because further including having mounting rod 18, second bearing seat 19, third shaft 20, cylinder 21, scraper 22, third belt pulley
23, the 4th belt pulley 24 and the second flat belt 26, there are two mounting rod 18, two mounting rods, 18 ends for the installation of 5 left side lower part of framework
End is Embedded to be equipped with second bearing seat 19, and the bearing in two second bearing seats 19 is connected with third shaft 20, and third turns
20 middle part of axis is equipped with cylinder 21, and cylinder 21 is between two mounting rods 18, and the circumferential direction of cylinder 21 is connected with scraper 22, and third turns
20 rear end of axis is equipped with third belt pulley 23, and 5 left lower of framework is provided with the second opening 25, and 8 front of first rotating shaft is equipped with the
Four belt pulleys 24, are connected with the second flat belt 26 between third belt pulley 23 and the 4th belt pulley 24.So first rotating shaft 8 rotates
The 4th belt pulley 24 is driven to rotate, the 4th belt pulley 24 drives third belt pulley 23 to rotate by the second flat belt 26, third skin
Belt wheel 23 can drive third shaft 20 to rotate, and third shaft 20 can drive cylinder 21 to rotate, and cylinder 21 can drive scraper
22 rotations, ground can be dug out sulculus by scraper 22, to which the efficiency of ditching can be improved.
Because further including having transverse slat 27, guide rod 29, the first spring 30, arc rubber pad 31, two sides of bottom or so in frame 1
It is mounted on transverse slat 27, two transverse slats, 27 top is provided with slide opening 28, and slidingtype is equipped with guide rod 29,29 bottom of guide rod in slide opening 28
The first spring 30 is connected between portion and slide opening 28,29 top of guide rod is equipped with arc rubber pad 31.So being moved down when sliding block 4 is past
When dynamic, after sliding block 4 touches arc rubber pad 31, under the cushioning effect of the first spring 30 and guide rod 29, you can so that sliding
Block 4 is without departing from sliding rail 3.
Because further including having mounting plate 32, sleeve 33, motion bar 34, arc panel 35 and second spring 36, the outer left side of frame 1
Face lower part is equipped with mounting plate 32, and 32 bottom left of mounting plate is equipped with sleeve 33, and 33 inner sliding type of sleeve is equipped with motion bar
34, second spring 36 is connected between 33 inner top of 34 top of motion bar and sleeve, and 34 bottom end of motion bar is equipped with arc panel 35.
So working as the present invention when moving, arc panel 35 is under the action of motion bar 34 and second spring 36, you can is connect always with ground
It touches, so as to push the sundries such as the stone in front, to not interfere with the normal work of the present invention.
The preferred embodiment of the present invention above described embodiment only expresses, the description thereof is more specific and detailed, but simultaneously
Cannot the limitation to the scope of the claims of the present invention therefore be interpreted as.It should be pointed out that for those of ordinary skill in the art
For, without departing from the inventive concept of the premise, several deformations can also be made, improves and substitutes, these belong to this hair
Bright protection domain.Therefore, the protection domain of patent of the present invention should be determined by the appended claims.
Claims (4)
1. a kind of blow-off pipe, which is laid with, uses ditching equipment, which is characterized in that include frame (1), pushing hands (2), sliding rail (3), sliding block
(4), framework (5), cylinder (6), first bearing seat (7), first rotating shaft (8), roller (9), scraping blade (10), universal wheel (11),
One belt pulley (12), first motor (14), the second shaft (15), the second belt pulley (16) and the first flat belt (17), frame (1)
Outer top is equipped with pushing hands (2), and frame (1) interior front and rear sides are respectively mounted there are two sliding rail (3), and sliding rail (3) medial surface slides
Formula is equipped with sliding block (4), and framework (5) is equipped between front and back sliding block (4), and frame (1) inner top is installed there are two cylinder (6),
Top is connect outside with framework (5) for the telescopic rod bottom end of two cylinders (6), Embedded in the middle part of framework (5) front and rear sides to be equipped with
First bearing seat (7), the bearing in two first bearing seats (7) are connected with first rotating shaft (8), are equipped in the middle part of first rotating shaft (8)
Roller (9), the circumferential direction of roller (9) is evenly spaced to be equipped with scraping blade (10), frame (1) bottom is evenly spaced be equipped with it is universal
It takes turns (11), first rotating shaft (8) rear is equipped with the first belt pulley (12), and framework (5) top center is provided with the first opening (13), frame
Body (5) outer top rear is equipped with first motor (14), and second is connected with by shaft coupling on the output shaft of first motor (14)
Shaft (15), the second shaft (15) rear end are equipped with the second belt pulley (16), the first belt pulley (12) and the second belt pulley (16)
Between be connected with the first flat belt (17).
2. a kind of blow-off pipe according to claim 1, which is laid with, uses ditching equipment, which is characterized in that further include having mounting rod
(18), second bearing seat (19), third shaft (20), cylinder (21), scraper (22), third belt pulley (23), the 4th belt pulley
(24) it is installed there are two mounting rod (18) with the second flat belt (26), framework (5) left side lower part, two mounting rods (18) end is equal
Embedded to be equipped with second bearing seat (19), the bearing in two second bearing seats (19) is connected with third shaft (20), third
Cylinder (21) is installed in the middle part of shaft (20), between two mounting rods (18), the circumferential direction of cylinder (21) is connected with cylinder (21)
Scraper (22), third shaft (20) rear end are equipped with third belt pulley (23), and framework (5) left lower is provided with the second opening
(25), the 4th belt pulley (24) is installed in front of first rotating shaft (8), connects between third belt pulley (23) and the 4th belt pulley (24)
It is connected to the second flat belt (26).
3. a kind of blow-off pipe according to claim 2, which is laid with, uses ditching equipment, which is characterized in that further include having transverse slat
(27), guide rod (29), the first spring (30), arc rubber pad (31), two sides of frame (1) interior bottom or so are mounted on transverse slat
(27), it is provided with slide opening (28) at the top of two transverse slats (27), slidingtype is equipped with guide rod (29), guide rod (29) bottom in slide opening (28)
The first spring (30) is connected between portion and slide opening (28), guide rod (29) top is equipped with arc rubber pad (31).
4. a kind of blow-off pipe according to claim 3, which is laid with, uses ditching equipment, which is characterized in that further include having mounting plate
(32), sleeve (33), motion bar (34), arc panel (35) and second spring (36), the outer left side lower part of frame (1) are equipped with peace
Loading board (32), mounting plate (32) bottom left are equipped with sleeve (33), and sleeve (33) inner sliding type is equipped with motion bar (34), lives
Second spring (36) is connected between lever (34) top and sleeve (33) inner top, motion bar (34) bottom end is equipped with arc panel
(35)。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810380914.3A CN108589815B (en) | 2018-04-25 | 2018-04-25 | Blow off pipe is laid and is used ditching equipment |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810380914.3A CN108589815B (en) | 2018-04-25 | 2018-04-25 | Blow off pipe is laid and is used ditching equipment |
Publications (2)
Publication Number | Publication Date |
---|---|
CN108589815A true CN108589815A (en) | 2018-09-28 |
CN108589815B CN108589815B (en) | 2020-10-13 |
Family
ID=63609723
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810380914.3A Active CN108589815B (en) | 2018-04-25 | 2018-04-25 | Blow off pipe is laid and is used ditching equipment |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108589815B (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110499797A (en) * | 2019-09-02 | 2019-11-26 | 邢旭英 | A kind of profile groove for agricultural irrigation is built canals device |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4825569A (en) * | 1988-05-17 | 1989-05-02 | Porter Roger D | Trench digging, cable laying and trench filling apparatus |
DE202008016851U1 (en) * | 2008-12-22 | 2009-03-12 | Franz, Roman | Device for introducing a ground hole in the ground |
CN206212617U (en) * | 2016-11-15 | 2017-06-06 | 杨建锋 | One kind plantation efficient digging apparatus of tangerine orange |
CN206438496U (en) * | 2017-02-08 | 2017-08-25 | 长兴佳源园林建设有限公司 | A kind of ramming machine for building |
CN206768768U (en) * | 2017-03-25 | 2017-12-19 | 于树霞 | A kind of drain pipe for farmlands |
CN107869157A (en) * | 2017-11-17 | 2018-04-03 | 南昌首诺科技有限公司 | A kind of mud-stone flow disaster cleaning equipment |
-
2018
- 2018-04-25 CN CN201810380914.3A patent/CN108589815B/en active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4825569A (en) * | 1988-05-17 | 1989-05-02 | Porter Roger D | Trench digging, cable laying and trench filling apparatus |
DE202008016851U1 (en) * | 2008-12-22 | 2009-03-12 | Franz, Roman | Device for introducing a ground hole in the ground |
CN206212617U (en) * | 2016-11-15 | 2017-06-06 | 杨建锋 | One kind plantation efficient digging apparatus of tangerine orange |
CN206438496U (en) * | 2017-02-08 | 2017-08-25 | 长兴佳源园林建设有限公司 | A kind of ramming machine for building |
CN206768768U (en) * | 2017-03-25 | 2017-12-19 | 于树霞 | A kind of drain pipe for farmlands |
CN107869157A (en) * | 2017-11-17 | 2018-04-03 | 南昌首诺科技有限公司 | A kind of mud-stone flow disaster cleaning equipment |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110499797A (en) * | 2019-09-02 | 2019-11-26 | 邢旭英 | A kind of profile groove for agricultural irrigation is built canals device |
Also Published As
Publication number | Publication date |
---|---|
CN108589815B (en) | 2020-10-13 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN114030824B (en) | Shield mud dregs transportation equipment | |
CN210499615U (en) | Subway segment arc surface grinding device | |
CN205770037U (en) | Over-water floats removes robot | |
CN209816621U (en) | Marking clearing device for municipal construction | |
CN113547165A (en) | Pipeline cutting equipment for hydraulic engineering | |
CN108589815A (en) | A kind of blow-off pipe laying ditching equipment | |
CN107932750A (en) | A kind of urban construction ceramic tile cutting device | |
CN208005852U (en) | A kind of plate cutting device | |
CN206652922U (en) | A kind of reinforcing bar automatic cutting equipment | |
CN211394219U (en) | River course ecological management device | |
CN213194552U (en) | Yellow sand screening anti-blocking device for building construction | |
CN108570975A (en) | A kind of water surface foreign matter cleaning plant | |
CN109911513B (en) | Anti-sticking chain scraper conveyor | |
CN209125936U (en) | A kind of diaphragm die-cutting machine chip removal device | |
CN111119008A (en) | Road surface router | |
CN205419003U (en) | Letter easily movable formula automatic discharge conveying mechanism | |
KR100220503B1 (en) | Sediment removal device for intake | |
CN211200682U (en) | Conveniently clear up silt processing apparatus for water conservancy construction of pipeline inner wall | |
CN219527777U (en) | Silt cleaning equipment | |
CN212741171U (en) | Turning device for bio-organic fertilizer | |
CN212294272U (en) | Ground planing, milling and slag removing integrated machine for house construction engineering | |
CN219639654U (en) | Building underground water pipe auxiliary installation device | |
CN219383772U (en) | Efficient conveying device of pulverizer | |
CN211472816U (en) | Municipal administration pipeline pull throughs | |
CN214526442U (en) | Conveying belt cleaning device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
TA01 | Transfer of patent application right | ||
TA01 | Transfer of patent application right |
Effective date of registration: 20200909 Address after: 314031 room 318, 1663 Hong Gao Road, Xiuzhou District, Jiaxing, Zhejiang. Applicant after: Jiaxing City Xun Cheng Information Technology Co. Ltds Address before: 510000 Whampoa West Road, Guangdong, Guangzhou, No. 601, No. Applicant before: Wu Huabin |
|
GR01 | Patent grant | ||
GR01 | Patent grant |