CN108708409A - A kind of frame structure building lifting correcting method - Google Patents

A kind of frame structure building lifting correcting method Download PDF

Info

Publication number
CN108708409A
CN108708409A CN201810508794.0A CN201810508794A CN108708409A CN 108708409 A CN108708409 A CN 108708409A CN 201810508794 A CN201810508794 A CN 201810508794A CN 108708409 A CN108708409 A CN 108708409A
Authority
CN
China
Prior art keywords
lifted
concrete
correcting method
frame structure
isolated footing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810508794.0A
Other languages
Chinese (zh)
Inventor
贾强
张鑫
孙剑平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong Jianzhu University
Original Assignee
Shandong Jianzhu University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong Jianzhu University filed Critical Shandong Jianzhu University
Priority to CN201810508794.0A priority Critical patent/CN108708409A/en
Publication of CN108708409A publication Critical patent/CN108708409A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D35/00Straightening, lifting, or lowering of foundation structures or of constructions erected on foundations

Abstract

The invention discloses a kind of frame structure buildings to be lifted correcting method, includes the following steps:1) working pit is excavated in the foundation soil in the relatively large region of settlement of foundation of the building of run-off the straight, exposes the isolated footing below frame column at this;2) it drills downwards the working pit bottom excavated since step 1), until hard bearing stratum;3) steel reinforcement cage is placed in drilling, concrete perfusion forms cast-in-place concrete pile;4) support device is horizontally disposed on frame column;5) lifting apparatus is placed between bored concrete pile top surface and support device;6) frame column for settling major part and isolated footing are lifted by support device with lifting apparatus, the differential settlement between building inclination rate and frame column is measured during lifting;Stop lifting after the differential settlement between building inclination rate and frame column is less than tolerance as defined in specification;7) it interspaces interior casting concrete in isolated footing and foundation soil.

