CN108506018A - The new supporting structure and its construction method of duct pieces of shield tunnel opening - Google Patents

The new supporting structure and its construction method of duct pieces of shield tunnel opening Download PDF

Info

Publication number
CN108506018A
CN108506018A CN201810273232.2A CN201810273232A CN108506018A CN 108506018 A CN108506018 A CN 108506018A CN 201810273232 A CN201810273232 A CN 201810273232A CN 108506018 A CN108506018 A CN 108506018A
Authority
CN
China
Prior art keywords
jurisdiction
shield tunnel
section
duct pieces
supporting structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810273232.2A
Other languages
Chinese (zh)
Inventor
孙东波
谢家化
李广涛
魏玉省
何爱华
李献航
曹楷
朱韬
李正华
刘庆方
刘玉杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Liuyuan Group Co Ltd
Original Assignee
China Railway Liuyuan Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Liuyuan Group Co Ltd filed Critical China Railway Liuyuan Group Co Ltd
Priority to CN201810273232.2A priority Critical patent/CN108506018A/en
Publication of CN108506018A publication Critical patent/CN108506018A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/08Lining with building materials with preformed concrete slabs
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/08Lining with building materials with preformed concrete slabs
    • E21D11/083Methods or devices for joining adjacent concrete segments
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating
    • E21D11/385Sealing means positioned between adjacent lining members
    • E21D11/386Sealing means positioned between adjacent lining members inflatable sealing means
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The new supporting structure and its construction method of duct pieces of shield tunnel opening, it is related to shield tunnel technical field;It includes shear connector, section of jurisdiction opening, water expandable waterstop, steel reinforcement cage;It is equipped with the shear connector mutually suited at the segment joint of the section of jurisdiction open circumferential, and drills at segment joint, installation water expandable waterstop and steel reinforcement cage in hole.What the present invention generated has the beneficial effect that:Additional shape steel bracket supporting need not be used, section of jurisdiction can be directly abolished;It is transported in hole when suspension device does not influence to influence constructing tunnel;Suspension device construction technology is simple, and construction investment is few.

Description

The new supporting structure and its construction method of duct pieces of shield tunnel opening
Technical field
The present invention relates to shield tunnel technical fields, and in particular to the new supporting structure of duct pieces of shield tunnel opening.
Background technology
Currently, being required for installation interim when the structure constructions such as accessory structure of shield tunnel such as service channel, waste water pump house Shaped steel supporting construction after abolish assembled tunnel segment structure, then implement excavation construction in hole, to reduce section of jurisdiction opening construction Interference to main tunnel piercing and ensure that the structure safety of section of jurisdiction opening and stabilization are in duct pieces of shield tunnel opening construction Weight difficult point.General support pattern is typically to support section of jurisdiction using formed steel construction central shoring or portal frame, to ensure shield duct piece Opening safety, but the pipelines such as the water and electricity supply of cleaning shield machine are needed before these measures construction, temporary track transport is interrupted, is influenced The production scheduling that shield machine normally tunnels, or need after equal tunnel holing throughs can the construction period it is longer.It is managed in order to avoid reducing Influence of the piece opening to shield tunnel construction, while ensuring section of jurisdiction hatch frame safety, shear connector supporting section of jurisdiction need to be used to be open Support pattern.
Invention content
In view of the defects and deficiencies of the prior art, the present invention intends to provide a kind of simple structure and reasonable design, make The new supporting structure and its construction method being open with convenient duct pieces of shield tunnel.
To achieve the above object, the technical solution adopted by the present invention is:The new supporting structure of duct pieces of shield tunnel opening, It includes shear connector, section of jurisdiction opening, water expandable waterstop, steel reinforcement cage;It is set at the segment joint of the section of jurisdiction open circumferential There is the shear connector mutually suited, and drills at segment joint, installation water expandable waterstop and steel reinforcement cage in hole.
Preferably, pouring slightly expanded concrete in the hole.
The construction method of the new supporting structure of duct pieces of shield tunnel opening, it is comprised the following steps:
1, driving passes through tunnel duct piece open area, shield segment assembling;
2, drill at the segment joint of duct pieces of shield tunnel open circumferential, drill in installation water expandable waterstop, solid Determine steel reinforcement cage, pours slightly expanded concrete;
3, section of jurisdiction is abolished, implements to excavate in hole.
The operation principle of the present invention is that:By drilling at the segment joint of duct pieces of shield tunnel open circumferential, drilling Interior installation water expandable waterstop, the shear connector of pouring reinforcement concrete structure form rigid connection between segment joint, lead to It crosses shear connector and bears section of jurisdiction opening and abolish the shearing generated behind section of jurisdiction, the internal force in open loop is transferred on adjacent ring, from And ensure the stability of pipe-plate lining, additional supporting need not be used, transports and ensures in hole when not influencing constructing tunnel Structure safety.
Using the above structure with after construction method, what the present invention generated has the beneficial effect that:
1, additional shape steel bracket supporting need not be used, section of jurisdiction can be directly abolished;
2, it is transported in hole when suspension device does not influence to influence constructing tunnel;
3, suspension device construction technology is simple, and construction investment is few.
Description of the drawings
Fig. 1 is the plane outspread drawing that the present invention is mounted in shield tunnel;
Fig. 2 is the local drawing that the present invention is mounted in shield tunnel;
Fig. 3 is the usage state diagram that the present invention is mounted in shield tunnel.
Reference sign:
Shear connector 1, section of jurisdiction opening 2, water expandable waterstop 3, steel reinforcement cage 4.
Specific implementation mode
In order to more clearly explain the embodiment of the invention or the technical proposal in the existing technology, to embodiment or will show below There is attached drawing needed in technology description to be briefly described, it should be apparent that, the accompanying drawings in the following description is only this Some embodiments of invention without having to pay creative labor, may be used also for those of ordinary skill in the art With obtain other attached drawings according to these attached drawings.
Referring to such as Fig. 1 --- shown in Fig. 3, present embodiment adopts the following technical scheme that:Duct pieces of shield tunnel is open New supporting structure, it include shear connector 1, section of jurisdiction opening 2, water expandable waterstop 3, steel reinforcement cage 4;The section of jurisdiction opening It is equipped with the shear connector 1 mutually suited at the segment joint on 2 peripheries, and drills at segment joint, water-swellable sealing is installed in hole Item 3 and steel reinforcement cage 4.
Preferably, pouring slightly expanded concrete in the hole.
The construction method of the new supporting structure of duct pieces of shield tunnel opening is as follows:
1, driving passes through tunnel duct piece open area, shield segment assembling;
2, drill at the segment joint of duct pieces of shield tunnel open circumferential, drill in installation water expandable waterstop, solid Determine steel reinforcement cage, pours slightly expanded concrete;
3, section of jurisdiction is abolished, implements to excavate in hole.
Using the above structure with after construction method, what present embodiment generated has the beneficial effect that:
1, additional shape steel bracket supporting need not be used, section of jurisdiction can be directly abolished;
2, it is transported in hole when suspension device does not influence to influence constructing tunnel;
3, suspension device construction technology is simple, and construction investment is few.
The basic principles and main features and advantages of the present invention of the present invention have been shown and described above.The skill of the industry Art personnel it should be appreciated that the present invention is not limited to the above embodiments, the above embodiments and description only describe The principle of the present invention, without departing from the spirit and scope of the present invention, various changes and improvements may be made to the invention, these Changes and improvements all fall within the protetion scope of the claimed invention.The claimed scope of the invention by appended claims and Its equivalent thereof.

Claims (3)

1. the new supporting structure of duct pieces of shield tunnel opening, it is characterised in that:It is swollen comprising shear connector, section of jurisdiction opening, chance water Swollen sealing rod, steel reinforcement cage;The shear connector mutually suited, and segment joint are equipped at the segment joint of the section of jurisdiction open circumferential Place drills, installation water expandable waterstop and steel reinforcement cage in hole.
2. the construction method of the new supporting structure of duct pieces of shield tunnel opening, it is characterised in that it is comprised the following steps:
(1), driving passes through tunnel duct piece open area, shield segment assembling;
(2), it drills at the segment joint of duct pieces of shield tunnel open circumferential, drill interior installation water expandable waterstop, fixation Steel reinforcement cage pours slightly expanded concrete;
(3), section of jurisdiction is abolished, implements to excavate in hole.
3. the new supporting structure of duct pieces of shield tunnel opening according to claim 1, it is characterised in that:In the hole Pour slightly expanded concrete.
CN201810273232.2A 2018-03-29 2018-03-29 The new supporting structure and its construction method of duct pieces of shield tunnel opening Pending CN108506018A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810273232.2A CN108506018A (en) 2018-03-29 2018-03-29 The new supporting structure and its construction method of duct pieces of shield tunnel opening

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810273232.2A CN108506018A (en) 2018-03-29 2018-03-29 The new supporting structure and its construction method of duct pieces of shield tunnel opening

Publications (1)

Publication Number Publication Date
CN108506018A true CN108506018A (en) 2018-09-07

Family

ID=63378001

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810273232.2A Pending CN108506018A (en) 2018-03-29 2018-03-29 The new supporting structure and its construction method of duct pieces of shield tunnel opening

Country Status (1)

Country Link
CN (1) CN108506018A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113027466A (en) * 2021-03-30 2021-06-25 中交一公局集团有限公司 Underground excavation construction process for tunnel with extremely small clear distance

Citations (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0220799A (en) * 1988-07-11 1990-01-24 Yoshiji Matsumoto Segment not needing coupling bolt
JPH11323920A (en) * 1998-05-13 1999-11-26 Ozawa Tokushu Giken:Kk Cast-in-place concrete pile construction method
JP2004360398A (en) * 2003-06-06 2004-12-24 Sumiken Concrete Kogyo Kk Pipe body made of concrete, concrete segment and manufacturing method for concrete segment
CN101024959A (en) * 2007-02-12 2007-08-29 纪明涛 Slurry-pressing technology for extruding and enlarging poured-pile
JP2008308886A (en) * 2007-06-14 2008-12-25 Shimizu Corp Method of reinforcing opening part of shield tunnel
CN101705829A (en) * 2009-10-21 2010-05-12 上海隧道工程股份有限公司 Method for controlling quality of tunnel pipe sheet built by using shield method and pipe sheet structure
KR20130124262A (en) * 2013-10-18 2013-11-13 한국건설기술연구원 Method constructing the shield tunnel using segments with the prestressed strand cables of a longitudinal direction and the shear keys of a horizontal direction
CN104005414A (en) * 2014-06-12 2014-08-27 广州市城市规划勘测设计研究院 Method for constructing large-diameter reinforced concrete cast-in-place pile supporting stand column
CN204457797U (en) * 2015-02-04 2015-07-08 北京市政建设集团有限责任公司 A kind of top longitudinal beam structure of subway station
CN105041337A (en) * 2015-08-12 2015-11-11 河海大学 Seam splicing structure of underground shield tunnel lining segments and waterproof method
CN105484763A (en) * 2015-12-03 2016-04-13 中国矿业大学(北京) Semi-closed reinforced concrete prefabricated segment support system
KR20160075901A (en) * 2014-12-19 2016-06-30 한국건설기술연구원 Segment structure having shear key of island type and longitudinal strand for shield tunnel
CN107387123A (en) * 2017-08-22 2017-11-24 中铁十局集团城市轨道工程有限公司 The construction method of pressure grouting leak stopping is carried out for shield duct piece piece Seepage
CN107435548A (en) * 2017-07-17 2017-12-05 中铁隧道勘测设计院有限公司 A kind of waterproof structure of shield tunnel segment seam and its construction method
CN107503764A (en) * 2017-08-18 2017-12-22 中铁隧道集团海外工程有限公司 Using the supporting construction and construction method of shear pin supporting duct pieces of shield tunnel opening
CN107575250A (en) * 2017-09-30 2018-01-12 康泰卓越(北京)建筑科技有限公司 Operation phase duct pieces of shield tunnel seam blowby area method for blocking and radical cure method for maintaining
CN208010362U (en) * 2018-03-29 2018-10-26 中铁第六勘察设计院集团有限公司 The new supporting structure of duct pieces of shield tunnel opening

Patent Citations (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0220799A (en) * 1988-07-11 1990-01-24 Yoshiji Matsumoto Segment not needing coupling bolt
JPH11323920A (en) * 1998-05-13 1999-11-26 Ozawa Tokushu Giken:Kk Cast-in-place concrete pile construction method
JP2004360398A (en) * 2003-06-06 2004-12-24 Sumiken Concrete Kogyo Kk Pipe body made of concrete, concrete segment and manufacturing method for concrete segment
CN101024959A (en) * 2007-02-12 2007-08-29 纪明涛 Slurry-pressing technology for extruding and enlarging poured-pile
JP2008308886A (en) * 2007-06-14 2008-12-25 Shimizu Corp Method of reinforcing opening part of shield tunnel
CN101705829A (en) * 2009-10-21 2010-05-12 上海隧道工程股份有限公司 Method for controlling quality of tunnel pipe sheet built by using shield method and pipe sheet structure
KR20130124262A (en) * 2013-10-18 2013-11-13 한국건설기술연구원 Method constructing the shield tunnel using segments with the prestressed strand cables of a longitudinal direction and the shear keys of a horizontal direction
CN104005414A (en) * 2014-06-12 2014-08-27 广州市城市规划勘测设计研究院 Method for constructing large-diameter reinforced concrete cast-in-place pile supporting stand column
KR20160075901A (en) * 2014-12-19 2016-06-30 한국건설기술연구원 Segment structure having shear key of island type and longitudinal strand for shield tunnel
CN204457797U (en) * 2015-02-04 2015-07-08 北京市政建设集团有限责任公司 A kind of top longitudinal beam structure of subway station
CN105041337A (en) * 2015-08-12 2015-11-11 河海大学 Seam splicing structure of underground shield tunnel lining segments and waterproof method
CN105484763A (en) * 2015-12-03 2016-04-13 中国矿业大学(北京) Semi-closed reinforced concrete prefabricated segment support system
CN107435548A (en) * 2017-07-17 2017-12-05 中铁隧道勘测设计院有限公司 A kind of waterproof structure of shield tunnel segment seam and its construction method
CN107503764A (en) * 2017-08-18 2017-12-22 中铁隧道集团海外工程有限公司 Using the supporting construction and construction method of shear pin supporting duct pieces of shield tunnel opening
CN107387123A (en) * 2017-08-22 2017-11-24 中铁十局集团城市轨道工程有限公司 The construction method of pressure grouting leak stopping is carried out for shield duct piece piece Seepage
CN107575250A (en) * 2017-09-30 2018-01-12 康泰卓越(北京)建筑科技有限公司 Operation phase duct pieces of shield tunnel seam blowby area method for blocking and radical cure method for maintaining
CN208010362U (en) * 2018-03-29 2018-10-26 中铁第六勘察设计院集团有限公司 The new supporting structure of duct pieces of shield tunnel opening

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113027466A (en) * 2021-03-30 2021-06-25 中交一公局集团有限公司 Underground excavation construction process for tunnel with extremely small clear distance

Similar Documents

Publication Publication Date Title
CN103469817B (en) Existing subway station main structure broadening construction method
CN103266896B (en) Construction method for shield tunneling machine retaining structure taking position firstly and being constructed secondly and for shield shaft excavation
CN109026012A (en) Vertical shaft surrounding rock supporting structure and its excavation supporting method
CN103375171B (en) Start in a kind of shield structure hole counter-force frame
CN107664035A (en) The construction method of well after shield piping lane elder generation shield
CN112780305B (en) Reinforcing structure for shield overlapping subway tunnel and reinforcing method thereof
CN206987887U (en) Subway tunnel electromechanical equipment and pipeline quick fixation structure
CN208441842U (en) A kind of shield launching counter-force support system
CN109487813A (en) A kind of integrated prefabricated tube coupling and its construction method of pipe gallery street crossing push pipe
CN108506018A (en) The new supporting structure and its construction method of duct pieces of shield tunnel opening
CN208010362U (en) The new supporting structure of duct pieces of shield tunnel opening
CN207453966U (en) The attached wind booth vertical shaft section in subway station excavates structure of slagging tap
CN208668462U (en) A kind of pipe gallery supporting structure
CN105673034A (en) Split starting shield tunneling machine and temporary deslagging system
CN209742907U (en) Shield tunnel segment structure and shield tunnel lining
CN105863673B (en) Pusher fuselage can return to formula pipe jacking construction method and constructing structure
CN107503764A (en) Using the supporting construction and construction method of shear pin supporting duct pieces of shield tunnel opening
CN107386273A (en) A kind of shield launching receives and uses novel compositions H types stake and its construction technology
CN207750084U (en) The closely connected construction supporting structure for passing through existing building of newly-built underground engineering
CN206539353U (en) A kind of tunnel-liner infiltration punishment is reserved to check aperture apparatus
CN206608195U (en) Shaped form bamboo reinforcement grouted anchor bar
CN110056370A (en) It a kind of shield launching and reaches end pipe piece and pours ring beam attachment device with after
CN107642359A (en) The attached wind booth vertical shaft section in subway station excavates slag tap structure and construction method
CN108412518A (en) A kind of double set cylinder drill pipes and its construction method with orientation given layer slip casting function
CN204163730U (en) Slurry shield Slurry treatment system mud pit

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20180907

WD01 Invention patent application deemed withdrawn after publication