WO2021093732A1 - Displacement inclination rectification method for building - Google Patents
Displacement inclination rectification method for building Download PDFInfo
- Publication number
- WO2021093732A1 WO2021093732A1 PCT/CN2020/127864 CN2020127864W WO2021093732A1 WO 2021093732 A1 WO2021093732 A1 WO 2021093732A1 CN 2020127864 W CN2020127864 W CN 2020127864W WO 2021093732 A1 WO2021093732 A1 WO 2021093732A1
- Authority
- WO
- WIPO (PCT)
- Prior art keywords
- displacement
- frame column
- building
- foundation
- frame
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Ceased
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G23/00—Working measures on existing buildings
- E04G23/06—Separating, lifting, removing of buildings; Making a new sub-structure
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D35/00—Straightening, lifting, or lowering of foundation structures or of constructions erected on foundations
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G23/00—Working measures on existing buildings
- E04G23/06—Separating, lifting, removing of buildings; Making a new sub-structure
- E04G23/065—Lifting of buildings
Definitions
- the application relates to the field of building tilt correction, and in particular to a method for building tilt correction.
- Building tilt correction refers to the uneven settlement of the foundation due to the foundation, foundation or the building itself, and the upper structure of the building tilts away from the vertical position.
- the tilt of the building exceeds the requirements of the relevant national regulations, it is serious Measures taken to ensure the safety of the building and restore its normal use function when it affects the safety and normal use of the building.
- tilt correction examples include: stacking pressure correction method, soil excavation correction method, water immersion correction method, soil excavation and irrigation method, etc. Most of these methods increase the settlement on the side of the building where the settlement is small, so as to adjust the differential settlement of the entire foundation. So as to achieve the purpose of correcting the tilt of the building. These methods need to estimate the amount of settlement, and carry out a large number of theoretical calculations on the amount of soil digging and irrigation.
- the purpose of this application is to provide a method for building displacement correction in view of the defects of the prior art.
- the pillars of the building are respectively built on the base, and the displacement rails of different heights are equipped according to the settlement amount. In the process of displacement, it is raised to the corresponding height at the same horizontal distance, and finally reaches the process of lifting each building column to the same horizontal position to complete the tilt correction process.
- a method for building displacement correction including the following steps:
- an inclined linear displacement track is arranged along the displacement direction, and the highest point of each displacement track is flush with the foundation corresponding to the frame column with the smallest settlement;
- a roller is arranged on the displacement track corresponding to each frame column, and a channel steel parallel to the extension direction of the displacement track is arranged above the roller, and concrete is poured on the channel steel to form an underpinning beam;
- the underpinning beam is connected with the steel bars pre-implanted in the frame column to be fixedly connected to the building as a whole, and the underpinning beams corresponding to all frame columns in the same row are fixed as a whole through the connecting beam;
- a sliding rail is arranged on the longitudinal side of the frame column, the sliding rail is fitted with a sliding block that freely slides along the longitudinal direction of the sliding rail, and the sliding block is connected with a driving mechanism;
- the drive mechanism horizontally drives the slider to drive the frame column to move along the shift track until the end of the shift;
- each frame column corresponds to two displacement rails, and the two displacement rails are respectively located on both sides of the frame column and clamp the corresponding frame column.
- a steel plate is arranged on the top surface of the displacement rail to cooperate with the roller to realize relative rolling.
- the lifting height of the displacement rail is equal to the settlement difference between the corresponding frame column and the frame column with the smallest settlement amount.
- each frame column corresponds to two underpinning beams parallel to the displacement track, and the two underpinning beams are respectively located on both sides of the frame column and clamp the corresponding frame column.
- channel steel is used as the bottom template of the underpinning beam to pour concrete to form the underpinning beam, and the underpinning beam contacts the roller through the channel steel at the bottom.
- sliding rail is arranged on the side of the underpinning beam, and adjacent sliding blocks are connected, so that all the sliding blocks are kept at the same level.
- the driving mechanism includes a traction device, and the output end of the traction device is connected to the sliding block, and the output end and the sliding block are kept at the same level; during the driving process of the traction device, the sliding block slides along with the climbing of the frame column.
- roller is also fitted with a stopper for limiting the rolling of the roller when the building stops moving.
- the section of the frame column is aligned with the foundation of the new site, the butt joint is formed by welding longitudinal steel bars, and concrete is poured to form a support.
- the frame columns are configured with corresponding displacement rails, so that they can be towed and displaced at the same time, so that the frame columns with different settlement differences are raised at the same time, while reducing the settlement difference and realizing tilt correction, compared with the traditional one-by-one lifting Or forced landing method to correct the tilt, the efficiency is higher, and the simultaneous operation can avoid the increase of the settlement difference between adjacent frame columns, and the one-by-one jacking or forced landing will cause the settlement difference of adjacent columns to further increase, resulting in further structural damage. Damage; the use of shifting tilt correction frame column settlement difference is in a state of continuous reduction until the level is equal, the tilt correction process is safer, and the structure of the building can be better protected;
- the sliding block and the sliding rail are used to cooperate with each other to offset the vertical displacement of the frame column during the lifting process, so that the traction force can always be kept perpendicular to the frame column, and all the blocks are At the same level, the positions of the columns can be mutually restricted to avoid the problem of bending of a single column during the displacement process; compared with the traditional method of continuous rope pulling and supporting beam to move, a slider is used By offsetting the vertical displacement change of the column lifting, the traction structure can always maintain the output state and avoid the problem that the continuous output of the lifting rope is too long due to the height.
- Figure 1 is a side elevation view of the foundation with uneven settlement before tilt correction in Example 1 of the application;
- Figure 2 is a basic plan view of the old site before tilt correction in Example 1 of the application;
- Figure 3 is a side elevation view of the foundation of the old site exposed by the excavation of the foundation soil in Example 1 of the application;
- Fig. 4 is a side elevation view of the foundation of the new site constructed in the shift direction in Example 1 of the application;
- Fig. 5 is a basic plan view of the construction of a new site in the displacement direction in Example 1 of the application;
- Fig. 6 is a side elevation view of the construction of the displacement track in Example 1 of the application;
- Fig. 7 is a plan view of the construction of the displacement track according to the embodiment 1 of the application.
- Fig. 8 is a side elevation view of a roller laid on the top surface of the shift track in Example 1 of the application;
- FIG. 9 is a plan view of laying rollers on the top surface of the displacement track in Embodiment 1 of the application.
- Figure 10 is a side elevation view of the underpinning beam and the connecting beam constructed in Example 1 of the application;
- Figure 11 is a plan view of the construction of underpinning beams and connecting beams in Example 1 of the application;
- Fig. 12 is a side elevation view of the traction equipment and the sliding rail-sliding block coordination provided in the embodiment 1 of the application;
- Fig. 13 is a plan view of setting traction equipment and sliding rail-sliding block cooperation according to embodiment 1 of the application;
- Fig. 14 is a side elevational view of the embodiment 1 of the application when the frame column is towed and moved to directly above the independent foundation of the new site;
- Fig. 15 is a plan view of embodiment 1 of the application when the frame column is towed and displaced directly above the independent foundation of the new site;
- Figure 16 is a side elevation view of the embodiment 1 of the application connecting the pillars of the building to the independent foundation of the new site;
- Figure 17 is a side elevation view of the foundation soil backfill after removing the underpinning beams and rollers in Example 1 of the application;
- Figure 18 is a plan view of the backfill of the foundation soil after removing the underpinning beam and rollers in Example 1 of the application;
- 19 is a schematic diagram of the iron wedge fixing the roller in the embodiment 1 of the application.
- FIG. 20 is a schematic diagram of the process of moving the sliding rail and the sliding block in cooperation with the frame column in Embodiment 1 of the present application.
- the common methods of tilt correction in the prior art such as stacking pressure correction method, soil digging correction method, immersion correction method, soil digging and irrigation method, etc.
- the problem is that most of these methods increase the settlement on the side of the building where the settlement is small, so as to adjust the differential settlement of the entire foundation. So as to achieve the purpose of correcting the tilt of the building.
- FIGS. 1 to 20 a method for building displacement correction is proposed, which is particularly suitable for situations where there are multiple rows of frame columns and the settlement of different rows of frame columns is inconsistent.
- each frame column 3 from the corresponding old site foundation to the new site foundation 6, an inclined linear displacement track is arranged along the displacement direction, and the highest point of each displacement track is flush with the foundation corresponding to the frame pillar with the smallest settlement amount ;
- a roller 9 is arranged on the displacement track corresponding to each frame column, and a channel steel parallel to the extension direction of the displacement track is arranged above the roller, and concrete is poured on the channel steel to form an underpinning beam;
- the underpinning beam is connected with the steel bars pre-implanted in the frame column to be fixedly connected with the building as a "chassis" for the displacement of the building.
- the underpinning beams corresponding to all frame columns in the same row are fixedly connected by the connecting beam 12
- a sliding rail is arranged on the longitudinal side of the frame column, the sliding rail is fitted with a sliding block that freely slides along the longitudinal direction of the sliding rail, and the sliding block is connected with a driving mechanism;
- the drive mechanism horizontally drives the slider to drive the frame column to move along the shift track until the end of the shift;
- the settlement of multiple rows of columns can be corrected.
- Different rows of columns with different settlements are equipped with shifting rails with different lifting heights.
- the vertical of the frame columns is corrected.
- the height is changed to form a targeted height increase, and finally all the frame columns are at the same level, and targeted correction is achieved.
- the foundation corresponding to the row of frame columns with the smallest amount of settlement is used as the reference, that is, the first original site foundation 1, and other parts with a settlement greater than the row of frame columns correspond to the second original site foundation 2.
- the height of the foundation of the first original site is greater than the height of the foundation of the second original site; after the displacement, the height of the frame column with the smallest settlement amount remains unchanged, and the other frame columns are used as a benchmark to upgrade to the frame column with the smallest settlement amount Corresponding level, complete tilt correction.
- the correspondingly arranged second shift track 8 is an inclined linear shift track
- the side surface is matched with the horizontally arranged first underpinning beam 10
- the frame column matching the second shift rail is matched with the side surface being inclined.
- the second underpinning beam 11 ensures that the underpinning beam is parallel to the displacement track.
- the driving mechanism includes a traction device, the output end of the traction device is connected to the slider, and the output end and the slider are kept at the same level; during the driving of the traction device, The sliding block slides along the sliding rail as the frame column climbs;
- the traction device 14 adopts a through jack.
- a reaction pier 13 is provided on one side of the building.
- the through jack is fitted on the reaction pier.
- the output end of the through jack is connected to the slider through a traction cable 15 so that the slider passes through the slide rail. Apply horizontal thrust to the frame column;
- the sliding block and the sliding rail are used together to offset the vertical displacement of the frame column during the lifting process of the frame column by sliding up and down, so that the traction force can always be kept vertical to the frame column, and all the blocks are at the same level.
- the height can restrict the positions of the columns to each other, avoiding the problem of single column bending during the displacement process; compared with the traditional method of continuous rope pulling underpinning beams, the slider is used to offset the vertical column lifting.
- the change in direction displacement can keep the traction structure always in the state of output, avoiding the problem that the height of the lifting rope is too long and cannot be continuously output.
- each frame column corresponds to two shift rails, and the two shift rails are respectively located on both sides of the frame column and clamp the corresponding frame column; the top surface of the shift rail A steel plate is arranged to cooperate with the roller to realize relative rolling; the lifting height of the displacement rail is equal to the settlement difference between the corresponding frame column and the frame column with the smallest settlement amount;
- each frame column corresponds to two underpinning beams parallel to the displacement track, and the two underpinning beams are respectively located on both sides of the frame column and clamp the corresponding frame column; the channel steel
- concrete is poured to form the underpinning beam, and the underpinning beam contacts the roller through the channel steel at the bottom.
- the displacement rails are located on both sides of the corresponding frame columns, and the underpinning beams are also located on both sides of the corresponding frame columns. That is, the underpinning beams are located directly above the shifting track, and the underpinning beams carry the entire building through the columns.
- the weight After the weight is weighed, it can be vertically transferred to the shift rail through the roller and steel plate, and then transferred to the ground by the shift rail; if the underpinning beam and the shift rail are staggered, the force received by the load beam will pass through the roller After the axial transmission of the steel plate reaches the steel plate and the displacement track, the supporting force and the bearing point are not collinear, resulting in shear stress, resulting in the bending of the roller; the above-mentioned problems are avoided through the transmission of the vertical force;
- Two underpinning beams are used to clamp and fix the underpinning beams from both sides of the frame column.
- the underpinning beams are supported by the two tracks arranged below to avoid the deviation of the output on both sides of the column.
- the force of the beam is transmitted vertically downwards, that is, underpinning beam-roller-steel plate-track foundation-foundation, to avoid shear stress on the roller, causing the roller to bend, thereby improving the stability of the entire displacement process Sex.
- the stress of the roller can be indirectly transmitted through the steel plate, avoiding the problem of concrete crushing caused by the line contact between the roller and the top surface of the track, and improving the operation of the roller.
- Smoothness; the upper and lower contacts of the roller are channel steel and steel plate respectively, which ensure the stability of their contact and the good transmission of the rolling process; in addition, it can also avoid the concrete being crushed by the line contact between the roller and other planes. This problem improves the safety during operation and ensures the integrity of the track and the underpinning beam.
- the roller rolls out from the end of the underpinning beam close to the starting point of the displacement, and the rolled out roller is moved to the end of the underpinning beam close to the end of the shift and fills in the underpinning beam and steel plate.
- the gap between them forms a roller cycle to drive the building to move continuously; the roller is also matched with a stopper to limit the rolling of the roller when the building stops moving.
- the stop When the building is moved to a new site or needs to be temporarily stopped in the middle of the displacement, the stop must be driven behind the roller to prevent the building from retreating along the displacement track; in this embodiment, the stop is an iron wedge 17.
- the frame column is configured with the corresponding displacement track to make it carry out traction and displacement at the same time, so that the frame columns with different settlement differences are lifted at the same time, and the settlement difference is reduced at the same time, and the tilt correction is realized.
- the method is more efficient, and the simultaneous operation can avoid the increase in the settlement difference of adjacent frame columns, and the successive jacking or forced landing will cause the settlement difference of adjacent columns to further increase, causing further damage to the structure;
- the displacement correction frame column settlement difference is in a state of continuously decreasing until the level height is equal, the tilt correction process is safer, and the structure of the building can be better protected.
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Structural Engineering (AREA)
- Civil Engineering (AREA)
- Chemical & Material Sciences (AREA)
- Chemical Kinetics & Catalysis (AREA)
- Electrochemistry (AREA)
- Mechanical Engineering (AREA)
- Paleontology (AREA)
- Mining & Mineral Resources (AREA)
- General Engineering & Computer Science (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Life Sciences & Earth Sciences (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
- Foundations (AREA)
Abstract
Description
本申请涉及建筑物纠倾领域,具体涉及一种建筑物移位纠倾方法。The application relates to the field of building tilt correction, and in particular to a method for building tilt correction.
建筑物纠倾系指建筑物由于地基、基础或建筑物本身的某种原因造成基础不均匀沉降,其上部结构偏离竖直位置而发生倾斜,当建筑物的倾斜程度超过国家有关规范要求、严重影响建筑物安全及正常使用时所采取的以期确保建筑物安全及恢复其正常使用功能的纠倾扶正、加固稳定的措施。Building tilt correction refers to the uneven settlement of the foundation due to the foundation, foundation or the building itself, and the upper structure of the building tilts away from the vertical position. When the tilt of the building exceeds the requirements of the relevant national regulations, it is serious Measures taken to ensure the safety of the building and restore its normal use function when it affects the safety and normal use of the building.
发明人发现,目前纠倾的常用方法有:堆载加压纠倾法、掏土纠倾法、浸水纠倾法和掏土灌水法等。这些方法多是在建筑物沉降小的一侧增大沉降量,借以调整整个基础的差异沉降。从而起到矫正建筑物倾斜的目的。这些方法需要预估沉降量,对掏土量、灌水量进行大量的理论计算,经验性很强,理论也不成熟;对于现有技术中申请号为201810821610.6的专利“旋转移位框架结构建筑物纠倾法”和申请号为201810821600.2的专利“旋转移位砖混结构建筑物纠倾法”,提出了利用旋转移位技术对建筑物纠倾的思路,但该技术针对的是建筑物的整体倾斜,而对于具有多排框架柱的建筑物,在多排柱沉降不一致的情况时,上述旋转纠倾方法并不适用。The inventor found that the current common methods for tilt correction include: stacking pressure correction method, soil excavation correction method, water immersion correction method, soil excavation and irrigation method, etc. Most of these methods increase the settlement on the side of the building where the settlement is small, so as to adjust the differential settlement of the entire foundation. So as to achieve the purpose of correcting the tilt of the building. These methods need to estimate the amount of settlement, and carry out a large number of theoretical calculations on the amount of soil digging and irrigation. The experience is very strong, and the theory is not mature; for the patent application number 201810821610.6 in the prior art, the "rotation shift frame structure building" Tilt correction method” and the patent “Rotational displacement correction method of brick-concrete structure building” with the application number of 201810821600.2, proposed the idea of using the rotation displacement technology to correct the tilt of the building, but the technology is aimed at the whole building Inclined, and for buildings with multiple rows of frame columns, the above-mentioned rotation correction method is not applicable when the settlement of the multiple rows of columns is inconsistent.
发明内容Summary of the invention
本申请的目的是针对现有技术存在的缺陷,提供一种建筑物移位纠倾方法,将建筑物的立柱分别进行建立底座,根据沉降量配以不同高度的移位轨道,在将建筑物移位的过程中,使其在相同的水平距离上提升相应的高度,最终达到将各 个建筑立柱提升至相同水平位置完成纠倾的过程。The purpose of this application is to provide a method for building displacement correction in view of the defects of the prior art. The pillars of the building are respectively built on the base, and the displacement rails of different heights are equipped according to the settlement amount. In the process of displacement, it is raised to the corresponding height at the same horizontal distance, and finally reaches the process of lifting each building column to the same horizontal position to complete the tilt correction process.
为了实现上述目的,采用以下技术方案:In order to achieve the above objectives, the following technical solutions are adopted:
一种建筑物移位纠倾方法,包括以下步骤:A method for building displacement correction, including the following steps:
确定沉降量最小的一排框架柱,获取其他排框架柱与该排框架柱的沉降差;Determine the row of frame columns with the smallest settlement, and obtain the settlement difference between other rows of frame columns and the row of frame columns;
开挖地基,露出旧址基础,并确立移位终点,布置新址基础;Excavate the foundation to expose the foundation of the old site, establish the end of the displacement, and arrange the foundation of the new site;
对应每根框架柱,从对应的旧址基础到新址基础,沿移位方向均布设倾斜直线移位轨道,每条移位轨道的最高点均与沉降量最小的框架柱对应的基础平齐;Corresponding to each frame column, from the corresponding old site foundation to the new site foundation, an inclined linear displacement track is arranged along the displacement direction, and the highest point of each displacement track is flush with the foundation corresponding to the frame column with the smallest settlement;
在每根框架柱对应的移位轨道上布置滚轴,并在滚轴上方布置平行于移位轨道延伸方向的槽钢,对槽钢浇注混凝土形成托换梁;A roller is arranged on the displacement track corresponding to each frame column, and a channel steel parallel to the extension direction of the displacement track is arranged above the roller, and concrete is poured on the channel steel to form an underpinning beam;
托换梁连接预先植入框架柱内的钢筋,与建筑物固连为一体,同一排的所有框架柱对应的托换梁通过连系梁固连为一体;The underpinning beam is connected with the steel bars pre-implanted in the frame column to be fixedly connected to the building as a whole, and the underpinning beams corresponding to all frame columns in the same row are fixed as a whole through the connecting beam;
在框架柱纵向侧面布置滑轨,所述滑轨上配合有沿滑轨纵向自由滑动的滑块,滑块连接有驱动机构;A sliding rail is arranged on the longitudinal side of the frame column, the sliding rail is fitted with a sliding block that freely slides along the longitudinal direction of the sliding rail, and the sliding block is connected with a driving mechanism;
截断框架柱与旧址基础的连接,使建筑物的重量完全由移位轨道支撑;Cut off the connection between the frame column and the foundation of the old site, so that the weight of the building is completely supported by the shift rail;
驱动机构水平驱动滑块从而带动框架柱沿移位轨道移动,直至移位终点;The drive mechanism horizontally drives the slider to drive the frame column to move along the shift track until the end of the shift;
所有框架柱的均处于同一水平高度,完成纠倾,将框架柱与新址基础对应,并对接支撑;All the frame columns are at the same level, the tilt correction is completed, the frame columns are aligned with the foundation of the new site, and they are butt-supported;
待对接支撑稳定后,拆除滑轨-滑块、托换梁及滚轴,恢复地面。After the butt support is stable, remove the slide rail-slider, underpinning beam and roller, and restore the ground.
进一步地,每根框架柱均对应两条移位轨道,两条移位轨道分别位于框架柱的两侧,夹住对应的框架柱。Further, each frame column corresponds to two displacement rails, and the two displacement rails are respectively located on both sides of the frame column and clamp the corresponding frame column.
进一步地,所述移位轨道的顶面布置有钢板,用于配合滚轴实现相对滚动。Further, a steel plate is arranged on the top surface of the displacement rail to cooperate with the roller to realize relative rolling.
进一步地,所述移位轨道的抬升高度等于对应框架柱与沉降量最小框架柱的 沉降差值。Further, the lifting height of the displacement rail is equal to the settlement difference between the corresponding frame column and the frame column with the smallest settlement amount.
进一步地,每根框架柱均对应两个平行于移位轨道的托换梁,两个托换梁分别位于框架柱的两侧,夹住对应的框架柱。Further, each frame column corresponds to two underpinning beams parallel to the displacement track, and the two underpinning beams are respectively located on both sides of the frame column and clamp the corresponding frame column.
进一步地,所述的槽钢作为托换梁的底部模板浇注混凝土形成托换梁,托换梁通过底部的槽钢接触滚轴。Further, the channel steel is used as the bottom template of the underpinning beam to pour concrete to form the underpinning beam, and the underpinning beam contacts the roller through the channel steel at the bottom.
进一步地,所述滑轨布置在托换梁的侧面,相邻滑块之间连接,使所有滑块均保持处于同一水平高度。Further, the sliding rail is arranged on the side of the underpinning beam, and adjacent sliding blocks are connected, so that all the sliding blocks are kept at the same level.
进一步地,所述驱动机构包括牵引设备,所述牵引设备的输出端连接滑块,并保持输出端与滑块处于同一水平高度;牵引设备驱动过程中,滑块随框架柱的爬升而沿滑轨滑动。Further, the driving mechanism includes a traction device, and the output end of the traction device is connected to the sliding block, and the output end and the sliding block are kept at the same level; during the driving process of the traction device, the sliding block slides along with the climbing of the frame column. The rail slides.
进一步地,滚轴还配合有止挡,用于在建筑物停止移动时限定滚轴的滚动。Further, the roller is also fitted with a stopper for limiting the rolling of the roller when the building stops moving.
进一步地,建筑物移位到终点后,将框架柱的截断面与新址基础对齐,通过焊接纵向钢筋形成对接,并浇筑混凝土,形成支撑。Furthermore, after the building is shifted to the end point, the section of the frame column is aligned with the foundation of the new site, the butt joint is formed by welding longitudinal steel bars, and concrete is poured to form a support.
与现有技术相比,本申请具有的优点和积极效果是:Compared with the prior art, the advantages and positive effects of this application are:
(1)通过浇筑斜向托换梁的技术,使得多排柱沉降得以纠正,对不同沉降量的不同排立柱配以不同提升高度的移位轨道,在水平移位的过程中,对框架柱的竖直高度进行改变,形成针对性的高度提升,最终实现所有的框架柱均处于同一水平高度,实现了针对性的纠偏;(1) By pouring the oblique underpinning beam technology, the settlement of multiple rows of columns can be corrected. Different rows of columns with different settlements are equipped with shifting tracks with different lifting heights. In the process of horizontal shifting, the frame column The vertical height of the frame is changed to form a targeted height increase, and finally all the frame columns are at the same level, and targeted deviation correction is achieved;
(2)采用将框架柱配置对应的移位轨道,使其同时进行牵引移位,使得不同沉降差的框架柱同时提升,同时减少沉降差,实现纠倾,相较于传统的逐根顶升或迫降的方法纠倾,效率更高,并且同时操作能够避免相邻框架柱沉降差的增大,而逐根顶升或迫降则会引起相邻立柱沉降差的进一步增大,造成结构进一步 的损伤;采用移位纠倾框架柱沉降差处于不断减小直至水平高度相等的状态,纠倾过程更为安全,对建筑物的结构能够更好的进行保护;(2) The frame columns are configured with corresponding displacement rails, so that they can be towed and displaced at the same time, so that the frame columns with different settlement differences are raised at the same time, while reducing the settlement difference and realizing tilt correction, compared with the traditional one-by-one lifting Or forced landing method to correct the tilt, the efficiency is higher, and the simultaneous operation can avoid the increase of the settlement difference between adjacent frame columns, and the one-by-one jacking or forced landing will cause the settlement difference of adjacent columns to further increase, resulting in further structural damage. Damage; the use of shifting tilt correction frame column settlement difference is in a state of continuous reduction until the level is equal, the tilt correction process is safer, and the structure of the building can be better protected;
(3)采用滑块和滑轨配合的方式,利用滑块的上下滑动抵消框架柱提升过程中竖向的位移变化,从而使牵引力能够始终与框架柱保持垂直状态,并且,所有的滑块均处于同一水平高度,能够对立柱之间的位置进行相互约束,避免移位过程中出现单根立柱折弯的问题;相较于传统的绳索连续牵拉托换梁进行移动的方式,采用滑块进行抵消立柱提升竖向位移变化,能够使牵引结构始终保持出力状态,避免因高度提升绳索过长而无法连续出力的问题。(3) The sliding block and the sliding rail are used to cooperate with each other to offset the vertical displacement of the frame column during the lifting process, so that the traction force can always be kept perpendicular to the frame column, and all the blocks are At the same level, the positions of the columns can be mutually restricted to avoid the problem of bending of a single column during the displacement process; compared with the traditional method of continuous rope pulling and supporting beam to move, a slider is used By offsetting the vertical displacement change of the column lifting, the traction structure can always maintain the output state and avoid the problem that the continuous output of the lifting rope is too long due to the height.
构成本申请的一部分的说明书附图用来提供对本申请的进一步理解,本申请的示意性实施例及其说明用于解释本申请,并不构成对本申请的不当限定。The drawings of the specification forming a part of the application are used to provide a further understanding of the application, and the exemplary embodiments and descriptions of the application are used to explain the application, and do not constitute an improper limitation of the application.
图1为本申请实施例1纠倾前基础出现不均匀沉降而倾斜的侧立面图;Figure 1 is a side elevation view of the foundation with uneven settlement before tilt correction in Example 1 of the application;
图2为本申请实施例1纠倾前旧址基础平面图;Figure 2 is a basic plan view of the old site before tilt correction in Example 1 of the application;
图3为本申请实施例1地基土开挖暴露旧址基础的侧立面图;Figure 3 is a side elevation view of the foundation of the old site exposed by the excavation of the foundation soil in Example 1 of the application;
图4为本申请实施例1移位方向建造新址基础侧立面图;Fig. 4 is a side elevation view of the foundation of the new site constructed in the shift direction in Example 1 of the application;
图5为本申请实施例1移位方向建造新址基础平面图;Fig. 5 is a basic plan view of the construction of a new site in the displacement direction in Example 1 of the application;
图6为本申请实施例1建造移位轨道的侧立面图;Fig. 6 is a side elevation view of the construction of the displacement track in Example 1 of the application;
图7为本申请实施例1建造移位轨道的平面图;Fig. 7 is a plan view of the construction of the displacement track according to the embodiment 1 of the application;
图8为本申请实施例1移位轨道顶面铺设滚轴的侧立面图;Fig. 8 is a side elevation view of a roller laid on the top surface of the shift track in Example 1 of the application;
图9为本申请实施例1移位轨道顶面铺设滚轴的平面图;FIG. 9 is a plan view of laying rollers on the top surface of the displacement track in Embodiment 1 of the application; FIG.
图10为本申请实施例1建造托换梁和连系梁的侧立面图;Figure 10 is a side elevation view of the underpinning beam and the connecting beam constructed in Example 1 of the application;
图11为本申请实施例1建造托换梁和连系梁的平面图;Figure 11 is a plan view of the construction of underpinning beams and connecting beams in Example 1 of the application;
图12为本申请实施例1设置牵引设备、滑轨-滑块配合的侧立面图;Fig. 12 is a side elevation view of the traction equipment and the sliding rail-sliding block coordination provided in the embodiment 1 of the application;
图13为本申请实施例1设置牵引设备、滑轨-滑块配合的平面图;Fig. 13 is a plan view of setting traction equipment and sliding rail-sliding block cooperation according to embodiment 1 of the application;
图14为本申请实施例1将框架柱牵引移位至新址独立基础正上方的侧立面图;Fig. 14 is a side elevational view of the embodiment 1 of the application when the frame column is towed and moved to directly above the independent foundation of the new site;
图15为本申请实施例1将框架柱牵引移位至新址独立基础正上方的平面图;Fig. 15 is a plan view of embodiment 1 of the application when the frame column is towed and displaced directly above the independent foundation of the new site;
图16为本申请实施例1将建筑物的柱与新址的独立基础相连的侧立面图;Figure 16 is a side elevation view of the embodiment 1 of the application connecting the pillars of the building to the independent foundation of the new site;
图17为本申请实施例1去除托换梁和滚轴后地基土回填的侧立面图;Figure 17 is a side elevation view of the foundation soil backfill after removing the underpinning beams and rollers in Example 1 of the application;
图18为本申请实施例1去除托换梁和滚轴后地基土回填的平面图;Figure 18 is a plan view of the backfill of the foundation soil after removing the underpinning beam and rollers in Example 1 of the application;
图19为本申请实施例1铁楔块固定滚轴的示意图;19 is a schematic diagram of the iron wedge fixing the roller in the embodiment 1 of the application;
图20位本申请实施例1滑轨和滑块配合框架柱移动的过程示意图。FIG. 20 is a schematic diagram of the process of moving the sliding rail and the sliding block in cooperation with the frame column in Embodiment 1 of the present application.
其中,1、第一原址基础,2、第二原址基础,3、框架柱,4、框架梁板,5、地基,6、新址基础,7、第一移位轨道,8、第二移位轨道,9、滚轴,10、第一托换梁,11、第二托换梁,12、连系梁,13、反力墩,14、牵引设备,15、牵引索,16、支撑,17、铁楔块。Among them, 1, the first original site foundation, 2, the second original site foundation, 3, the frame column, 4, the frame beam slab, 5, the foundation, 6, the new site foundation, 7, the first displacement track, 8, the second displacement Track, 9, roller, 10, first underpinning beam, 11, second underpinning beam, 12, connecting beam, 13, reaction pier, 14, traction equipment, 15, traction rope, 16, support, 17 , Iron wedges.
应该指出,以下详细说明都是例示性的,旨在对本申请提供进一步地说明。除非另有指明,本文使用的所有技术和科学术语具有与本申请所属技术领域的普通技术人员通常理解的相同含义。It should be pointed out that the following detailed descriptions are all illustrative, and are intended to provide further explanations for this application. Unless otherwise specified, all technical and scientific terms used herein have the same meaning as commonly understood by those of ordinary skill in the technical field to which this application belongs.
需要注意的是,这里所使用的术语仅是为了描述具体实施方式,而非意图限制根据本申请的示例性实施方式。如在这里所使用的,除非上下文另外明确指出,否则单数形式也意图包括复数形式,此外,还应当理解的是,当在本说明书中使用术语“包含”和/或“包括”时,其指明存在特征、步骤、操作、器件、组件和/或 它们的组合;It should be noted that the terms used here are only for describing specific embodiments, and are not intended to limit the exemplary embodiments according to the present application. As used herein, unless the context clearly indicates otherwise, the singular form is also intended to include the plural form. In addition, it should also be understood that when the terms "comprising" and/or "including" are used in this specification, they indicate There are features, steps, operations, devices, components, and/or combinations thereof;
为了方便叙述,本申请中如果出现“上”、“下”、“左”“右”字样,仅表示与附图本身的上、下、左、右方向一致,并不对结构起限定作用,仅仅是为了便于描述本发明和简化描述,而不是指示或暗示所指的设备或元件必须具有特定的方位,以特定的方位构造和操作,因此不能理解为对本申请的限制。For the convenience of description, if the words "upper", "lower", "left" and "right" appear in this application, they only mean that they are consistent with the upper, lower, left, and right directions of the drawing itself, and do not limit the structure, but only It is for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation of the present application.
术语解释部分:本申请中的术语“安装”、“相连”、“连接”、“固定”等术语应做广义理解,例如,可以是固定连接,也可以是可拆卸连接,或为一体;可以是机械连接,也可以是电连接,可以是直接连接,也可以是通过中间媒介间接相连,可以是两个元件内部连接,或者两个元件的相互作用关系,对于本领域的普通技术人员而言,可以根据具体情况理解上述术语在本发明的具体含义。Term explanation part: The terms "installed", "connected", "connected", "fixed" and other terms in this application should be understood in a broad sense. For example, it can be a fixed connection, a detachable connection, or a whole; It can be a mechanical connection, an electrical connection, a direct connection, or an indirect connection through an intermediate medium, an internal connection between two components, or an interaction relationship between two components. For those of ordinary skill in the art The specific meaning of the above terms in the present invention can be understood according to the specific situation.
正如背景技术中所介绍的,现有技术中纠倾的常用方法如堆载加压纠倾法、掏土纠倾法、浸水纠倾法和掏土灌水法等,在实际施工中存在较多问题,这些方法多是在建筑物沉降小的一侧增大沉降量,借以调整整个基础的差异沉降。从而起到矫正建筑物倾斜的目的。这些方法需要预估沉降量,对掏土量、灌水量进行大量的理论计算,经验性很强,理论也不成熟;对于现有技术中提出的利用旋转移位技术对建筑物纠倾的思路,但该技术针对的是建筑物的整体倾斜,而对于具有多排框架柱的建筑物,在多排柱沉降不一致的情况时,上述旋转纠倾方法并不适用;针对上述技术问题,本申请提出了一种建筑物移位纠倾方法。As described in the background art, the common methods of tilt correction in the prior art, such as stacking pressure correction method, soil digging correction method, immersion correction method, soil digging and irrigation method, etc., exist in actual construction. The problem is that most of these methods increase the settlement on the side of the building where the settlement is small, so as to adjust the differential settlement of the entire foundation. So as to achieve the purpose of correcting the tilt of the building. These methods need to estimate the amount of settlement, and carry out a large number of theoretical calculations on the amount of soil digging and irrigation, which are very empirical and the theory is not mature; for the idea of using the rotation displacement technology to correct the tilt of the building proposed in the prior art , But this technology is aimed at the overall tilt of the building, and for buildings with multiple rows of frame columns, the above-mentioned rotation correction method is not applicable when the settlement of the multiple rows of columns is inconsistent; in view of the above technical problems, this application A method of building displacement correction is proposed.
实施例1Example 1
本申请的一种典型的实施方式中,如图1-图20所示,提出了一种建筑物移位纠倾方法,特别适用于具有多排框架柱且不同排框架柱沉降不一致的情况。In a typical implementation of the present application, as shown in FIGS. 1 to 20, a method for building displacement correction is proposed, which is particularly suitable for situations where there are multiple rows of frame columns and the settlement of different rows of frame columns is inconsistent.
具体过程如下:The specific process is as follows:
确定沉降量最小的一排框架柱,获取其他排框架柱与该排框架柱的沉降差;Determine the row of frame columns with the smallest settlement, and obtain the settlement difference between other rows of frame columns and the row of frame columns;
开挖地基5,露出旧址基础,并确立移位终点,布置新址基础;Excavate
对应每根框架柱3,从对应的旧址基础到新址基础6,沿移位方向均布设倾斜直线移位轨道,每条移位轨道的最高点均与沉降量最小的框架柱对应的基础平齐;Corresponding to each
在每根框架柱对应的移位轨道上布置滚轴9,并在滚轴上方布置平行于移位轨道延伸方向的槽钢,对槽钢浇注混凝土形成托换梁;A roller 9 is arranged on the displacement track corresponding to each frame column, and a channel steel parallel to the extension direction of the displacement track is arranged above the roller, and concrete is poured on the channel steel to form an underpinning beam;
托换梁连接预先植入框架柱内的钢筋,与建筑物固连为一体,作为建筑物移位的“底盘”,同一排的所有框架柱对应的托换梁通过连系梁12固连为一体;The underpinning beam is connected with the steel bars pre-implanted in the frame column to be fixedly connected with the building as a "chassis" for the displacement of the building. The underpinning beams corresponding to all frame columns in the same row are fixedly connected by the connecting
在框架柱纵向侧面布置滑轨,所述滑轨上配合有沿滑轨纵向自由滑动的滑块,滑块连接有驱动机构;A sliding rail is arranged on the longitudinal side of the frame column, the sliding rail is fitted with a sliding block that freely slides along the longitudinal direction of the sliding rail, and the sliding block is connected with a driving mechanism;
截断框架柱与旧址基础的连接,使建筑物的重量完全由移位轨道支撑;Cut off the connection between the frame column and the foundation of the old site, so that the weight of the building is completely supported by the shift rail;
驱动机构水平驱动滑块从而带动框架柱沿移位轨道移动,直至移位终点;The drive mechanism horizontally drives the slider to drive the frame column to move along the shift track until the end of the shift;
移位到新址后,框架柱之间的沉降差和倾斜值已减小到规范允许值之内,所有框架柱的均处于同一水平高度,上部结构弯曲的框架梁板4恢复水平状态,完成纠倾,将框架柱与新址基础对应,并对接支撑16;After moving to the new site, the settlement difference and inclination values between the frame columns have been reduced to within the allowable values of the specifications. All frame columns are at the same level. The
待对接支撑稳定后,拆除滑轨-滑块、托换梁及滚轴,恢复地面。After the butt support is stable, remove the slide rail-slider, underpinning beam and roller, and restore the ground.
通过浇筑斜向托换梁的技术,使得多排柱沉降得以纠正,对不同沉降量的不同排立柱配以不同提升高度的移位轨道,在水平移位的过程中,对框架柱的竖直高度进行改变,形成针对性的高度提升,最终实现所有的框架柱均处于同一水平高度,实现了针对性的纠偏。Through the technology of pouring oblique underpinning beams, the settlement of multiple rows of columns can be corrected. Different rows of columns with different settlements are equipped with shifting rails with different lifting heights. During the horizontal shifting process, the vertical of the frame columns is corrected. The height is changed to form a targeted height increase, and finally all the frame columns are at the same level, and targeted correction is achieved.
具体的,在确定沉降量时,以沉降量最小的一排框架柱对应的基础作为基准, 即第一原址基础1,其他沉降量大于该排框架柱的部分对应的为第二原址基础2,第一原址基础的高度大于第二原址基础的高度;在移位后,沉降量最小的框架柱的高度是不变的,其他的框架柱都以其作为基准,提升到沉降量最小的框架柱对应的水平高度,完成纠倾。Specifically, when determining the amount of settlement, the foundation corresponding to the row of frame columns with the smallest amount of settlement is used as the reference, that is, the first original site foundation 1, and other parts with a settlement greater than the row of frame columns correspond to the second
当然,对应沉降量最小框架柱,其需要进行水平方向的移位,而无需进行竖直方向的提升,引起其对应布置的第一移位轨道7为水平布置的,其他的框架柱在进行水平方向移位的同时,还具有竖直方向上的提升量,因此,对应布置的第二移位轨道8为倾斜的直线移位轨道;Of course, corresponding to the frame column with the smallest amount of settlement, it needs to be displaced in the horizontal direction without lifting in the vertical direction, causing its correspondingly arranged
依次类推,对于配合第一移位轨道的框架柱,其侧面所配合的为水平设置的第一托换梁10,而配合第二移位轨道的框架柱,其侧面所配合的为倾斜设置的第二托换梁11,从而保证托换梁与移位轨道的平行。By analogy, for the frame column matching the first shift rail, the side surface is matched with the horizontally arranged
具体的,对于保证水平移位稳定进行的牵引过程而言,采用了相应的设备及方法,如图20所示,其中,所述滑轨布置在托换梁的侧面,相邻滑块之间连接,使所有滑块均保持处于同一水平高度;所述驱动机构包括牵引设备,所述牵引设备的输出端连接滑块,并保持输出端与滑块处于同一水平高度;牵引设备驱动过程中,滑块随框架柱的爬升而沿滑轨滑动;Specifically, for the traction process to ensure stable horizontal displacement, corresponding equipment and methods are used, as shown in Figure 20, wherein the slide rails are arranged on the side of the underpinning beam and between adjacent sliding blocks Connected to keep all the sliders at the same level; the driving mechanism includes a traction device, the output end of the traction device is connected to the slider, and the output end and the slider are kept at the same level; during the driving of the traction device, The sliding block slides along the sliding rail as the frame column climbs;
所述的牵引设备14采用穿心千斤顶,在建筑物的一侧设置反力墩13,穿心千斤顶配合在反力墩上,其输出端通过牵引索15连接滑块,使滑块通过滑轨对框架柱施加水平推力;The
采用滑块和滑轨配合的方式,利用滑块的上下滑动抵消框架柱提升过程中竖向的位移变化,从而使牵引力能够始终与框架柱保持垂直状态,并且,所有的滑块均处于同一水平高度,能够对立柱之间的位置进行相互约束,避免移位过程中 出现单根立柱折弯的问题;相较于传统的绳索连续牵拉托换梁的方式,采用滑块进行抵消立柱提升竖向位移变化,能够使牵引结构始终保持出力状态,避免因高度提升绳索过长而无法连续出力的问题。The sliding block and the sliding rail are used together to offset the vertical displacement of the frame column during the lifting process of the frame column by sliding up and down, so that the traction force can always be kept vertical to the frame column, and all the blocks are at the same level. The height can restrict the positions of the columns to each other, avoiding the problem of single column bending during the displacement process; compared with the traditional method of continuous rope pulling underpinning beams, the slider is used to offset the vertical column lifting. The change in direction displacement can keep the traction structure always in the state of output, avoiding the problem that the height of the lifting rope is too long and cannot be continuously output.
进一步地,对于移位轨道的配置,每根框架柱均对应两条移位轨道,两条移位轨道分别位于框架柱的两侧,夹住对应的框架柱;所述移位轨道的顶面布置有钢板,用于配合滚轴实现相对滚动;所述移位轨道的抬升高度等于对应框架柱与沉降量最小框架柱的沉降差值;Further, for the configuration of the shift rails, each frame column corresponds to two shift rails, and the two shift rails are respectively located on both sides of the frame column and clamp the corresponding frame column; the top surface of the shift rail A steel plate is arranged to cooperate with the roller to realize relative rolling; the lifting height of the displacement rail is equal to the settlement difference between the corresponding frame column and the frame column with the smallest settlement amount;
对于托换梁的设置,每根框架柱均对应两个平行于移位轨道的托换梁,两个托换梁分别位于框架柱的两侧,夹住对应的框架柱;所述的槽钢作为托换梁的底部模板浇注混凝土形成托换梁,托换梁通过底部的槽钢接触滚轴。For the setting of underpinning beams, each frame column corresponds to two underpinning beams parallel to the displacement track, and the two underpinning beams are respectively located on both sides of the frame column and clamp the corresponding frame column; the channel steel As the bottom template of the underpinning beam, concrete is poured to form the underpinning beam, and the underpinning beam contacts the roller through the channel steel at the bottom.
需要指出的是,移位轨道位于对应框架柱的两侧,托换梁也位于对应框架柱的两侧,即托换梁位于移位轨道的正上方,托换梁通过立柱承接整个建筑物的重量后,能够通过滚轴、钢板竖直传递到移位轨道上,进而由移位轨道传递到地面;若将托换梁和移位轨道错开布置,则承载梁收到的力会通过滚轴的轴向传递后到达钢板和移位轨道,就导致支撑力与承载点不共线,产生剪切应力,造成滚轴的弯曲;而通过竖直方向力的传递,则避免了上述问题;It should be pointed out that the displacement rails are located on both sides of the corresponding frame columns, and the underpinning beams are also located on both sides of the corresponding frame columns. That is, the underpinning beams are located directly above the shifting track, and the underpinning beams carry the entire building through the columns. After the weight is weighed, it can be vertically transferred to the shift rail through the roller and steel plate, and then transferred to the ground by the shift rail; if the underpinning beam and the shift rail are staggered, the force received by the load beam will pass through the roller After the axial transmission of the steel plate reaches the steel plate and the displacement track, the supporting force and the bearing point are not collinear, resulting in shear stress, resulting in the bending of the roller; the above-mentioned problems are avoided through the transmission of the vertical force;
利用两根托换梁从框架柱的两侧对其进行夹持固定,配合下方布置的两条轨道对托换梁进行对应的支撑,在避免立柱两侧出力偏移的同时,能够使托换梁的力竖直向下传递,即托换梁-滚轴-钢板-轨道基础-地基,避免在滚轴上产生剪切应力,造成滚轴的折弯,从而提高整个移位过程中的平稳性。Two underpinning beams are used to clamp and fix the underpinning beams from both sides of the frame column. The underpinning beams are supported by the two tracks arranged below to avoid the deviation of the output on both sides of the column. The force of the beam is transmitted vertically downwards, that is, underpinning beam-roller-steel plate-track foundation-foundation, to avoid shear stress on the roller, causing the roller to bend, thereby improving the stability of the entire displacement process Sex.
对于钢板的布置,由于轨道顶面为混凝土材料,通过钢板能够将滚轴的应力间接传递,避免滚轴与轨道顶面的线接触造成的混凝土被压破碎的问题,提高了 滚轴运行过程中的平稳性;滚轴上下方的接触物分别为槽钢和钢板,保证了其接触的稳定性和滚动过程的良好传递;另外还能够避免滚轴与其他平面进行线接触造成的混凝土被压碎的问题,提高了运行过程中的安全性,保证了轨道和托换梁的整体性。For the layout of the steel plate, since the top surface of the track is made of concrete material, the stress of the roller can be indirectly transmitted through the steel plate, avoiding the problem of concrete crushing caused by the line contact between the roller and the top surface of the track, and improving the operation of the roller. Smoothness; the upper and lower contacts of the roller are channel steel and steel plate respectively, which ensure the stability of their contact and the good transmission of the rolling process; in addition, it can also avoid the concrete being crushed by the line contact between the roller and other planes. This problem improves the safety during operation and ensures the integrity of the track and the underpinning beam.
进一步地,在建筑物移动过程中,滚轴从托换梁靠近移位起点的一端滚出,将滚出的滚轴移动至托换梁靠近移位终点的一端并填入托换梁与钢板之间的间隙,形成滚轴循环带动建筑物连续移动;滚轴还配合有止挡,用于在建筑物停止移动时限定滚轴的滚动。Furthermore, during the movement of the building, the roller rolls out from the end of the underpinning beam close to the starting point of the displacement, and the rolled out roller is moved to the end of the underpinning beam close to the end of the shift and fills in the underpinning beam and steel plate. The gap between them forms a roller cycle to drive the building to move continuously; the roller is also matched with a stopper to limit the rolling of the roller when the building stops moving.
建筑物移至新址或者移位中途需要临时停歇,滚轴后方均需要打入止挡,防止建筑物沿移位轨道退回;在本实施例中,所述的止挡选用铁楔块17。When the building is moved to a new site or needs to be temporarily stopped in the middle of the displacement, the stop must be driven behind the roller to prevent the building from retreating along the displacement track; in this embodiment, the stop is an
进一步地,建筑物移位到终点后,将框架柱的截断面与新址基础对齐,通过焊接纵向钢筋形成对接,并浇筑混凝土,形成支撑;当混凝土养护到需求的强度后,才能够拆除托换梁和滚轴。Furthermore, after the building is shifted to the end point, align the cross-section of the frame column with the foundation of the new site, weld longitudinal steel bars to form a butt, and pour concrete to form a support; when the concrete is cured to the required strength, the underpinning can be removed Beams and rollers.
采用将框架柱配置对应的移位轨道,使其同时进行牵引移位,使得不同沉降差的框架柱同时提升,同时减少沉降差,实现纠倾,相较于传统的逐根顶升或迫降的方法纠倾,效率更高,并且同时操作能够避免相邻框架柱沉降差的增大,而逐根顶升或迫降则会引起相邻立柱沉降差的进一步增大,造成结构进一步的损伤;采用移位纠倾框架柱沉降差处于不断减小直至水平高度相等的状态,纠倾过程更为安全,对建筑物的结构能够更好的进行保护。The frame column is configured with the corresponding displacement track to make it carry out traction and displacement at the same time, so that the frame columns with different settlement differences are lifted at the same time, and the settlement difference is reduced at the same time, and the tilt correction is realized. Compared with the traditional lifting or forced landing The method is more efficient, and the simultaneous operation can avoid the increase in the settlement difference of adjacent frame columns, and the successive jacking or forced landing will cause the settlement difference of adjacent columns to further increase, causing further damage to the structure; The displacement correction frame column settlement difference is in a state of continuously decreasing until the level height is equal, the tilt correction process is safer, and the structure of the building can be better protected.
以上所述仅为本申请的优选实施例而已,并不用于限制本申请,对于本领域的技术人员来说,本申请可以有各种更改和变化。凡在本申请的精神和原则之内,所作的任何修改、等同替换、改进等,均应包含在本申请的保护范围之内。The above descriptions are only preferred embodiments of the application, and are not intended to limit the application. For those skilled in the art, the application can have various modifications and changes. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of this application shall be included in the protection scope of this application.
Claims (10)
Applications Claiming Priority (2)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201911102476.5 | 2019-11-12 | ||
| CN201911102476.5A CN110805306B (en) | 2019-11-12 | 2019-11-12 | A method of building displacement and tilting correction |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| WO2021093732A1 true WO2021093732A1 (en) | 2021-05-20 |
Family
ID=69502565
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| PCT/CN2020/127864 Ceased WO2021093732A1 (en) | 2019-11-12 | 2020-11-10 | Displacement inclination rectification method for building |
Country Status (2)
| Country | Link |
|---|---|
| CN (1) | CN110805306B (en) |
| WO (1) | WO2021093732A1 (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN114809712A (en) * | 2022-05-24 | 2022-07-29 | 河南建科城市更新工程技术有限公司 | Building translation quantitative deviation correcting device |
Families Citing this family (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN110805306B (en) * | 2019-11-12 | 2021-04-30 | 山东建筑大学 | A method of building displacement and tilting correction |
| CN111608215A (en) * | 2020-06-16 | 2020-09-01 | 上海工谷土木工程技术有限公司 | Building deviation rectifying asynchronous jacking method |
| CN111962910B (en) * | 2020-08-14 | 2021-08-31 | 山东建筑大学 | A Rotational Displacement and Tilt Correction Method for Building Underpinning Foundation |
| CN112459145A (en) * | 2020-11-17 | 2021-03-09 | 山东建筑大学 | Pile foundation support inclination correcting method for frame structure building |
| CN112963012B (en) * | 2021-02-07 | 2022-02-18 | 浙江瑞邦科特检测有限公司 | Large chassis structure local translation deviation rectifying method and system |
| CN113668892B (en) * | 2021-08-31 | 2023-03-14 | 山东建筑大学 | Underground storey-adding method for downhill displacement of frame structure building |
Citations (9)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| DE3633473A1 (en) * | 1985-10-21 | 1987-04-23 | Christiani & Nielsen Ingenieur | Process and arrangement for hydraulically underpinning a structure during its displacement |
| CN102979317A (en) * | 2012-12-19 | 2013-03-20 | 山东建筑大学 | Displacement and location method of building with bidirectional rollers and shock-insulation supports |
| CN204676615U (en) * | 2015-05-18 | 2015-09-30 | 中国化学工程第三建设有限公司 | A kind of device of independent bent columns slant correction |
| CN106320736A (en) * | 2016-08-19 | 2017-01-11 | 山东建筑大学 | Method for shifting, climbing, lifting and steering of building |
| CN108425386A (en) * | 2018-05-24 | 2018-08-21 | 山东建筑大学 | Frame structure building promotes correcting method |
| JP2018131812A (en) * | 2017-02-15 | 2018-08-23 | 株式会社セーフティーシステムズ | Building reinforcement method and seismic reinforcement member |
| KR101906326B1 (en) * | 2018-04-05 | 2018-10-11 | 박창민 | Computer hydraulic synchronization system having leveler-mounted hydraulic jack and 3-axis clinometer for restoring and lifting structure, and method for the same |
| CN109869009A (en) * | 2019-04-04 | 2019-06-11 | 山东建筑大学 | A kind of disconnected column inclination correction method of frame structure building |
| CN110805306A (en) * | 2019-11-12 | 2020-02-18 | 山东建筑大学 | A method of building displacement and tilting correction |
Family Cites Families (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| RU2124099C1 (en) * | 1998-05-05 | 1998-12-27 | Закрытое акционерное общество "СКС-Инвест" | Method for erection of framework for stories added to dwelling building |
| JP2002013299A (en) * | 2000-06-30 | 2002-01-18 | Yutaka Kouen | Structure transferring device |
| CN108999226B (en) * | 2018-07-24 | 2020-06-05 | 山东建筑大学 | Tilt rectification method for rotating and shifting frame structure buildings |
-
2019
- 2019-11-12 CN CN201911102476.5A patent/CN110805306B/en active Active
-
2020
- 2020-11-10 WO PCT/CN2020/127864 patent/WO2021093732A1/en not_active Ceased
Patent Citations (9)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| DE3633473A1 (en) * | 1985-10-21 | 1987-04-23 | Christiani & Nielsen Ingenieur | Process and arrangement for hydraulically underpinning a structure during its displacement |
| CN102979317A (en) * | 2012-12-19 | 2013-03-20 | 山东建筑大学 | Displacement and location method of building with bidirectional rollers and shock-insulation supports |
| CN204676615U (en) * | 2015-05-18 | 2015-09-30 | 中国化学工程第三建设有限公司 | A kind of device of independent bent columns slant correction |
| CN106320736A (en) * | 2016-08-19 | 2017-01-11 | 山东建筑大学 | Method for shifting, climbing, lifting and steering of building |
| JP2018131812A (en) * | 2017-02-15 | 2018-08-23 | 株式会社セーフティーシステムズ | Building reinforcement method and seismic reinforcement member |
| KR101906326B1 (en) * | 2018-04-05 | 2018-10-11 | 박창민 | Computer hydraulic synchronization system having leveler-mounted hydraulic jack and 3-axis clinometer for restoring and lifting structure, and method for the same |
| CN108425386A (en) * | 2018-05-24 | 2018-08-21 | 山东建筑大学 | Frame structure building promotes correcting method |
| CN109869009A (en) * | 2019-04-04 | 2019-06-11 | 山东建筑大学 | A kind of disconnected column inclination correction method of frame structure building |
| CN110805306A (en) * | 2019-11-12 | 2020-02-18 | 山东建筑大学 | A method of building displacement and tilting correction |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN114809712A (en) * | 2022-05-24 | 2022-07-29 | 河南建科城市更新工程技术有限公司 | Building translation quantitative deviation correcting device |
| CN114809712B (en) * | 2022-05-24 | 2023-12-12 | 河南建科城市更新工程技术有限公司 | Building translation ration deviation correcting device |
Also Published As
| Publication number | Publication date |
|---|---|
| CN110805306A (en) | 2020-02-18 |
| CN110805306B (en) | 2021-04-30 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| WO2021093732A1 (en) | Displacement inclination rectification method for building | |
| CN109267494B (en) | Hoop type hydraulic climbing formwork system for cylindrical pier construction and construction method | |
| CN111119071A (en) | Construction method for assembling precast concrete segment box girder | |
| CN113279341B (en) | A bridge resetting bracket and a bridge resetting method | |
| CN108999226B (en) | Tilt rectification method for rotating and shifting frame structure buildings | |
| CN110565983B (en) | Building jacking and shifting method | |
| WO2021093731A1 (en) | Method for moving tall building uphill | |
| CN108999225B (en) | Inclination correcting method for rotary shifting brick-concrete structure building | |
| CN115404786A (en) | Incremental launching construction method for steel-concrete composite beam | |
| CN108265618A (en) | A kind of reverse increasing layer construction method in overpass pier base underground | |
| CN110924436A (en) | Railway frame bridge jacking front guide type steel box shed edge angle and construction method thereof | |
| CN219793684U (en) | Long-distance pushing steel box girder crossing existing highway girder falling guide device | |
| CN110939071A (en) | Non-buttress construction method for assembled steel-concrete I-shaped composite beam bridge | |
| CN117988357B (en) | A super-large diameter column pile foundation support structure and construction method | |
| CN111379199B (en) | Construction device, construction system and construction method for void pile plate structure | |
| CN220705161U (en) | Concrete floor post-cast strip hanging walking template system | |
| CN110512474A (en) | A railway track overhead reinforcement structure and method | |
| CN108316671B (en) | Method for realizing displacement and steering of building by adjusting diameter of roller | |
| CN221798120U (en) | Bridge body of pilot hole lifting trestle and pilot hole lifting trestle | |
| CN116738558B (en) | Visual processing method, auxiliary moving mechanism and pushing system | |
| CN113047188B (en) | Small bridge post-earthquake resetting method and device | |
| CN222685313U (en) | A steel pipe support frame for a bridge widening and erecting machine | |
| CN113957936B (en) | A deflection correction structure and method for horizontal deflection of a transmission tower | |
| CN117684472A (en) | A rapid construction method for bridge built-in steel frame beams | |
| CN204455878U (en) | Urban interchange maintenance is used can length travel temporary support system |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| 121 | Ep: the epo has been informed by wipo that ep was designated in this application |
Ref document number: 20888461 Country of ref document: EP Kind code of ref document: A1 |
|
| NENP | Non-entry into the national phase |
Ref country code: DE |
|
| 122 | Ep: pct application non-entry in european phase |
Ref document number: 20888461 Country of ref document: EP Kind code of ref document: A1 |
|
| 122 | Ep: pct application non-entry in european phase |
Ref document number: 20888461 Country of ref document: EP Kind code of ref document: A1 |
|
| 32PN | Ep: public notification in the ep bulletin as address of the adressee cannot be established |
Free format text: NOTING OF LOSS OF RIGHTS PURSUANT TO RULE 112(1) EPC (EPO FORM 1205 DATED 22.05.2023) |
|
| 122 | Ep: pct application non-entry in european phase |
Ref document number: 20888461 Country of ref document: EP Kind code of ref document: A1 |