CN108487908A - A kind of basil device and its construction method of the shoveling of jacking construction auxiliary - Google Patents

A kind of basil device and its construction method of the shoveling of jacking construction auxiliary Download PDF

Info

Publication number
CN108487908A
CN108487908A CN201810170921.0A CN201810170921A CN108487908A CN 108487908 A CN108487908 A CN 108487908A CN 201810170921 A CN201810170921 A CN 201810170921A CN 108487908 A CN108487908 A CN 108487908A
Authority
CN
China
Prior art keywords
basil
steel
jacking
pipe
main body
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN201810170921.0A
Other languages
Chinese (zh)
Inventor
王海波
魏炜
吴鹏
祁敢
刘星浩
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Sixth Group Co Ltd
Beijing Railway Construction Co of China Railway Sixth Group Co Ltd
Original Assignee
China Railway Sixth Group Co Ltd
Beijing Railway Construction Co of China Railway Sixth Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Sixth Group Co Ltd, Beijing Railway Construction Co of China Railway Sixth Group Co Ltd filed Critical China Railway Sixth Group Co Ltd
Priority to CN201810170921.0A priority Critical patent/CN108487908A/en
Publication of CN108487908A publication Critical patent/CN108487908A/en
Withdrawn legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L1/00Laying or reclaiming pipes; Repairing or joining pipes on or under water
    • F16L1/024Laying or reclaiming pipes on land, e.g. above the ground
    • F16L1/028Laying or reclaiming pipes on land, e.g. above the ground in the ground
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L1/00Laying or reclaiming pipes; Repairing or joining pipes on or under water
    • F16L1/024Laying or reclaiming pipes on land, e.g. above the ground
    • F16L1/06Accessories therefor, e.g. anchors

Abstract

A kind of basil device and its construction method of the shoveling of jacking construction auxiliary.Basil device includes main body steel plate, steel ring of putting more energy into, basil ribs and connection bolt;Main body steel plate rear portion is rear end connecting plate, and front front upper portion is cover board of front end, and front lower part extends forward and forms two steel basils;Steel ring of putting more energy into is welded in the boundary of cover board of front end and rear end connecting plate on main body inner surface of steel plate;The bottom of each steel basil sets that there are one basil ribs.Advantage of the present invention:In jack-in process; native ability, which is cut, using the main body steel plate with the steel basil cuts the soil body in advance; construction personnel carries out digging under the protection of cover board of front end; substantially increase the safety that small-bore push pipe is manually unearthed; the front soil body easily caves in during solving jacking construction, and worker's construction safety cannot be guaranteed, and safeguard procedures are difficult to problem in place; there is very strong applicability to the push pipe of diameter 1.0m~2.5m, there is stronger dissemination in actual work progress.

Description

A kind of basil device and its construction method of the shoveling of jacking construction auxiliary
Technical field
The invention belongs to construction auxiliary equipment in the civil engineering confined space and method and technology fields, more particularly to a kind of push pipe The basil device and its construction method that construction auxiliary is cut the earth.
Background technology
With the fast development of China's urbanization, the development of comprehensive pipeline is also gradually brought into schedule, and existing pipeline and city City's development scale is more and more incompatible, it is therefore desirable to which constantly newly-built pipeline is repaired and even replaces old pipeline, and city is busy Traffic greatly reduces the possibility of cut and cover method pipeline installation again, in construction parts such as undercrossing tunnel, highways, breaks off a friendship in order not in It is logical, construction infection is preferably minimized, many pipeline constructions take construction by pipeline jacking method technique, to reduce construction to existing traffic It influences.It is unstable due to geologic structure in pipeline jack-in process, even if using per-fore pouring liquid with small pipe, suspension roof support Etc. pre-reinforcements measure, still have great uncertainty during practice of construction, there is security risks, threaten constructor The personal safety of member, reduces unearthed efficiency.To minimize security risk, while ensureing construction quality and progress, urgently Need a kind of device that can ensure safety and work efficiency simultaneously.
Invention content
To solve the above-mentioned problems, simple, easy to use, work efficiency height, warp being made the purpose of the present invention is to provide a kind of Ji is applicable in, and supportability is strong and can accelerate basil device and its construction method that the jacking construction auxiliary of unearthed speed is cut the earth.
In order to achieve the above object, the basil device that jacking construction provided by the invention auxiliary is cut the earth include main body steel plate, Put more energy into steel ring, basil ribs and connection bolt;Wherein main body steel plate is the overall structure of cross section semicircular in shape, and rear portion is paving The rear end connecting plate being located on the outer circumference surface of tool pipe top, rear end connecting plate and tool pipe top are each formed with multiple corresponding Bolt hole and reserved injected hole, and using connection bolt-through bolt hole method rear end connecting plate and tool pipe is mutually solid It is fixed;The front of main body steel plate is stretched out outside tool pipe front end, and front upper portion is cover board of front end, and front lower part extends and shape forward At two steel basils;Steel ring of putting more energy into is semicircle steel member, is welded in cover board of front end on main body inner surface of steel plate and is connect with rear end The boundary of plate, and it is tightly attached to the upper front end of tool pipe;The bottom of each steel basil sets that there are one basil ribs, the basils The front end of ribs is flushed with the tip of the steel basil, and the rear end of two basil ribs is welded with two lower ends of steel ring of putting more energy into respectively It connects in succession.
The main body steel plate is high-strength alloy steel plate, and the length of thickness 5mm, cover board of front end are 1.0m, and rear end connects The length of fishplate bar is 1.5m, angle of circumference 180 degree.
The steel basil is dogtooth, is arc-shaped with the front end junction of cover board of front end.
The bolt hole is in quincuncial arrangement, spacing 35cm × 35cm, and the spacing at corner location suitably reduces.
Pvc pipe or small pipe for slip casting closed at both ends are removably inserted in the reserved injected hole.
The construction method that the basil device auxiliary cut the earth using jacking construction provided by the invention auxiliary is excavated includes by suitable The following steps that sequence carries out:
1) this basil device, is transported to construction site, and is hung rear end connecting plate thereon in tool pipe using crane On the outer circumference surface of top, the method then using connection bolt-through respective bolt holes is mutually solid by rear end connecting plate and tool pipe It is fixed, and a pvc pipe closed at both ends is inserted into each pair of reserved injected hole on rear end connecting plate and tool pipe;
2) push pipe jacking, is carried out using top pick, two steel basils incision front soil body first on main body steel plate, Zhi Houqian End casing also cuts the front soil body therewith, per pick jacking 0.8m-1m;
3), after the completion of per pick jacking, stop jacking, in construction personnel's entering tool pipe, under the protection of cover board of front end, people Work excavates the front soil body, and is unearthed in time, until being excavated to no cover board of front end protective position, retains two steel basil tips and is inserted in State in the soil body of front;
4) when, encountering adverse geological condition, stop jacking, extract the pvc pipe reserved in injected hole and to be inserted into grouting small Conduit, then by ductule, adverse soil mass carries out slip casting outward;After slip casting, ductule is extracted, clears up and reserves slip casting Then hole is inserted into pvc pipe closed at both ends, in case reserved injected hole next time uses;
5) continue jacking after the completion of, hand excavation is unearthed, repeat step 2) -5), until jacking construction is fully completed;
6) connection bolt, is unclamped, the basil device on removal tool pipe cleans up in case next time uses.
The basil device and its construction method that jacking construction auxiliary provided by the invention is cut the earth have the following advantages that:In jacking In the process, it cuts native ability using the main body steel plate with the steel basil and cuts the soil body, protection of the construction personnel in cover board of front end in advance Lower carry out digging, substantially increases the safety that small-bore push pipe is manually unearthed, and solves front during jacking construction The soil body easily caves in, and worker's construction safety cannot be guaranteed, and safeguard procedures are difficult to problem in place, to the top of diameter 1.0m~2.5m Pipe has very strong applicability, there is stronger dissemination in actual work progress.
Description of the drawings
Fig. 1 is the basil device stereogram that jacking construction provided by the invention auxiliary is cut the earth.
Fig. 2 is the basil device sectional schematic diagram that jacking construction provided by the invention auxiliary is cut the earth.
Specific implementation mode
In the following with reference to the drawings and specific embodiments to jacking construction provided by the invention auxiliary cut the earth basil device and its Construction method is described in detail.
Now illustrated so that certain pumping plant sewage pipeline changes and moves engineering as an example:The engineering raw sewage pipeline is located inside foundation pit, Buried depth 7m, influences excavation of foundation pit and box culvert is prefabricated, need to newly plan that route location creates sewage pipeline outside foundation pit before construction, will be former Sewage pipeline is abolished.The RC pipejacking caliber that the push pipe is related to be 1550mm, push up Cheng Quanchang 135m, under wear it is existing small red Social connections and site operation place, greenbelt, buried depth 8m, soil property is based on sandy soil, clay.It is tight in the duration, task weight In the case of, when jacking construction, uses this basil device and carries out cutting native jacking, and protection of cutting the earth saves the construction time, reduces Construction cost ensure that the safety of construction personnel.
As shown in Figure 1 and Figure 2, the basil device that jacking construction auxiliary provided by the invention is cut the earth includes main body steel plate, puts more energy into Steel ring 2, basil ribs 5 and connection bolt 6;Wherein main body steel plate is the overall structure of cross section semicircular in shape, and rear portion is paving The rear end connecting plate 3 being located on 8 top outer circumference surface of tool pipe, rear end connecting plate 3 and 8 top of tool pipe are each formed with multiple phases Corresponding bolt hole and reserved injected hole 7, and using connection bolt 6 through bolt hole method by rear end connecting plate 3 and tool Pipe 8 is fixed to each other;The front of main body steel plate is stretched out outside 8 front end of tool pipe, and front upper portion is cover board of front end 1, for blocking The top soil body protects worker's excavation and construction, and front lower part extends forward and forms two steel basils 4;Steel ring 2 of putting more energy into is semicircle Steel member, is welded in the boundary of cover board of front end 1 and rear end connecting plate 3 on main body inner surface of steel plate, and is tightly attached to tool pipe 8 Upper front end, can play keep 1 annulus shape of cover board of front end distortion and so that top power is directly acted in jacking In on steel ring 2 of putting more energy into, the shear stress of bolt 6 is connected with reduction;The bottom of each steel basil 4 is set there are one basil ribs 5, is used In the rigidity and intensity of reinforcing the steel basil 4, the front end of basil ribs 5 is flushed with the tip of the steel basil 4, two basil ribs 5 rear end is welded to connect with two lower ends of steel ring 2 of putting more energy into respectively.
The main body steel plate is high-strength alloy steel plate, and the length of thickness 5mm, cover board of front end 1 are 1.0m, and rear end connects The length of fishplate bar 3 is 1.5m, angle of circumference 180 degree.
The steel basil 4 is dogtooth, is arc-shaped with the front end junction of cover board of front end 1, and when jacking is cut in advance The soil body, the soil body upward soil pressure force effect when playing guiding and reducing jacking.
The bolt hole is in quincuncial arrangement, spacing 35cm × 35cm, and the spacing at corner location suitably reduces.
Pvc pipe or small pipe for slip casting closed at both ends are removably inserted in the reserved injected hole 7.
The construction method that the basil device auxiliary cut the earth using jacking construction provided by the invention auxiliary is excavated includes by suitable The following steps that sequence carries out:
1) this basil device, is transported to construction site, and is hung rear end connecting plate 3 thereon in tool pipe using crane On 8 top outer circumference surfaces, then using connection bolt 6 through respective bolt holes method by 8 phase of rear end connecting plate 3 and tool pipe It is mutually fixed, and a pvc pipe closed at both ends is inserted into each pair of reserved injected hole 7 on rear end connecting plate 3 and tool pipe 8, with Anti-clogging;
2) push pipe jacking, is carried out using top pick, two steel basils 4 incision front soil body first on main body steel plate, later Cover board of front end 1 also cuts the front soil body therewith, per pick jacking 0.8m-1m;The jacking that should watch with the deepest concern in native jack-in process is cut for the first time The stability of pressure value and cover board of front end 1 connects the tightness of bolt 6;Jacking pressure rise, push pipe are encountered in jack-in process Not when normal the case where advancing, it should stop operation in time, can continue jacking after excluding the barrier in front of this basil device, with Prevent cover board of front end (1) from having sticked up or having bent, to influence the normal performance of its function;
3), after the completion of per pick jacking, stop jacking, in construction personnel's entering tool pipe 8, under the protection of cover board of front end 1, The soil body in front of hand excavation, and be unearthed in time, until being excavated to 1 protective position of no cover board of front end, retain two 4 tips of the steel basil The state being inserted in the soil body of front;
4) when, encountering adverse geological condition, stop jacking, extract the pvc pipe reserved in injected hole 7 and to be inserted into grouting small Conduit, then by ductule, adverse soil mass carries out slip casting outward, to carry out solidification improvement to the soil body;After slip casting, pull out Go out ductule, clear up and reserve injected hole 7, be then inserted into pvc pipe closed at both ends, in case reserved injected hole uses for 7 next time;
5) continue jacking after the completion of, hand excavation is unearthed, repeat step 2) -5), until jacking construction is fully completed;
6) connection bolt 6, is unclamped, the basil device on removal tool pipe 8 cleans up in case next time uses.

Claims (6)

1. a kind of basil device that jacking construction auxiliary is cut the earth, it is characterised in that:The basil that the jacking construction auxiliary is cut the earth Device includes main body steel plate, steel ring of putting more energy into (2), basil ribs (5) and connection bolt (6);Wherein main body steel plate is cross section The overall structure of semicircular in shape, rear portion are the rear end connecting plate (3) being laid on the outer circumference surface of tool pipe (8) top, and rear end connects Fishplate bar (3) and tool pipe (8) top are each formed with multiple corresponding bolts hole and reserved injected hole 7, and utilize connection bolt (6) rear end connecting plate (3) and tool pipe (8) are fixed to each other by the method for running through bolt hole;The front of main body steel plate is stretched out in work Outside tool pipe (8) front end, front upper portion is cover board of front end (1), and front lower part extends forward and forms two steel basils (4);Add Strength steel ring (2) is semicircle steel member, is welded in the boundary of cover board of front end 1 and rear end connecting plate 3 on main body inner surface of steel plate, And it is tightly attached to the upper front end of tool pipe (8);The bottom of each steel basil (4) sets that there are one basil ribs (5), and the basil adds The front end of strong rib (5) is flushed with the tip of the steel basil (4), the rear ends of two basil ribs (5) respectively with steel ring of putting more energy into (2) Two lower ends are welded to connect.
2. the basil device that jacking construction auxiliary according to claim 1 is cut the earth, it is characterised in that:The main body steel plate Length for high-strength alloy steel plate, thickness 5mm, cover board of front end 1 is 1.0m, and the length of rear end connecting plate 3 is 1.5m, circumference Angle 180 degree.
3. the basil device that jacking construction auxiliary according to claim 1 is cut the earth, it is characterised in that:The steel basil (4) it is dogtooth, is arc-shaped with the front end junction of cover board of front end 1.
4. the basil device that jacking construction auxiliary according to claim 1 is cut the earth, it is characterised in that:The bolt hole is in Quincuncial arrangement, spacing 35cm × 35cm, the spacing at corner location suitably reduce.
5. the basil device that jacking construction auxiliary according to claim 1 is cut the earth, it is characterised in that:The reserved slip casting Pvc pipe or small pipe for slip casting closed at both ends are removably inserted in hole 7.
6. a kind of construction method that the basil device auxiliary cut the earth using jacking construction auxiliary described in claim 1 is excavated includes The following steps carried out in order:
1) this basil device, is transported to construction site, and is hung rear end connecting plate (3) thereon in tool pipe using crane (8) on the outer circumference surface of top, then using connection bolt (6) through respective bolt holes method by rear end connecting plate (3) and work Tool pipe (8) is fixed to each other, and is inserted into a both ends in each pair of reserved injected hole (7) on rear end connecting plate (3) and tool pipe (8) Closed pvc pipe;
2) push pipe jacking, is carried out using top pick, two steel basils (4) incision front soil body first on main body steel plate, Zhi Houqian End casing (1) also cuts the front soil body therewith, per pick jacking 0.8m-1m;
3), after the completion of per pick jacking, stopping jacking, construction personnel's entering tool pipe (8) is interior, under the protection of cover board of front end (1), The soil body in front of hand excavation, and be unearthed in time, until being excavated to no cover board of front end (1) protective position, retain two steel basils (4) Tip is inserted in the state in the soil body of front;
4) when, encountering adverse geological condition, stop jacking, extract the pvc pipe reserved in injected hole (7) and be inserted into that grouting is small to lead Pipe, then by ductule, adverse soil mass carries out slip casting outward;After slip casting, ductule is extracted, clears up and reserves injected hole (7), it is then inserted into pvc pipe closed at both ends, in case reserved injected hole (7) next time uses;
5) continue jacking after the completion of, hand excavation is unearthed, repeat step 2) -5), until jacking construction is fully completed;
6) connection bolt (6), is unclamped, the basil device on removal tool pipe (8) cleans up in case next time uses.
CN201810170921.0A 2018-03-01 2018-03-01 A kind of basil device and its construction method of the shoveling of jacking construction auxiliary Withdrawn CN108487908A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810170921.0A CN108487908A (en) 2018-03-01 2018-03-01 A kind of basil device and its construction method of the shoveling of jacking construction auxiliary

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810170921.0A CN108487908A (en) 2018-03-01 2018-03-01 A kind of basil device and its construction method of the shoveling of jacking construction auxiliary

Publications (1)

Publication Number Publication Date
CN108487908A true CN108487908A (en) 2018-09-04

Family

ID=63340863

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810170921.0A Withdrawn CN108487908A (en) 2018-03-01 2018-03-01 A kind of basil device and its construction method of the shoveling of jacking construction auxiliary

Country Status (1)

Country Link
CN (1) CN108487908A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114876491A (en) * 2022-04-28 2022-08-09 中国十九冶集团有限公司 Pipe jacking construction system for large pipe gallery

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104154326A (en) * 2014-08-14 2014-11-19 中石化第十建设有限公司 Rigid sleeve head for desert and silt geology jacking pipe and jacking pipe construction method thereof
CN204004781U (en) * 2014-08-14 2014-12-10 中石化第十建设有限公司 A kind of desert, mud geology push pipe use rigidity pullover
CN104315251A (en) * 2014-09-25 2015-01-28 济南城建集团有限公司 Manual pipe jacking construction method for earth and rock combined geological conditions
CN106402490A (en) * 2016-10-31 2017-02-15 中铁二十局集团第五工程有限公司 Silty soil stratum pipe-jacking jacking construction method based on tool pipe with steel sleeve head
CN206830946U (en) * 2017-06-12 2018-01-02 郑州水务建筑工程股份有限公司 A kind of concrete sleeve jacking construction structure
CN206958387U (en) * 2017-03-24 2018-02-02 新兴铸管股份有限公司 Spigot-and-socket metal push pipe with self-anchoring joint

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104154326A (en) * 2014-08-14 2014-11-19 中石化第十建设有限公司 Rigid sleeve head for desert and silt geology jacking pipe and jacking pipe construction method thereof
CN204004781U (en) * 2014-08-14 2014-12-10 中石化第十建设有限公司 A kind of desert, mud geology push pipe use rigidity pullover
CN104315251A (en) * 2014-09-25 2015-01-28 济南城建集团有限公司 Manual pipe jacking construction method for earth and rock combined geological conditions
CN106402490A (en) * 2016-10-31 2017-02-15 中铁二十局集团第五工程有限公司 Silty soil stratum pipe-jacking jacking construction method based on tool pipe with steel sleeve head
CN206958387U (en) * 2017-03-24 2018-02-02 新兴铸管股份有限公司 Spigot-and-socket metal push pipe with self-anchoring joint
CN206830946U (en) * 2017-06-12 2018-01-02 郑州水务建筑工程股份有限公司 A kind of concrete sleeve jacking construction structure

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114876491A (en) * 2022-04-28 2022-08-09 中国十九冶集团有限公司 Pipe jacking construction system for large pipe gallery

Similar Documents

Publication Publication Date Title
CN104533446B (en) Construction method and its structure that a kind of big cross section Support System in Soft Rock Tunnels bilayer pre- Geological disaster prevention of preliminary bracing occurs
CN103758123B (en) The construction method of manually digging hole filling pile retaining wall lining
CN105781571A (en) Construction method for soft rock deformation tunnel lining support dismantling-replacing arch
CN111335902B (en) Construction method for shield tunneling ground connection wall underpass operation subway station
CN106437798B (en) A kind of preprocess method of the anchor cable group across shield driving section
CN106351670A (en) Closed pre-support tunnel structure
CN108547639B (en) Tunnel closes on the advanced same more conduit delamination pour slurry construction methods in hole of existing buildings
CN203080518U (en) Self-drilling type recoverable anchor wire
CN103628885A (en) Tunnel exit cover-excavation construction method of Ultra-shadow buried tunnel
CN107091101A (en) Mine shield handing-over tunnel folded type joint design and construction method in the middle part of marine site
CN106988750A (en) The embodiment at existing station is worn under a kind of large span running tunnel super close distance
CN109707399A (en) Tunnel outlet support structure and its construction method
CN103993885A (en) Construction method for underground excavation tunnel side-direction hole opening supporting system
CN105065037A (en) Double-layer arch center support construction method for highway soft rock tunnel
CN109372520A (en) One kind passing through Debris Flow Deposition area tunnel support structure and its construction method
CN109578014A (en) Anti- dash forward of one kind gushes back cover structure and construction method
CN110306559A (en) A kind of construction method of subway entrance support pile
CN109630173A (en) A kind of prestress anchorage cable cleaning plant and method
CN105544603A (en) Construction method for underground pipeline reinforcement
CN209083308U (en) A kind of prestress anchorage cable cleaning plant
CN103215958A (en) Construction method of dewatering and retaining and protecting of deep foundation pit in expansive-soil area
CN108374674B (en) Six pilot tunnels, 12 step Underground Space Excavation method for protecting support
CN101994314A (en) Longhole rectangular terraced antiskid pile jump-preventing excavating construction
CN109339800A (en) A kind of Rapid Construction of Tunnels method in the connected section of bridge tunnel
CN109594992A (en) A kind of juxtaposition tunneling method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WW01 Invention patent application withdrawn after publication

Application publication date: 20180904

WW01 Invention patent application withdrawn after publication