CN108551147A - A kind of deicer for power transmission line taking energy based on CT - Google Patents

A kind of deicer for power transmission line taking energy based on CT Download PDF

Info

Publication number
CN108551147A
CN108551147A CN201810689510.2A CN201810689510A CN108551147A CN 108551147 A CN108551147 A CN 108551147A CN 201810689510 A CN201810689510 A CN 201810689510A CN 108551147 A CN108551147 A CN 108551147A
Authority
CN
China
Prior art keywords
deicing
transmission line
pedestal
auxiliary support
propeller
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810689510.2A
Other languages
Chinese (zh)
Other versions
CN108551147B (en
Inventor
马旭东
李小康
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Henan Power Co Dengzhou Power Supply Co
Original Assignee
Henan Power Co Dengzhou Power Supply Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Henan Power Co Dengzhou Power Supply Co filed Critical Henan Power Co Dengzhou Power Supply Co
Priority to CN201810689510.2A priority Critical patent/CN108551147B/en
Publication of CN108551147A publication Critical patent/CN108551147A/en
Application granted granted Critical
Publication of CN108551147B publication Critical patent/CN108551147B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G7/00Overhead installations of electric lines or cables
    • H02G7/16Devices for removing snow or ice from lines or cables
    • H02J5/005

Landscapes

  • Suspension Of Electric Lines Or Cables (AREA)
  • Rehabilitation Tools (AREA)

Abstract

The present invention provides a kind of deicer for power transmission line taking energy based on CT, including deicing pedestal, suspension mechanism on the deicing pedestal is set, mobile mechanism on the deicing pedestal is set, auxiliary support mechanism on the deicing pedestal is set, deicing mechanism on the deicing pedestal is set, and the control mechanism for suspension mechanism, mobile mechanism, auxiliary support mechanism and deicing mechanism coordinate control is set on the deicing pedestal;The invention does not increase the smooth deicing of grid load quality, device body not only without carrying more electric energy, but also can reduce the deicer for power transmission line that energy is taken based on CT of the difficulty of suspension.

Description

A kind of deicer for power transmission line taking energy based on CT
Technical field
The present invention relates to removing ice of power transmission line equipment technical fields, and in particular to a kind of to take the transmission line of electricity of energy to remove based on CT Ice production apparatus.
Background technology
Electric shock transmission line icing disaster is one of the principal element for influencing transmission line of electricity operational safety in winter, main former Because being to adhere to a large amount of ice cube thereon, increase so as to cause transmission line of electricity quality, when it is more than to a certain degree to carry quality, then can Tower bar occurs to collapse, the phenomenon that cause transmission line of electricity to paralyse, there are two types of one is enhancing transmission lines of electricity for solution Design strength carries out deicing one is timely, and existing deicer, is divided into the mode of hand-held, suspension type or unmanned plane, Hand-held is the most original, can increase the operation difficulty of operator, and suspension type its can increase the quality of transmission line of electricity, using nobody The mode of machine can increase the consumption of the energy.And existing deicing mechanism is required for electrical energy drive, deicer is in order to keep floating Weight cannot be too big, if consumption electric energy is more, accumulator volume can be very big, influences the working time of device and increases device Energy consumption.
A kind of overhead transmission line electrified deicing device is disclosed in Authorization Notice No. is CN103414136A, including exhausted Edge type removes ice lolly, described to be provided with driving mechanism on the side of transmission line of electricity, carrier rack except ice lolly is arranged by carrier rack;Institute It includes two montants disposed in parallel to state carrier rack, passes through at least two cross bar positioning disposed in parallel between two montants;Institute The top for stating every montant is suspended on by suspension mechanism on transmission pressure respectively;It is described except ice lolly is vertically set on first crossbar The end for stretching out montant, except the height of ice lolly is corresponding to the tip height of montant;The driving mechanism includes driving wheel and twines Around insulated transmission rope on the drive wheel.The invention is although simple in structure, but still can still increase transmission of electricity by the way of suspension The quality of circuit, and hang and take inconvenience.
A kind of removing ice of power transmission line robot is disclosed in Authorization Notice No. is CN103701081A, belongs to mechanical neck Domain.It is whole to hang symmetrical deployment mechanisms using three arms, using two driving walking modules and an auxiliary walking module The pattern being combined;Dynamic walking module is arranged in robot rear and front end, and auxiliary walking module arrangement is front and back on the whole in center Symmetrically;More barrier module is integrated with driving walking module, auxiliary walking module respectively, and stable module connect one with auxiliary walking module Rise, be arranged in robot centered position, deicing module arrangement below driving walking module and auxiliary walking module between. Advantage is:Functions such as " walkings-obstacle detouring-deicing " may be implemented in the present invention, complete the cleaning work to the attached ice of transmission line of electricity, reach To the purpose for safeguarding transmission line of electricity;It still uses suspension type so that hangs and takes difficulty, increases the carrying quality of transmission line of electricity.
To sum up, one kind is needed not increase the smooth deicing of grid load quality not only, without carrying more electric energy, but also The deicer for power transmission line that energy is taken based on CT of the difficulty of suspension can be reduced.
Invention content
In view of this, the present invention provides a kind of deicer for power transmission line taking energy based on CT, do not increase power transmission line not only The smooth deicing of road load quality, device body are without carrying more electric energy, and the difficulty that can reduce suspension is taken based on CT The deicer for power transmission line of energy.
To solve the above problems, the present invention provides a kind of deicer for power transmission line taking energy based on CT, including deicing base Seat, is arranged the suspension mechanism on the deicing pedestal, and the mobile mechanism on the deicing pedestal is arranged, and setting is removed described Auxiliary support mechanism on ice pedestal is arranged the deicing mechanism on the deicing pedestal, and is arranged in the deicing pedestal On for suspension mechanism, mobile mechanism, auxiliary support mechanism and deicing mechanism carry out coordinate control control mechanism;
The deicing mechanism includes the third two axle The Cloud Terraces being arranged on the deicing pedestal, is arranged in the third two axle The Cloud Terraces On third Auxiliary support telescopic rod, the 4th two axle The Cloud Terraces in the third Auxiliary support telescopic rod end are set, and setting exists The cross in the 4th Auxiliary support telescopic rod end is arranged in the 4th Auxiliary support telescopic rod in 4th two axle The Cloud Terraces Arc panel is arranged in the front end of arm, the transverse arm, and heating cable is arranged in the arc panel medial surface, and CT is arranged in the rear end of the transverse arm Qu Neng mechanisms, CT Qu Neng mechanisms are connect with the accumulator being arranged on arc panel, the accumulator and the heating cable Connection.
CT Qu Neng mechanisms include the L-type support of the transverse arm rear end setting, down-set first C in transverse arm rear end Shaped iron core, winding setting enameled wire, the enameled wire pass through rectification stable pressuring unit and the accumulator on the first c-type iron core Connection, the L-type support end set up electric telescopic rod, and the end set insulating bar of the electric telescopic rod is described exhausted Edge bar upper end corresponds to the first c-type iron core and the second c-type iron core is arranged, and the electric telescopic rod is connect with the control mechanism.
The suspension mechanism includes the suspension air bag for being arranged on the deicing pedestal and being made of multiple air bags, and setting exists The first three-way magnetic valve being connected on the suspension air bag and with each air bag, the outlet end of first three-way magnetic valve are equal It is connected with the first compressed tanks being arranged on the deicing pedestal by connecting tube.
Setting and the matched anticollision metal mesh of the suspension air bag on the deicing pedestal.
The mobile mechanism includes the ellipse track being arranged in deicing pedestal side, is arranged on the ellipse track more A fixed pulley, is arranged the belt on multiple fixed pulleys, be arranged on deicing pedestal and with matched turn an of fixed pulley To motor, the propeller module that is arranged on the belt.
The propeller module includes the propeller protecting frame being arranged on the belt, and setting is protected in the propeller The propeller in the propeller driving motor output shaft is arranged in propeller driving motor in frame, is arranged in the spiral Paddle rear portion and the water conservancy diversion motor on the propeller protecting frame, and be arranged on the water conservancy diversion motor output shaft and with institute State the matched deflector of propeller.
Setting helium, hydrogen or neon in first compressed tanks.
The auxiliary support mechanism includes the first two axle The Cloud Terraces being arranged on the deicing pedestal, is arranged described first Second liang of axis cloud in the first Auxiliary support telescopic rod end is arranged in the first Auxiliary support telescopic rod in two axle The Cloud Terraces Platform, the second Auxiliary support telescopic rod being arranged in second two axle The Cloud Terraces are arranged in the second Auxiliary support telescopic rod End and with the matched electromagnetic clamp of transmission line of electricity.
The control mechanism includes the CPU being arranged on the deicing pedestal, is sensed with the wind direction of cpu signal interconnection Device and air velocity transducer, the high-definition camera with cpu signal interconnection, interconnect with the cpu signal and are arranged in deicing base The MEMS gyroscope and MEMS accelerometer at seat center, the rechargeable lithium battery with cpu signal interconnection, with the cpu signal The data transmission module of interconnection, the tablet computer with data transmission module wireless signal interconnection.
It is a kind of based on CT take can deicer for power transmission line application method:
S1:It carries near the present apparatus to pending transmission line of electricity, checks and verify whether each component works normally, then pass through Tablet computer controls multiple first three-way magnetic valves and is inflated into suspension air bag, so that drive of the present apparatus in suspension air bag Under, it is floated near transmission line of electricity;
S2:The air speed data and wind direction data that CPU is obtained according to air velocity transducer and wind transducer, by steering motor by its It adjusts with wind in the opposite direction, and adjust revolution speed of propeller to offset wind speed, it is ensured that the present apparatus can smoothly rise to defeated Near electric line;
S3:Then wherein gas is excluded by the first three-way magnetic valve, avoids continuing to rise, realize that the present apparatus suspends in the air, Then the coordinate of conducting wire is locked by high-definition camera and by auxiliary support mechanism electromagnetic clamp is consolidated with transmission line of electricity It is fixed;
S4:Make deicing mechanism close to transmission line of electricity with two axle The Cloud Terraces by the Auxiliary support telescopic rod in deicing mechanism, CT takes Energy mechanism carries out circuit package to take energy, and then the electric energy of conversion, which is first sent to accumulator, to be sent to heating cable so that arc panel Internal surface temperature rises, and carrying out heating to the icing on circuit top makes its thawing;
S5:When detecting a large amount of deicing of needs, then the position of propeller can be adjusted, and adjust suitable angle with rotating speed along defeated Electric line is walked, and realizes the effect for continuing deicing;
S6:After completing deicing, deicing mechanism and work of the auxiliary support mechanism to transmission line of electricity are released, and pass through tablet computer It controls the present apparatus to return at operator, completes entire work.
The present invention hangs and takes difficulty for suspension type exists in the prior art, and will increase showing for transmission line of electricity carrying quality As, provide it is a kind of not increasing the smooth deicing of grid load quality not only, but also can reduce suspension difficulty based on CT Take the deicer for power transmission line of energy;, using deicing pedestal as matrix, suspension mechanism is arranged on it ensures that the present apparatus being capable of nothing for it Power realizes air suspension, and the mobile mechanism being arranged ensure that the present apparatus can move position in the air, preferably be removed Ice, and the present apparatus can be well combined together by the auxiliary support mechanism being arranged in operation with transmission line of electricity, avoid removing Ice operation or the unstable phenomenon of present apparatus working environment caused by when there is strong wind weather, and the control mechanism being arranged can be more Good carries out coordination control to the present apparatus, realizes highly efficient deicing effect.
In addition, the suspension mechanism used includes the suspension air bag for being arranged on deicing pedestal and being made of multiple air bags, energy It enough is inflated realization Buoyance adjustment for single air bag, and the first three-way magnetic valve being arranged can be realized to each suspension gas The Buoyance adjustment of capsule can avoid the phenomenon that integrally falling after there is a rupture, and the first compressed tanks being arranged, Neng Gou It is provided with one kind of helium, neon or hydrogen, it is ensured that the gas being filled in suspension air bag can generate a large amount of buoyancy, it is ensured that The present apparatus can float in the air;In order to avoid occurring the phenomenon that collision rupture in flotation process, it is arranged on deicing pedestal Anticollision metal mesh ensures the stability of structure.
In addition, the mobile mechanism used includes the ellipse track being arranged in deicing pedestal side, setting is more in orbit A fixed pulley, and belt is set on multiple fixed pulleys, in order to realize better turning function, it is arranged on a fixed pulley wherein Steering motor realizes the position adjustment of propeller module, the more conducively movement in direction;And the propeller module being arranged includes setting Propeller protecting frame on belt, damage and transmission line of electricity damage phenomenon caused by avoiding propeller from collision occur, and in spiral shell The propeller driving motor being arranged on rotation paddle protecting frame can ensure to provide enough thrust for propeller, and be arranged in propeller Water conservancy diversion motor on protecting frame can adjust the direction of deflector, so that more flexible when the present apparatus moves in the air.
In addition, the auxiliary support mechanism used includes the first two axle The Cloud Terraces being arranged on deicing pedestal, it is arranged first The first Auxiliary support telescopic rod and the second two axle The Cloud Terraces in two axle The Cloud Terraces and the second Auxiliary support telescopic rod so that electromagnetism Press from both sides it is more flexible transmission line of electricity is clamped, the deicing mechanism similarly used also for two two axle The Cloud Terraces with two support The mode of telescopic supporting rod cooperation, it is ensured that transverse arm can be parallel with transmission line of electricity so that when arc panel is fitted in circuit top, Two iron cores, which can dock, to carry out circuit package to take energy, to be powered to the heating cable of arc panel inner surface, melts Icing on circuit.And it is taken and can be carried out taking electricity directly from transmission line of electricity, protect without carrying higher volume of accumulator using CT Continuation of the journey and the device for having demonstrate,proved whole device are easy to implement.
In addition, the control mechanism used includes the CPU being arranged on deicing pedestal, the side of PLC controls also can be used certainly Formula, wind transducer and air velocity transducer with the interconnection of its signal so that be used cooperatively with MEMS gyroscope and MEMS accelerometer When, it can preferably realize suspension and movement, in order to ensure effect and mobile effect and the accuracy of clamping of deicing, if It has set high-definition camera and has carried out image recognition, and the data transmission module used can ensure the stability of data transfer, it can To be transmitted using Bluetooth signal, infrared signal transmission also can be used, preferably transmitted certainly using 4G signals, it is ensured that the present apparatus Stability, and the rechargeable lithium battery being arranged can ensure the stability of structure operation, the side using tablet computer as remote control Formula can ensure the agility of structure manipulation, the mode of smart mobile phone also can be used certainly.
Description of the drawings
Fig. 1 be the present invention is based on CT take can deicer for power transmission line structural schematic diagram;
Fig. 2 is the enlarged structure schematic diagram at A of the present invention;
Fig. 3 is the structural schematic diagram of deicing mechanism of the present invention;
Fig. 4 is the structural schematic diagram of CT Qu Neng of the present invention mechanisms;
Fig. 5 is the structural schematic diagram of auxiliary support mechanism of the present invention.
Specific implementation mode
In order to make the object, technical scheme and advantages of the embodiment of the invention clearer, below in conjunction with the embodiment of the present invention Attached drawing 1-5, the technical solution of the embodiment of the present invention is clearly and completely described.Obviously, described embodiment is this A part of the embodiment of invention, instead of all the embodiments.Based on described the embodiment of the present invention, the common skill in this field The every other embodiment that art personnel are obtained, shall fall within the protection scope of the present invention.
Embodiment one
A kind of deicer for power transmission line taking energy based on CT, including deicing pedestal 3 are present embodiments provided, setting is removed described The mobile mechanism on the deicing pedestal 3 is arranged in suspension mechanism on ice pedestal 3, is arranged auxiliary on the deicing pedestal 3 Help supporting mechanism 7, the deicing mechanism 6 on the deicing pedestal 3 be set, and be arranged on the deicing pedestal 3 for pair Suspension mechanism, mobile mechanism, auxiliary support mechanism and deicing mechanism coordinate the control mechanism of control;
The deicing mechanism 6 includes the third two axle The Cloud Terraces 61 being arranged on the deicing pedestal 3, is arranged in two axis of the third The 4th liang of axis cloud in 62 end of third Auxiliary support telescopic rod is arranged in third Auxiliary support telescopic rod 62 on holder 61 The 4th Auxiliary support telescopic rod 64 in the 4th two axle The Cloud Terraces 63 is arranged in platform 63, is arranged in the 4th Auxiliary support Arc panel 67, the setting fever of 67 medial surface of the arc panel is arranged in the front end of the transverse arm 66 of 64 end of telescopic rod, the transverse arm 66 Cable 68, the rear end setting CT Qu Neng mechanisms of the transverse arm 66, CT Qu Neng mechanisms and the accumulator being arranged on arc panel 69 connections, the accumulator 69 are connect with the heating cable 68.
CT Qu Neng mechanisms include the L-type support 615 of 66 rear end of transverse arm setting, and 66 rear end of the transverse arm is to dividing into The first c-type iron core 611 is set, setting enameled wire 610 is wound on the first c-type iron core 611, the enameled wire 610 passes through rectification Voltage regulation unit is connect with the accumulator 69, and 615 end of the L-type support sets up electric telescopic rod 614, described electronic to stretch The end set insulating bar 613 of contracting bar 614,613 upper end of the insulating bar correspond to the first c-type iron core 611 and the second c-type are arranged Iron core 612, the electric telescopic rod 614 are connect with the control mechanism.
First c-type iron core is first placed on the top of transmission line of electricity by CT Qu Neng mechanisms when working, then electric telescopic rod extends So that the second c-type iron core is docked with the first c-type iron core, at this time because by alternating current in transmission line of electricity, enameled wire can produce Raw electric current, rectification stable pressuring unit take structure designed in energy equipment, including rectification circuit, filtered electrical using CT conventional at present Road, regulator circuit etc., these belong to routine techniques and do not describe excessively, and the electric current of generation is sent after voltage stabilizing rectification to accumulator, Accumulator as stand-by power supply, volume do not have to it is too big, only store the electric energy to generate electricity immediately and be fed directly to heating cable into It exercises and uses.Electric telescopic rod is connect with control mechanism, and staff can control electric telescopic rod by computer in lower section, from And it is interior that transmission line of electricity is wrapped in by two iron cores.
The suspension mechanism includes the suspension air bag for being arranged on the deicing pedestal 3 and being made of multiple air bags 1, setting The first three-way magnetic valve 14 being connected on the suspension air bag and with each air bag 1, first three-way magnetic valve 14 Outlet end is connected by connecting tube 5 with the first compressed tanks 4 being arranged on the deicing pedestal 3.
The mobile mechanism includes the ellipse track being arranged in 3 side of deicing pedestal, is arranged on the ellipse track Multiple fixed pulleys 12, the belt 13 being arranged on multiple fixed pulleys 12, be arranged on deicing pedestal 3 and with a fixed pulley 12 Matched steering motor 15, the propeller module being arranged on the belt 13.
The propeller module includes the propeller protecting frame 20 being arranged on the belt 13, is arranged in the propeller The propeller 19 on 16 output shaft of propeller driving motor is arranged in propeller driving motor 16 in protecting frame 20, if It sets in 19 rear portion of the propeller and the water conservancy diversion motor 17 on the propeller protecting frame 20, and is arranged in the water conservancy diversion On 17 output shaft of motor and with 19 matched deflector 18 of the propeller.
Helium is set in first compressed tanks 4.
The auxiliary support mechanism 7 includes the first two axle The Cloud Terraces 71 being arranged on the deicing pedestal 3, is arranged described The first Auxiliary support telescopic rod 72 in first two axle The Cloud Terraces 71 is arranged the of 72 end of the first Auxiliary support telescopic rod Two two axle The Cloud Terraces 73, the second Auxiliary support telescopic rod 74 being arranged in second two axle The Cloud Terraces 73 are arranged described second 74 end of Auxiliary support telescopic rod and with the matched electromagnetic clamp of transmission line of electricity 75.
The control mechanism includes the CPU11 being arranged on the deicing pedestal 3, the wind with CPU11 signals interconnection To sensor 21 and air velocity transducer 23, the high-definition camera 8 with cpu signal interconnection is interconnected and is set with the cpu signal The MEMS gyroscope 9 and MEMS accelerometer 10 in deicing base central are set, the rechargeable lithium battery 2 with cpu signal interconnection, With the data transmission module 22 of cpu signal interconnection, the tablet computer with the interconnection of 22 wireless signal of the data transmission module.
Embodiment two
Its with embodiment one difference lies in:Setting and the matched anticollision metal of the suspension air bag on the deicing pedestal 3 Net.
The anticollision metal mesh used in the embodiment is preferably located on balloon surface, and by the way of flexible strip.
Embodiment three
Its with embodiment two difference lies in:Hydrogen is set in first compressed tanks 4.
The compressed gas used in the embodiment is hydrogen, due to being in low temperature environment, and generates preferable buoyancy, because This danger is relatively low.
Example IV
It is a kind of based on CT take can deicer for power transmission line application method:
S1:It carries near the present apparatus to pending transmission line of electricity, checks and verify whether each component works normally, then pass through Tablet computer controls multiple first three-way magnetic valves and is inflated into suspension air bag, so that drive of the present apparatus in suspension air bag Under, it is floated near transmission line of electricity;
S2:The air speed data and wind direction data that CPU is obtained according to air velocity transducer and wind transducer, by steering motor by its It adjusts with wind in the opposite direction, and adjust revolution speed of propeller to offset wind speed, it is ensured that the present apparatus can smoothly rise to defeated Near electric line;
S3:Then wherein gas is excluded by the first three-way magnetic valve, avoids continuing to rise, realize that the present apparatus suspends in the air, Then the coordinate of conducting wire is locked by high-definition camera and by auxiliary support mechanism electromagnetic clamp is consolidated with transmission line of electricity It is fixed;
S4:Make deicing mechanism close to transmission line of electricity with two axle The Cloud Terraces by the Auxiliary support telescopic rod in deicing mechanism, CT takes Energy mechanism carries out circuit package to take energy, and then the electric energy of conversion, which is first sent to accumulator, to be sent to heating cable so that arc panel Internal surface temperature rises, and carrying out heating to the icing on circuit top makes its thawing;
S5:When detecting a large amount of deicing of needs, then the position of propeller can be adjusted, and adjust suitable angle with rotating speed along defeated Electric line is walked, and realizes the effect for continuing deicing;
S6:After completing deicing, deicing mechanism and work of the auxiliary support mechanism to transmission line of electricity are released, and pass through tablet computer It controls the present apparatus to return at operator, completes entire work.
The above is the preferred embodiment of the present invention, it is noted that for those skilled in the art For, without departing from the principles of the present invention, it can also make several improvements and retouch, these improvements and modifications It should be regarded as protection scope of the present invention.

Claims (9)

1. a kind of deicer for power transmission line taking energy based on CT, it is characterised in that:Including deicing pedestal, it is arranged in the deicing The mobile mechanism on the deicing pedestal is arranged in suspension mechanism on pedestal, and the auxiliary branch on the deicing pedestal is arranged Support mechanism, is arranged the deicing mechanism on the deicing pedestal, and be arranged on the deicing pedestal for suspension mechanism, Mobile mechanism, auxiliary support mechanism and deicing mechanism coordinate the control mechanism of control;
The deicing mechanism includes the third two axle The Cloud Terraces being arranged on the deicing pedestal, is arranged in the third two axle The Cloud Terraces On third Auxiliary support telescopic rod, the 4th two axle The Cloud Terraces in the third Auxiliary support telescopic rod end are set, and setting exists The cross in the 4th Auxiliary support telescopic rod end is arranged in the 4th Auxiliary support telescopic rod in 4th two axle The Cloud Terraces Arc panel is arranged in the front end of arm, the transverse arm, and heating cable is arranged in the arc panel medial surface, and CT is arranged in the rear end of the transverse arm Qu Neng mechanisms, CT Qu Neng mechanisms are connect with the accumulator being arranged on arc panel, the accumulator and the heating cable Connection.
2. the deicer for power transmission line of energy is taken based on CT as described in claim 1, it is characterised in that:The suspension mechanism packet Include the suspension air bag for being arranged on the deicing pedestal and being made of multiple air bags, be arranged on the suspension air bag and with it is each The first three-way magnetic valve that air bag is connected, the outlet end of first three-way magnetic valve by connecting tube be arranged described The first compressed tanks on deicing pedestal are connected.
3. the deicer for power transmission line of energy is taken based on CT as claimed in claim 2, it is characterised in that:Mobile mechanism's packet The ellipse track being arranged in deicing pedestal side is included, multiple fixed pulleys are set on the ellipse track, is arranged multiple fixed Belt on pulley, be arranged on deicing pedestal and with a matched steering motor of fixed pulley, be arranged in the belt On propeller module.
4. the deicer for power transmission line of energy is taken based on CT as claimed in claim 3, it is characterised in that:The propeller module Including the propeller protecting frame being arranged on the belt, the propeller driving motor in the propeller protecting frame is set, Propeller in the propeller driving motor output shaft is set, and setting is at the propeller rear portion and is located at the propeller Water conservancy diversion motor on protecting frame, and be arranged on the water conservancy diversion motor output shaft and with the matched water conservancy diversion of the propeller Plate.
5. the deicer for power transmission line of energy is taken based on CT as claimed in claim 4, it is characterised in that:First compressed tanks Interior setting helium, hydrogen or neon.
6. the deicer for power transmission line of energy is taken based on CT as claimed in claim 5, it is characterised in that:On the deicing pedestal Setting and the matched anticollision metal mesh of the suspension air bag.
7. the deicer for power transmission line of energy is taken based on CT as claimed in claim 6, it is characterised in that:
The auxiliary support mechanism includes the first two axle The Cloud Terraces being arranged on the deicing pedestal, is arranged in first liang of axis The first Auxiliary support telescopic rod on holder, is arranged the second two axle The Cloud Terraces in the first Auxiliary support telescopic rod end, if The second Auxiliary support telescopic rod in second two axle The Cloud Terraces is set, is arranged in the second Auxiliary support telescopic rod end And with the matched electromagnetic clamp of transmission line of electricity.
8. the deicer for power transmission line of energy is taken based on CT as claimed in claim 7, it is characterised in that:The control mechanism packet The CPU being arranged on the deicing pedestal is included, wind transducer and air velocity transducer with cpu signal interconnection are and described Cpu signal interconnection high-definition camera, with the cpu signal interconnect and be arranged deicing base central MEMS gyroscope and MEMS accelerometer, the rechargeable lithium battery with cpu signal interconnection, the data transmission module with cpu signal interconnection, with The tablet computer of the data transmission module wireless signal interconnection.
9. it is a kind of based on CT take can deicer for power transmission line application method, it is characterised in that:
S1:It carries near the present apparatus to pending transmission line of electricity, checks and verify whether each component works normally, then pass through Tablet computer controls multiple first three-way magnetic valves and is inflated into suspension air bag, so that drive of the present apparatus in suspension air bag Under, it is floated near transmission line of electricity;
S2:The air speed data and wind direction data that CPU is obtained according to air velocity transducer and wind transducer, by steering motor by its It adjusts with wind in the opposite direction, and adjust revolution speed of propeller to offset wind speed, it is ensured that the present apparatus can smoothly rise to defeated Near electric line;
S3:Then wherein gas is excluded by the first three-way magnetic valve, avoids continuing to rise, realize that the present apparatus suspends in the air, Then the coordinate of conducting wire is locked by high-definition camera and by auxiliary support mechanism electromagnetic clamp is consolidated with transmission line of electricity It is fixed;
S4:Make deicing mechanism close to transmission line of electricity with two axle The Cloud Terraces by the Auxiliary support telescopic rod in deicing mechanism, CT takes Energy mechanism carries out circuit package to take energy, and then the electric energy of conversion, which is first sent to accumulator, to be sent to heating cable so that arc panel Internal surface temperature rises, and carrying out heating to the icing on circuit top makes its thawing;
S5:When detecting a large amount of deicing of needs, then the position of propeller can be adjusted, and adjust suitable angle with rotating speed along defeated Electric line is walked, and realizes the effect for continuing deicing;
S6:After completing deicing, deicing mechanism and work of the auxiliary support mechanism to transmission line of electricity are released, and pass through tablet computer It controls the present apparatus to return at operator, completes entire work.
CN201810689510.2A 2018-06-28 2018-06-28 Transmission line defroster based on CT gets ability Active CN108551147B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810689510.2A CN108551147B (en) 2018-06-28 2018-06-28 Transmission line defroster based on CT gets ability

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810689510.2A CN108551147B (en) 2018-06-28 2018-06-28 Transmission line defroster based on CT gets ability

Publications (2)

Publication Number Publication Date
CN108551147A true CN108551147A (en) 2018-09-18
CN108551147B CN108551147B (en) 2020-11-24

Family

ID=63493075

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810689510.2A Active CN108551147B (en) 2018-06-28 2018-06-28 Transmission line defroster based on CT gets ability

Country Status (1)

Country Link
CN (1) CN108551147B (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109103810A (en) * 2018-10-31 2018-12-28 国家电网有限公司 A kind of online replacement insulator arrangement
CN109193538A (en) * 2018-09-30 2019-01-11 国网河南省电力公司社旗县供电公司 A kind of overhead transmission line periodic cleaning equipment
CN109217173A (en) * 2018-09-30 2019-01-15 国网河南省电力公司西峡县供电公司 A kind of vibration damper on power transmission line hotline maintenance robot
CN109301751A (en) * 2018-10-27 2019-02-01 国网河南省电力公司西峡县供电公司 A kind of damper hotline maintenance robot
CN109327005A (en) * 2018-09-30 2019-02-12 国网河南省电力公司西峡县供电公司 A kind of field removing ice of power transmission line and waterproofing agent flusher
CN109449819A (en) * 2018-10-31 2019-03-08 国家电网有限公司 A kind of insulator surface on-Line Monitor Device
CN114614430A (en) * 2022-03-29 2022-06-10 国网河南省电力公司栾川县供电公司 Electric wire snow removing equipment

Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH01243812A (en) * 1988-03-25 1989-09-28 Ngk Insulators Ltd Covered snow removing method and sleet removing device
JPH05176441A (en) * 1991-12-19 1993-07-13 Tohoku Electric Power Co Inc Device for taking ice and snow off cable
DE202005018756U1 (en) * 2005-12-01 2006-02-09 Rohrer, Emil Deicer for power supply line, has housing driven along flow cable by impeller, and defrosting device attached in housing for defrosting ice layer on cable by mechanical effect such as by oppressive rolls pressing against each other
RU2011135617A (en) * 2011-08-26 2011-12-27 Владимир Анатольевич Ефремов (RU) METHOD AND DEVICE FOR PROTECTING THE OBJECT FROM HAZARDOUS SEDIMENTS
CN103904772A (en) * 2014-03-07 2014-07-02 广东工业大学 Hybrid power supply device oriented to power grid wireless sensor network node
CN203787916U (en) * 2014-04-09 2014-08-20 大同柏盛电子电气有限公司 High-voltage power transmission line operation state automatic monitoring ice-melting device
JP2015042104A (en) * 2013-08-23 2015-03-02 株式会社ビスキャス Spiral rod for overhead transmission line, and electric wire
CN204210726U (en) * 2014-11-11 2015-03-18 张宏志 A kind of solar power rotor inflation soft body unmanned airship
CN105947212A (en) * 2016-05-16 2016-09-21 苏州金建达智能科技有限公司 Intelligent fast meal delivery flying robot
CN107826246A (en) * 2017-10-11 2018-03-23 深圳市奈士迪技术研发有限公司 It is a kind of with road surface is anti-freeze and the unmanned plane of electric wire snow removing function
CN108134410A (en) * 2017-12-18 2018-06-08 安徽伊格瑞德电气设备有限公司 A kind of CT energy taking devices for high-pressure system

Patent Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH01243812A (en) * 1988-03-25 1989-09-28 Ngk Insulators Ltd Covered snow removing method and sleet removing device
JPH05176441A (en) * 1991-12-19 1993-07-13 Tohoku Electric Power Co Inc Device for taking ice and snow off cable
DE202005018756U1 (en) * 2005-12-01 2006-02-09 Rohrer, Emil Deicer for power supply line, has housing driven along flow cable by impeller, and defrosting device attached in housing for defrosting ice layer on cable by mechanical effect such as by oppressive rolls pressing against each other
RU2011135617A (en) * 2011-08-26 2011-12-27 Владимир Анатольевич Ефремов (RU) METHOD AND DEVICE FOR PROTECTING THE OBJECT FROM HAZARDOUS SEDIMENTS
JP2015042104A (en) * 2013-08-23 2015-03-02 株式会社ビスキャス Spiral rod for overhead transmission line, and electric wire
CN103904772A (en) * 2014-03-07 2014-07-02 广东工业大学 Hybrid power supply device oriented to power grid wireless sensor network node
CN203787916U (en) * 2014-04-09 2014-08-20 大同柏盛电子电气有限公司 High-voltage power transmission line operation state automatic monitoring ice-melting device
CN204210726U (en) * 2014-11-11 2015-03-18 张宏志 A kind of solar power rotor inflation soft body unmanned airship
CN105947212A (en) * 2016-05-16 2016-09-21 苏州金建达智能科技有限公司 Intelligent fast meal delivery flying robot
CN107826246A (en) * 2017-10-11 2018-03-23 深圳市奈士迪技术研发有限公司 It is a kind of with road surface is anti-freeze and the unmanned plane of electric wire snow removing function
CN108134410A (en) * 2017-12-18 2018-06-08 安徽伊格瑞德电气设备有限公司 A kind of CT energy taking devices for high-pressure system

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109217173B (en) * 2018-09-30 2020-08-28 国网河南省电力公司西峡县供电公司 Electrified maintenance robot for shockproof hammer of power transmission line
CN109193538A (en) * 2018-09-30 2019-01-11 国网河南省电力公司社旗县供电公司 A kind of overhead transmission line periodic cleaning equipment
CN109217173A (en) * 2018-09-30 2019-01-15 国网河南省电力公司西峡县供电公司 A kind of vibration damper on power transmission line hotline maintenance robot
CN109327005B (en) * 2018-09-30 2020-09-01 国网河南省电力公司西峡县供电公司 Deicing and waterproofing agent spraying device for field power transmission line
CN109327005A (en) * 2018-09-30 2019-02-12 国网河南省电力公司西峡县供电公司 A kind of field removing ice of power transmission line and waterproofing agent flusher
CN109301751B (en) * 2018-10-27 2020-09-01 国网河南省电力公司西峡县供电公司 Electrified maintenance robot for damper
CN109301751A (en) * 2018-10-27 2019-02-01 国网河南省电力公司西峡县供电公司 A kind of damper hotline maintenance robot
CN109103810B (en) * 2018-10-31 2020-06-09 国家电网有限公司 Online insulator replacing device
CN109449819B (en) * 2018-10-31 2020-07-03 国家电网有限公司 Insulator surface on-line monitoring device
CN109449819A (en) * 2018-10-31 2019-03-08 国家电网有限公司 A kind of insulator surface on-Line Monitor Device
CN109103810A (en) * 2018-10-31 2018-12-28 国家电网有限公司 A kind of online replacement insulator arrangement
CN114614430A (en) * 2022-03-29 2022-06-10 国网河南省电力公司栾川县供电公司 Electric wire snow removing equipment
CN114614430B (en) * 2022-03-29 2024-03-26 国网河南省电力公司栾川县供电公司 Wire snow removing equipment

Also Published As

Publication number Publication date
CN108551147B (en) 2020-11-24

Similar Documents

Publication Publication Date Title
CN108551147A (en) A kind of deicer for power transmission line taking energy based on CT
CN104724284B (en) A kind of many rotor diving unmanned vehicles and control method thereof
CN108945347B (en) A kind of underwater rescue outfit
CN108832575A (en) A kind of floated deicer for power transmission line
CN105799876B (en) A kind of bionic intelligence machine fish
WO2015008599A1 (en) Contactless power supply system
CN105947168A (en) Multi-rotor manned craft adopting helium balloon to overcome part of gravity
CN108853846A (en) Electric power equipment fire-fighting device on a kind of bar
CN208299411U (en) A kind of deicer for power transmission line
CN208069975U (en) A kind of auxiliary balance device for unmanned boat
CN109225961A (en) A kind of ultra-high-tension power transmission line surface layer dirt removal device
CN108832576A (en) A kind of powerline ice-covering remove device
CN108808609A (en) A kind of deicer for power transmission line
CN109013419A (en) A kind of transmission line of electricity deashing device taking energy based on CT
CN105818943B (en) The marine overboard unmanned salvage device of the wounded applied to carrier-based helicopter
CN210882549U (en) Rescue unmanned aerial vehicle on water
CN205931212U (en) Many rotor manned vehicle of partly gravity is overcome with helium balloon
CN107914842A (en) A kind of lifesaving ship for being capable of anti-rollover
CN207617941U (en) A kind of novel and multifunctional deliverance apparatus waterborne
CN102193558B (en) Stretchable driven type detection robot based on tumbleweed simulation
CN107176294A (en) A kind of overwater flight device
CN212529334U (en) Wireless unmanned aerial vehicle that charges
CN207216427U (en) A kind of search and rescue robot
CN108879480A (en) A kind of overhead transmission line twister cleaning plant
CN109573005A (en) A kind of airborne making-up air device of pneumatic operation of landing gear of unmanned plane

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant