CN206830946U - A kind of concrete sleeve jacking construction structure - Google Patents
A kind of concrete sleeve jacking construction structure Download PDFInfo
- Publication number
- CN206830946U CN206830946U CN201720677451.8U CN201720677451U CN206830946U CN 206830946 U CN206830946 U CN 206830946U CN 201720677451 U CN201720677451 U CN 201720677451U CN 206830946 U CN206830946 U CN 206830946U
- Authority
- CN
- China
- Prior art keywords
- outer tube
- inner tube
- concrete
- tube
- jacking construction
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Abstract
It the utility model is related to a kind of concrete sleeve jacking construction structure, including inner tube and outer tube, the pipe diameter size of described inner tube and outer tube selects according to construction condition, it is characterised in that:Described outer tube caliber is 1.5 2 times and arranged concentric of inner tube diameter;Base is provided between described outer tube and inner tube;Described base is located at the bottom in outer tube, and lower end is that the arcuate structure that matches with the internal diameter of outer tube, upper end are provided with the trapezoidal groove to match with the external diameter of inner tube;Generally, the utility model has simple in construction easy to use, and steel pipe operation is instead of by casing operation, it ensure that the normal construction of push pipe operation, the security and bearing capacity of pipeline operations are considerably increased, increases pipeline service life, there is the advantages of high practical value.
Description
Technical field
The utility model belongs to jacking construction field, and the position technology of pressure is born suitable for major trunk roads, road surface bearing capacity
Field, more particularly to a kind of concrete sleeve jacking construction structure.
Background technology
At present, in water supply and sewage work Zhong Chuan highways, river course, heavy construction, push pipe operation is typically taken, in order to hold
By the enough bearing capacity in top of constructing, steel pipe operation is typically taken, but due to being rubbed caused by steel pipe operation process and soil layer
The anticorrosive coat that power is easily destroyed top layer is wiped, reduces the service life of steel pipe.
The content of the invention
The purpose of this utility model is overcome the deficiencies in the prior art, and provides a kind of simple in construction, easy to use, contracting
Casual labourer's phase, the bearing capacity for increasing pipeline, there is the concrete sleeve jacking construction structure of high practical value.
The technical solution of the utility model is:A kind of concrete sleeve jacking construction structure, including inner tube and outer tube, it is described
Inner tube and the pipe diameter size of outer tube selected according to construction condition, it is characterised in that:Described outer tube caliber is inner tube pipe
1.5-2 times and the arranged concentric in footpath;Base is provided between described outer tube and inner tube;Described base is located at the bottom in outer tube
Portion, lower end are that the arcuate structure that matches with the internal diameter of outer tube, upper end are provided with the trapezoidal groove to match with the external diameter of inner tube;
Described trapezoidal chassis interior is disposed with reinforced mesh;Described reinforced mesh is made up of arch steel and transverse steel
Network structure;
Waling is uniformly mounted between described outer tube docking pipe seam;The top of described waling and steel
Muscle mesh sheet is connected as one;
Described base is to be connected the casting on the whole formed with reinforced mesh on the top of waling by concrete
Form.
Described waling is arranged according to the modes of 16~18@of φ 200.
Described reinforced mesh is to be arranged by arch steel with transverse steel according to the modes of 8~10@of φ 200.
Concrete grade is identical used by concrete grade and pipeline used by described base.
Beneficial effect is caused by this programme:Generally, the utility model has simple in construction easy to use, by sleeve pipe
Operation instead of steel pipe operation, ensure that the normal construction of push pipe operation, considerably increase security and the carrying of pipeline operations
Power, increase pipeline service life, there is the advantages of high practical value.
Brief description of the drawings
Fig. 1 is the utility model pipeline jacking profile.
Fig. 2 is the utility model outer tube pipe seam profile.
Fig. 3 is reinforced mesh structural representation of the present utility model.
In figure:1st, inner tube 2, outer tube 3, trapezoidal base 4, reinforced mesh 5, waling 6, arcuate structure 7, ladder
Connected in star 8, transverse steel 9, arch steel.
Embodiment:
The technical solution of the utility model is described further below in conjunction with the accompanying drawings.
As shown in Fig. 1-3:A kind of concrete sleeve jacking construction structure, including inner tube 1 and outer tube 2, described inner tube 1
Selected with the pipe diameter size of outer tube 2 according to construction condition, it is characterised in that:The described caliber of outer tube 2 is the caliber of inner tube 1
1.5-2 again and arranged concentric;Base 3 is provided between described outer tube 2 and inner tube 1;Described base 3 is located in outer tube 2
Bottom, lower end be the arcuate structure 6 that matches with the internal diameter of outer tube 2, upper end be provided with match with the external diameter of inner tube 1 it is trapezoidal
Groove 7;Reinforced mesh 4 is disposed with inside described trapezoidal base 3;Described reinforced mesh 4 is by arch steel 9 and horizontal steel
The network structure that muscle 8 is formed;
Described outer tube 2 is uniformly mounted with waling 5 between docking pipe seam;The top of described waling 5
It is connected as one with reinforced mesh 4;
Described base 3 is to be connected pouring on the whole of being formed with reinforced mesh 4 on the top of waling 5 by concrete
Casting forms.
Described waling 5 is arranged according to the modes of 16~18@of φ 200.
Described reinforced mesh 4 is to be arranged by arch steel 9 with transverse steel 8 according to the modes of 8~10@of φ 200.
Concrete grade is identical used by concrete grade and pipeline used by described trapezoidal base 3.
The utility model Specific construction mode:First the jacking pipe construction process jacking outer tube by, outer pipe construction finish examination
Afterwards, unwrapping wire is measured in outer tube, trapezoidal base is poured in outer tube inner bottom part, the internal diameter of described trapezoidal base and outer tube,
The external diameter of inner tube coincide, and concrete grade is identical used by concrete grade and pipeline used by described trapezoidal base,
Described steel bar arrangement:Dispose waling between outer tube butt tube seam, the reinforcing bar for φ 16~18 200, to increase
Add the shearing resistance of armored concrete, prevent armored concrete in inner tube jack-in process and produce crack and displacement.Trapezoidal reinforced concrete
Handwoven cloth puts the@200 of φ 8~10 reinforced mesh, and waling top connects with bar-mat reinforcement to be integrally formed, to increase reinforced concrete
The intensity of soil, shearing resistance, twisting resistance.Then unwrapping wire is measured, the equipment for installing inner tube jacking, treats that strength of reinforced concrete reaches
To after construction bearing capacity, inner tube jacking operation is carried out.
Claims (4)
- A kind of 1. pipe diameter size root of concrete sleeve jacking construction structure, including inner tube and outer tube, described inner tube and outer tube Selected according to construction condition, it is characterised in that:Described outer tube caliber is 1.5-2 times and arranged concentric of inner tube diameter;Institute Base is provided between the outer tube and inner tube stated;Described base is located at the bottom in outer tube, and lower end is the internal diameter phase with outer tube The arcuate structure of matching, upper end are provided with the trapezoidal groove to match with the external diameter of inner tube;Described trapezoidal chassis interior arrangement There is reinforced mesh;Described reinforced mesh is the network structure being made up of arch steel and transverse steel;Waling is uniformly mounted between described outer tube docking pipe seam;The top of described waling and bar-mat reinforcement Piece is connected as one;Described base is to be connected the casting on the whole formed with reinforced mesh on the top of waling by concrete to form.
- A kind of 2. concrete sleeve jacking construction structure according to claim 1, it is characterised in that:Described is longitudinally reinforced Muscle is arranged according to the modes of 16~18@of φ 200.
- A kind of 3. concrete sleeve jacking construction structure according to claim 1, it is characterised in that:Described reinforced mesh It is to be arranged by arch steel with transverse steel according to the modes of 8~10@of φ 200.
- A kind of 4. concrete sleeve jacking construction structure according to claim 1, it is characterised in that:Described base is adopted Concrete grade is identical used by concrete grade and pipeline.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720677451.8U CN206830946U (en) | 2017-06-12 | 2017-06-12 | A kind of concrete sleeve jacking construction structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720677451.8U CN206830946U (en) | 2017-06-12 | 2017-06-12 | A kind of concrete sleeve jacking construction structure |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206830946U true CN206830946U (en) | 2018-01-02 |
Family
ID=60775526
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201720677451.8U Expired - Fee Related CN206830946U (en) | 2017-06-12 | 2017-06-12 | A kind of concrete sleeve jacking construction structure |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206830946U (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108487908A (en) * | 2018-03-01 | 2018-09-04 | 中铁六局集团有限公司 | A kind of basil device and its construction method of the shoveling of jacking construction auxiliary |
CN108487097A (en) * | 2018-04-09 | 2018-09-04 | 大连久鼎祥瑞特种工程技术研究院有限公司 | Horizontal seepage well or pipeline push pipe rapid constructing method |
CN110410577A (en) * | 2019-07-16 | 2019-11-05 | 中国建筑第八工程局有限公司 | Pipe-jacking with large diameter drag reduction construction method under miscellaneous fill geological condition |
-
2017
- 2017-06-12 CN CN201720677451.8U patent/CN206830946U/en not_active Expired - Fee Related
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108487908A (en) * | 2018-03-01 | 2018-09-04 | 中铁六局集团有限公司 | A kind of basil device and its construction method of the shoveling of jacking construction auxiliary |
CN108487097A (en) * | 2018-04-09 | 2018-09-04 | 大连久鼎祥瑞特种工程技术研究院有限公司 | Horizontal seepage well or pipeline push pipe rapid constructing method |
CN110410577A (en) * | 2019-07-16 | 2019-11-05 | 中国建筑第八工程局有限公司 | Pipe-jacking with large diameter drag reduction construction method under miscellaneous fill geological condition |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN206830946U (en) | A kind of concrete sleeve jacking construction structure | |
CN103075158B (en) | Steel plate and steel reinforced concrete well wall | |
CN103243745B (en) | A kind of method of pile tube deviation rectification | |
CN109183607A (en) | Precast spliced UHPC pipe-concrete super-high pier and construction method | |
CN104563147A (en) | Composite structure pile foundation applied to karst area and construction method of composite structure pile foundation | |
CN201627200U (en) | Blockage-slurry strengthening earth anchor | |
CN103726670B (en) | Adopt steel beam concrete slab on inhering architecture, increase the method for interlayer | |
CN203533005U (en) | Prestressed steel-concrete composite pressure jacking pipe | |
CN206299921U (en) | Pipeline | |
CN106468075A (en) | A kind of toilet pipe sleeve fixing meanss | |
CN204456073U (en) | A kind of steel pipe composite pile | |
CN105951865A (en) | HDPE double-wall corrugated pipe foundation and construction process thereof | |
CN201902715U (en) | Liner column concrete pipe with prestressed pipe base | |
CN205370079U (en) | Modular an electric power safety protection sleeve section of thick bamboo | |
CN204827500U (en) | Pinniform wedge body stock | |
CN208122861U (en) | A kind of elliptic cross-section hollow steel tube concrete support component that bending resistance is strengthened | |
CN209511303U (en) | A kind of novel jacking construction method cylinder concrete pipe | |
CN208415309U (en) | A kind of shield export & import soil body end ruggedized construction | |
CN207846534U (en) | A kind of rainwater-collecting recovery system constructing device | |
CN104532828A (en) | Steel tube composite pile and design method thereof | |
CN201943071U (en) | Implantable steel tube anchor rod with stabs | |
CN205805581U (en) | A kind of prolongation tunnel reinforced concrete lining cutting structure in service life | |
CN204850004U (en) | Inspection shaft | |
CN217631464U (en) | Be used for damaged cement wire pole to restore and use reinforcing mold | |
CN204849829U (en) | Inspection shaft |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20180102 Termination date: 20190612 |