CN207761645U - Shield piping lane system - Google Patents

Shield piping lane system Download PDF

Info

Publication number
CN207761645U
CN207761645U CN201721784815.9U CN201721784815U CN207761645U CN 207761645 U CN207761645 U CN 207761645U CN 201721784815 U CN201721784815 U CN 201721784815U CN 207761645 U CN207761645 U CN 207761645U
Authority
CN
China
Prior art keywords
piping lane
shield
integration node
linkage section
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn - After Issue
Application number
CN201721784815.9U
Other languages
Chinese (zh)
Inventor
陈思
刘元重
王瑀
尹力文
刘轶群
宋永茂
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhongye Jingcheng Engineering Technology Co Ltd
Original Assignee
Zhongye Jingcheng Engineering Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhongye Jingcheng Engineering Technology Co Ltd filed Critical Zhongye Jingcheng Engineering Technology Co Ltd
Priority to CN201721784815.9U priority Critical patent/CN207761645U/en
Application granted granted Critical
Publication of CN207761645U publication Critical patent/CN207761645U/en
Withdrawn - After Issue legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model is a kind of shield piping lane system, shield piping lane system includes being spliced along longitudinal direction by multiple shield piping lane standard paragraphs or piping lane main line that a shield piping lane standard paragraphs are constituted, launching shaft is respectively set in the both ends of shield piping lane standard paragraphs and shield terminates well, multiple piping lane integration node units are arranged in the external side interval of piping lane main line, each piping lane integration node unit can be connected to by piping lane linkage section with piping lane main line, and the one end of each piping lane linkage section far from piping lane integration node unit can seal and linkage section partition board is arranged with capable of opening.The shield piping lane system overcomes the problems such as construction period existing in the prior art is long, piping lane integration node construction space is limited, construction cost is high, the construction degree of association of shield circuit and piping lane integration node unit can be reduced, reduce the shield piping lane system whole duration, the advantage that shield piping lane is implemented over long distances is given full play to, construction cost is reduced.

Description

Shield piping lane system
Technical field
The utility model is related to city integrated piping lane technical field more particularly to a kind of shield piping lane systems.
Background technology
Pipe gallery technology has obtained extensive concern as municipal pipeline laying form, there is very ripe case in each state Example, special China's pipe gallery build development in recent years rapidly, and pipe gallery is built in newly built city district can usually face particular surroundings, Long-distance transport pipes such as the larger river of river cross-section width, undercrossing tunnel, highway, present situation water delivery, gas transmission, oil transportation etc. are worn as follows, Heavy excavation form of construction work is restricted, it is necessary to use non-excavating construction mode;Usually have for built urban construction pipe gallery There are the various features such as implementation condition is limited, limiting factor is more, coverage is larger, difficulty of construction is larger, it is also necessary to using non- Excavation construction mode.And (shield method is promoted in ground using shield to shield method, is supported all around by shield shell and section of jurisdiction Rock prevents caving in tunnel, while carrying out soil excavation with cutterhead in front of excavation face, and by being unearthed, machinery transports hole Outside, it leans on propelling cylinder in rear pressurization jacking, and assembled precast concrete section of jurisdiction, forms a kind of mechanized construction of tunnel structure Method.There is the method overall process to realize automated job, and construction labor intensity is low, does not influence traffic above-ground and facility;In construction Climate condition does not influence, and does not generate noise and disturbance;The larger long tunnel of buried depth is built in soft water-bearing layer often to be had The superiority of technology and economic aspect) as efficiently, safety no-dig technique mode obtained society approval.
Shield piping lane technology is transformed in municipal technology of track traffic at present, using piping lane integration node as track The station of traffic is handled, using the working procedure of " backing of first standing ".Working procedure completes launching shaft 11, shield in advance Terminate piping lane integration node 92 necessary to well 12 and piping lane (for during pipe gallery use ventilation, the works such as feed intake Sequence is must be provided on pipe gallery, and setting spacing need to meet piping lane specification regulation), as shown in Fig. 2, existing piping lane Integration node 92 is set in pipe gallery main body 91, and when shield machine reaches piping lane integration node, bursting node headwall is reserved Shield hole, stop shield, then it is flat-pushing cross piping lane integration node, carry out secondary shield.Existing shield piping lane and its construction Method has following problem:
(1) " backing of first standing " technique leads to that piping lane integration node must be completed in advance with construction, and all nodes are implemented When reserved shield hole, the construction period of the complicated construction technique of piping lane integration node, piping lane integration node itself is longer;Due to Piping lane integration node is located in pipe gallery main body, and piping lane integration node is associated with pipe gallery main body in the presence of construction, and the two is not It can construct simultaneously, usually after the construction of piping lane integration node, carry out pipe gallery main body shield-tunneling construction, increase shield pipe The construction period of corridor entirety.
(2) piping lane specification provides piping lane fire retarding division distance no more than 200 meters, to play the excellent of shield piping lane long range Gesture usually expands the distance between piping lane integration node (600 meters to 800 meters), and ventilation subregion includes 3 to 4 fire compartments, pipe Corridor integration node is larger, and shield piping lane usually uses in built city, builds limited space, large-scale synthesis node location is often Lack and build space, causes the routing of piping lane shield to extend, cost increases substantially.
The present inventor relies on experience and the practice for being engaged in relevant industries for many years as a result, proposes a kind of shield piping lane system, with It overcomes the deficiencies of existing technologies.
Utility model content
The purpose of this utility model is to provide a kind of shield piping lane systems, overcome the construction period existing in the prior art Long, the problems such as piping lane integration node construction space is limited, construction cost is high, piping lane integration node unit in the shield piping lane system Simple in structure, short construction period can reduce the construction degree of association of shield circuit and piping lane integration node unit, reduce shield pipe The corridor system whole duration, the advantage that shield piping lane is implemented over long distances is given full play to, reduces construction cost.
The purpose of this utility model is achieved in that a kind of shield piping lane system, the shield piping lane system include by The piping lane main line that multiple shield piping lane standard paragraphs splice along longitudinal direction or a shield piping lane standard paragraphs are constituted, the shield piping lane mark Launching shaft is respectively set in the both ends of quasi- section and shield terminates well, and multiple pipes are arranged in the external side interval of the piping lane main line Corridor integration node unit, each piping lane integration node unit can be connected to by piping lane linkage section with the piping lane main line, each institute Stating the one end of piping lane linkage section far from the piping lane integration node unit can seal and linkage section partition board is arranged with capable of opening.
In a better embodiment of the utility model, lining cutting is in the pipe on the inner wall of each shield piping lane standard paragraphs Corridor section of jurisdiction is reinforced concrete segment, and lining cutting is steel tunnel segment in the linkage section section of jurisdiction on the inner wall of each piping lane linkage section, The linkage section section of jurisdiction linkage section partition board is steel tunnel segment.
In a better embodiment of the utility model, the length of each shield piping lane standard paragraphs is 2000 to 3000 Rice.
From the above mentioned, shield piping lane system provided by the utility model has the advantages that:
(1) in the shield piping lane system of the utility model, piping lane integration node unit is set to the outside one of piping lane main line Side, can reduce the construction degree of association of shield circuit and piping lane integration node unit, and the two construction can be carried out at the same time, reduce The waiting duration of " backing of first standing " is not required to carry out shield simultaneously because piping lane integration node unit is no longer set on piping lane main line The construction at structure hole, the structure of itself are further simplified, and reduce the construction period of piping lane integration node unit;Shield piping lane In standard paragraphs, by no longer stopping shield when piping lane integration node cell position, one time shield distance effectively lengthens shield machine, improves shield Structure efficiency effectively reduces the shield-tunneling construction duration, in conclusion the shield piping lane system of the utility model effectively reduces entirety Construction period;
(2) the piping lane integration node cell position of the shield piping lane system of the utility model is more flexible, reduces piping lane Influence of the integration node cell position to the circuit of piping lane main line;
(3) the shield piping lane system of the utility model gives full play to the advantage that shield piping lane is implemented over long distances, reduces construction Cost;It is applied widely, it can be used in that there is the shield pipe gallery in different cabins, enter the shield synthesis of corridor pipeline with difference The shield pipe gallery of piping lane and newly-built and built city.
Description of the drawings
The following drawings is only intended in doing schematic illustration and explanation to the utility model, does not limit the model of the utility model It encloses.Wherein:
Fig. 1:For the structural schematic diagram of the shield piping lane system of the utility model.
Fig. 2:For the structural schematic diagram of shield piping lane in the prior art.
In figure:
100, shield piping lane system;
1, piping lane main line;
10, shield piping lane standard paragraphs;11, launching shaft;12, shield terminates well;
2, piping lane integration node unit;
21, piping lane linkage section;22, linkage section partition board;
91, pipe gallery main body;92, piping lane integration node.
Specific implementation mode
For a clearer understanding of the technical features, objectives and effects of the utility model, existing control description of the drawings Specific embodiment of the present utility model.
As shown in Figure 1, the utility model provides a kind of shield piping lane system 100, shield piping lane system 100 includes by multiple The piping lane main line 1 that shield piping lane standard paragraphs 10 splice along longitudinal direction or a shield piping lane standard paragraphs 10 are constituted, shield piping lane standard Launching shaft 11 is respectively set in the both ends of section 10 and shield terminates well 12, and the external side interval setting of piping lane main line 1 is multiple Piping lane integration node unit 2 (spacing distance of each piping lane integration node unit meets piping lane specification regulation), each piping lane synthesis section Dot element 2 can be connected to by piping lane linkage section 21 with piping lane main line 1, and each piping lane linkage section 21 is far from piping lane integration node unit 2 One end can seal and linkage section partition board 22 is set with capable of opening.In the shield piping lane system 100 of the utility model, piping lane synthesis Node unit is set to the external side of piping lane main line, can reduce shield circuit and is associated with the construction of piping lane integration node unit Degree, the two construction can be carried out at the same time, and reduce the waiting duration of " backing of first standing ", simultaneously because piping lane integration node unit is not It is set to again on piping lane main line, is not required to carry out the construction at shield hole, the structure of itself is further simplified, and it is comprehensive to reduce piping lane Close the construction period of node unit;In shield piping lane standard paragraphs, shield machine when piping lane integration node cell position by no longer stopping Shield, one time shield distance effectively lengthens, and improves shield efficiency, effectively reduces the shield-tunneling construction duration, in conclusion the utility model Shield piping lane system 100 effectively reduce the integral construction duration;The piping lane of the shield piping lane system 100 of the utility model is comprehensive It is more flexible to close node unit position, reduces influence of the piping lane integration node cell position to the circuit of piping lane main line;This reality The advantage that shield piping lane is implemented over long distances is given full play to novel shield piping lane system 100, reduces construction cost, the scope of application Extensively, can be used in the shield pipe gallery with different cabins, with it is different enter corridor pipeline shield pipe gallery and it is newly-built and The shield pipe gallery in built city.
Further, in the piping lane section of jurisdiction on the inner wall of each shield piping lane standard paragraphs 10, (prior art, section of jurisdiction are piping lanes for lining cutting The structure of support system, carries out while shield driving assembled, ensures the stabilization of the soil body and prevents the extruding of the soil body from causing in time The deformation of section;Section of jurisdiction is usually piecemeal segmentation lining cutting successively, and a ring of the section of shield piping lane is generally by 4 to 12 assembly Constitute) it is reinforced concrete segment, lining cutting is steel tunnel segment, connection in the linkage section section of jurisdiction on the inner wall of each piping lane linkage section 21 Section partition board 22 is made of steel tunnel segment.
Further, the length of each shield piping lane standard paragraphs 10 is 2000 to 3000 meters, and piping lane integration node unit is set to The external side of piping lane main line, during shield-tunneling construction, shield machine no longer needs to stop shield, a jacking distance by original 600 to 800 meters increase to 2000 meters to 3000 meters, and shield machine is capable of the construction of jacking completion shield piping lane standard paragraphs 10, improves shield Structure efficiency reduces the construction period of shield-tunneling construction.
The construction method of the shield piping lane system 100 of the utility model, includes the following steps,
Step a, piping lane integration node unit 2 is carried out at the design position of piping lane integration node unit 2 to construct, while into The launching shaft 11 and shield of row shield piping lane standard paragraphs 10 terminate well 12 and construct, when piping lane main line 1 is by multiple shield piping lanes When standard paragraphs 10 are spliced to form along longitudinal direction, between two neighboring shield piping lane standard paragraphs 10, previous shield piping lane standard paragraphs 10 Shield terminates the launching shaft 11 that well 12 constitutes latter shield piping lane standard paragraphs 10, which is properly termed as piping lane master Line intermediate wells;
When constructing in the case where construction space is sufficiently large, piping lane integration node unit 2 may be used heavy excavation mode into Row construction;When construction area is by limited time, piping lane integration node unit 2 is using vertical supporting form of construction work or using vertical heavy Well construction mode carries out construction.
Step b, launching shaft 11 and shield terminate well 12 (when piping lane main line 1 is by multiple 10 edges of shield piping lane standard paragraphs Further include the shared piping lane main line intermediate wells of adjacent shield piping lane standard paragraphs 10 when longitudinal spliced composition) construction beginning after the completion The construction of the shield-tunneling construction of piping lane main line 1, shield-tunneling construction and piping lane integration node unit 2 can be carried out at the same time, shield piping lane mark In quasi- section 10, shield-tunneling construction is completed in jacking of shield machine;
Step c, after piping lane integration node unit 2 is constructed, complete piping lane integration node unit 2 and piping lane main line 1 it Between piping lane linkage section 21 construction, each piping lane linkage section 21 far from piping lane integration node unit 2 one end setting can seal The linkage section partition board 22 of each piping lane linkage section 21 and piping lane main line 1 is isolated;
Form of construction work that there are two types of piping lane linkage sections 21, one is, the use of piping lane linkage section 21 New Austrian Tunneling Method (prior art, secretly One kind of digging, tunneling generally comprise New Austrian Tunneling Method, push bench process, shield method.) construction, from piping lane integration node unit 2 to piping lane main line 1 (design position of piping lane main line 1, at this time the not yet shield of piping lane main line 1 to shield terminate well or be over shield-tunneling construction) Carry out tunneling;Second is that piping lane linkage section 21 is limited due to geology etc., needs to apply by the way of push pipe or shield Work.
Step d, after the shield-tunneling construction for completing piping lane main line 1, each linkage section partition board 22 is opened, is connected to piping lane integration node list Member 2 and piping lane main line 1, complete the construction of shield piping lane system 100.
Correspondingly with two kinds of forms of construction work of piping lane linkage section 21, the method for opening each linkage section partition board 22 has corresponding two Kind mode.
When piping lane linkage section 21 is constructed using New Austrian Tunneling Method, piping lane linkage section 21 is from piping lane integration node unit 2 to piping lane Main line 1 carry out tunneling, when dig to linkage section partition board 22 when, remove part linkage section partition board 22 (steel tunnel segment), and part into Row cutting, the linkage section partition board 22 (steel tunnel segment) after cutting are welded with the pre-buried steel plate of tunneling piping lane linkage section 21, and piping lane is comprehensive It closes node unit 2 to be connected to piping lane main line 1 by piping lane linkage section 21, forms complete shield piping lane system.
When piping lane linkage section 21 is constructed by the way of push pipe or shield, piping lane linkage section 21 can from piping lane main line 1 to Piping lane integration node unit 2 carries out shield, and the size of shield machine is limited by shield line section at this time;Piping lane linkage section 21 Shield can also be carried out from piping lane integration node unit 2 to piping lane main line 1.When using this form of construction work, 22 (steel of linkage section partition board Section of jurisdiction) it is external carry out mortar depositing construction in advance, cure the periphery soil body, complete after piping lane linkage section 21 constructs, to remove linkage section partition board 22 (steel tunnel segments), piping lane integration node unit 2 are connected to by piping lane linkage section 21 with piping lane main line 1, and complete shield is formed Piping lane system.
From the above mentioned, shield piping lane system provided by the utility model has the advantages that:
(1) in the shield piping lane system of the utility model, piping lane integration node unit is set to the outside one of piping lane main line Side, can reduce the construction degree of association of shield circuit and piping lane integration node unit, and the two construction can be carried out at the same time, reduce The waiting duration of " backing of first standing " is not required to carry out shield simultaneously because piping lane integration node unit is no longer set on piping lane main line The construction at structure hole, the structure of itself are further simplified, and reduce the construction period of piping lane integration node unit;Shield piping lane In standard paragraphs, by no longer stopping shield when piping lane integration node cell position, one time shield distance effectively lengthens shield machine, improves shield Structure efficiency effectively reduces the shield-tunneling construction duration, in conclusion the shield piping lane system of the utility model effectively reduces entirety Construction period;
(2) the piping lane integration node cell position of the shield piping lane system of the utility model is more flexible, reduces piping lane Influence of the integration node cell position to the circuit of piping lane main line;
(3) the shield piping lane system of the utility model gives full play to the advantage that shield piping lane is implemented over long distances, reduces construction Cost;It is applied widely, it can be used in that there is the shield pipe gallery in different cabins, enter the shield synthesis of corridor pipeline with difference The shield pipe gallery of piping lane and newly-built and built city.
The above descriptions are merely exemplary embodiments of the present utility model, is not limited to the model of the utility model It encloses.Any those skilled in the art, made equivalent change under the premise of not departing from the design and principle of the utility model Change and change, the range of the utility model protection should all be belonged to.

Claims (3)

1. a kind of shield piping lane system, the shield piping lane system includes being spliced along longitudinal direction by multiple shield piping lane standard paragraphs or one The piping lane main line that a shield piping lane standard paragraphs are constituted, launching shaft and shield is respectively set in the both ends of the shield piping lane standard paragraphs Structure terminates well, which is characterized in that multiple piping lane integration node units are arranged in the external side interval of the piping lane main line, each described Piping lane integration node unit can be connected to by piping lane linkage section with the piping lane main line, and each piping lane linkage section is far from the pipe One end of corridor integration node unit can seal and linkage section partition board is arranged with capable of opening.
2. shield piping lane system as described in claim 1, which is characterized in that lining cutting is in each shield piping lane standard paragraphs Piping lane section of jurisdiction on wall is reinforced concrete segment, and lining cutting is steel in the linkage section section of jurisdiction on the inner wall of each piping lane linkage section Tubulation piece, the linkage section partition board are steel tunnel segment.
3. shield piping lane system as described in claim 1, which is characterized in that the length of each shield piping lane standard paragraphs is 2000 to 3000 meters.
CN201721784815.9U 2017-12-19 2017-12-19 Shield piping lane system Withdrawn - After Issue CN207761645U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721784815.9U CN207761645U (en) 2017-12-19 2017-12-19 Shield piping lane system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721784815.9U CN207761645U (en) 2017-12-19 2017-12-19 Shield piping lane system

Publications (1)

Publication Number Publication Date
CN207761645U true CN207761645U (en) 2018-08-24

Family

ID=63187210

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721784815.9U Withdrawn - After Issue CN207761645U (en) 2017-12-19 2017-12-19 Shield piping lane system

Country Status (1)

Country Link
CN (1) CN207761645U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107905801A (en) * 2017-12-19 2018-04-13 中冶京诚工程技术有限公司 Shield piping lane system and its construction method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107905801A (en) * 2017-12-19 2018-04-13 中冶京诚工程技术有限公司 Shield piping lane system and its construction method

Similar Documents

Publication Publication Date Title
CN105298501A (en) Construction method for auxiliary air duct structure of underground excavation station
CN108547639B (en) Tunnel closes on the advanced same more conduit delamination pour slurry construction methods in hole of existing buildings
CN110439574B (en) Tunnel structure for shield lateral translation starting and slag discharging material conveying and construction method
CN107091101A (en) Mine shield handing-over tunnel folded type joint design and construction method in the middle part of marine site
CN112160755B (en) Subway line construction method for expanding excavation station after shield tunnel construction in advance
CN110017145B (en) Sea area shield mine junction tunnel intra-cavity connection joint and construction method thereof
CN105673046A (en) Twin-arch tunnel middle pilot tunnel vault backfilling construction method
CN109779653B (en) Construction method for crossing of soft rock large-section tunnel
CN107218045A (en) The rapid constructing method of rocky stratum tunneling subway station gateway tunneling section
CN105781595A (en) Method for mechanical branch underground excavation construction of rectangular and quasi-rectangular cross-section underground engineering
CN108868814A (en) Collapsible loess combination land pebble stratum tunneling air duct connects the ventilating shaft of shield tunnel
CN104712342A (en) Method of providing working plane for station expanding excavation construction in large-diameter shield tunnel
CN105065040B (en) A kind of prefabricated underground space tunneling construction method of top plate
CN204851266U (en) Secretly dig shaft structure directly over station
CN207761645U (en) Shield piping lane system
CN105041348B (en) A kind of underground space tunneling construction method of use compound roof
CN112727484B (en) Shield-pipe-jacking up-down parallel overlapping tunnel structure and construction method thereof
CN207420587U (en) One kind is suitable for TBM tunnel-liner rings
CN207033463U (en) Mine shield handing-over tunnel folded type joint design in the middle part of marine site
CN105863673B (en) Pusher fuselage can return to formula pipe jacking construction method and constructing structure
CN107269283B (en) A kind of big cross section tunneling subway station and running tunnel penetrate through construction method
CN101660418B (en) Box culvert jack-in replacement rectangular pipe support method used for tunnel construction
CN107574830A (en) A kind of subway station combines the precipitation method of piping lane construction
CN107905801A (en) Shield piping lane system and its construction method
CN208816132U (en) Collapsible loess combination land pebble stratum tunneling air duct connects the ventilating shaft of shield tunnel

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
AV01 Patent right actively abandoned
AV01 Patent right actively abandoned
AV01 Patent right actively abandoned

Granted publication date: 20180824

Effective date of abandoning: 20230512

AV01 Patent right actively abandoned

Granted publication date: 20180824

Effective date of abandoning: 20230512