CN108425386A - Frame structure building promotes correcting method - Google Patents

Frame structure building promotes correcting method Download PDF

Info

Publication number
CN108425386A
CN108425386A CN201810508799.3A CN201810508799A CN108425386A CN 108425386 A CN108425386 A CN 108425386A CN 201810508799 A CN201810508799 A CN 201810508799A CN 108425386 A CN108425386 A CN 108425386A
Authority
CN
China
Prior art keywords
elevator
pile
building
piling
piling hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810508799.3A
Other languages
Chinese (zh)
Inventor
贾强
张鑫
孙剑平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong Jianzhu University
Original Assignee
Shandong Jianzhu University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong Jianzhu University filed Critical Shandong Jianzhu University
Priority to CN201810508799.3A priority Critical patent/CN108425386A/en
Publication of CN108425386A publication Critical patent/CN108425386A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D35/00Straightening, lifting, or lowering of foundation structures or of constructions erected on foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D35/00Straightening, lifting, or lowering of foundation structures or of constructions erected on foundations
    • E02D35/005Lowering or lifting of foundation structures

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Foundations (AREA)

Abstract

The invention discloses a kind of frame structure buildings to promote correcting method, including excavates working pit, exposes isolated footing;Piling hole is opened up at the top of isolated footing, the both sides in the piling hole at the top of isolated footing, installation connecting element;Place first segment prefabricated pile vertically in piling hole, stake top is inserted in pile cover, and elevator is installed on pile cover, and the hoisting rope of elevator is connected with the connector on basis top;Elevator is started, prefabricated pile is pressed into the foundation soil of ground beneath;When the prefabricated stake top of first segment is depressed near piling hole, pile cover and elevator are temporarily removed, prefabricated pile is saved in first segment stake top spreading second, pile cover and elevator is installed, continue to start elevator piling;The differential settlement between building inclination rate and frame column is measured in basic lifting process;Stop being promoted after the differential settlement between building inclination rate and frame column is less than tolerance as defined in specification;Pea gravel concreten is perfused being elevated in basis and foundation soil gap and piling hole.

Description

Frame structure building promotes correcting method
Technical field
The invention belongs to civil construction fields, and in particular to a kind of building inclination rectification method.
Background technology
Building inclination rectification means that building causes basis uneven due to certain of ground, basis or building itself Sedimentation, upper part structure deviate upright position and run-off the straight, when the inclined degree of building be more than the related code requirement of country, Seriously affect taken when building safety and normal use to ensuring building safety and restore its normal usage function Rectification righting, reinforce stable measure.
The common method of rectification has:Pressing Ioad correcting method, soil digging correcting method, immersion correcting method and soil digging douche etc.. These methods are mostly to increase settling amount in the small side of building settlement, so as to adjusting the relative settlement on entire basis.To rise To the inclined purpose of correction building.These methods need to estimate settling amount, and a large amount of theoretical meter is carried out to soil digging amount, irrigation quantity It calculates, it is empirical very strong, it is theoretical also immature.In fact big side will be settled to promote building, can equally reach rectification Purpose, and tilting procedure is simple, controllable.
Invention content
In view of the above shortcomings of the prior art, the object of the present invention is to provide a kind of promotions for frame structure building Correcting method.
In order to achieve the goal above, the technical scheme is that:
A kind of frame structure lifting inclination-correcting method, includes the following steps:
1) working pit is excavated in the foundation soil in the relatively large region of settlement of foundation of the building of run-off the straight, exposure Go out the isolated footing below frame column at this;
2) piling hole is opened up at the top of isolated footing, piling hole is low wide and up narrow broadening formation;
3) suspension hook is installed in the both sides in the piling hole at the top of isolated footing;
4) first segment prefabricated pile is placed vertically in piling hole, stake top is inserted in pile cover, and elevator is installed on pile cover, will carry The hoisting rope of the machine of liter is connected with the suspension hook on basis top;
5) elevator is started, prefabricated pile is pressed into the foundation soil of ground beneath using building weight as counter-force;
6) when the prefabricated stake top of first segment is depressed near piling hole, pile cover and elevator are temporarily removed, in first segment stake Apical grafting length the second section prefabricated pile, installs pile cover and elevator, continues to start elevator piling;
7) constantly spreading and piling, until first segment prefabricated pile pile top reaches hard soil layer;
8) continue to start elevator, since prefabricated pile is supported on hard soil layer, do not continue to, isolated footing can quilt It is promoted;The differential settlement between building inclination rate and frame column is measured in basic lifting process;When building inclination rate and frame Differential settlement between column stops being promoted after being less than tolerance as defined in specification;
9) pea gravel concreten is perfused being elevated in basis and foundation soil gap and piling hole.
Further, the minimum place aperture in piling hole not only needs receiving correction prefabricated pile, but also when considering rectification Building isolated footing horizontal offset;
Further, suspension hook is installed by the method for bar planting.
Further, the piling hole number at least two, two or more drillings are in the isolated footing Top be uniformly distributed.
Further, the total height of prefabricated pile, pile cover and elevator is usually no more than architecture bottom layer floor height.
Further, frame column fractional load is transmitted to prefabricated pile and heavily fortified point by the frictional force of pea gravel concreten in piling hole Hard soil layer;Separately there is fractional load to be transmitted in foundation soil by the pea gravel concreten that ground beneath is filled;
Further, further include that step 10) removes pile cover and elevator, the basic prefabricated pile remaining at most of amputation;
Further, further include step 11) backfilling working hole, restore ground.
Beneficial effects of the present invention are:
It is simpler compared to the method for forced landing, safe, controllable using the method for promotion, settling amount need not be estimated in advance, draw Soil and irrigation quantity, it is only necessary to intuitively complete rectification using conventional measurement means.In addition, superstructure load passes through prefabricated pile It is transmitted with two paths of original basis, safety and reliability reduces posterior settlement.
Description of the drawings
The accompanying drawings which form a part of this application are used for providing further understanding of the present application, and the application's shows Meaning property embodiment and its explanation do not constitute the improper restriction to the application for explaining the application.
Fig. 1 is the side view before building inclination rectification;
Fig. 2 is the side view after excavating operating pit at sedimentation major part isolated footing;
Fig. 3 is to open up piling hole on a stand alone basis and install the side view of suspension hook;
Fig. 4 is the schematic diagram for placing prefabricated pile, pile cover, elevator and steel wire rope;
Fig. 5 is that first segment prefabricated pile is depressed into the schematic diagram near piling hole;
Fig. 6 is that first segment prefabricated pile pile top reaches hard soil layer schematic diagram;
Fig. 7 is the schematic diagram that isolated footing is elevated;
Fig. 8 is to fill pea gravel concreten schematic diagram in gap between isolated footing and foundation soil and piling hole;
Fig. 9 cheats for backfilling working, restores ground schematic diagram;
The horizontal offset schematic diagram that isolated footing generates when Figure 10 is rectification.
Wherein:1, frame column, 2, Vierendeel girder, plate, 3, isolated footing, 4, foundation soil, 5, hard soil layer, 6, working pit, 7, Piling hole, 8, suspension hook, 9, prefabricated pile, 10, steel wire rope, 11, pile cover, 12, elevator, 13, isolated footing and foundation soil and pressure Gap between stake holes, 14, pea gravel concreten, 15, rectification when the isolated footing horizontal offset that generates.
Specific implementation mode
It is noted that following detailed description is all illustrative, it is intended to provide further instruction to the application.Unless another It indicates, all technical and scientific terms used herein has usual with the application person of an ordinary skill in the technical field The identical meanings of understanding.
It should be noted that term used herein above is merely to describe specific implementation mode, and be not intended to restricted root According to the illustrative embodiments of the application.As used herein, unless the context clearly indicates otherwise, otherwise singulative It is also intended to include plural form, additionally, it should be understood that, when in the present specification using term "comprising" and/or " packet Include " when, indicate existing characteristics, step, operation, device, component and/or combination thereof;
In order to facilitate narration, if there is "upper", "lower", " left side " " right side " printed words, only expression and attached drawing itself in the present invention Upper and lower, left and right direction it is consistent, not to structure rise restriction effect, it is only for convenient for description the present invention and simplification retouch It states, does not indicate or imply the indicated equipment or element must have a particular orientation, with specific azimuth configuration and operation, Therefore it is not considered as limiting the invention.
As background technology is introduced, the common method of rectification in the prior art has:Pressing Ioad correcting method, soil digging Correcting method, immersion correcting method and soil digging douche etc..These methods are mostly to increase settling amount in the small side of building settlement, are borrowed To adjust the relative settlement on entire basis.To play the inclined purpose of correction building.These methods need to estimate settling amount, A large amount of theoretical calculation is carried out to soil digging amount, irrigation quantity, it is empirical very strong, it is theoretical also immature.In fact big one will be settled Side promotes building, can equally achieve the purpose that rectification, and tilting procedure is simple, controllable., in order to solve skill as above Art problem, present applicant proposes a kind of (subject names).
In a kind of typical embodiment of the application, as shown in Figure 1, the side view before the building inclination rectification indicated in Fig. 1 Figure;It includes frame column 1, Vierendeel girder, plate 2, isolated footing 3, foundation soil 4, hard soil layer 5;Whole building tilts to the right, Specific inclination correction method as shown in figs. 2-10, includes the following steps:
1) working pit is excavated in the foundation soil in the relatively large region of settlement of foundation of the building of run-off the straight, exposure Go out the isolated footing below frame column at this;Specifically as shown in Fig. 2, excavating working pit on the right side of building, expose at this Isolated footing 3 below frame column;
2) piling hole 7 is opened up at the top of isolated footing 3, piling hole 7 is low wide and up narrow broadening formation, and aperture is not at minimum It only needs to accommodate correction prefabricated pile, and to consider building isolated footing horizontal offset when rectification;Specifically such as Fig. 3 institutes Show;
Further, piling hole is at least arranged two in the present invention, two or more piling holes are along the independence The top on basis is uniformly distributed, and ensures whole building uniform force;Specific quantity can be according to the weight of actual building Amount is configured, and is essentially that structural quality is bigger, the quantity of jack is more, and drilling hole amount is also more.
3) in the both sides in 3 top piling hole of isolated footing, by the method installation connecting element of bar planting, the connector can To select the suspension hook 8 in figure;Specific requirement is that the both sides in each piling hole are respectively mounted two suspension hooks 8.
4) first segment prefabricated pile is placed vertically in each piling hole 7, stake top is inserted in pile cover 11, pacifies on each pile cover 11 Motor hoist 12 is filled, the steel wire rope of elevator 12 is connected with the suspension hook that isolated footing is pushed up, suspension hook here refers to that installation carries Rise the suspension hook beside the prefabricated pile of machine 12;The total height of pile cover and elevator is usually no more than architecture bottom layer floor height;Specifically As shown in Figure 4, Figure 5.
5) while multiple elevators 12 are started, multiple while prefabricated pile is pressed into basis using building weight as counter-force In the foundation soil of lower section;
6) when the prefabricated stake top of first segment in each piling hole 7 is depressed into piling hole near top, pile cover is temporarily removed And elevator installs pile cover and elevator, continues to start elevator piling in first segment stake top connection the second section prefabricated pile;
7) constantly spreading and piling, until first segment prefabricated pile pile top reaches hard soil layer;As shown in fig. 6, being first It saves prefabricated pile pile top and reaches hard soil layer schematic diagram;
8) continue to start multiple elevators, since prefabricated pile is supported on hard soil layer, do not continue to, isolated footing It can be elevated;
9) differential settlement between building inclination rate and frame column is measured in basic lifting process.When building inclination rate and Differential settlement between frame column stops being promoted after being less than tolerance as defined in specification.
10) it is being elevated perfusion pea gravel concreten 14 in basis and foundation soil gap and piling hole.Frame post part lotus It carries and prefabricated pile and hard soil layer is transmitted to by the frictional force of pea gravel concreten in piling hole;Separately there is fractional load to pass through basis The pea gravel concreten of lower section filling is transmitted in foundation soil;As shown in Figure 8;
11) pile cover and elevator, the basic prefabricated pile remaining at most of amputation are removed;
12) backfilling working is cheated, and restores ground, as shown in Figure 9.
The horizontal offset schematic diagram that isolated footing generates when Figure 10 is rectification in the present invention.
Above-mentioned, although the foregoing specific embodiments of the present invention is described with reference to the accompanying drawings, not to invention protection domain Limitation, those skilled in the art should understand that, based on the technical solutions of the present invention, those skilled in the art are not required to It is still within the scope of the present invention to make the creative labor the various modifications or changes that can be made.
The foregoing is merely the preferred embodiments of the application, are not intended to limit this application, for the skill of this field For art personnel, the application can have various modifications and variations.Within the spirit and principles of this application, any made by repair Change, equivalent replacement, improvement etc., should be included within the protection domain of the application.

Claims (8)

1. a kind of frame structure building promotes correcting method, which is characterized in that include the following steps:
1) working pit is excavated in the foundation soil in the relatively large region of settlement of foundation of the building of run-off the straight, exposes this Locate the isolated footing below frame column;
2) piling hole is opened up at the top of isolated footing, piling hole is low wide and up narrow broadening formation;
3) both sides in the piling hole at the top of isolated footing, installation connecting element;
4) first segment prefabricated pile is placed vertically in piling hole, stake top is inserted in pile cover, and elevator is installed on pile cover, by elevator Hoisting rope with basis top connector be connected;
5) elevator is started, prefabricated pile is pressed into the foundation soil of ground beneath using building weight as counter-force;
6) when the prefabricated stake top of first segment is depressed near piling hole, pile cover and elevator is temporarily removed, is connect in first segment stake top Long second section prefabricated pile, installs pile cover and elevator, continues to start elevator piling;
7) constantly spreading and piling, until first segment prefabricated pile pile top reaches hard soil layer;
8) continue to start elevator, since prefabricated pile is supported on hard soil layer, do not continue to, isolated footing can be carried It rises;The differential settlement between building inclination rate and frame column is measured in basic lifting process;When building inclination rate and frame column Between differential settlement be less than as defined in specification and stop after tolerance being promoted;
9) pea gravel concreten is perfused being elevated in basis and foundation soil gap and piling hole.
2. frame structure building as described in claim 1 promotes correcting method, which is characterized in that aperture at the minimum in piling hole It not only needs to accommodate correction prefabricated pile, but also to consider building isolated footing horizontal offset when rectification.
3. frame structure building as described in claim 1 promotes correcting method, which is characterized in that installed by the method for bar planting The connector.
4. frame structure building as described in claim 1 promotes correcting method, which is characterized in that the piling hole number is extremely It it is less two, two or more drillings are uniformly distributed at the top of the isolated footing.
5. frame structure building as described in claim 1 promotes correcting method, which is characterized in that prefabricated pile, pile cover and promotion The total height of machine is usually no more than architecture bottom layer floor height.
6. frame structure building as described in claim 1 promotes correcting method, which is characterized in that frame column fractional load passes through The frictional force of pea gravel concreten is transmitted to prefabricated pile and hard soil layer in piling hole;Separately there is fractional load to be filled out by ground beneath The pea gravel concreten filled is transmitted in foundation soil.
7. frame structure building as described in claim 1 promotes correcting method, which is characterized in that further include that step 10) is removed Pile cover and elevator, the basic prefabricated pile remaining at most of amputation.
8. frame structure building as described in claim 1 promotes correcting method, which is characterized in that further include step 11) backfill Working pit restores ground.
CN201810508799.3A 2018-05-24 2018-05-24 Frame structure building promotes correcting method Pending CN108425386A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810508799.3A CN108425386A (en) 2018-05-24 2018-05-24 Frame structure building promotes correcting method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810508799.3A CN108425386A (en) 2018-05-24 2018-05-24 Frame structure building promotes correcting method

Publications (1)

Publication Number Publication Date
CN108425386A true CN108425386A (en) 2018-08-21

Family

ID=63164045

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810508799.3A Pending CN108425386A (en) 2018-05-24 2018-05-24 Frame structure building promotes correcting method

Country Status (1)

Country Link
CN (1) CN108425386A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2021093732A1 (en) * 2019-11-12 2021-05-20 山东建筑大学 Displacement inclination rectification method for building

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101858082A (en) * 2010-06-12 2010-10-13 上海智平基础工程有限公司 Soft soil foundation new construction post pile pressing technology and construction method thereof
CN102561721A (en) * 2012-02-29 2012-07-11 化学工业岩土工程有限公司 Building jacking deviation rectifying method
CN102605783A (en) * 2012-01-10 2012-07-25 葛培中 Construction method for applying prestress to anchor jacked piles
CN103321261A (en) * 2013-07-18 2013-09-25 张继红 Construction method for directional expansion-rise deviation rectification
CN104047305A (en) * 2014-05-26 2014-09-17 江苏鼎泰工程材料有限公司 Fast repairing method of house sinking
CN105839946A (en) * 2016-03-31 2016-08-10 山东建筑大学 Brick-concrete structure building lifting add-layer method
CN107035159A (en) * 2017-05-05 2017-08-11 山东建筑大学 A kind of method suitable for frame structure isolated footing building underground increasing layer
CN107842046A (en) * 2017-11-27 2018-03-27 杨孝 A kind of strengthening of foundation error-correction structure and the method for strengthening of foundation correction

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101858082A (en) * 2010-06-12 2010-10-13 上海智平基础工程有限公司 Soft soil foundation new construction post pile pressing technology and construction method thereof
CN102605783A (en) * 2012-01-10 2012-07-25 葛培中 Construction method for applying prestress to anchor jacked piles
CN102561721A (en) * 2012-02-29 2012-07-11 化学工业岩土工程有限公司 Building jacking deviation rectifying method
CN103321261A (en) * 2013-07-18 2013-09-25 张继红 Construction method for directional expansion-rise deviation rectification
CN104047305A (en) * 2014-05-26 2014-09-17 江苏鼎泰工程材料有限公司 Fast repairing method of house sinking
CN105839946A (en) * 2016-03-31 2016-08-10 山东建筑大学 Brick-concrete structure building lifting add-layer method
CN107035159A (en) * 2017-05-05 2017-08-11 山东建筑大学 A kind of method suitable for frame structure isolated footing building underground increasing layer
CN107842046A (en) * 2017-11-27 2018-03-27 杨孝 A kind of strengthening of foundation error-correction structure and the method for strengthening of foundation correction

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
何国平: "上海软土地基建筑物纠倾加固方法及工程实例分析", 《CNKI优秀硕士学位论文全文库》 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2021093732A1 (en) * 2019-11-12 2021-05-20 山东建筑大学 Displacement inclination rectification method for building

Similar Documents

Publication Publication Date Title
CN110080318B (en) Deviation rectifying method for local settlement of pile foundation building
CN108708409A (en) A kind of frame structure building lifting correcting method
CN103452147B (en) Self-balancing anchor counterweight broken pile forced-landing tilt correcting method
CN102352632B (en) Anchor rod sheet pile combined structure and method for reinforcing high filling body on one side of slope
CN108086340A (en) Open caisson construction structure and its construction method
CN108999226A (en) Rotation displacement frame structure building correcting method
CN105887811A (en) Ultra-deep soft soil pile integral construction method based on high-precision information monitoring
CN108999225A (en) Rotation displacement building with brick-concrete structure correcting method
CN108824445A (en) A kind of foundation pit construction engineering method with enclosure-type mud equilibrium function building enclosure
CN108643255A (en) Frame structure building lifting inclination-correcting method
CN108425386A (en) Frame structure building promotes correcting method
CN205152942U (en) Novel combination steel sheet pile and be applied to construction leading truck of this steel sheet pile
CN110485424A (en) Deep basal pit underground structure contrary sequence method steel pipe column positioning device and positioning construction method
CN109610446A (en) A kind of borehole filling pile cage of reinforcement and anti-floating cage method
CN109706987A (en) A kind of frame structure building inside lifting inclination-correcting method
CN206128080U (en) A support system for subway foundation pit
CN109869009B (en) Inclination correcting method for broken columns of frame structure building
CN107142955A (en) A kind of open caisson construction method
CN111851611A (en) Application of spiral square pipe pile in preventing and treating foundation settlement and construction method thereof
CN110453734A (en) A kind of air bag jacking building inclination rectification method
CN105256848B (en) Coordinating and controllable soil digging and slant rectifying method in roadway
CN114319323A (en) Construction method of upright post pile
CN208088318U (en) Stake top counterfort wall supporting construction
CN106801384A (en) Assembled steel reinforced concrete aliform type culvert opening and construction method
CN218479178U (en) Anti-skidding supporting system of inclined strut

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20180821