CN105673046A - Twin-arch tunnel middle pilot tunnel vault backfilling construction method - Google Patents

Twin-arch tunnel middle pilot tunnel vault backfilling construction method Download PDF

Info

Publication number
CN105673046A
CN105673046A CN201610036578.1A CN201610036578A CN105673046A CN 105673046 A CN105673046 A CN 105673046A CN 201610036578 A CN201610036578 A CN 201610036578A CN 105673046 A CN105673046 A CN 105673046A
Authority
CN
China
Prior art keywords
middle drift
pilot tunnel
vault
tunnel
side pilot
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610036578.1A
Other languages
Chinese (zh)
Other versions
CN105673046B (en
Inventor
张�荣
胡方华
虞贵期
刘世艳
熊建武
李新明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Gezhouba Group No 1 Engineering Co Ltd
Original Assignee
China Gezhouba Group No 1 Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Gezhouba Group No 1 Engineering Co Ltd filed Critical China Gezhouba Group No 1 Engineering Co Ltd
Priority to CN201610036578.1A priority Critical patent/CN105673046B/en
Publication of CN105673046A publication Critical patent/CN105673046A/en
Application granted granted Critical
Publication of CN105673046B publication Critical patent/CN105673046B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/102Removable shuttering; Bearing or supporting devices therefor

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention provides a twin-arch tunnel middle pilot tunnel vault backfilling construction method. The method comprises the following steps that a middle pilot tunnel is excavated, and a support is constructed; after the middle pilot tunnel is excavated and the support extends forwards by a certain distance, a left pilot tunnel is excavated, and a support is constructed; after the middle pilot tunnel is excavated to a certain depth, a middle partition wall is poured; an in-the-hole drill is arranged in position, drill holes are formed, and the drill holes are led to a middle pilot tunnel vault space in the top of the middle partition wall from the left pilot tunnel or a right pilot tunnel; a conveying pipe is installed in the drill holes so that sprayed concrete can enter the middle pilot tunnel vault space in the top of the middle partition wall; twin-arch tunnel middle pilot tunnel vault backfilling construction is achieved. Backfilling of the middle pilot tunnel vault is conducted in the manner that upper steps of the left pilot tunnel are drilled to form the holes. The technical problem that under the working condition that pouring of the middle partition wall is conducted in two directions, the middle pilot tunnel vault can not be backfilled is solved, middle pilot tunnel vault backfilling and middle partition wall pouring are conducted at the same time, and the effective working time is shortened greatly.

