CN108487569A - A kind of assembled curtain wall decoration rod structure and method - Google Patents

A kind of assembled curtain wall decoration rod structure and method Download PDF

Info

Publication number
CN108487569A
CN108487569A CN201810580723.1A CN201810580723A CN108487569A CN 108487569 A CN108487569 A CN 108487569A CN 201810580723 A CN201810580723 A CN 201810580723A CN 108487569 A CN108487569 A CN 108487569A
Authority
CN
China
Prior art keywords
crossbeam
pendant
curtain wall
dalle
column
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810580723.1A
Other languages
Chinese (zh)
Inventor
赵敬义
孙洲
闫礼德
国海滨
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ji'nan Calendar Holding Group Co Ltd
Original Assignee
Ji'nan Calendar Holding Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ji'nan Calendar Holding Group Co Ltd filed Critical Ji'nan Calendar Holding Group Co Ltd
Priority to CN201810580723.1A priority Critical patent/CN108487569A/en
Publication of CN108487569A publication Critical patent/CN108487569A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F13/00Coverings or linings, e.g. for walls or ceilings
    • E04F13/07Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor
    • E04F13/072Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor composed of specially adapted, structured or shaped covering or lining elements
    • E04F13/073Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor composed of specially adapted, structured or shaped covering or lining elements for particular building parts, e.g. corners or columns
    • E04F13/0736Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor composed of specially adapted, structured or shaped covering or lining elements for particular building parts, e.g. corners or columns for columns

Abstract

The invention discloses a kind of assembled curtain wall decoration rod structure and methods, it solves the problems, such as that needing scene to weld installation edge list by scaffold in the prior art can assemble with that can realize factorial praluction in factory, the advantageous effect of the dependence to skilled worker is reduced, scheme is as follows:A kind of assembled curtain wall decoration rod structure, the more vertical upright columns including constituting rectangular cylinder, crossbeam is set to connect column between every adjacent two root posts in rectangular cylinder, barricade panel is fixed in rectangular cylinder side, the non-barricade panel side of rectangular cylinder fixes dalle, structure pendant of the setting for rectangular cylinder can be articulated to curtain wall construction built-in fitting on the inside of barricade panel, crossbeam are attached by bolt respectively with column, barricade panel and column, dalle and column or crossbeam.

Description

A kind of assembled curtain wall decoration rod structure and method
Technical field
The present invention relates to the stone curtain wall of building curtain wall (or artificial board) design fields, more particularly to a kind of assembled Curtain wall decoration rod structure and method.
Background technology
The works such as the decoration beam column of existing Bartlit curtain wall is usually site operation part, and scene is welded or cut Make, can not be factory produced, in addition, integral construction uses welding manner, relies on the level of skill of construction personnel, but it is traditional Stone decoration column beam engineering method needs multiplexing kind to coordinate, and quality cannot control, and construction speed can not improve, and specifically exists and asks as follows Topic:
1) it is connected by welding manner between keel, between keel and bearing, human weld varies with each individual, and curtain wall Inner structural members are more, there are problems that being not easy to weld at part;
2) on-site cutting keel cause dimensional accuracy not high;
3) site welding needs to set up scaffold, or installation hanging basket, and construction cost is higher and safety is relatively low;
4) drilling welding position needs touch-up paint;
5) whole to need to check that supervisor ensures to be welded in place, rely primarily on the qualification of worker's installation.
Therefore, it is necessary to study a kind of assembled curtain wall decoration rod structure.
Invention content
For overcome the deficiencies in the prior art, the present invention provides a kind of assembled curtain wall decoration rod structure, pass through bolt Without being welded to connect construction quality is effectively ensured, and can improve speed of application, and to the dependence of skilled worker in the mode of connection Degree is relatively low.
A kind of concrete scheme of assembled curtain wall decoration rod structure is as follows:
A kind of assembled curtain wall decoration rod structure, including more vertical upright columns of rectangular cylinder are constituted, it is every in rectangular cylinder Crossbeam is set to connect column, barricade panel, the non-barricade of rectangular cylinder are fixed in rectangular cylinder side between adjacent two root posts Panel side fixes dalle, and the knot for rectangular cylinder can be articulated to curtain wall construction built-in fitting is arranged on the inside of barricade panel Structure pendant, crossbeam are bolted with column, barricade panel and column, and dalle is tapped into column or crossbeam by back of the body bolt Row connection.
Further, the crossbeam is equipped with multilayer, and each layer of crossbeam forms a frame structure, adjacent frame structure Be spaced setpoint distance setting, by the setting of crossbeam, not only contribute to the setting stability for improving column, and facilitate crossbeam with The connection of dalle;
Alternatively, being respectively equipped with vertical diagonal brace in the both sides of rectangular cylinder between adjacent two layers frame structure, adjacent is vertical Diagonal brace misorientation is arranged, and for diagonal brace vertical in this way in the both sides w profiles arrangement of rectangular cylinder, vertical hound is steel or aluminium, Steel surface needs to do antirust treatment, and vertical diagonal brace is connect by bolt with upper layer and lower layer crossbeam, and vertical diagonal brace bottom is curved Folding is arranged to facilitate the installation of bolt.
Further, structure pendant one end is bolted with the barricade panel, and other end lower part is provided with Card slot facilitates entire decoration rod structure being hung on curtain wall construction built-in fitting by the setting of card slot;
Alternatively, the barricade panel sides are equipped at least two structure pendants.
Further, the frame structure diagonal line that the crossbeam is constituted is disposed with horizontal diagonal brace, and two horizontal diagonal braces interlock Arrangement, horizontal diagonal brace are steel or aluminium, and steel surface needs to do antirust treatment, determine horizontal diagonal brace according to Structure Calculation and erect To the width of diagonal brace;
Alternatively, it is horizontally-supported with crossbeam by being attached to wearing bolt (assembling keel with) nut.
Further, the crossbeam be L-type part, each layer of crossbeam constitute frame structure in adjacent two crossbeam setting side To on the contrary, along crossbeam length direction, that is, edge list width direction, L-type crossbeam side is arranged upward, with the crossbeam Adjacent crossbeam side is arranged downward, is convenient for the installation of dalle, crossbeam side that through-hole is arranged, decorates the front side board of rod structure The back of the body bolt of material is attached by through-hole and crossbeam.
Further, in optimal case, the vertical upright column is equipped with four, and four columns constitute the structure of cuboid;
Alternatively, the column being connect with the barricade panel is hollow pillar stand (two behind decoration rod structure), it is hollow vertical Column interior energy is packed into grafting and covers core to realize the connection of neighbouring two curtain wall decorations rod structure;
In addition, the column oppositely arranged with hollow pillar stand is L-type column (two before decoration rod structure).
Further, the crossbeam is equipped with trepanning pendant, and trepanning pendant side is connect with the crossbeam, and the other side passes through Spiral shell back of the body bolt is connect with dalle;
Alternatively, the crossbeam is equipped with fluting pendant, fluting pendant side is connect with the crossbeam, and card slot is arranged in the other side The back of the body bolt being used to support on the inside of dalle, dalle lower part back of the body bolt are fixed by card slot and fluting pendant, top and trepanning Pendant is fixed, and back of the body bolt, which is caught in after card slot, setting activity space, ensure curtain wall can bear certain uneven external force load or Deformation under temperature load effect, increases the flexibility and non-deformability of curtain wall, has better load adaptability.
Wherein, the trepanning pendant is arranged with the fluting pendant staggered floor, and the crossbeam of this two faulted layer is disposed adjacent, according to The height of dalle determines that the crossbeam position being attached thereto, the crossbeam being connect with dalle upper semisection are provided that trepanning is hung Part, the crossbeam being connect with lower semisection in dalle are provided that fluting pendant.
Further, trepanning is respectively set in the dalle back side, and back of the body bolt is equipped in trepanning;
Alternatively, the gap filling between adjacent dalle, between dalle and barricade panel has filling member, and stitch It is sealed by fluid sealant at gap, filling member selects PE foam rods, fluid sealant to select silica gel.
For overcome the deficiencies in the prior art, the present invention also provides a kind of assembly sides of assembled curtain wall decoration rod structure Method is as follows:
1) vertical upright column, crossbeam, vertical diagonal brace and horizontal diagonal brace are processed respectively;
2) more crossbeams are formed into frame structure, and horizontal diagonal brace is set in frame structure inner opposite angle line direction, it is horizontal oblique The both ends of support pass through the connection to wearing bolt realization crossbeam and horizontal diagonal brace respectively;
3) structure of multigroup step 2) is assembled, and assembled structure is installed with column successively, and is being assembled Adjacent two layers frame structure between in the both sides of rectangular cylinder vertical diagonal brace is installed respectively, adjacent vertical diagonal brace misorientation is set It sets;
4) the barricade panel equipped with structure pendant is fixed in rectangular cylinder side;
5) in each layer of frame structure mounting opening pendant of rectangular cylinder both sides or fluting pendant;
6) back of the body bolt is installed at the back of dalle;
7) structure that step 5) assembles is installed on to the keel frame for being used to support assembling structure by structure pendant;
8) dalle of step 6) assembling is passed through into angle steel pendant or fluting pendant or edge list architecture front-side plank The structure of step 7) is installed on by back of the body bolt and through-hole;
9) gap between adjacent dalle, between dalle and barricade panel is sealed;
10) integrated member that step 9) is completed is transported to construction site, is hung overall structure by structure pendant Part is installed on curtain wall construction embedded part;
11) integrated member of installation last layer is repeated, and seals adjacent upper layer and lower layer unit.
Wherein structure pendant is curtain wall three-dimensional regulation pendant, and entire rod structure of decorating passes through curtain wall three-dimensional regulation part and building Built-in fitting connection in agent structure, realize curtain wall unit in the horizontal direction, vertical direction and longitudinal direction be accurately positioned, institute It is the common node structure in curtain wall engineering to state three-dimensional regulation component.
Compared with prior art, the beneficial effects of the invention are as follows:
1) present invention can facilitate the quick connection of all parts by integrally-built setting, realize prefabrication, be not necessarily to Scene cut, welded again, the work such as touch-up paint, and total is without welding, and assembly precision is high, and assembling speed is fast, high-quality, It is low to experienced operator's degree of dependence.
2) present invention not only facilitates the structural member of assembling being mounted on keel frame by the setting of structure pendant, ensures The safety of transport, and be also convenient for entire component being mounted on curtain wall construction embedded part.
3) present invention is by the setting of crossbeam angle steel pendant and fluting pendant, the installation of Handy finishing board material, and ensures to connect The stability and reliability connect.
4) overall structure of the present invention can also be installed at the construction field (site), without building scaffold, be protected from weather influences assembling, Construction safety is quick, and quality is better than traditional engineering method, and repair is easy to change, and method is more energy saving, encircle, safety and facility.
Description of the drawings
The accompanying drawings which form a part of this application are used for providing further understanding of the present application, and the application's shows Meaning property embodiment and its explanation do not constitute the improper restriction to the application for explaining the application.
Fig. 1 is overall structure of the present invention;
Fig. 2 is the beam structure schematic diagram of the invention with angle steel pendant;
Fig. 3 is beam structure schematic diagram of the present invention with fluting pendant;
Fig. 4 is decorative plate structure schematic diagram of the present invention;
In figure:1. dalle, 2. columns, 3. vertical diagonal braces, 4. crossbeams, 5. horizontal diagonal braces, 6. pairs are worn bolt, 7. back ofs the body Bolt, 8. trepanning pendants, 9. fluting pendants, 11. fluid sealants, 12. barricade panels, 13. grafting cover core, 14. structure pendants.
Specific implementation mode
It is noted that following detailed description is all illustrative, it is intended to provide further instruction to the application.Unless another It indicates, all technical and scientific terms used herein has usual with the application person of an ordinary skill in the technical field The identical meanings of understanding.
It should be noted that term used herein above is merely to describe specific implementation mode, and be not intended to restricted root According to the illustrative embodiments of the application.As used herein, unless the context clearly indicates otherwise, otherwise singulative It is also intended to include plural form, additionally, it should be understood that, when in the present specification using term "comprising" and/or " packet Include " when, indicate existing characteristics, step, operation, device, component and/or combination thereof.
As background technology is introduced, the deficiencies in the prior art, in order to solve technical problem as above, this Shen It please propose a kind of assembled curtain wall decoration rod structure.
In a kind of typical embodiment of the application, as shown in Figure 1, a kind of assembled curtain wall decoration rod structure, including More vertical upright columns 2 of rectangular cylinder are constituted, column is divided into front and back column, needs to provide section according to Structure Calculation, can be steel Material and aluminium, steel surface need to do antirust treatment, per setting crossbeam 4 between adjacent two root posts 2 to connect in rectangular cylinder The non-barricade panel side of column 2, barricade panel 12 in the fixed chamber of rectangular cylinder side, rectangular cylinder fixes 1 (stone material of dalle Or artificial board), structure pendant of the barricade panel inside setting for rectangular cylinder can be articulated to curtain wall construction built-in fitting, Crossbeam 4 is attached by bolt respectively with column 2, barricade panel 12 and column 2, dalle 1 and column or crossbeam 4.
Crossbeam 4 be equipped with multilayer, be divided into X to Y-direction crossbeam, need according to Structure Calculation provide section, can be steel and aluminium Material, surface need to do antirust treatment, and each layer of crossbeam 4 forms a frame structure, the setting of adjacent frame structure interval away from From setting, by the setting of crossbeam 4, the setting stability for improving column 2 is not only contributed to, and facilitate crossbeam 4 and decorative panel The connection of material 1;
It is respectively equipped with vertical diagonal brace 3 in the both sides of rectangular cylinder between adjacent two layers frame structure, the needs of vertical diagonal brace 3 are pressed Section is provided according to Structure Calculation, can be steel and aluminium, if steel surface needs to do antirust treatment, adjacent vertical diagonal brace 3 is wrong To setting, for diagonal brace 3 vertical in this way in the both sides w profile arrangement of rectangular cylinder, 3 bar of vertical diagonal brace is steel or aluminium, steel Surface needs to do antirust treatment, and vertical diagonal brace is connect by bolt with upper layer and lower layer crossbeam, and vertical diagonal brace bottom bending is set It sets to facilitate the installation of bolt.
Structure pendant one end is bolted with the barricade panel, and other end lower part is provided with card slot, passes through card slot Setting, facilitate and entire decoration rod structure be hung on curtain wall construction built-in fitting;Barricade panel sides are hung equipped at least two structures Part.
Wherein, the frame structure diagonal line that crossbeam is constituted is disposed with horizontal diagonal brace 5, two 5 interlaced arrangements of horizontal diagonal brace, water Flat diagonal brace 5 is steel or aluminium, and steel surface needs to do antirust treatment, according to Structure Calculation determine horizontal diagonal brace 5 and it is vertical tiltedly The width of support 3;
Alternatively, it is horizontally-supported with crossbeam by being attached to wearing bolt 6 (assembling keel with) nut.
Crossbeam 4 be L-type part, each layer of crossbeam 4 constitute frame structure in adjacent two crossbeam 4 setting direction on the contrary, edge The length direction of crossbeam 4, that is, the width direction of edge list, L-type crossbeam side is arranged upward, the cross adjacent with the crossbeam Beam side is arranged downward, is convenient for the installation of dalle 1.
In optimal case, vertical upright column 2 is equipped with four or the six roots of sensation, wherein two are set between two adjacent upright.
Alternatively, the column 2 being connect with barricade panel 12 is hollow pillar stand, hollow pillar stand (two behind decoration rod structure) Interior energy is packed into grafting and covers core 13 to realize the connection of neighbouring two curtain wall decorations rod structure;
In addition, the column oppositely arranged with hollow pillar stand is L-type column (two before decoration rod structure).
Trepanning is respectively set with the dalle back side in barricade panel, and stainless steel back of the body bolt is equipped in trepanning;
In optimal case, one layer of crossbeam is equipped with fluting pendant 9, fluting 9 side of pendant by wear bolt 6 with it is described Crossbeam 4 connect, the other side setting card slot be used to support the back of the body bolt 7 on the inside of dalle;Fluting pendant be with trepanning pendant Angle steel pendant, another layer crossbeam 4 are equipped with trepanning pendant, and 8 side of trepanning pendant is connect with the crossbeam, and the other side passes through Back of the body bolt 7 is connect with dalle 1, and the crossbeam equipped with angle steel pendant 8 is arranged with the crossbeam staggered floor equipped with fluting pendant, this two layers horizontal Beam is disposed adjacent, wherein fluting pendant 9 is used to support the back of the body bolt on the inside of dalle, angle steel pendant can be galvanized steel, stainless steel Or aluminum alloy materials, 4 position of crossbeam being attached thereto is determined according to the height of dalle 1, is connect with 1 upper semisection of dalle Crossbeam 4 be provided that trepanning pendant 8, the crossbeam 4 being connect with lower semisection in dalle be provided that fluting pendant 9.
Alternatively, the gap filling between adjacent dalle, between dalle and barricade panel has filling member, and stitch It is sealed by fluid sealant at gap, filling member selects PE foam rods, fluid sealant to select silica gel 11.
In a further embodiment, crossbeam is equipped with trepanning pendant, and trepanning pendant side is connect with the crossbeam, the other side It is connect with dalle by back of the body bolt;
Alternatively, crossbeam is equipped with fluting pendant, fluting pendant side is connect with the crossbeam, and other side setting card slot is used for Support the back of the body bolt on the inside of dalle.
For overcome the deficiencies in the prior art, the present invention also provides a kind of assembly sides of assembled curtain wall decoration rod structure Method is as follows:
1) vertical upright column 2, crossbeam 4, vertical diagonal brace 3 and horizontal diagonal brace 5 are processed respectively;
2) more crossbeams 4 are formed into frame structure, and horizontal diagonal brace 5 is set in frame structure inner opposite angle line direction, it is horizontal The both ends of diagonal brace 5 pass through the connection to wearing bolt 6 realization crossbeam and horizontal diagonal brace 5 respectively;
3) structure of multigroup step 2) is assembled, and assembled structure is installed with column 2 successively, and is being assembled Adjacent two layers frame structure between in the both sides of rectangular cylinder vertical diagonal brace 3 is installed respectively, adjacent 3 misorientation of vertical diagonal brace is set It sets;
4) the barricade panel 12 equipped with structure pendant is fixed in rectangular cylinder side;
5) in each layer of frame structure mounting opening pendant 8 of rectangular cylinder both sides or fluting pendant 9;
6) back of the body bolt is installed at the trepanning 7 of 1 inside of dalle;
7) structure that step 5) assembles is installed on major structure of construction by structure pendant 14;
8) dalle of step 6) assembling is installed on to the structure of step 7) by trepanning pendant or fluting pendant;
9) gap between adjacent dalle, between dalle and barricade panel is sealed;
10) integrated member that step 9) is completed is transported to construction site, is hung overall structure by structure pendant Part is installed on curtain wall construction embedded part;
11) integrated member of installation last layer is repeated, and seals adjacent upper layer and lower layer unit.
The foregoing is merely the preferred embodiments of the application, are not intended to limit this application, for the skill of this field For art personnel, the application can have various modifications and variations.Within the spirit and principles of this application, any made by repair Change, equivalent replacement, improvement etc., should be included within the protection domain of the application.

Claims (10)

1. a kind of assembled curtain wall decoration rod structure, which is characterized in that the more vertical upright columns including constituting rectangular cylinder, rectangle For setting crossbeam to connect column, barricade panel, rectangular cylinder are fixed in rectangular cylinder side between every adjacent two root posts in cylinder Non- barricade panel side fix dalle, setting is pre- for can rectangular cylinder be articulated to curtain wall construction on the inside of barricade panel The structure pendant of embedded part, crossbeam are bolted with column, barricade panel and column, and dalle is distinguished with column or crossbeam It is attached by back of the body bolt.
2. a kind of assembled curtain wall decoration rod structure according to claim 1, which is characterized in that the crossbeam is equipped with more Layer, each layer of crossbeam form a frame structure;
Alternatively, being respectively equipped with vertical diagonal brace, adjacent vertical diagonal brace in the both sides of rectangular cylinder between adjacent two layers frame structure Misorientation is arranged.
3. a kind of assembled curtain wall decoration rod structure according to claim 1, which is characterized in that structure pendant one end It is bolted with the barricade panel, other end lower part is provided with card slot;
Alternatively, the barricade panel sides are equipped at least two structure pendants.
4. a kind of assembled curtain wall decoration rod structure according to claim 2, which is characterized in that the frame that the crossbeam is constituted Body structure diagonal line is disposed with horizontal diagonal brace, two horizontal diagonal brace interlaced arrangements;
Alternatively, it is horizontally-supported with crossbeam by being attached to wearing bolt and nut.
5. a kind of assembled curtain wall decoration rod structure according to claim 2, which is characterized in that the crossbeam is L-type part, The setting direction of adjacent two crossbeam is opposite in the frame structure that each layer of crossbeam is constituted.
6. a kind of assembled curtain wall decoration rod structure according to claim 1, which is characterized in that the vertical upright column is equipped with Four;
Alternatively, the column being connect with the barricade panel be hollow pillar stand, hollow pillar stand interior energy be packed into grafting cover core to realize on Under adjacent two curtain wall decorations rod structure connection;
It is L-type column with the oppositely arranged column of hollow pillar stand.
7. a kind of assembled curtain wall decoration rod structure according to claim 1, which is characterized in that the crossbeam is equipped with trepanning Pendant, trepanning pendant side are connect with the crossbeam, and the other side is connect by spiral shell back of the body bolt with dalle;
Alternatively, the crossbeam is equipped with fluting pendant, fluting pendant side is connect with the crossbeam, and other side setting card slot is used for Support the back of the body bolt on the inside of dalle.
8. a kind of assembled curtain wall decoration rod structure according to claim 7, which is characterized in that the trepanning pendant and institute State fluting pendant staggered floor setting.
9. a kind of assembled curtain wall decoration rod structure according to claim 1, which is characterized in that the dalle back side Trepanning is set, the back of the body bolt is equipped in trepanning;
Alternatively, the gap filling between adjacent dalle, between dalle and barricade panel has filling member, and at gap It is sealed by fluid sealant.
10. a kind of assembly method of assembled curtain wall decoration rod structure according to any one of claim 1-9, feature It is, is as follows:
1) vertical upright column, crossbeam, vertical diagonal brace and horizontal diagonal brace are processed respectively;
2) more crossbeams are formed into frame structure, and horizontal diagonal brace is set in frame structure inner opposite angle line direction, horizontal diagonal brace Both ends pass through the connection to wearing bolt realization crossbeam and horizontal diagonal brace respectively;
3) structure of multigroup step 2) is assembled, and assembled structure is installed with column successively, and in assembled phase Vertical diagonal brace, the setting of adjacent vertical diagonal brace misorientation are installed respectively in the both sides of rectangular cylinder between adjacent two layers of frame structure;
4) the barricade panel equipped with structure pendant is fixed in rectangular cylinder side;
5) in rectangular cylinder frame structure side mounting opening pendant or fluting pendant;
6) back of the body bolt is installed at the back of dalle;
7) structure that step 5) assembles is installed on by keel frame by structure pendant;
8) dalle of step 6) assembling is passed through by angle steel pendant or fluting pendant or edge list architecture front-side plank Back of the body bolt is installed on the structure of step 7) with through-hole;;
9) gap between adjacent dalle, between dalle and barricade panel is sealed;
10) integrated member that step 9) is completed is transported to construction site, is pacified overall structure pendant by structure pendant Loaded on curtain wall construction embedded part;
11) integrated member of installation last layer is repeated, and seals adjacent upper layer and lower layer unit.
CN201810580723.1A 2018-06-07 2018-06-07 A kind of assembled curtain wall decoration rod structure and method Pending CN108487569A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810580723.1A CN108487569A (en) 2018-06-07 2018-06-07 A kind of assembled curtain wall decoration rod structure and method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810580723.1A CN108487569A (en) 2018-06-07 2018-06-07 A kind of assembled curtain wall decoration rod structure and method

Publications (1)

Publication Number Publication Date
CN108487569A true CN108487569A (en) 2018-09-04

Family

ID=63342126

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810580723.1A Pending CN108487569A (en) 2018-06-07 2018-06-07 A kind of assembled curtain wall decoration rod structure and method

Country Status (1)

Country Link
CN (1) CN108487569A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113356523A (en) * 2021-07-07 2021-09-07 杨洋 Construction method for constructing decorative column

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0953288A (en) * 1995-08-14 1997-02-25 Ykk Architect Prod Kk Mounting construction of curtain wall unit and mullion bearing the curtain wall unit and joint construction of transom
CN104831845A (en) * 2015-04-07 2015-08-12 中铁建设集团有限公司 Stone curtain wall-used keel supporting system unit
CN205171782U (en) * 2015-11-18 2016-04-20 成都江河幕墙系统工程有限公司 Frame curtain system between stone material edge list
CN205259413U (en) * 2015-12-21 2016-05-25 浙江亚厦幕墙有限公司 Connection structure of stone material curtain stand
CN105839821A (en) * 2016-06-07 2016-08-10 中国航空规划设计研究总院有限公司 Slotted stone curtain wall sealing system, curtain wall system and construction method for same
CN208267265U (en) * 2018-06-07 2018-12-21 济南历下控股集团有限公司 A kind of assembled curtain wall decoration rod structure

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0953288A (en) * 1995-08-14 1997-02-25 Ykk Architect Prod Kk Mounting construction of curtain wall unit and mullion bearing the curtain wall unit and joint construction of transom
CN104831845A (en) * 2015-04-07 2015-08-12 中铁建设集团有限公司 Stone curtain wall-used keel supporting system unit
CN205171782U (en) * 2015-11-18 2016-04-20 成都江河幕墙系统工程有限公司 Frame curtain system between stone material edge list
CN205259413U (en) * 2015-12-21 2016-05-25 浙江亚厦幕墙有限公司 Connection structure of stone material curtain stand
CN105839821A (en) * 2016-06-07 2016-08-10 中国航空规划设计研究总院有限公司 Slotted stone curtain wall sealing system, curtain wall system and construction method for same
CN208267265U (en) * 2018-06-07 2018-12-21 济南历下控股集团有限公司 A kind of assembled curtain wall decoration rod structure

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
雍本: "《幕墙工程施工手册第3版》", 31 January 2017, 中国计划出版社, pages: 82 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113356523A (en) * 2021-07-07 2021-09-07 杨洋 Construction method for constructing decorative column

Similar Documents

Publication Publication Date Title
CN208267265U (en) A kind of assembled curtain wall decoration rod structure
CN106049728B (en) A kind of Wind-Pressure Resistance glass stone material solid combined curtain wall
CN104763109B (en) Quick construction method for pressed bottom tile of large-span steel structure factory building roof
CN105908836A (en) Mobile house
CN103883054B (en) A kind of rope bar girt strip composite floor system and construction method thereof
CN108005265A (en) A kind of prefabricated steel reinforced concrete shear wall structure of multilayer and its preparation and construction method
CN104372961A (en) Anti-seismic integrated lightweight steel construction house
CN203296166U (en) Supporting structure of main module unit in module building
CN108487569A (en) A kind of assembled curtain wall decoration rod structure and method
JP6667940B2 (en) Exterior wall panel and column layout structure of exterior wall and layout construction method
CN108915140A (en) The installation method of super 10m high curved arc full glass curtain wall
CN208267190U (en) A kind of big face stone material or artificial board curtain wall construction
CN106368368A (en) Stone material aluminum honeycomb composite slab suspended ceiling construction method based on T-shaped and Z-shaped hanging parts
JP6271399B2 (en) Exterior wall panel mounting structure
CN108487528A (en) A kind of big face stone material or artificial board curtain wall construction and method
CN204311776U (en) A kind of integrated lightweight steel construction room of antidetonation
KR101222115B1 (en) Roof structure
CN207177310U (en) A kind of crane beam on rock wall for underground power house reinforcing bar is from steady structure
CN206859469U (en) A kind of superelevation light steel keel gypsum board wall body structure
CN113653272B (en) Archaized eave of steel structure of high-rise building and construction method thereof
CN109356338A (en) Steel skeleton daughter's wall construction
CN212428012U (en) Parapet combination operation platform
CN204282788U (en) Shaping type scaffold can be assembled
CN102322136A (en) Full-module-assembly adhesion type lifting scaffold
CN209620622U (en) A kind of promotion platform

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination