CN203420713U - Shield launching tunnel portal extension steel ring - Google Patents

Shield launching tunnel portal extension steel ring Download PDF

Info

Publication number
CN203420713U
CN203420713U CN201320417259.7U CN201320417259U CN203420713U CN 203420713 U CN203420713 U CN 203420713U CN 201320417259 U CN201320417259 U CN 201320417259U CN 203420713 U CN203420713 U CN 203420713U
Authority
CN
China
Prior art keywords
plate
ring flat
steel loop
ring
steel ring
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201320417259.7U
Other languages
Chinese (zh)
Inventor
刘尧庆
沙权贤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 13th Bureau Group Co Ltd
Original Assignee
China Railway 13th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 13th Bureau Group Co Ltd filed Critical China Railway 13th Bureau Group Co Ltd
Priority to CN201320417259.7U priority Critical patent/CN203420713U/en
Application granted granted Critical
Publication of CN203420713U publication Critical patent/CN203420713U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

The utility model discloses a shield launching tunnel portal extension steel ring. The shield launching tunnel portal extension steel ring is characterized in that the steel ring comprises a steel body (1), the width of the steel ring body (1) is at least 45mm, one end of the steel ring body (1) is connected with a first ring plate (2), the inner diameter of the first ring plate (2) is equal to that of the steel ring body (1), the outer diameter of the first ring plate (2) is larger than the diameter of the steel ring body (1), the first ring plate (2) is fixedly connected with a second ring plate (3), the thickness of the second ring plate (3) is two times that of the first ring plate (2), and the second ring plate (3) is embedded into a wall of a tunnel portal. The shield launching tunnel portal extension steel ring is simple in structure, indigenous in design, and capable of avoiding dust pollution caused by manual pile breaking and improving the work efficiency of a shield tunneling machine.

Description

Shield launching portal extends steel loop
Technical field
The utility model relates to a kind of shield launching portal supplementary structure, and particularly a kind of shield launching portal extends steel loop.
Background technology
In subway shield tunnel construction, starting of shield machine is a considerable link, in construction in the past, because the distance between portal sealing and face is very near, in order to make the cutterhead of shield machine when carrying out broken pile, can not damage cord rubber tile, before broken pile, conventionally will adopt manually-operated mode that face is abolished to 60cm dark, to guarantee the space of cutterhead rotation.But, artificial broken pile construction can produce a large amount of dust, and because plate in the station of missing the stop seals often, dust cannot be discharged smoothly, air quality in station is sharply declined, have a strong impact on workman's construction environment, also can affect the assembly working of technique on shield machine's station-crossing, thereby seriously delay the progress of technique on shield machine's station-crossing construction simultaneously.Therefore need now a kind of new structure that can address the above problem or device.
Summary of the invention
The utility model is in order to solve the existing above-mentioned deficiency of prior art, propose a kind of simple in structure, design ingenious, the dust pollution of avoiding artificial broken pile to cause, and the shield launching portal that can improve shield machine operating efficiency extends steel loop.
Technical solution of the present utility model is: a kind of shield launching portal extends steel loop, it is characterized in that: described steel loop comprises steel loop body 1, the width of steel loop body 1 is at least 45mm, one end of steel loop body 1 is connected with the first ring flat-plate 2, the internal diameter of the first ring flat-plate 2 is identical with steel loop body 1, the external diameter of the first ring flat-plate 2 is greater than the diameter of steel loop body 1, be fixedly connected with the second ring flat-plate 3 with the first ring flat-plate 2, the thickness of the second ring flat-plate 3 is the twice of the first ring flat-plate 2 thickness, and the second ring flat-plate 3 is embedded in portal body of wall.
On described steel loop body 1, be evenly distributed with a plurality of gussets 4, and on circumference, differ 15 degree between adjacent gusset 4.
Described steel loop body 1 and the thickness of the first ring flat-plate 2 are 10mm, the internal diameter of the diameter of steel loop body 1, the first ring flat-plate 2 and the second ring flat-plate 3 is 6500mm, and the external diameter of the first ring flat-plate 2 and the second ring flat-plate 3 is 6800mm, and the thickness of gusset 4 is 20mm, length is 450mm, and width is 115mm.
Compared with the existing technology, tool has the following advantages the utility model:
The shield launching portal of this kind of form of structure extends steel loop, it is simple in structure, it is ingenious to design, it is for the existing defect of existing construction technology, on portal, be provided with an outward extending steel loop, so just exempted artificial broken pile working procedure in traditional work progress, the problem that has fundamentally solved the interior dust in station in the work progress that misses the stop, when improving workman's construction operation environment, can also improve the construction speed of technique on shield machine's station-crossing; In the mode of portal extension steel loop replacement Traditional Man broken pile, can also reduce the cost of shield-tunneling construction, and site operation is convenient simultaneously; Therefore can say that portal extends steel loop and in subway shield tunnel construction, has higher practicality, be particularly suitable for applying in the art, its market prospects are very wide.
Accompanying drawing explanation
Fig. 1 is the top view of the utility model embodiment.
Fig. 2 is that the A of Fig. 1 is to view.
The specific embodiment
Below in conjunction with accompanying drawing, the specific embodiment of the present utility model is described.As shown in Figure 1 and Figure 2: a kind of shield launching portal extends steel loop, it comprises steel loop body 1, the width of this steel loop body 1 is at least 45mm, the internal diameter that one end of steel loop body 1 is connected with the first ring flat-plate 2, the first ring flat-plates 2 is identical with steel loop body 1, and the external diameter of the first ring flat-plate 2 is greater than the diameter of steel loop body 1, form a step-like ring flat-plate, the thickness that is fixedly connected with the second ring flat-plate 3, the second ring flat-plates 3 with the first ring flat-plate 2 is the twice of the first ring flat-plate 2 thickness, and the second ring flat-plate 3 is embedded in portal body of wall.In order to strengthen bulk strength, on steel loop body 1, be also evenly distributed with a plurality of gussets 4, and on circumference, differ 15 degree between adjacent gusset 4.The thickness of above-mentioned steel loop body 1 and the first ring flat-plate 2 is 10mm, therefore the thickness of the second ring flat-plate 3 is 20mm, the internal diameter of the diameter of steel loop body 1, the first ring flat-plate 2 and the second ring flat-plate 3 is 6500mm, the external diameter of the first ring flat-plate 2 and the second ring flat-plate 3 is 6800mm, the thickness of gusset 4 is 20mm, length is 450mm, and width is 115mm.
The shield launching portal of the utility model embodiment extends steel loop, pre-buried the second ring flat-plate 3 in portal body of wall, and be fixedly connected sequentially thus the first ring flat-plate 2 and steel loop body 1, consideration in bulk strength, on steel loop body 1, be also provided with gusset 4, gusset 4 is connected with the first ring flat-plate 2 with steel loop body 1 simultaneously, its existence is equivalent to the protruding annular canister of portal body of wall, the cutterhead rotation that this annular canister is shield machine provides space, has therefore also avoided the variety of problems that in traditional handicraft, artificial broken pile construction produces.

Claims (3)

1. a shield launching portal extends steel loop, it is characterized in that: described steel loop comprises steel loop body (1), the width of steel loop body (1) is at least 45mm, one end of steel loop body (1) is connected with the first ring flat-plate (2), the internal diameter of the first ring flat-plate (2) is identical with steel loop body (1), the external diameter of the first ring flat-plate (2) is greater than the diameter of steel loop body (1), be fixedly connected with the second ring flat-plate (3) with the first ring flat-plate (2), the thickness of the second ring flat-plate (3) is the twice of the first ring flat-plate (2) thickness, and the second ring flat-plate (3) is embedded in portal body of wall.
2. shield launching portal according to claim 1 extends steel loop, it is characterized in that: on described steel loop body (1), be evenly distributed with a plurality of gussets (4), and on circumference, differ 15 degree between adjacent gusset (4).
3. shield launching portal according to claim 2 extends steel loop, it is characterized in that: described steel loop body (1) and the thickness of the first ring flat-plate (2) are 10mm, the internal diameter of the diameter of steel loop body (1), the first ring flat-plate (2) and the second ring flat-plate (3) is 6500mm, the external diameter of the first ring flat-plate (2) and the second ring flat-plate (3) is 6800mm, the thickness of gusset (4) is 20mm, length is 450mm, and width is 115mm.
CN201320417259.7U 2013-07-15 2013-07-15 Shield launching tunnel portal extension steel ring Expired - Fee Related CN203420713U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201320417259.7U CN203420713U (en) 2013-07-15 2013-07-15 Shield launching tunnel portal extension steel ring

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201320417259.7U CN203420713U (en) 2013-07-15 2013-07-15 Shield launching tunnel portal extension steel ring

Publications (1)

Publication Number Publication Date
CN203420713U true CN203420713U (en) 2014-02-05

Family

ID=50019812

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201320417259.7U Expired - Fee Related CN203420713U (en) 2013-07-15 2013-07-15 Shield launching tunnel portal extension steel ring

Country Status (1)

Country Link
CN (1) CN203420713U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103397892A (en) * 2013-07-15 2013-11-20 中铁十三局集团有限公司 Shield starting tunnel portal extension steel ring
CN103982194A (en) * 2014-06-04 2014-08-13 北京建筑大学 Method for barrier-free starting of shield tunneling machine

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103397892A (en) * 2013-07-15 2013-11-20 中铁十三局集团有限公司 Shield starting tunnel portal extension steel ring
CN103982194A (en) * 2014-06-04 2014-08-13 北京建筑大学 Method for barrier-free starting of shield tunneling machine

Similar Documents

Publication Publication Date Title
CN204783026U (en) It prevents rotary device initiatively to articulate formula shield structure single cylinder hydro -cylinder
CN203420713U (en) Shield launching tunnel portal extension steel ring
CN205779496U (en) A kind of tower reversed balancing flange
CN103397892A (en) Shield starting tunnel portal extension steel ring
CN203547742U (en) Telescopic part of heading machine
CN201320643Y (en) Internal and external circles chamfering machine
CN104028505A (en) Dust collection device for injection product
CN203655316U (en) Top isolating device for coal mine filling bracket
CN205633899U (en) Clear coal device of scraper conveyor scraper blade
CN204754240U (en) Bar planting dust removal dross removal mechanism
CN204200081U (en) It is a kind of that nutation type is semi-automatic changes bar hydraulic rock drilling machine
CN201873007U (en) Sealed sleeve telescopic joint for bulk machine
CN202743522U (en) Dual-90 DEG tile overturning device
CN106703817A (en) Construction method for reducing damaged segments and offset deformation by small-radius curved shield tunneling
CN201972656U (en) Quick packer for coal mine gas drainage holes
CN206764670U (en) It is easy to the instrument of cylinder body installation sealing ring
CN206265871U (en) A kind of automation vacuum intaking device for granular material
CN204495591U (en) Concrete test block sampler
CN205171325U (en) Cold aggregate dust collector in pitch station
CN204725052U (en) A kind of crane web welding auxiliary guide
CN203429692U (en) Detachable loader drawing assembly
CN203223221U (en) Shovel plate for heading machine
CN213918072U (en) Valve packing extraction element
CN205858172U (en) Rig revolution wind sector
CN202977555U (en) Battery quick-changing device for electrombile

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20140205

Termination date: 20210715

CF01 Termination of patent right due to non-payment of annual fee