CN108487097A - Horizontal seepage well or pipeline push pipe rapid constructing method - Google Patents
Horizontal seepage well or pipeline push pipe rapid constructing method Download PDFInfo
- Publication number
- CN108487097A CN108487097A CN201810310845.9A CN201810310845A CN108487097A CN 108487097 A CN108487097 A CN 108487097A CN 201810310845 A CN201810310845 A CN 201810310845A CN 108487097 A CN108487097 A CN 108487097A
- Authority
- CN
- China
- Prior art keywords
- push pipe
- level
- pipe
- drill bit
- push
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01F—ADDITIONAL WORK, SUCH AS EQUIPPING ROADS OR THE CONSTRUCTION OF PLATFORMS, HELICOPTER LANDING STAGES, SIGNS, SNOW FENCES, OR THE LIKE
- E01F5/00—Draining the sub-base, i.e. subgrade or ground-work, e.g. embankment of roads or of the ballastway of railways or draining-off road surface or ballastway drainage by trenches, culverts, or conduits or other specially adapted means
- E01F5/005—Culverts ; Head-structures for culverts, or for drainage-conduit outlets in slopes
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F16—ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
- F16L—PIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
- F16L1/00—Laying or reclaiming pipes; Repairing or joining pipes on or under water
- F16L1/024—Laying or reclaiming pipes on land, e.g. above the ground
- F16L1/028—Laying or reclaiming pipes on land, e.g. above the ground in the ground
Landscapes
- Engineering & Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Excavating Of Shafts Or Tunnels (AREA)
Abstract
The invention discloses a kind of horizontal seepage well or pipeline push pipe rapid constructing methods, using the scheme of classification jacking during pushing tow, after level-one jacking to designated depth, casing as two level push pipe, two level push pipe reaches level-one push pipe most deep end, is connected with detachable drill bit two level drill bit, continue forward pushing tow to designated depth, after the completion of pushing tow, reversely level-one push pipe is pulled out.Three-level push pipe operates repeated as above, to the last level-one jacking construction finishes, 4 high-pressure water pipes of push pipe outside weldings are connected at drill bit always, construction starts, jack starts to start high-pressure hydraulic pump while pushing tow, high-pressure water pipe high speed sprays mud, and original structure is made to loosen, and forms one layer of lubricating film.Reduce the side friction during pushing tow.The present invention method do not excavate ground, do not remove, do not destroy above ground structure, not welding, do not influence pipeline segment difference deformation push pipe fast jacking construction effect.
Description
Technical field
The present invention relates to the technical fields such as bridge, bridges and culverts, diversion works, water engineering.
Background technology
Currently, seepage well and pipeline are widely used in the fields such as bridge, bridges and culverts, diversion works, water engineering, however
Some cannot go up excavation, heavy traffic, the construction area that densely populated, above ground structure is numerous and underground utilities are complicated in large area
Domain, how rapid construction, reduction quantities and saving engineering land used are always a technical barrier.
If by reconnoitring engineering geology, hydrological geological conditions, cannot carry out Ground slot operation region,
The construction technology of push pipe fast jacking is taken, the frictional force of seepage well or pipeline and surrounding soil can be reduced, by seepage well or pipeline
It is headed into soil by the gradient of design, rapid construction can be efficiently solved, quantities is reduced, save the construction difficult problems such as engineering land used,
And with economic, efficient, the comprehensive function of environmental protection.
Invention content
Technical problem solved by the invention is to provide a kind of horizontal seepage well or pipeline push pipe quick construction technology, use are non-
It is quick to solve bridge, bridges and culverts, diversion works, the horizontal seepage well in the engineering fields such as water engineering or pipeline for excavation construction mode
The construction difficult problem of jacking.
The technical solution adopted by the present invention is horizontal seepage well or pipeline push pipe rapid constructing method, is included the following steps:
One, jack is connected at designated position erection construction platform, operation platform, push pipe front uses detachable drill bit,
Push pipe includes at least two-stage, and caliber is descending to be set in together, and drill bit is equipped with the connector with push pipes at different levels, each push pipe
It is externally provided with high-pressure water pipe, high-pressure water pipe is communicated in high-pressure hydraulic pump, and high-pressure water pipe is equipped with water jet;
Two, jack starts to start high-pressure hydraulic pump while pushing tow, and high-pressure water pipe high speed sprays mud, and soil layer construction is made to loosen,
And form one layer of lubricating film;
Three, after level-one jacking to designated depth, level-one push pipe is detached with drill bit, be sleeved on two level in level-one push pipe with it is separable
Formula drill bit is connected, and continues jacking forward and then reversely pulls out level-one push pipe to designated depth;
Four, two level push pipe is detached with drill bit, and the three-level push pipe being sleeved in two level push pipe is connected with drill bit, continues jacking forward extremely
Then designated depth reversely pulls out two level push pipe;
Five, the operation of step 4 is repeated, until afterbody push pipe reaches designated depth.
Water jet in high-pressure water pipe is strip crevice or hole.
Afterbody push pipe uses floral tube, ensures that water is penetrated into, flowed into.
The beneficial effects of the invention are as follows a kind of horizontal seepage well of offer or pipeline push pipe quick construction technologies, realize bridge, bridge
In the engineering fields such as culvert, diversion works, water engineering, ground is not excavated, is not removed, is not destroyed above ground structure, do not destroy ring
The construction effect for the push pipe fast jacking that border, the segment difference for not influencing pipeline deform.
Description of the drawings
Fig. 1 is the structural diagram of the present invention.
Fig. 2 is in Fig. 1 along A-A sectional views.
Fig. 3 is in Fig. 1 along B-B sectional views.
Fig. 4 is jacking pipe structure figure.
Fig. 5 is high-pressure water pipe sectional view.
Fig. 6 is drill bit sectional view.
Fig. 7 is two level push pipe jacking state diagram.
Fig. 8 is three-level push pipe jacking state diagram.
In figure label for:1- repairs stair;2- maintenance platforms;3- well inner conduits;4- push pipes;5- operating platforms;6- catchments
Well;7- bottom plates;8- high-pressure water pipes;9- holes;10- level-one push pipes;11- two level push pipes;12- three-level push pipes;13- level Four push pipes;
14- steel pipe supports;15- drill bits.
Specific implementation mode
1. horizontal seepage well or pipeline push pipe rapid constructing method, include the following steps:It is flat in designated position erection construction
Platform connects jack at operation platform, and push pipe front uses detachable drill bit,
One, jack is connected at designated position erection construction platform, operation platform, push pipe front uses detachable drill bit
15, bit diameter is set according to the diameter of push pipe.As shown in Figure 1, can construct in open caisson, design position sets up dimension in well
Stair 1, maintenance platform 2 and operating platform 5 are repaiied, after the completion of setting up, jack is installed on operating platform 5, push pipe bearing etc. is set
It applies;
Push pipe includes several grades, and caliber is descending to be set in together, and drill bit 15 is equipped with the connector with push pipes at different levels,
Each push pipe 4 high-pressure water pipes 8 of outside weldings, high-pressure water pipe 8 are connected to always at drill bit 15, are dug in high-pressure water pipe 8
Gap or hole 9, high-pressure water pipe 8 are communicated in high-pressure hydraulic pump, and it is high material injection will to be sprayed in high pressure pond by high-pressure hydraulic pump
Pressure pipe 8, water or mud may be selected in injection material in high pressure pond.High-pressure water pipe is sequentially connected, and is continuously connected to high-pressure pump
It stands;
Two, jack starts to start high-pressure hydraulic pump while pushing tow, and high-pressure water pipe 8 sprays at a high speed mud or water, makes original soil layer
Connection loosing, and one layer of mud is formed as lubricating film, reduce the side friction during pushing tow.
Three, using the scheme of classification jacking, after level-one jacking to designated depth, level-one push pipe 10 and drill bit during pushing tow
15 separation, the two level push pipe 11 being sleeved in level-one push pipe 10 are connected with detachable drill bit 15, continue jacking forward and extremely refer to
Then depthkeeping degree reversely pulls out level-one push pipe 10;
Four, two level push pipe 11 is detached with drill bit 15, and the three-level push pipe 12 being sleeved in two level push pipe 11 is connected with drill bit 15, is continued
Forward then jacking reversely pulls out two level push pipe 11 to designated depth;
Five, the operation of step 4 is repeated, until afterbody push pipe reaches designated depth.
Several push pipes of jacking are classified, afterbody push pipe is only the final goal of this time construction.According to construction environment and
Pipeline applications can make afterbody push pipe different designs, such as construction final purpose is structure seepage well, then last
Grade push pipe uses floral tube, ensures that water is penetrated into, flowed into.
Claims (3)
1. horizontal seepage well or pipeline push pipe rapid constructing method, include the following steps:
One, jack is connected at designated position erection construction platform, operation platform, push pipe front uses detachable drill bit,
Push pipe includes at least two-stage, and caliber is descending to be set in together, and drill bit is equipped with the connector with push pipes at different levels, each push pipe
It is externally provided with high-pressure water pipe, high-pressure water pipe is communicated in high-pressure hydraulic pump, and high-pressure water pipe is equipped with water jet;
Two, jack starts to start high-pressure hydraulic pump while pushing tow, and high-pressure water pipe high speed sprays mud, and soil layer construction is made to loosen,
And form one layer of lubricating film;
Three, after level-one jacking to designated depth, level-one push pipe is detached with drill bit, be sleeved on two level in level-one push pipe with it is separable
Formula drill bit is connected, and continues jacking forward and then reversely pulls out level-one push pipe to designated depth;
Four, two level push pipe is detached with drill bit, and the three-level push pipe being sleeved in two level push pipe is connected with drill bit, continues jacking forward extremely
Then designated depth reversely pulls out two level push pipe;
Five, the operation of step 4 is repeated, until afterbody push pipe reaches designated depth.
2. horizontal seepage well as described in claim 1 or pipeline push pipe rapid constructing method, it is characterised in that:The high-pressure water pipe
On water jet be strip crevice or hole.
3. horizontal seepage well as described in claim 1 or pipeline push pipe rapid constructing method, it is characterised in that:Afterbody push pipe
Using floral tube, ensure that water is penetrated into, flowed into.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810310845.9A CN108487097A (en) | 2018-04-09 | 2018-04-09 | Horizontal seepage well or pipeline push pipe rapid constructing method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810310845.9A CN108487097A (en) | 2018-04-09 | 2018-04-09 | Horizontal seepage well or pipeline push pipe rapid constructing method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108487097A true CN108487097A (en) | 2018-09-04 |
Family
ID=63314975
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810310845.9A Pending CN108487097A (en) | 2018-04-09 | 2018-04-09 | Horizontal seepage well or pipeline push pipe rapid constructing method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108487097A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN116556979A (en) * | 2023-05-25 | 2023-08-08 | 浙江金城建设集团有限公司 | Pipe jacking construction equipment and method |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102032393A (en) * | 2010-11-10 | 2011-04-27 | 博大建设有限公司 | Small-bore long distance curved pipe jacking method |
CN104358927A (en) * | 2014-10-30 | 2015-02-18 | 国强建设集团有限公司 | Push pipe construction method and push pipe device |
CN104534167A (en) * | 2014-12-08 | 2015-04-22 | 中国十七冶集团有限公司 | Drag reduction method of thixotropic slurry |
US20150369394A1 (en) * | 2010-10-08 | 2015-12-24 | Harr Technologies, Inc. | Trenchless drainage structure replacement |
CN206830946U (en) * | 2017-06-12 | 2018-01-02 | 郑州水务建筑工程股份有限公司 | A kind of concrete sleeve jacking construction structure |
-
2018
- 2018-04-09 CN CN201810310845.9A patent/CN108487097A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20150369394A1 (en) * | 2010-10-08 | 2015-12-24 | Harr Technologies, Inc. | Trenchless drainage structure replacement |
CN102032393A (en) * | 2010-11-10 | 2011-04-27 | 博大建设有限公司 | Small-bore long distance curved pipe jacking method |
CN104358927A (en) * | 2014-10-30 | 2015-02-18 | 国强建设集团有限公司 | Push pipe construction method and push pipe device |
CN104534167A (en) * | 2014-12-08 | 2015-04-22 | 中国十七冶集团有限公司 | Drag reduction method of thixotropic slurry |
CN206830946U (en) * | 2017-06-12 | 2018-01-02 | 郑州水务建筑工程股份有限公司 | A kind of concrete sleeve jacking construction structure |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN116556979A (en) * | 2023-05-25 | 2023-08-08 | 浙江金城建设集团有限公司 | Pipe jacking construction equipment and method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102661172B (en) | Advanced precipitation method for deep-buried tunnel | |
CN108223911B (en) | Trenchless repairing method for small-diameter pipeline collapse | |
CN107152035A (en) | The construction method of underground pipe gallery river crossing | |
CN104818713A (en) | Profile steel cement soil pile construction method adaptive to various stratums | |
US9840835B2 (en) | Temporary drainage wells in loose granular soils | |
CN105257908A (en) | Jacking-pushing drilling construction device and method of underground pipeline | |
CN105064379B (en) | H-shaped steel foundation pit supporting device and method | |
CN111236387B (en) | Construction method for connecting newly-built sewage pipe with existing sewage pipe | |
CN105113530A (en) | Caisson aid-sinking process adopting high-pressure injection | |
CN108487097A (en) | Horizontal seepage well or pipeline push pipe rapid constructing method | |
CN202559363U (en) | Foundation pit supporting structure for underground diaphragm wall with steel structure | |
CN205762953U (en) | In-situ chemical injects repairs individual well multilamellar injected system | |
CN201078234Y (en) | Integral hydraulic pressure steel sheet piling curtain of vertical shaft construction overflowing sand bed | |
CN215630060U (en) | Reusable precipitation well casing | |
CN212054705U (en) | Novel underground pipeline poling is used in communication device | |
CN201158823Y (en) | Recoverable impact drill steel pipe downcast well | |
CN105586978A (en) | Construction method of soil replacement stir waterproof curtain based on gravels | |
CN211143179U (en) | Fractional pressing-in type recharge well structure | |
CN114592892A (en) | Implementation method for pulling out anchor cable of shield tunnel in steel sleeve in soft soil area | |
CN103603371B (en) | Environments such as subsea pipe-jacking project is removed obstacles backfill jacking construction method in advance | |
CN114482107A (en) | Construction method of impervious wall | |
CN106402505A (en) | Adjustable through-wall hole water stop device | |
CN206034466U (en) | Foundation ditch or basic groove precipitation system for construction | |
CN201433395Y (en) | Tri-circular safe pile casing for environment-friendly manual-excavated piles | |
CN205857212U (en) | Corrugated steel cofferdam borehole hollow pile |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20180904 |
|
RJ01 | Rejection of invention patent application after publication |