CN108518071A - The installation method of the double-deck large-span steel vestibule - Google Patents

The installation method of the double-deck large-span steel vestibule Download PDF

Info

Publication number
CN108518071A
CN108518071A CN201810245982.9A CN201810245982A CN108518071A CN 108518071 A CN108518071 A CN 108518071A CN 201810245982 A CN201810245982 A CN 201810245982A CN 108518071 A CN108518071 A CN 108518071A
Authority
CN
China
Prior art keywords
vestibule
lower layer
monolithic
semi
span
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810245982.9A
Other languages
Chinese (zh)
Other versions
CN108518071B (en
Inventor
郭华新
刘建
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hebei 20 Smelting Construction Co Ltd
China MCC20 Group Corp Ltd
Original Assignee
Hebei 20 Smelting Construction Co Ltd
China MCC20 Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hebei 20 Smelting Construction Co Ltd, China MCC20 Group Corp Ltd filed Critical Hebei 20 Smelting Construction Co Ltd
Priority to CN201810245982.9A priority Critical patent/CN108518071B/en
Publication of CN108518071A publication Critical patent/CN108518071A/en
Application granted granted Critical
Publication of CN108518071B publication Critical patent/CN108518071B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements

Abstract

The present invention provides a kind of installation methods of the double-deck large-span steel vestibule, include the following steps:A, correspond to the holder that support vestibule is equipped at the position at vestibule both ends on the ground;B, the middle part to lower layer's vestibule and bottom splicing are assembled into lower layer's vestibule semi-monolithic, and identical first truck crane of two tonnages, two first truck cranes is selected to be located at the both sides at the span centre of lower layer's vestibule semi-monolithic in the width direction;C, after the completion of waiting for frame bottom concrete construction, lower layer's vestibule semi-monolithic lifting is placed into the top of holder using two the first truck cranes;D, preparation and vestibule top plate is installed;E, upper layer vestibule main couple is divided into three sections to make and transport to construction site, two sections of upper layers vestibule end main couple is lifted respectively to corresponding position on vestibule top plate using third truck crane, is lifted main couple among the vestibule of upper layer to vestibule top plate using the second truck crane;Coupling beam and tie-rod of the installation for enhancing its intensity on the vestibule main couple of upper layer.

Description

The installation method of the double-deck large-span steel vestibule
Technical field
The present invention relates to a kind of construction technologies of building vestibule, more particularly, to a kind of double-deck large-span steel vestibule Installation method.
Background technology
When general progress large-span steel vestibule installation, the installation that vestibule is carried out by large-scale lifting appliance is needed, especially It is the vestibule of large span, then more larger equipment is needed to carry out lifting installation.But in some remote areas, due to ground The limitation of manage bar part can not accommodate the lifting appliance of large-tonnage, this just brings to the installation of large-span steel vestibule very big Difficulty.
Invention content
It is existing double to solve it is an object of the invention to provide a kind of installation method of the double-deck large-span steel vestibule Layer large-span steel vestibule construction method it is existing due to construction site can not accommodate large tonnage crane cause it is difficult to install Problem.
The object of the present invention is achieved like this:
A kind of installation method of bilayer large-span steel vestibule, includes the following steps:
A, correspond to the holder that support vestibule is equipped at the position at vestibule both ends on the ground, in mounting bracket to each Frame bottom carries out the construction of concrete;
B, the middle part to lower layer's vestibule and bottom carry out splicing assembling, are assembled into an entirety, and it is logical that this is collectively referred to as lower layer Corridor semi-monolithic selects identical first truck crane of two tonnages, this two first truck cranes to be located at lower layer's vestibule semi-monolithic Span centre at both sides in the width direction;
C, after the completion of waiting for frame bottom concrete construction, the foundation pit backfill of frame bottom is finished, two first vapour are utilized Vehicle suspension hook hangs the both sides at lower layer's vestibule semi-monolithic span centre, and lower layer's vestibule semi-monolithic lifting is placed into the top of holder, choosing With second truck crane, the position of the second truck crane adjustment lower layer vestibule semi-monolithic is utilized;
D, preparation and vestibule top plate is installed:Vestibule top plate is made according to the size of vestibule, utilizes two described first in step b The vestibule top plate is lifted into the top of lower layer's vestibule semi-monolithic by truck crane, and logical by second truck crane cooperation adjustment Vestibule top plate is fixedly connected by the position of corridor top plate with the top of lower layer vestibule semi-monolithic later;
E, upper layer vestibule main couple is divided into three sections to make and transport to construction site, is located at upper layer vestibule main couple along span side It is upper layer vestibule end main couple to the main couple section at both ends, is located at main couple of the upper layer vestibule main couple in the middle part of span direction Section is main couple among the vestibule of upper layer, and a third truck crane is selected to be placed on vestibule top plate, using third truck crane by two Section upper layer vestibule end main couple is lifted respectively to corresponding position on vestibule top plate, is led to upper layer using second truck crane Main couple is lifted to vestibule top plate among corridor, and main truss rack position among upper layer vestibule end main couple and upper layer vestibule is adjusted Weld together with lower layer vestibule after splicing is good;Coupling beam for enhancing its intensity is installed on the vestibule main couple of upper layer and is Bar.
In stepb, the quality control of lower layer's vestibule semi-monolithic is 60 tons or less than 60 ton.
In stepb, it after lower layer's vestibule semi-monolithic splicing is completed, is horizontally arranged on the ground, the lower layer The center of vestibule semi-monolithic is located at the span centre of vestibule, and the line of centres between two stands and lower layer's vestibule semi-monolithic There is angle between length direction.
The tonnage of first truck crane is 160 tons.
The tonnage of second truck crane is 70 tons.
The tonnage of the third truck crane is 25 tons.
In stepb, the springing height of lower layer's vestibule semi-monolithic is the 3 ‰ of its span;
In step e, the springing height for splicing the upper layer vestibule main couple of completion is the 3 ‰ of its span.
In step c, the suspension hook of every first truck crane is being located at lower layer's vestibule semi-monolithic span centre respective side just Top, each the lifting point of the corresponding lower layer's vestibule semi-monolithic of first truck crane is two, each first automobile The suspension hook hung is fixedly connected by steel wire rope with two lifting points, the angle between two steel wire ropes of each first truck crane Degree is equal to or less than 60 °, and the lifting point of lower layer's vestibule semi-monolithic is distributed on the lower boom of its respective side.
In stepb, it installs and is used at the span centre of lower layer's vestibule semi-monolithic when splicing assembles lower layer's vestibule semi-monolithic Support the falsework of vestibule top plate.
The present invention selects identical first truck crane of two tonnages, two first truck cranes to be located at lower layer's vestibule semi-monolithic Span centre at both sides in the width direction, that is, use double crane span centre erect-position technologies, can be quick by smaller tonnage truck crane And the safety for being accurately performed Corridor is in place.
Description of the drawings
Fig. 1 is the structural schematic diagram of vestibule installation of the present invention.
Fig. 2 is the floor map of vestibule lifting of the present invention.
Fig. 3 is the elevational schematic view of Fig. 1.
Fig. 4 is the annexation figure of vestibule lifting point and corresponding truck crane.
In figure:1, lower layer's vestibule semi-monolithic;2, the first truck crane;3, holder.
Specific implementation mode
As shown in Fig. 1 ~ Fig. 4, a kind of installation method of bilayer large-span steel vestibule includes the following steps:
A, correspond to the holder 3 that support vestibule is equipped at the position at vestibule both ends on the ground, in mounting bracket 3 to each 3 bottom of holder carries out the construction of concrete.
B, the middle part to lower layer's vestibule and bottom carry out splicing assembling, are assembled into an entirety, this is collectively referred to as down Layer vestibule semi-monolithic 1 selects identical first truck crane 2 of two tonnages, and it is whole that this two the first truck cranes 2 are located at lower layer's vestibule half Both sides at the span centre of body 1 in the width direction, i.e. two the first truck cranes 2 are located at the side along its length of lower layer's vestibule semi-monolithic 1 To the both sides of the width direction at middle part, the projection of the arm axis of the first truck crane 2 on ground is vertical with the span direction of vestibule, It is its middle part along its length at the span centre of vestibule in the present invention.Upper layer vestibule main couple can make lower part during the installation process Vestibule will camber become smaller, to avoid during installing upper layer vestibule lower layer's vestibule from continuing to sink, in splicing assemble lower layer Installation is used to support the falsework of vestibule top plate, falsework 3 at the span centre of lower layer's vestibule semi-monolithic 1 when vestibule semi-monolithic It is made by H profile steel.After the splicing of lower layer's vestibule semi-monolithic 1 is completed, falsework is removed.In the present embodiment, lower layer's vestibule For 60 tons or less than 60 tons, the mounting height of lower layer's vestibule semi-monolithic 1 is 30 meters for the quality control of semi-monolithic 1.Since vestibule is adopted Take upper layer and lower layer layering lifting, in assembly in view of single layer it is whole in place after since section is small deform big, lower layer's vestibule half Whole 1 springing height is the 3 ‰ of its span, should strictly control lower layer's vestibule half after its single-piece geometric dimension of repetition measurement before assembly Whole 1 length, camber and lateral bending, the stringent assembled geometric accuracy of control.The splicing of lower layer's vestibule semi-monolithic 1 is completed Afterwards, it is horizontally arranged on the ground, the center of lower layer's vestibule semi-monolithic 1 is located at the span centre of vestibule, and the center between two stands 3 There is angle, i.e., during lower layer's vestibule semi-monolithic 1 is with vestibule span centre point between line and the length direction of lower layer's vestibule semi-monolithic 1 The heart is obliquely arranged horizontally in close to the root of two holders 3.The tonnage of first truck crane 2 is 160 tons.In the present embodiment In, lower layer's vestibule is box-structure, and vestibule top plate is provided at the top of lower layer's vestibule, is provided in the bottom of lower layer's vestibule logical Corridor bottom plate.
C, after the completion of waiting for the construction of 3 lower concrete of holder, the foundation pit backfill of 3 bottom of holder is finished, utilizes two first Both sides at 2 hook block lower layer vestibule semi-monolithic of truck crane, 1 span centre, and lower layer's vestibule semi-monolithic 1 is lifted to the top for being placed into holder 3 Second truck crane is selected at end, utilizes the position of the second truck crane adjustment lower layer vestibule semi-monolithic 1.Lower layer's vestibule semi-monolithic 1 Weight it is larger, high in this way, big, weight steel construction installed on ground it is integral, by the first truck crane 2 disposably lifting by it just Position is conducive to improve efficiency, accelerates installation progress, ensures installation quality, reduces security risk.The tonnage of second truck crane is 70 Ton.Suspension centre should be reasonably selected according to lifting span and hoisting weight when being lifted to lower layer's vestibule semi-monolithic 1, due to this hair Bright lower layer's vestibule be box-structure, the structural focus of lower layer's vestibule in its center, the full symmetric arrangement bar in both ends in assembly Part.The lifting point of general Traverse truss is selected on top boom, this vestibule is selected on lower boom.That is every first truck crane 2 is hung Hook is located at the surface of respective side at 1 span centre of lower layer's vestibule semi-monolithic, 2 corresponding lower layer's vestibule semi-monolithic of each first truck crane 1 lifting point is two, and the suspension hook of each first truck crane 2 is fixedly connected by steel wire rope with two lifting points, Mei Ge Angle between two steel wire ropes of one truck crane 2 is equal to or less than 60 °, i.e. every 2 corresponding two lifting of the first truck crane Point is respectively positioned on the both sides along span direction at the span centre of lower layer's vestibule semi-monolithic 1, and the lifting point of lower layer's vestibule semi-monolithic 1 is divided equally Cloth is on the lower boom of its respective side.Every 8 meters of length of steel rope.This knockdown Hoisting Program of upper layer vestibule is conducive to carry High crane utilization rate is saved machine-team and is taken.Each section of lifting point of upper layer vestibule main couple is arranged on its lower boom, thereon It is easily deformed after H profile steel stress, steel plate can be used and reinforced as gusset, when metal binding wire rope is lined with sleeper, steel wire rope again It is protected with the truss girder contact position pipe skin of each section of main couple of upper layer vestibule.The lifting point position of the present invention is reasonable, Ke Yitong The lifting for completing large-scale component using the truck crane of smaller tonnage is crossed, preferable economic benefit is achieved.
D, preparation and vestibule top plate is installed:Vestibule top plate is made according to the size of vestibule, utilizes two first in step b Vestibule top plate is lifted into the top of lower layer's vestibule semi-monolithic 1 by truck crane 2, and coordinates adjustment vestibule top plate by the second truck crane Position, vestibule top plate is fixedly connected with the top of lower layer vestibule semi-monolithic 1 later.
E, by upper layer vestibule main couple be divided into three sections make and transport to construction site, be located at upper layer vestibule main couple along across The main couple section for spending direction both ends is upper layer vestibule end main couple, is located at master of the upper layer vestibule main couple in the middle part of span direction Truss section is main couple among the vestibule of upper layer, selects a third truck crane to be placed on vestibule top plate, utilizes third truck crane Two sections of upper layers vestibule end main couple is lifted respectively to corresponding position on vestibule top plate, the tonnage of third truck crane is 25 Ton.Main couple among the vestibule of upper layer is lifted to vestibule top plate using the second truck crane, by upper layer vestibule end main couple and Weld together with lower layer vestibule after main truss rack position adjustment splicing is good among upper layer vestibule, by 8 meters of height when being designed due to vestibule Calculated rigidity is spent, installation layered carries out, therefore is 3 ‰ by code requirement arch camber value when vestibule making, and vestibule arch camber amount reaches To 160mm, that is, the springing height for splicing the upper layer vestibule main couple of completion is the 3 ‰ of its span.Upper layer vestibule main couple makes When reserved splicing size to be adjusted.Coupling beam and tie-rod of the installation for enhancing its intensity on the vestibule main couple of upper layer. In the present embodiment, lower layer's vestibule is box-structure, and upper layer vestibule is truss structure.The span of large span vestibule in the present invention is big In 56 meters, the tonnage of usually said large automobile crane is equal to or more than 200 tons.

Claims (9)

1. a kind of installation method of bilayer large-span steel vestibule, which is characterized in that include the following steps:
A, correspond to the holder that support vestibule is equipped at the position at vestibule both ends on the ground, in mounting bracket to each Frame bottom carries out the construction of concrete;
B, the middle part to lower layer's vestibule and bottom carry out splicing assembling, are assembled into an entirety, and it is logical that this is collectively referred to as lower layer Corridor semi-monolithic selects identical first truck crane of two tonnages, this two first truck cranes to be located at lower layer's vestibule semi-monolithic Span centre at both sides in the width direction;
C, after the completion of waiting for frame bottom concrete construction, the foundation pit backfill of frame bottom is finished, two first vapour are utilized Vehicle suspension hook hangs the both sides at lower layer's vestibule semi-monolithic span centre, and lower layer's vestibule semi-monolithic lifting is placed into the top of holder, choosing With second truck crane, the position of the second truck crane adjustment lower layer vestibule semi-monolithic is utilized;
D, preparation and vestibule top plate is installed:Vestibule top plate is made according to the size of vestibule, utilizes two described first in step b The vestibule top plate is lifted into the top of lower layer's vestibule semi-monolithic by truck crane, and logical by second truck crane cooperation adjustment Vestibule top plate is fixedly connected by the position of corridor top plate with the top of lower layer vestibule semi-monolithic later;
E, upper layer vestibule main couple is divided into three sections to make and transport to construction site, is located at upper layer vestibule main couple along span side It is upper layer vestibule end main couple to the main couple section at both ends, is located at main couple of the upper layer vestibule main couple in the middle part of span direction Section is main couple among the vestibule of upper layer, and a third truck crane is selected to be placed on vestibule top plate, using third truck crane by two Section upper layer vestibule end main couple is lifted respectively to corresponding position on vestibule top plate, is led to upper layer using second truck crane Main couple is lifted to vestibule top plate among corridor, and main truss rack position among upper layer vestibule end main couple and upper layer vestibule is adjusted Weld together with lower layer vestibule after splicing is good;Coupling beam for enhancing its intensity is installed on the vestibule main couple of upper layer and is Bar.
2. the installation method of bilayer large-span steel vestibule according to claim 1, which is characterized in that in stepb, The quality control of lower layer's vestibule semi-monolithic is 60 tons or less than 60 ton.
3. the installation method of bilayer large-span steel vestibule according to claim 1, which is characterized in that in stepb, After lower layer's vestibule semi-monolithic splicing is completed, it is horizontally arranged on the ground, the centre bit of lower layer's vestibule semi-monolithic There is folder between the line of centres and the length direction of lower layer's vestibule semi-monolithic at the span centre of vestibule, and between two stands Angle.
4. the installation method of bilayer large-span steel vestibule according to claim 1, which is characterized in that first vapour The tonnage that vehicle is hung is 160 tons.
5. the installation method of bilayer large-span steel vestibule according to claim 1, which is characterized in that second vapour The tonnage that vehicle is hung is 70 tons.
6. the installation method of bilayer large-span steel vestibule according to claim 1, which is characterized in that the third vapour The tonnage that vehicle is hung is 25 tons.
7. the installation method of bilayer large-span steel vestibule according to claim 1, which is characterized in that in stepb, The springing height of lower layer's vestibule semi-monolithic is the 3 ‰ of its span;
In step e, the springing height for splicing the upper layer vestibule main couple of completion is the 3 ‰ of its span.
8. the installation method of bilayer large-span steel vestibule according to claim 1, which is characterized in that in step c, The suspension hook of every first truck crane is located at the surface of respective side at lower layer's vestibule semi-monolithic span centre, each first vapour The lifting point that vehicle hangs corresponding lower layer's vestibule semi-monolithic is two, the suspension hook of each first truck crane by steel wire rope with Two lifting points are fixedly connected, and the angle between two steel wire ropes of each first truck crane is described equal to or less than 60 ° The lifting point of lower layer's vestibule semi-monolithic is distributed on the lower boom of its respective side.
9. the installation method of bilayer large-span steel vestibule according to claim 1, which is characterized in that in stepb, When splicing assembles lower layer's vestibule semi-monolithic, installation is used to support the interim of vestibule top plate at the span centre of lower layer's vestibule semi-monolithic Holder.
CN201810245982.9A 2018-03-23 2018-03-23 Installation method of double-layer large-span steel structure corridor Active CN108518071B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810245982.9A CN108518071B (en) 2018-03-23 2018-03-23 Installation method of double-layer large-span steel structure corridor

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810245982.9A CN108518071B (en) 2018-03-23 2018-03-23 Installation method of double-layer large-span steel structure corridor

Publications (2)

Publication Number Publication Date
CN108518071A true CN108518071A (en) 2018-09-11
CN108518071B CN108518071B (en) 2020-08-11

Family

ID=63434199

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810245982.9A Active CN108518071B (en) 2018-03-23 2018-03-23 Installation method of double-layer large-span steel structure corridor

Country Status (1)

Country Link
CN (1) CN108518071B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109653513A (en) * 2019-01-09 2019-04-19 中国五冶集团有限公司 A kind of large-scale 7 font truss structure turn-over hanging method
CN112124858A (en) * 2020-09-22 2020-12-25 九州职业技术学院 Waste coal mine corridor reinforcing method

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN204804378U (en) * 2015-06-02 2015-11-25 浙江恒誉建设有限公司 Two layers of interim support frame of steel construction dome construction and installation
CN105332515A (en) * 2015-10-29 2016-02-17 中冶建工集团有限公司 Erection method of large-span truss structure in limited space

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN204804378U (en) * 2015-06-02 2015-11-25 浙江恒誉建设有限公司 Two layers of interim support frame of steel construction dome construction and installation
CN105332515A (en) * 2015-10-29 2016-02-17 中冶建工集团有限公司 Erection method of large-span truss structure in limited space

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
孟红宾: "大跨度超长超高双层皮带钢通廊安装技术", 《山西建筑》 *
岳敏: "渣油加氢装置大型反应器吊装方案研究", 《炼油技术与工程》 *
钟彪: "钢结构通廊吊装技术", 《安装》 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109653513A (en) * 2019-01-09 2019-04-19 中国五冶集团有限公司 A kind of large-scale 7 font truss structure turn-over hanging method
CN112124858A (en) * 2020-09-22 2020-12-25 九州职业技术学院 Waste coal mine corridor reinforcing method

Also Published As

Publication number Publication date
CN108518071B (en) 2020-08-11

Similar Documents

Publication Publication Date Title
CN110259145A (en) A kind of arch tubular truss rapid constructing method
CN106592432B (en) A kind of prefabricated bent cap shell segmentation construction method of installation of huge thin-walled
CN102979313A (en) High-altitude lifting construction method for overweight steel truss of transferring layer
CN105908902A (en) Positioning frame for prefabricated pier column reinforcing bar cages and construction method of pier column reinforcing bar cages
CN102134832B (en) Movable support and movable support assisted method for erecting steel box beams through non-variable amplitude frame beam crane
CN208899886U (en) Cantilever frame platform
CN110499702A (en) A kind of cable saddle positioning reinforcing device of Cable-stayed Bridge Pylon
CN108518071A (en) The installation method of the double-deck large-span steel vestibule
CN107268455B (en) Concrete girder gooseneck composite structure beam cradle construction method
CN108842954A (en) A kind of huge different section Honeycomb Beam structural system construction method of installation of aerofoil profile roofing
CN104989111A (en) Construction method for steel structure high-rise hoisting
CN202064281U (en) Slip form frame
CN106544959A (en) The construction method of the lifting sections of the king-tower containing saddle and bridge main tower saddle
CN207293909U (en) A kind of precast beam reinforced bar skeleton hanging apparatus
CN105951683A (en) Construction method for corbel steel reinforcements of gate pier
CN203187288U (en) Box girder hanger
CN205348731U (en) Core section of thick bamboo reinforcing bar post is from promoting formula operation platform
CN210288878U (en) Precast concrete Y type roof beam subassembly
CN209924407U (en) Combined working platform for steel structure high-altitude installation
CN208294101U (en) A kind of large-span steel girder mounting slip and promote coupling apparatus
CN102383376A (en) Ground moulding and integral hoisting method for large-tonnage steel bar bound finished product member
CN105084229B (en) Roof crane and application to roof-midspan longitudinal steel beam hoisting
CN105970988B (en) The construction method of elevator sidewall reinforcing bar is installed in raft foundation
CN212425240U (en) Winch support structure and bridge floor hoisting structure
CN208700464U (en) A kind of precast beam reinforced bar installation auxiliary device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant