CN108518239A CN201810267374.8A CN201810267374A CN108518239A CN 108518239 A CN108518239 A CN 108518239A CN 201810267374 A CN201810267374 A CN 201810267374A CN 108518239 A CN108518239 A CN 108518239A
Authority
CN
China
Prior art keywords
box culvert
constructing tunnel
tunnel
aerated
sealing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810267374.8A
Other languages
Chinese (zh)
Inventor
杨信美
张晓平
钱玉华
华伟明
陈鹏
李延秋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuhan University WHU
China Railway 14th Bureau Group Shield Engineering Co Ltd
Economic and Technological Research Institute of State Grid Jiangsu Electric Power Co Ltd
Original Assignee
Wuhan University WHU
China Railway 14th Bureau Group Shield Engineering Co Ltd
Economic and Technological Research Institute of State Grid Jiangsu Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhan University WHU, China Railway 14th Bureau Group Shield Engineering Co Ltd, Economic and Technological Research Institute of State Grid Jiangsu Electric Power Co Ltd filed Critical Wuhan University WHU
Priority to CN201810267374.8A priority Critical patent/CN108518239A/en
Publication of CN108518239A publication Critical patent/CN108518239A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F1/00Ventilation of mines or tunnels; Distribution of ventilating currents
    • E21F1/006Ventilation at the working face of galleries or tunnels
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F1/00Ventilation of mines or tunnels; Distribution of ventilating currents
    • E21F1/04Air ducts
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F1/00Ventilation of mines or tunnels; Distribution of ventilating currents
    • E21F1/08Ventilation arrangements in connection with air ducts, e.g. arrangements for mounting ventilators

Abstract

The invention discloses a kind of method being aerated using box culvert during constructing tunnel, during constructing tunnel, processing, formation ventilating duct are sealed to the seam crossing of box culvert and box culvert, box culvert and hole wall;Processing, and reserved connecting hole are sealed to the box culvert outer end face of constructing tunnel originating terminal;The ventilating duct formed to box culvert assembly is divulged information in advance, tests the friction property coefficient and air leakage coefficient, rated wind pressure of box culvert, and match wind turbine;It carries out pinging wind after installation connection wind turbine, and detects box culvert and leak out situation and fan operation situation;Start wind turbine, monitors each position in real time and leak out situation, and processing is sealed in time to serious position of leaking out;As constructing tunnel promotes, internal box culvert constantly assembled can forward extend, and per one section of box culvert of assembly, will be sealed processing.The present invention makes full use of tunnel existing structure, not only strengthens ventilation effect, but also save material, substantially reduces cost.

Description

A method of it is aerated using box culvert during constructing tunnel
Technical field
The invention belongs to constructing tunnel fields, are related to a kind of construction ventilation of tunnel method, and in particular to one kind is applied in tunnel The method being aerated using box culvert during work.This method can increase drafting efficiency in tunnel excavating process, reduce ventilation Energy consumption.
Background technology
In tunnel excavating process, air flow property is poor in tunnel, and due to the influence of Work machine etc., the sky in tunnel Gas deterioration jeopardizes equipment and the safety of staff, is the technical barrier in current constructing tunnel.
During constructing tunnel, tunnel not yet penetrates through, and only unilateral and air communication can not pass through the natural flowing of air To improve the air quality in tunnel.Especially in the tunneling process of long distance tunnel, if without other secondary ventilation modes, tunnel Air is substantially at stationary state in road, and pollutant cannot be spread in tunnel, be built up, will when reaching a certain concentration Jeopardize the equipment in tunnel and the safety of staff, cause safety accident, leads to construction delay and economic loss.
Long distance tunnel mostly uses the tunneling methods such as drilling and blasting method, shield method.In drilling and blasting method driving, often exploding will once produce Raw a large amount of toxic and harmful gas;In shield method execution, Shield-type machinery continuously tunnels, and requires material transportation high, I. C. engine steam Tail gas discharge is big, these can all cause temperature in tunnel to increase, and air quality declines, it is necessary to efficient draft type is taken, The construction environment in tunnel is set to reach the requirement of related specifications.
In long distance tunnel work progress, common draft type is mostly zip mode pneumatic hose forced ventilation, in hole At the outer fresh wind in ground, using wind turbine by air hose to tunnel front air feed, waste air is discharged by tunnel return air outside hole.But In internal box culvert and tunnel piercing synchronous construction, since box culvert occupied space is big, tunnel internal can be used for laying the sky of air hose Between reduce, cause dust diameter to reduce.In tunnel, one timing of required airflow and ventilation distance, required with the reduction of dust diameter The inversely proportional increase of wind pressure.But the maximum wind pressure that the maximum wind pressure that can provide of wind turbine and air hose can be born is restricted, The draft type cannot be satisfied the ventilation requirement of engineering under extreme case.
Invention content
It is tired it is an object of the invention to divulge information for the long distance tunnel of current tunnel piercing and internal box culvert synchronous construction Difficult problem provides a kind of method that can reduce ventilation energy consumption and improve drafting efficiency.To box culvert and box culvert, box culvert and hole The seam crossing of wall is sealed processing, and using the box culvert after sealing as the transfer passage of fresh wind in tunnel, recycles fresh Wind conveying fan and short air hose by it is fresh it is distinguished and admirable be pumped in box culvert, and then send to the method for tunnel inner working face, reach tunnel Air-conditioning requirement and the purpose for saving energy consumption.
In view of the needs transported in hole, internal box culvert mostly uses prefabricated outside segmented hole, assembled form of construction work in hole. Box culvert forms closed-loop with Tunnel wall on cross section;Box culvert is concrete structure, and has certain thickness;But box culvert There is hole with box culvert, box culvert and hole wall seam crossing, can cause to leak out.Therefore it only needs to be sealed at abutment joint, box culvert is It can be used as conveyance conduit of the fresh wind in hole.It divulges information in this way, air hose need not be separately set in hole, phase can be saved The manpower and material cost answered.And space is big in box culvert, and in tunnel, one timing of required airflow, required wind pressure can be significantly less than wind Wind pressure needed for pipe, can also reduce the energy consumption of fresh wind conveying fan, cost-effective.
In order to solve the above-mentioned technical problem, the technical solution adopted in the present invention is:
A method of it is aerated using box culvert during constructing tunnel, which is characterized in that include the following steps:
Step 1: during constructing tunnel, after the completion of every segment box culvert assembly, to this section of box culvert and adjacent box culvert and hole The seam crossing of wall is sealed processing, forms ventilating duct;
Step 2: being sealed processing to the box culvert outer end face of constructing tunnel originating terminal, and reserves and matched with air hose size Connecting hole;
Step 3: being divulged information in advance to the ventilating duct that box culvert assembly is formed by connecting hole, box culvert after encapsulation process is tested Friction property coefficient and air leakage coefficient, and according to tunnel required airflow rated wind pressure, and match wind turbine;
Step 4: installing matched fresh wind conveying fan in the fresh wind suitable position in tunnel originating terminal ground, and pass through Fresh wind conveying fan is connected by pipeline with the connecting hole of the box culvert outer end face of constructing tunnel originating terminal;
Step 5: after confirming that ventilating system is complete, carry out pinging wind, and detects box culvert and leak out situation and fan operation Situation;
Step 6: starting fresh wind conveying fan, ventilating system enters operating status, monitors each position in real time and leaks out feelings Condition, and processing is sealed in time to serious position of leaking out;
Step 7: as constructing tunnel promotes, internal box culvert constantly assembled can forward extend, complete in each section of box culvert assembly At rear repetition processing is sealed according to step 1.
As an improvement, the seam crossing of the box culvert and box culvert, box culvert and hole wall is sealed processing using mortar.
As an improvement, the seam crossing of the box culvert and box culvert, box culvert and hole wall is sealed processing using sealing strip.
As an improvement, the sealing strip is epoxy resin sealing strip and/or polysulfide sealing strip.
As an improvement, the fresh wind conveying fan is axial flow blower.
As an improvement, after the sealing of every segment box culvert is completed, it is necessary to carry out air leak test, to seal bad position and When adopt remedial measures, reseal.
As an improvement, box culvert using sealing strip seal when, can among box culvert seam preset packing material, the filling material Material is polyethylene item or batten.
As an improvement, box culvert first polishes to box culvert corresponding region before the sealing of adhesive seal item.
The beneficial effects of the invention are as follows:
The present invention effectively increases air feed using the box culvert after encapsulation process as the transfer passage of fresh wind in tunnel Pipeline crosses wind area, reduces the input amount of ventilation shaft, reduces ventilation wind pressure, reduces to fresh wind conveying fan Performance requirement has reached saving material, has reduced energy consumption, puies forward efficient purpose, after the completion of constructing tunnel, by box culvert outer end face Sealing remove, restore the original function of box culvert, dual-use material greatly reduces construction cost.
Description of the drawings
Fig. 1 is tunnel ventilation flow diagram of the present invention.
Fig. 2 is tunnel internal box culvert schematic cross-sectional view.
Fig. 3 is tunnel internal box culvert and the contact positions Dong Bi schematic diagram.
Fig. 4 is tunnel internal box culvert and box culvert contact position schematic diagram.
Fig. 5 is tunnel originating terminal box culvert outer end processing schematic diagram.
Fig. 6 is to use schematic diagram of the cement mortar as sealing material.
Fig. 7 is to use schematic diagram of the sealing strip as sealing material.
Fig. 8 is ventilating system schematic diagram.
1- box culverts, the holes 2- wall, 3- connecting holes.
Specific implementation mode
Below in conjunction with the accompanying drawings to a kind of method being aerated using box culvert during constructing tunnel provided by the invention It is described in detail.
As shown in Figure 1, a kind of method being aerated using box culvert during constructing tunnel, is included the following steps:
Step 1: during constructing tunnel, after the completion of every segment box culvert assembly, to this section of box culvert and adjacent box culvert and hole The seam crossing of wall is sealed processing, forms ventilating duct;
Step 2: being sealed processing to the box culvert outer end face of constructing tunnel originating terminal, and reserves and matched with air hose size Connecting hole;
Step 3: being divulged information in advance to the ventilating duct that box culvert assembly is formed by connecting hole, box culvert after encapsulation process is tested Friction property coefficient and air leakage coefficient, and according to tunnel required airflow rated wind pressure, and match wind turbine;
Step 4: installing matched fresh wind conveying fan (this implementation in the fresh wind suitable position in tunnel originating terminal ground Example is axial flow blower), and by pipeline by the connecting hole of fresh wind conveying fan and the box culvert outer end face of constructing tunnel originating terminal It is connected;
Step 5: after confirming that ventilating system is complete, carry out pinging wind, and detects box culvert and leak out situation and fan operation Situation;
Step 6: starting fresh wind conveying fan, ventilating system enters operating status, monitors each position in real time and leaks out feelings Condition, and processing is sealed in time to serious position of leaking out;
Step 7: as constructing tunnel promotes, internal box culvert constantly assembled can forward extend, complete in each section of box culvert assembly At rear repetition processing is sealed according to step 1.
Fresh wind conveying fan described in the embodiment of the present invention is axial flow blower.Axial flow blower is selected, is actually not limited to Axial flow blower, also can be selected other any air quantity and wind pressure meets the wind turbine of tunnel ventilation requirement.
The seam crossing of box culvert of the present invention and box culvert, box culvert and hole wall is that mortar can be used to be sealed processing, be can also be used Sealing strip is sealed processing, but is not limited to above two encapsulation process mode.
Can preset packing material, the packing material be poly- second among box culvert seam when box culvert is sealed using sealing strip Alkene foam strip or batten, but it is not limited to both materials.
First, be familiar with box culvert structure, find box culvert seam and box culvert and hole wall seam, measure seam size and Length primarily determines the dosage of sealing material.Then, suitable sealing material is chosen, and is chosen according to different sealing materials Suitable sealing means.In the process, the principle that need to meet is as follows:
A, the statistics of seam crossing is had to comprehensively accurate, can not omit, part otherwise can be caused to leak out, ventilating system is lost Effect.
B, sealing material must be kept in the case of vibration and temperature change good air-tightness, certain durability and Rigidity, and it is nontoxic, environmentally friendly, on the use of box culvert later stage without influence.
C, different sealing material sealing means are different, it is necessary to and it is reasonably combined, otherwise sealing effect can be caused bad, influenced The efficiency of entire ventilating system.
D, after selected sealing material and sealing means, it is necessary to carry out air-leakage test to the effect of sealing, ensure to reach To the requirement of engineering.
When selecting mortar as sealing material, should be wanted first according to slab culvert concrete intensity, joint gap, air-tightness It asks, selects suitable cement mortar ratio.Since mortar has mobility, seam should be filled to closely knit, guarantee gas using grouting mode Close property.Grouting pressure is unsuitable too small, avoids inside mortar that there are larger holes, can not ensure air-tightness;Grouting pressure should not mistake Greatly, mortar can be made to overflow if excessive, wastes material and easily filling is invalid.Select mortar as sealing material sealing means such as Shown in Fig. 6.
When selecting sealing strip as sealing material, first according to joint gap and air-tightness requirement, sealing strip is selected Material.Common sealing strip has epoxy resin sealing strip, polysulfide sealing strip etc..The width of sealing strip should be suitable, sealing strip width It is unsuitable too small, it has to be possible to cover all seam and both sides can be overlapped on, ensure air-tightness;Sealing strip width should not mistake Greatly, overlap is long meaningless and wastes material.In order to ensure air-tightness, it is necessary in both sides adhesive seal item, when necessary Can in the joint between the fillers such as filled polyethylene foam strip.Before adhesive seal item, first box culvert corresponding region should be beaten Mill ensures the intensity pasted, and reduces the hole for pasting contact surface.Select sealing means of the sealing strip as sealing material when As shown in Figure 7.
The sealing means of box culvert seam crossing are various, and sealing material also can flexibly be selected according to Practical Project, only be enumerated herein Above two mode, but it is not limited to above-mentioned form.
The foregoing is only a preferred embodiment of the present invention, but scope of protection of the present invention is not limited thereto, Any one skilled in the art in the technical scope disclosed by the present invention, the change or replacement that can be readily occurred in, It should be covered by the protection scope of the present invention.

Claims (8)

1. a kind of method being aerated using box culvert during constructing tunnel, which is characterized in that include the following steps:
Step 1: during constructing tunnel, after the completion of every segment box culvert assembly, to this section of box culvert and adjacent box culvert and hole wall Seam crossing is sealed processing, forms ventilating duct;
Step 2: being sealed processing, and the reserved and matched company of air hose size to the box culvert outer end face of constructing tunnel originating terminal Connect hole;
Step 3: being divulged information in advance to the ventilating duct that box culvert assembly is formed by connecting hole, box culvert rubs after test encapsulation process Property coefficient and air leakage coefficient are wiped, and according to tunnel required airflow rated wind pressure, and matches wind turbine;
Step 4: installing matched fresh wind conveying fan in the fresh wind suitable position in tunnel originating terminal ground, and pass through pipeline Fresh wind conveying fan is connected with the connecting hole of the box culvert outer end face of constructing tunnel originating terminal;
Step 5: after confirming that ventilating system is complete, carry out pinging wind, and detects box culvert and leak out situation and fan operation shape Condition;
Step 6: starting fresh wind conveying fan, ventilating system enters operating status, monitors each position in real time and leaks out situation, and To leaking out, serious position is sealed processing in time;
Step 7: as constructing tunnel promotes, internal box culvert constantly assembled can forward extend, after the completion of each section of box culvert assembly It repeats to be sealed processing according to step 1.
2. a kind of method being aerated using box culvert during constructing tunnel as described in claim 1, it is characterised in that:Institute The seam crossing for stating box culvert and box culvert, box culvert and hole wall is sealed processing using mortar.
3. a kind of method being aerated using box culvert during constructing tunnel as described in claim 1, it is characterised in that:Institute The seam crossing for stating box culvert and box culvert, box culvert and hole wall is sealed processing using sealing strip.
4. a kind of method being aerated using box culvert during constructing tunnel as claimed in claim 3, it is characterised in that:Institute It is epoxy resin sealing strip and/or polysulfide sealing strip to state sealing strip.
5. a kind of method being aerated using box culvert during constructing tunnel as described in claim 1, it is characterised in that:Institute It is axial flow blower to state fresh wind conveying fan.
6. a kind of method being aerated using box culvert during constructing tunnel as described in claim 1, it is characterised in that: After being completed per the sealing of segment box culvert, it is necessary to carry out air leak test, adopt remedial measures in time to the position for sealing bad, again Sealing.
7. a kind of method being aerated using box culvert during constructing tunnel as claimed in claim 3, it is characterised in that:Case Contain using sealing strip sealing when, can among box culvert seam preset packing material, the packing material be polyethylene item or Batten.
8. a kind of method being aerated using box culvert during constructing tunnel as claimed in claim 3, it is characterised in that:Case Contain before the sealing of adhesive seal item, first polishes box culvert corresponding region.
CN201810267374.8A 2018-03-28 2018-03-28 A method of it is aerated using box culvert during constructing tunnel Pending CN108518239A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810267374.8A CN108518239A (en) 2018-03-28 2018-03-28 A method of it is aerated using box culvert during constructing tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810267374.8A CN108518239A (en) 2018-03-28 2018-03-28 A method of it is aerated using box culvert during constructing tunnel

Publications (1)

Publication Number Publication Date
CN108518239A true CN108518239A (en) 2018-09-11

Family

ID=63430808

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810267374.8A Pending CN108518239A (en) 2018-03-28 2018-03-28 A method of it is aerated using box culvert during constructing tunnel

Country Status (1)

Country Link
CN (1) CN108518239A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109854299A (en) * 2018-12-11 2019-06-07 中煤科工集团重庆研究院有限公司 Airway coefficient of frictional resistance fast determination method based on big data

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100686643B1 (en) * 2006-08-08 2007-02-26 주식회사 혜인이엔씨 Apparatus for collecting dust for road
CN203668970U (en) * 2013-12-17 2014-06-25 中国水电顾问集团华东勘测设计研究院有限公司 Ventilation pressure regulating structure of box culvert
CN104912099A (en) * 2015-06-16 2015-09-16 李全民 Fabricated precast concrete box culvert
CN206636576U (en) * 2016-12-27 2017-11-14 中国建筑第七工程局有限公司 A kind of new self-propelled hydraulic box culvert, tunnel trolley with air-cleaning function

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100686643B1 (en) * 2006-08-08 2007-02-26 주식회사 혜인이엔씨 Apparatus for collecting dust for road
CN203668970U (en) * 2013-12-17 2014-06-25 中国水电顾问集团华东勘测设计研究院有限公司 Ventilation pressure regulating structure of box culvert
CN104912099A (en) * 2015-06-16 2015-09-16 李全民 Fabricated precast concrete box culvert
CN206636576U (en) * 2016-12-27 2017-11-14 中国建筑第七工程局有限公司 A kind of new self-propelled hydraulic box culvert, tunnel trolley with air-cleaning function

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
戴洪伟: "超大直径盾构隧道巷道式通风技术", 《现代交通技术》 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109854299A (en) * 2018-12-11 2019-06-07 中煤科工集团重庆研究院有限公司 Airway coefficient of frictional resistance fast determination method based on big data
CN109854299B (en) * 2018-12-11 2020-10-23 中煤科工集团重庆研究院有限公司 Method for rapidly determining friction resistance coefficient of ventilation roadway based on big data

Similar Documents

Publication Publication Date Title
CN107191197B (en) Shield segment and construction method thereof in tunnel through mine method by shield air pushing
CN108825269A (en) Mechanical Method service channel T socket part position adaptive waterproof construction
CN107387145B (en) Long-long tunnel ventilation system with long-distance air supply function
CN108518239A (en) A method of it is aerated using box culvert during constructing tunnel
CN109139081B (en) High-gas ultra-long tunnel construction ventilation method
CN106223897A (en) A kind of fully-mechanized mining working crushes coal petrography deep hole segmenting slip casting method
CN205689234U (en) A kind of ventilation transportation system of monocline well many faces constructing tunnel
CN214499063U (en) Supplementary quick backfill system of two shield TBM crack rock segment bags
CN205244385U (en) Gas solid two phase seal structure
CN214145495U (en) Shield tunneling machine muck conveying device for water-rich stratum
CN206290859U (en) Socket joint interconnection system pipe with detachable bellmouth
CN111305853B (en) Shield tail leakage stopping method in shield construction
CN108194090B (en) Tunnel boring machine with waterproof film laying bin section and tunnel construction method
CN205978972U (en) Hafu joint
CN204127565U (en) Underground Steam Pipeline with Pipe-in-pipe Structure thermal insulation layer repairing device
CN212225294U (en) Assembled special-shaped air duct for long-distance tunnel construction ventilation
JPH06102957B2 (en) Underground joining method of shield tunnel
CN203420713U (en) Shield launching tunnel portal extension steel ring
CN113063052A (en) Pipeline lining grouting repair method
CN207761645U (en) Shield piping lane system
CN111677541A (en) Safe construction ventilation method for large-diameter earth pressure balance shield of low-gas tunnel
CN217735541U (en) Air supply and smoke exhaust structure for tunnel
CN212225216U (en) Water-rich stratum earth pressure balance shield starting tunnel portal sealing device
CN210738569U (en) Novel mortise and tenon type duct piece suitable for shield machine
CN106552805B (en) The application method of the centrifugal axial flow blower emission from vehicles device of biexhaust pipe

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20180911

RJ01 Rejection of invention patent application after publication