Description

A kind of frame structure building lifting correcting method
Technical field
The invention belongs to civil construction fields, and in particular to a kind of frame structure building lifting correcting method.
Background technology
Building inclination rectification means that building causes basic unevenness due to certain of ground, basis or building itself Even sedimentation, upper part structure deviate upright position and run-off the straight, when the inclined degree of building is more than that the related specification of country is wanted Ask, seriously affect taken when building safety and normal use to ensuring building safety and restore its normal use Stable measure is reinforced in the rectification righting of function.
The common method of rectification has:Pressing Ioad correcting method, soil digging correcting method, immersion correcting method and soil digging douche etc.. These methods are mostly to increase settling amount in the small side of building settlement, so as to adjusting the relative settlement on entire basis.To rise To the inclined purpose of correction building.These methods need to estimate settling amount, are carried out to soil digging amount, irrigation quantity a large amount of theoretical It calculates, it is empirical very strong, it is theoretical also immature.In fact big side will be settled to be lifted building, can equally reach and entangle The purpose inclined, and tilting procedure is simple, controllable.
Invention content
In view of the above shortcomings of the prior art, the object of the present invention is to provide a kind of lifts for frame structure building Rise correcting method.
In order to achieve the goal above, the technical scheme is that:
A kind of frame structure building lifting correcting method, includes the following steps:
1) working pit is excavated in the foundation soil in the relatively large region of settlement of foundation of the building of run-off the straight, cruelly Expose the isolated footing below frame column at this;
2) it drills downwards the working pit bottom excavated since step 1), until hard bearing stratum;
3) steel reinforcement cage is placed in drilling, concrete perfusion forms cast-in-place concrete pile;
4) support device is horizontally disposed on frame column;
5) lifting apparatus is placed between bored concrete pile top surface and support device;
6) frame column for settling major part and isolated footing are lifted by support device with lifting apparatus, were lifted The differential settlement between building inclination rate and frame column is measured in journey;Differential settlement between building inclination rate and frame column Less than stopping lifting after tolerance as defined in specification;
7) it interspaces interior casting concrete in isolated footing and foundation soil.
Further, drilling machine is installed in the isolated footing surrounding, drilling machine drilling is up to hard holding force Soil layer.
Further, the drilling is at least arranged two, two or more drillings are the four of the isolated footing Week is uniformly distributed.
Further, the support device is concrete hanging top.
Further, the construction method of the concrete hanging top is:In two lateral extent isolated footing end face of frame column At certain altitude position, concrete hanging top is arranged by the method for being implanted into reinforcing bar and casting concrete, Cantilever Beams both ends should prolong It extends to above the bored concrete pile of both sides, the arrangement of reinforcement of Cantilever Beams should ensure that does not generate destruction in the case where being lifted load action.
Further, the lifting apparatus is jack.
Further, jack is placed between bored concrete pile top surface and concrete hanging top.
Further, further include step 8), after concrete curing reaches some strength, remove jack.
Further, further include step 9) assembling reinforcement between Cantilever Beams and bored concrete pile, supporting module, pouring reinforcement Concrete column;Frame column load is not only transferred to foundation soil by isolated footing, but also is transferred to by Cantilever Beams, bored concrete pile Hard bearing stratum prevents isolated footing from further sedimentation occurs.
Further, further include step 10) backfilling working hole, restore ground.
Beneficial effects of the present invention are:
The method being lifted using jack, simpler compared to the method for forced landing, safe, controllable, it is heavy to estimate in advance Drop amount, soil digging and irrigation quantity, it is only necessary to intuitively complete rectification using conventional measurement means.It is bored in isolated footing end face Hole construction bored concrete pile is compared, and difficulty of construction is reduced.
Description of the drawings
The accompanying drawings which form a part of this application are used for providing further understanding of the present application, the application's Illustrative embodiments and their description do not constitute the improper restriction to the application for explaining the application.
Fig. 1 is the side view before building inclination rectification;
Fig. 2 is the side view after excavating operating pit at sedimentation major part isolated footing;
Fig. 3 is to drill and the side view for bored concrete pile of constructing in isolated footing both sides;
Fig. 4 is the schematic diagram that bar planting adds concrete hanging top on sedimentation major part frame column;
Fig. 5 is that jack schematic diagram is placed between Cantilever Beams and bored concrete pile;
Fig. 6 is jack lifting and the concrete perfusion schematic diagram under isolated footing;
Fig. 7 is to withdraw from jack and the casting concrete column schematic diagram between bored concrete pile and Cantilever Beams;
Fig. 8 cheats for backfilling working, restores ground schematic diagram.
Wherein:1, frame column, 2, Vierendeel girder, plate, 3, isolated footing, 4, foundation soil, 5, hard bearing stratum, 6, work Hole, 7, bored concrete pile, 8, Cantilever Beams, 9, jack, 10, the concrete being perfused below isolated footing, 11, bored concrete pile and Cantilever Beams Between the concrete column that pours.
Specific implementation mode
It is noted that following detailed description is all illustrative, it is intended to provide further instruction to the application.Unless Otherwise indicated, all technical and scientific terms used herein has and the application person of an ordinary skill in the technical field Normally understood identical meanings.
It should be noted that term used herein above is merely to describe specific implementation mode, and be not intended to restricted root According to the illustrative embodiments of the application.As used herein, unless the context clearly indicates otherwise, otherwise singular shape Formula is also intended to include plural form, additionally, it should be understood that, when in the present specification use term "comprising" and/or When " comprising ", existing characteristics, step, operation, device, component and/or combination thereof are indicated;
In order to facilitate narration, if there is "upper", "lower", " left side " " right side " printed words, only expression and attached drawing itself in the present invention Upper and lower, left and right direction it is consistent, not to structure rise restriction effect, it is only for convenient for description the present invention and simplification retouch It states, does not indicate or imply the indicated equipment or element must have a particular orientation, with specific azimuth configuration and behaviour Make, therefore is not considered as limiting the invention.
As background technology is introduced, the common method of rectification has in the prior art:Pressing Ioad correcting method, soil digging Correcting method, immersion correcting method and soil digging douche etc..These methods are mostly to increase settling amount in the small side of building settlement, So as to adjusting the relative settlement on entire basis.To play the inclined purpose of correction building.These methods needs estimate sedimentation Amount carries out a large amount of theoretical calculation to soil digging amount, irrigation quantity, empirical very strong, theoretical also immature.In fact it will settle big Side building is lifted, can equally achieve the purpose that rectification, and tilting procedure is simple, controllable, in order to solve as above The technical issues of, present applicant proposes a kind of frame structure buildings to be lifted correcting method.
In a kind of typical embodiment of the application, as shown in Figure 1, as shown in Fig. 2-Fig. 8, the building that is indicated in Fig. 1 Side view before object rectification;It includes frame column 1, Vierendeel girder, plate 2, isolated footing 3, foundation soil 4, hard bearing stratum 5; Whole building tilts to the right, and specific inclination correction method includes the following steps:
1) working pit 6 is excavated in the foundation soil in the relatively large region of settlement of foundation of the building of run-off the straight, cruelly Expose the isolated footing 3 below frame column at this;Specifically as shown in Fig. 2, excavating working pit on the right side of building, expose Isolated footing 3 at this below frame column;
2) drilling machine is installed in 3 both sides of isolated footing, drilling is up to hard bearing stratum 5;It is specific as shown in Figure 3;
Further, it drills in the present invention and is at least arranged two, two or more drillings are along the isolated footing Surrounding be uniformly distributed, ensure whole building uniform force;Specific quantity can according to the weight of actual building into Row setting, is essentially that structural quality is bigger, the quantity of jack is more, and drilling hole amount is also more.
3) steel reinforcement cage is placed in each drilling, concrete perfusion forms cast-in-place concrete pile 7;Specifically such as Fig. 4 institutes Show;
4) in 1 liang of lateral extent isolated footing end face certain altitude of frame column (this highly guarantees to place jack) position Concrete hanging top 8 is arranged by the method for being implanted into reinforcing bar and casting concrete in place, and 8 both ends of Cantilever Beams should extend to two lateral irrigations It notes above stake, the arrangement of reinforcement of Cantilever Beams 8 should ensure that does not generate destruction in the case where being lifted load action;
Or using otherwise can also, as long as can make jack be lifted frame column.
5) jack 9 is placed between 7 top surface of each bored concrete pile and concrete hanging top;The quantity and brill of jack 9 The quantity in hole is identical;
6) frame column for settling major part and isolated footing are lifted by Cantilever Beams with multiple jack 9, were lifted The differential settlement between building inclination rate and frame column is measured in journey.Differential settlement between building inclination rate and frame column Less than stopping lifting after tolerance as defined in specification.
7) it interspaces interior casting concrete in isolated footing 3 and foundation soil 4;Specifically as shown in fig. 6, jack is lifted The concrete 10 for rising and being perfused below the isolated footing under isolated footing in concrete perfusion schematic diagram;
9) after concrete curing reaches some strength, the jack 9 installed front is removed.;Specifically as shown in Fig. 7, remove Go out jack and the casting concrete column schematic diagram between bored concrete pile and Cantilever Beams;
10) assembling reinforcement between Cantilever Beams and bored concrete pile, supporting module, pouring reinforcement concrete column;Frame column load Foundation soil is not only transferred to by isolated footing, but also hard bearing stratum is transferred to by Cantilever Beams, bored concrete pile, is prevented solely Further sedimentation occurs for vertical basis;Specifically as shown in figure 8, the concrete column 11 poured between bored concrete pile and Cantilever Beams;
11) backfilling working is cheated, and restores ground.Specific construction method is same as the prior art.
The foregoing is merely the preferred embodiments of the application, are not intended to limit this application, for the skill of this field For art personnel, the application can have various modifications and variations.Within the spirit and principles of this application, any made by Modification, equivalent replacement, improvement etc., should be included within the protection domain of the application.

Claims (10)

1. a kind of frame structure building is lifted correcting method, which is characterized in that include the following steps:
1) working pit is excavated in the foundation soil in the relatively large region of settlement of foundation of the building of run-off the straight, exposes this Locate the isolated footing below frame column;
2) it drills downwards the working pit bottom excavated since step 1), until hard bearing stratum;
3) steel reinforcement cage is placed in drilling, concrete perfusion forms cast-in-place concrete pile;
4) support device is horizontally disposed on frame column;
5) lifting apparatus is placed between bored concrete pile top surface and support device;
6) frame column for settling major part and isolated footing are lifted by support device with lifting apparatus, are surveyed during lifting Measure the differential settlement between building inclination rate and frame column;When the differential settlement between building inclination rate and frame column is less than specification Stop lifting after defined tolerance;
7) it interspaces interior casting concrete in isolated footing and foundation soil.
2. as claim 1 frame structure building is lifted correcting method, which is characterized in that in the isolated footing surrounding installation Drilling machine, drilling machine drilling is up to hard bearing stratum.
3. as claim 1 frame structure building is lifted correcting method, which is characterized in that the drilling is at least arranged two, Two or more surroundings of drilling in the isolated footing are uniformly distributed.
4. as claim 1 frame structure building is lifted correcting method, which is characterized in that the support device is concrete suspension Outrigger.
5. as claim 4 frame structure building is lifted correcting method, which is characterized in that the construction of the concrete hanging top Method is:At two lateral extent isolated footing end face certain altitude position of frame column, by being implanted into reinforcing bar and casting concrete Concrete hanging top is arranged in method, and Cantilever Beams both ends should extend to above the bored concrete pile of both sides, and the arrangement of reinforcement of Cantilever Beams, which should ensure that, to be lifted It rises and does not generate destruction under load action.
6. as claim 1 frame structure building is lifted correcting method, which is characterized in that the lifting apparatus is jack.
7. as claim 6 frame structure building is lifted correcting method, which is characterized in that overhang in bored concrete pile top surface and concrete The jack is placed between beam.
8. as claim 7 frame structure building is lifted correcting method, which is characterized in that further include step 8), concrete curing After reaching some strength, jack is removed.
9. as claim 1 frame structure building is lifted correcting method, which is characterized in that further include step 9) in Cantilever Beams and filling Assembling reinforcement between note stake, supporting module, pouring reinforcement concrete column;Frame column load is not only transferred to ground by isolated footing Base soil, and hard bearing stratum is transferred to by Cantilever Beams, bored concrete pile, prevent isolated footing from further sedimentation occurs.
10. as claim 1 frame structure building is lifted correcting method, which is characterized in that further include step 10) backfilling working Ground is restored in hole.
CN201810508794.0A 2018-05-24 2018-05-24 A kind of frame structure building lifting correcting method Pending CN108708409A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810508794.0A CN108708409A (en) 2018-05-24 2018-05-24 A kind of frame structure building lifting correcting method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810508794.0A CN108708409A (en) 2018-05-24 2018-05-24 A kind of frame structure building lifting correcting method

Publications (1)

Publication Number Publication Date
CN108708409A true CN108708409A (en) 2018-10-26

Family

ID=63870600

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810508794.0A Pending CN108708409A (en) 2018-05-24 2018-05-24 A kind of frame structure building lifting correcting method

Country Status (1)

Country Link
CN (1) CN108708409A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109706987A (en) * 2019-02-25 2019-05-03 山东建筑大学 A kind of frame structure building inside lifting inclination-correcting method
CN111608175A (en) * 2020-06-12 2020-09-01 湖南城市学院 Reinforcing pile for building bridge
CN113774972A (en) * 2021-09-28 2021-12-10 中国矿业大学 Reinforcing method for overload punching damage of independent foundation under column
CN113846623A (en) * 2021-10-17 2021-12-28 熊明魁 House foundation settlement repairing process and equipment
CN113863285A (en) * 2021-10-14 2021-12-31 山东建大工程鉴定加固设计有限公司 Inclination stopping method for high-rise building with foundation side large-diameter pile and external box type structure
WO2022105267A1 (en) * 2020-11-17 2022-05-27 山东建筑大学 Frame structure building rectification method using pile foundation support

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104047305A (en) * 2014-05-26 2014-09-17 江苏鼎泰工程材料有限公司 Fast repairing method of house sinking
CN105863287A (en) * 2016-03-31 2016-08-17 山东建筑大学 Method for jacking storey-addition and shock insulation of framework-structure building
CN107035159A (en) * 2017-05-05 2017-08-11 山东建筑大学 A kind of method suitable for frame structure isolated footing building underground increasing layer
CN206902783U (en) * 2017-04-20 2018-01-19 南京工大桥隧与轨道交通研究院有限公司 For reducing the adjustable reinforcement and rectification structure of house differential settlement

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104047305A (en) * 2014-05-26 2014-09-17 江苏鼎泰工程材料有限公司 Fast repairing method of house sinking
CN105863287A (en) * 2016-03-31 2016-08-17 山东建筑大学 Method for jacking storey-addition and shock insulation of framework-structure building
CN206902783U (en) * 2017-04-20 2018-01-19 南京工大桥隧与轨道交通研究院有限公司 For reducing the adjustable reinforcement and rectification structure of house differential settlement
CN107035159A (en) * 2017-05-05 2017-08-11 山东建筑大学 A kind of method suitable for frame structure isolated footing building underground increasing layer

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109706987A (en) * 2019-02-25 2019-05-03 山东建筑大学 A kind of frame structure building inside lifting inclination-correcting method
CN111608175A (en) * 2020-06-12 2020-09-01 湖南城市学院 Reinforcing pile for building bridge
WO2022105267A1 (en) * 2020-11-17 2022-05-27 山东建筑大学 Frame structure building rectification method using pile foundation support
CN113774972A (en) * 2021-09-28 2021-12-10 中国矿业大学 Reinforcing method for overload punching damage of independent foundation under column
CN113774972B (en) * 2021-09-28 2022-06-07 中国矿业大学 Reinforcing method for overload punching damage of independent foundation under column
CN113863285A (en) * 2021-10-14 2021-12-31 山东建大工程鉴定加固设计有限公司 Inclination stopping method for high-rise building with foundation side large-diameter pile and external box type structure
CN113863285B (en) * 2021-10-14 2022-10-18 山东建大工程鉴定加固设计有限公司 Inclination stopping method for high-rise building with foundation side large-diameter pile and external box type structure
CN113846623A (en) * 2021-10-17 2021-12-28 熊明魁 House foundation settlement repairing process and equipment
CN113846623B (en) * 2021-10-17 2022-12-09 福建省泷澄建设集团有限公司 House foundation settlement repairing process and equipment

Similar Documents

Publication Publication Date Title
CN108708409A (en) A kind of frame structure building lifting correcting method
CN109487822B (en) Method for installing and adjusting steel pipe column in reverse construction and control device
CN110080318A (en) A kind of method for correcting error that pile foundation building locally settles
CN108086340A (en) Open caisson construction structure and its construction method
CN208996025U (en) A kind of double casing pile foundation construction structures of thick silt layer
CN103452147A (en) Self-balance anchor counter weight broken pile forced landing rectification method
CN108999226B (en) Inclination correcting method for building with rotary displacement frame structure
WO2021031859A1 (en) Slab lowering construction method for underground structure in reverse construction method
CN108999225A (en) Rotation displacement building with brick-concrete structure correcting method
CN1078285C (en) Controlled construction method and apparatus for rectifying inclined building
CN108643255A (en) Frame structure building lifting inclination-correcting method
CN109024719A (en) A kind of side disturbance drop resistance building inclination rectification method
CN104264682B (en) A kind of anchor draws the lagging pile first floor to add concrete beam method for supporting
CN109706987B (en) Jacking and inclination correcting method for interior of frame structure building
CN110725163B (en) Composite roadbed device based on existing rail transit roadbed and pile construction method
CN107142955A (en) A kind of open caisson construction method
CN109869009A (en) A kind of disconnected column inclination correction method of frame structure building
CN207828995U (en) Open caisson construction structure
CN110468721A (en) A kind of large span trestle Cantilever Construction Method
CN108425386A (en) Frame structure building promotes correcting method
CN211948542U (en) Anti-skid weight-balancing retaining wall assembly and retaining wall system
CN112459145A (en) Pile foundation support inclination correcting method for frame structure building
CN207260158U (en) One layer of basement supporting construction
CN108755669A (en) Across tunnel steel reinforced concrete bored concrete pile, conversion beam construction method
JPH0776845A (en) Method of settling open caisson

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20181026