Description

Double-arched tunnel middle drift vault backfill construction method
Technical field
The present invention relates to Double Multi-Arch Tunnel Construction field, particularly double-arched tunnel middle drift vault backfill construction method.
Background technology
Owing to being designed the constraint of structure and the restriction of stress system by double-arched tunnel itself, the excavation and support topped bar in main hole can be carried out after mid-board is built and vault has backfilled. That is, excavation and the preliminary bracing of middle drift is first carried out in opposite directions from import and outlet; Secondly, after middle drift is through from import to outlet or from outlet to import direction, i.e. the building of unidirectional enforcement mid-board; 3rd, the backfill of middle drift vault is built immediately following mid-board and to outlet or is exported to import direction by import, namely carries out the construction of jetting cement in the same direction; 4th, excavation and the preliminary bracing thereof topped bar in main hole are progressively pushed ahead immediately following the backfill of middle drift vault.
In practice of construction process, if middle drift mileage is longer or cannot carry out excavation and the preliminary bracing of middle drift in opposite directions from importing and exporting in a short time, then main wide open dig with support work by be seriously limited by the excavation of middle drift, supporting and mid-board build, the working procedure such as vault backfill.
When middle drift excavation and preliminary bracing not yet complete, in the middle part of middle drift to import or export carry out mid-board build with middle drift vault backfill construction collide with each other, namely the operation such as mid-board reinforcing bar binding, chassis movement in place, concreting influences each other with the backfill construction of middle drift vault, it is impossible to carry out simultaneously.
Summary of the invention
The technical problem to be solved is to provide a kind of double-arched tunnel middle drift vault backfill construction method, in the middle part of middle drift, mid-board can be implemented to import and export direction to build, and under the form of construction work after mid-board has been built, complete the backfill construction of middle drift vault, efficiency of construction can be improved, shorten the engineering time.
For solving above-mentioned technical problem, the technical solution adopted in the present invention is: a kind of double-arched tunnel middle drift vault backfill construction method, comprises the following steps:
One, middle drift excavation and supporting;
Two, after middle drift excavation and supporting extend forwardly into a segment distance, left side pilot tunnel and right side pilot tunnel and supporting are excavated;
Three, after middle drift is excavated to certain depth, mid-board is built;
Four, until mid-board build with spud carriage shifting after, arrange down-the-hole drill in place and form boring, holing and lead to the middle drift vault space at mid-board top from left side pilot tunnel or right side pilot tunnel;
Five, down-the-hole drill displacement, concrete spraying machine is in place, installs conveying pipe in boring, makes gunite concrete enter the middle drift vault space at mid-board top;
The backfill construction of double-arched tunnel middle drift vault is realized by above step.
Described boring, along middle drift axis, arranges one every 7 ~ 13 meters.
Bore diameter is 8 ~ 17cm.
Internal diameter of delivery hose is 5 ~ 10cm.
A kind of double-arched tunnel middle drift vault backfill construction method, comprises the following steps:
One, middle drift advance support;
Two, middle drift excavation, preliminary bracing;
Three, mid-board concrete construction;
Four, left side pilot tunnel is topped bar advance support;
Five, left side pilot tunnel is topped bar excavation, initial stage and gib;
Six, right side pilot tunnel is topped bar advance support;
Seven, right side pilot tunnel is topped bar excavation, initial stage and gib;
Eight, on the right side of mid-board, stull or backfill are set with middle drift right wall;
Nine, hole from left side pilot tunnel or right side pilot tunnel to middle drift vault space;
Ten, concrete spraying machine in place and install conveying pipe to middle drift vault space;
11, to gunite concrete in middle drift vault space;
The backfill construction of double-arched tunnel middle drift vault is realized by above step.
After middle drift excavation and supporting extend forward 20-40 rice, excavate left side pilot tunnel and right side pilot tunnel and supporting.
Excavation face distance between left side pilot tunnel and right side pilot tunnel answers >=30m.
After middle drift is excavated to certain depth or is through, in middle drift hole or breakthrough point to one end or import and export two ends build mid-board.
Start to build the time of mid-board and position, top bar the late start time of excavation and support according to left side pilot tunnel or right side pilot tunnel and determine.
Described boring, along middle drift axis, arranges one every 7 ~ 13 meters;
Bore diameter is 8 ~ 17cm.
A kind of double-arched tunnel middle drift vault backfill construction method provided by the invention, by changing middle drift vault of the prior art backfill scheme, realize no longer building and vault backfill construction by the unidirectional enforcement mid-board of import or export, and be adjusted in the middle part of middle drift to importing and exporting direction, namely building of two-way enforcement mid-board is constructed with the mixed backfill of middle drift vault spray. Owing to being limited by middle drift work space in prior art, the backfill construction of middle drift vault is built with mid-board and tops bar in main hole, and excavation interacts with preliminary bracing, it is difficult to construct simultaneously. For overcoming this defect, in the present invention, the backfill of middle drift vault adopts and tops bar from left side pilot tunnel or right side pilot tunnel is topped bar the mode of boring backfill construction. What can solve two-way enforcement mid-board builds the technical barrier that under working condition, middle drift vault cannot backfill, realize the backfill of middle drift vault to build carry out simultaneously with mid-board, it is to avoid build top bar with main hole and Core Soil excavates owing to middle drift backfill construction or backfill affects mid-board not in time. Present invention optimizes and build and the arrangement and method for construction of vault backfill to the unidirectional enforcement mid-board of the other end from middle drift one end, substantially reduce the effective time on Double Multi-Arch Tunnel Construction critical circuits.
Accompanying drawing explanation
Below in conjunction with drawings and Examples, the invention will be further described:
Fig. 1 is the construction procedure schematic diagram of the present invention.
In figure: middle drift advance support 1, middle drift excavates, preliminary bracing 2, mid-board concrete construction 3, left side pilot tunnel is topped bar advance support 4, left side pilot tunnel is topped bar excavation, initial stage and gib 5, right side pilot tunnel is topped bar advance support 6, right side pilot tunnel is topped bar excavation, initial stage and gib 7, stull or backfill 8 are set with the right wall of middle drift on the right side of mid-board, boring 9, concrete spraying machine 10, gunite concrete 11, top bar advance support 12 in main hole, left side, top bar arch Ring Cutting in main hole, left side, preliminary bracing 13, left side main hole top bar Core Soil excavation 14, top bar advance support 15 in main hole, right side, top bar arch Ring Cutting in main hole, right side, preliminary bracing 16, right side main hole top bar Core Soil excavation 17, stull 18.
Detailed description of the invention
As shown in fig. 1, a kind of double-arched tunnel middle drift vault backfill construction method, comprise the following steps:
One, middle drift advance support 1;
Two, middle drift excavation, preliminary bracing 2;
Three, mid-board reinforcing bar binding and chassis are in place, carry out mid-board concrete pouring construction 3; In preferred scheme, after middle drift is excavated to certain depth or is through, in middle drift hole or breakthrough point to one end or import and export two ends build mid-board.
Start to build the time of mid-board and position, top bar the late start time of excavation and support according to left side pilot tunnel or right side pilot tunnel and determine.
Mid-board concreting completes aftertable car and moves to next position in storehouse.
Four, left side pilot tunnel is topped bar advance support 4;
Five, left side pilot tunnel is topped bar excavation, initial stage and gib 5;
In preferred scheme, after middle drift excavation and supporting extend forward 20-40 rice, it is preferred to 30 meters, excavation left side pilot tunnel is topped bar.
Six, right side pilot tunnel is topped bar advance support 6;
Seven, right side pilot tunnel is topped bar excavation, initial stage and gib 7;
Excavation face distance between left side pilot tunnel and right side pilot tunnel answers >=30m. Thus scheme, it is to avoid due to the blasting vibration impact on mutual scope of operation surrounding rock stability.
Eight, stull 18 or backfill 8 are set with the right wall of middle drift on the right side of mid-board;
Nine, owing to being limited by middle drift work space, build in order to avoid middle drift vault backfill construction infection mid-board and top bar and excavate and preliminary bracing in main hole, therefore adopt down-the-hole drill to hole 9 from left side pilot tunnel or right side pilot tunnel. This example adopts from left side pilot tunnel through main hole, left side top bar and main hole, left side top bar Core Soil to middle drift vault space hole 9; In preferred scheme, described boring 9, along middle drift axis, arranges one every 7 ~ 13 meters; Preferred every 10 meters of layouts one. Preferred boring 9 diameters are 8 ~ 17cm. Preferred boring 9 diameters are 15cm. The preferred ZGYX420 of down-the-hole drill in this example.
Ten, concrete spraying machine 10 in place and install conveying pipe to middle drift vault space; Internal diameter of delivery hose is 5 ~ 10cm. This example is preferably 6.5cm. The preferred JRD-PS800 of concrete spraying machine 10 in this example.
11, to gunite concrete in middle drift vault space; Referring to the position of accompanying drawing labelling 11 indication in figure.
The backfill construction of double-arched tunnel middle drift vault is realized by above step.
In follow-up step:
12, top bar advance support 12 in main hole, left side;
13, top bar arch Ring Cutting, preliminary bracing 13 in main hole, left side;
14, main hole, left side top bar Core Soil excavation 14;
15, top bar advance support 15 in main hole, right side;
16, top bar arch Ring Cutting, preliminary bracing 16 in main hole, right side;
17, main hole, right side top bar Core Soil excavation 17.
The excavation of double-arched tunnel is completed by above-mentioned step.
The above embodiments are only the preferred technical solution of the present invention; and it is not construed as the restriction for the present invention; the technical characteristic recorded in the present invention; under the premise do not conflicted; use can be combined mutually; the technical scheme that protection scope of the present invention should be recorded with claim, is protection domain including the equivalents of technical characteristic in the technical scheme that claim is recorded. Namely equivalent replacement the within the scope of this is improved, also within protection scope of the present invention.

Claims (10)

1. a double-arched tunnel middle drift vault backfill construction method, is characterized in that comprising the following steps:
One, middle drift excavation and supporting;
Two, after middle drift excavation and supporting extend forwardly into a segment distance, left side pilot tunnel and right side pilot tunnel and supporting are excavated;
Three, after middle drift is excavated to certain depth, mid-board is built;
Four, until mid-board build with spud carriage shifting after, arrange down-the-hole drill in place and form boring (9), boring (9) is from left side pilot tunnel or right side pilot tunnel towards the middle drift vault space at mid-board top;
Five, down-the-hole drill displacement, concrete spraying machine (10) is in place, installs conveying pipe in boring (9), makes gunite concrete (11) enter the middle drift vault space at mid-board top;
The backfill construction of double-arched tunnel middle drift vault is realized by above step.
2. a kind of double-arched tunnel middle drift vault backfill construction method according to claim 1, is characterized in that: described boring (9), along middle drift axis, arranges one every 7 ~ 13 meters.
3. a kind of double-arched tunnel middle drift vault backfill construction method according to claim 1, is characterized in that: boring (9) diameter is 8 ~ 17cm.
4. a kind of double-arched tunnel middle drift vault backfill construction method according to claim 1, is characterized in that: internal diameter of delivery hose is 5 ~ 10cm.
5. a double-arched tunnel middle drift vault backfill construction method, is characterized in that comprising the following steps:
One, middle drift advance support (1);
Two, middle drift excavation, preliminary bracing (2);
Three, mid-board concrete construction (3);
Four, left side pilot tunnel is topped bar advance support (4);
Five, left side pilot tunnel is topped bar excavation, initial stage and gib (5);
Six, right side pilot tunnel is topped bar advance support (6);
Seven, right side pilot tunnel is topped bar excavation, initial stage and gib (7);
Stull or backfill (8) eight, are set with the right wall of middle drift on the right side of mid-board;
Nine, (9) are holed from left side pilot tunnel or right side pilot tunnel to middle drift vault space;
Ten, concrete spraying machine (10) in place and install conveying pipe to middle drift vault space;
11, to gunite concrete in middle drift vault space;
The backfill construction of double-arched tunnel middle drift vault is realized by above step.
6. a kind of double-arched tunnel middle drift vault backfill construction method according to claim 5, is characterized in that: after middle drift excavation and supporting extend forward 20-40 rice, excavate left side pilot tunnel and right side pilot tunnel and supporting.
7. a kind of double-arched tunnel middle drift vault backfill construction method according to claim 5, is characterized in that: the excavation face distance between left side pilot tunnel and right side pilot tunnel answers >=30m.
8. a kind of double-arched tunnel middle drift vault backfill construction method according to claim 5, is characterized in that: after middle drift is excavated to certain depth or is through, in middle drift hole or breakthrough point to one end or import and export two ends and build mid-board.
9. a kind of double-arched tunnel middle drift vault backfill construction method according to claim 8, is characterized in that: start to build time and the position of mid-board, tops bar the late start time of excavation and support according to left side pilot tunnel or right side pilot tunnel and determines.
10. a kind of double-arched tunnel middle drift vault backfill construction method according to claim 5, is characterized in that: described boring (9), along middle drift axis, arranges one every 7 ~ 13 meters;
Boring (9) diameter is 8 ~ 17cm.
CN201610036578.1A 2016-01-20 2016-01-20 Double-arched tunnel middle drift vault backfills construction method Active CN105673046B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610036578.1A CN105673046B (en) 2016-01-20 2016-01-20 Double-arched tunnel middle drift vault backfills construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610036578.1A CN105673046B (en) 2016-01-20 2016-01-20 Double-arched tunnel middle drift vault backfills construction method

Publications (2)

Publication Number Publication Date
CN105673046A true CN105673046A (en) 2016-06-15
CN105673046B CN105673046B (en) 2018-05-01

Family

ID=56302006

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610036578.1A Active CN105673046B (en) 2016-01-20 2016-01-20 Double-arched tunnel middle drift vault backfills construction method

Country Status (1)

Country Link
CN (1) CN105673046B (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106884665A (en) * 2017-04-19 2017-06-23 中铁局集团有限公司 A kind of Double Multi-Arch start tunneling method based on arch set arch
CN108843333A (en) * 2018-04-25 2018-11-20 广州地铁设计研究院有限公司 Collapsible Loess District tunneling double-arched tunnel passes through the construction method of existing railway
CN109209429A (en) * 2018-09-19 2019-01-15 中建三局基础设施建设投资有限公司 A kind of anti-sidesway support trolley of Middle Wall of Multi-Arch Highway Tunnel and its construction method
CN109882182A (en) * 2019-01-09 2019-06-14 中铁七局集团西安铁路工程有限公司 A kind of extra small clear distance construction method in tunnel
CN110017143A (en) * 2019-05-10 2019-07-16 兰州铁道设计院有限公司 A kind of auxiliary method of small interval loess tunnel construction of central division wall
CN112412474A (en) * 2020-11-25 2021-02-26 中交二航局第二工程有限公司 Multi-arch tunnel construction method
CN113622941A (en) * 2021-09-10 2021-11-09 中铁一局集团第五工程有限公司 Large-span double-arch tunnel excavation method under urban complex environment
CN114352292A (en) * 2021-12-31 2022-04-15 中交路桥建设有限公司 Shallow-buried bias-pressure multi-arch tunnel construction method for weathering phyllite stratum

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100752285B1 (en) * 2006-01-11 2007-08-29 주식회사 케이투기술단 Construction method for two arches tunnel
CN101864960A (en) * 2010-05-17 2010-10-20 中铁二十局集团有限公司 Carst region double-arch road tunnel construction method
CN102606168A (en) * 2012-03-16 2012-07-25 西安理工大学 Construction method for preventing settlement and deformation of shallow-buried-excavation tunnel in excavation
CN103256052A (en) * 2013-05-17 2013-08-21 北京国道通公路设计研究院股份有限公司 Construction method for integral straight middle wall type double-arch tunnel
CN103953366A (en) * 2014-05-20 2014-07-30 长安大学 Middle separation wall top original lining cavity backfilling construction method when single-hole tunnel is changed into multiple arches

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100752285B1 (en) * 2006-01-11 2007-08-29 주식회사 케이투기술단 Construction method for two arches tunnel
CN101864960A (en) * 2010-05-17 2010-10-20 中铁二十局集团有限公司 Carst region double-arch road tunnel construction method
CN102606168A (en) * 2012-03-16 2012-07-25 西安理工大学 Construction method for preventing settlement and deformation of shallow-buried-excavation tunnel in excavation
CN103256052A (en) * 2013-05-17 2013-08-21 北京国道通公路设计研究院股份有限公司 Construction method for integral straight middle wall type double-arch tunnel
CN103953366A (en) * 2014-05-20 2014-07-30 长安大学 Middle separation wall top original lining cavity backfilling construction method when single-hole tunnel is changed into multiple arches

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106884665A (en) * 2017-04-19 2017-06-23 中铁局集团有限公司 A kind of Double Multi-Arch start tunneling method based on arch set arch
CN106884665B (en) * 2017-04-19 2018-11-06 中铁一局集团有限公司 A kind of Double Multi-Arch start tunneling method based on arch set arch
CN108843333A (en) * 2018-04-25 2018-11-20 广州地铁设计研究院有限公司 Collapsible Loess District tunneling double-arched tunnel passes through the construction method of existing railway
CN109209429A (en) * 2018-09-19 2019-01-15 中建三局基础设施建设投资有限公司 A kind of anti-sidesway support trolley of Middle Wall of Multi-Arch Highway Tunnel and its construction method
CN109209429B (en) * 2018-09-19 2020-05-12 中建三局基础设施建设投资有限公司 Supporting trolley for preventing partition wall of multi-arch tunnel from moving laterally and construction method thereof
CN109882182A (en) * 2019-01-09 2019-06-14 中铁七局集团西安铁路工程有限公司 A kind of extra small clear distance construction method in tunnel
CN110017143A (en) * 2019-05-10 2019-07-16 兰州铁道设计院有限公司 A kind of auxiliary method of small interval loess tunnel construction of central division wall
CN112412474A (en) * 2020-11-25 2021-02-26 中交二航局第二工程有限公司 Multi-arch tunnel construction method
CN113622941A (en) * 2021-09-10 2021-11-09 中铁一局集团第五工程有限公司 Large-span double-arch tunnel excavation method under urban complex environment
CN114352292A (en) * 2021-12-31 2022-04-15 中交路桥建设有限公司 Shallow-buried bias-pressure multi-arch tunnel construction method for weathering phyllite stratum

Also Published As

Publication number Publication date
CN105673046B (en) 2018-05-01

Similar Documents

Publication Publication Date Title
CN105673046A (en) Twin-arch tunnel middle pilot tunnel vault backfilling construction method
CN110424969B (en) Construction method for open cut method station with tunnel before station
CN104533446A (en) Construction method and structure of two-layer preliminary support for preventing geological disaster of large-section weak surrounding rock tunnel
CN103061777B (en) Method for building urban underground tunnel shield cutter repairing space with preset reinforcing pile groups
CN101701646B (en) Method for slurry-water balance type pipe-pulling construction of underground pipeline
CN107905796B (en) A kind of operating room tunnels in soil Guan Peng construction method
CN104632235A (en) Method for expanding excavation of large-diameter shield tunnel for subway station construction through pile arch wall support
CN103835729A (en) Ground pre-grouting strengthening technology for deep long-distance roadway surrounding rock
CN107965341A (en) A kind of large-section underground pipe canopy pipe network concrete support method
CN109113757A (en) Tunnel cross mouth rapid constructing method
CN105256812A (en) Prefabricated assembly type concrete supporting structure for foundation pit and construction method of prefabricated assembly type concrete supporting structure
CN103244143B (en) A kind of underground construction excavating construction method and underground station
CN103321658A (en) Molded lining support structure and construction method for soft soil ground layer
CN107575237A (en) A kind of subsurface excavation method is combined the construction method of construction subway station with shield method
CN105909262B (en) A kind of bored tunnel driving method
CN104712342A (en) Method of providing working plane for station expanding excavation construction in large-diameter shield tunnel
CN204851266U (en) Secretly dig shaft structure directly over station
CN204457789U (en) A kind of stake arch wall supports the subway station digging large diameter shield tunnel and build
CN111485888B (en) Prefabricated piecemeal lining tunnel system in advance
CN112727484A (en) Shield-pipe-jacking up-down parallel overlapping tunnel structure and construction method thereof
CN105065774B (en) A kind of underground piping branch connects construction method
CN114718582B (en) Construction method for small-clear-distance horizontal joint shale geological tunnel portal section
CN205189880U (en) Shield constructs to be assembled section of jurisdiction and crosses undercut tunnel construction structures
CN113958322B (en) Tunnel excavation method under existing subway line
CN110159276A (en) Tunnel excavation technique in a kind of disintegration in water ultimate soft rock stratum

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant