CN108360551A - The positioning device of scene binding foundation bolt in steel construction - Google Patents
The positioning device of scene binding foundation bolt in steel construction Download PDFInfo
- Publication number
- CN108360551A CN108360551A CN201810229215.9A CN201810229215A CN108360551A CN 108360551 A CN108360551 A CN 108360551A CN 201810229215 A CN201810229215 A CN 201810229215A CN 108360551 A CN108360551 A CN 108360551A
- Authority
- CN
- China
- Prior art keywords
- steel
- foundation bolt
- positioning device
- scene
- plateform
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 229910000831 Steel Inorganic materials 0.000 title claims abstract description 77
- 239000010959 steel Substances 0.000 title claims abstract description 77
- 238000010276 construction Methods 0.000 title claims abstract description 21
- 230000027455 binding Effects 0.000 title claims abstract description 15
- 238000009739 binding Methods 0.000 title claims abstract description 15
- 238000011161 development Methods 0.000 abstract description 3
- 230000003247 decreasing effect Effects 0.000 abstract 1
- 230000007423 decrease Effects 0.000 description 2
- 238000013461 design Methods 0.000 description 2
- 238000010586 diagram Methods 0.000 description 2
- 238000005516 engineering process Methods 0.000 description 2
- 230000013011 mating Effects 0.000 description 2
- 238000000034 method Methods 0.000 description 2
- 238000012545 processing Methods 0.000 description 2
- 238000012937 correction Methods 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 238000003032 molecular docking Methods 0.000 description 1
- 210000003205 muscle Anatomy 0.000 description 1
- -1 profiled sheet Substances 0.000 description 1
- 230000003014 reinforcing effect Effects 0.000 description 1
- 238000003466 welding Methods 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/32—Foundations for special purposes
- E02D27/42—Foundations for poles, masts or chimneys
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The invention belongs to technical field of buildings, the positioning device of scene binding foundation bolt specially in steel construction.Scene binds the positioning device of foundation bolt, including steel plateform in steel construction, offers through-hole on steel plateform, the through-hole upper surface is welded with junction button, and lower surface is welded with steel bushing;Junction button, steel bushing and the through-hole is interconnected.The steel plateform side is also associated with steel knob.The positioning device of scene binding foundation bolt in steel construction provided by the invention, after the completion of factory is by prefabricated steel column, produce the corresponding stationary positioned device of every steel column, the device can be with the column kit, the secondary operation for sending the scene of being decreased to construction site together greatly improves efficiency, reduces the manual synchronizing time, improves accuracy, ensure being smoothed out for engineering, also conforms to the demand for development of steel building.
Description
Technical field
The invention belongs to technical field of buildings, the positioning device of scene binding foundation bolt specially in steel construction.
Background technology
Nowadays steel building is gradually applied to construction project field, girder steel, profiled sheet, steel in steel building
Column can be first prefabricated in the factory, then is transported to construction site and is installed, but since underground foundation part can not also apply this
Technology, the problem of connection with pre-erection there is always cast-in-place part when installation at the scene.
Such as foundation platform region, all reinforcing bars in cushion cap are all live bindings, and fall within the steel column on cushion cap in
It is produced in factory, therefore the docking of the two connection is not exactly accurate, often occurs the steel column foundation bolt on cushion cap at the scene
It can not be fully inserted into the bolt hole that steel column bottom plate is stayed, result in the need for carrying out manual synchronizing again, due on common cushion cap
Column foundation bolt diameter is all larger, and old friend's work causes high effort for, and the amount of correction not easy to control.
Invention content
The purpose of the present invention is to provide a kind of positioning devices of binding foundation bolt in scene in steel construction, are a kind of strip
The Interal fixation device of muscle sleeve, can be by the bolt hole of reserved column foundation bolt entirely accurate reserved into steel column bottom plate
In.
Specific technical solution is:
Scene binds the positioning device of foundation bolt, including steel plateform in steel construction, and multiple through-holes are offered on steel plateform,
The through hole upper surface is welded with junction button, and lower surface is welded with steel bushing;The junction button, steel bushing respectively with it is logical
Hole is connected to.
The steel plateform side is also associated with steel knob.
The steel bushing lower end is provided with convex angle.
The steel bushing inner wall is equipped with interior screw thread.
The positioning device of scene binding foundation bolt, mating with steel column in steel construction provided by the invention, in factory process
After the completion, it produces the corresponding stationary positioned device steel plate of every steel column to be sent together to construction site, decreases the secondary of scene
Processing greatly improves efficiency, reduces the manual synchronizing time, improves accuracy, ensures being smoothed out for engineering, also conform to
The demand for development of steel building.
Description of the drawings
Fig. 1 is the structural schematic diagram of the present invention;
Fig. 2 is that the present invention uses construction schematic diagram.
Specific implementation mode
Below in conjunction with the accompanying drawings, specific embodiments of the present invention are described in further detail:
As shown in Figure 1, scene binds the positioning device of foundation bolt, including steel plateform 1 in steel construction, opened on steel plateform 1
Equipped with multiple through-holes, the through hole upper surface is welded with junction button 2, and lower surface is welded with steel bushing 3;The junction button
2, steel bushing 3 is connected to through-hole respectively.
1 side of steel plateform is also associated with steel knob 4.
3 lower end of steel bushing is provided with convex angle 6.
3 inner wall of steel bushing is equipped with interior screw thread 5.
The positioning device abbreviation positioning device 15 of scene binding foundation bolt in steel construction.
As shown in Fig. 2, process for using:First foundation bolt 11 is embedded in cushion cap 14 when binding foundation bolt, then should
The steel bushing 3 of positioning device 15 is inserted in from 11 top of foundation bolt, adjusts steel bushing 3,1 top of steel plateform and 14 top surface of cushion cap
Maintain an equal level, foundation bolt 11 is fixed after whole is in place;After the completion of cushion cap 14, prefabricated steel column 13 can accurately be hung in scheduled position
It sets, the steel column end plate 12 of prefabricated steel column 13 is located on steel plateform 1.
In the prefabricated steel column 13 of plant produced, positioning device 15, the positioning device 15 and prefabricated steel column 13 are mating, send together to
Construction site decreases the secondary operation at scene, greatly improves efficiency, reduces the manual synchronizing time, improves accuracy,
Ensure being smoothed out for engineering, also conforms to the demand for development of steel building.
13 size of prefabricated steel column, the size design of institute's reserving hole first produced according to factory goes out corresponding steel plateform
1 size, and steel plateform 1 carries out trepanning processing according to steel column hole;Design the steel plateform of junction button 2, steel bushing 3 and trepanning
1 welding, junction button 2 are positioned for scene binding.
Wherein, the size of 1 trepanning of steel plateform is 11 diameter+2mm of foundation bolt, to facilitate foundation bolt 11 can be smoothly
It passes through.
Claims (4)
1. the positioning device of scene binding foundation bolt in steel construction, which is characterized in that including steel plateform(1), steel plateform
(1)On offer multiple through-holes, the through-hole upper surface is welded with junction button(2), lower surface is welded with steel bushing(3);Institute
The junction button stated(2), steel bushing(3)It is connected to respectively with through-hole.
2. the positioning device of scene binding foundation bolt in steel construction according to claim 1, which is characterized in that described
Steel plateform(1)Side is also associated with steel knob(4).
3. the positioning device of scene binding foundation bolt in steel construction according to claim 1 or 2, which is characterized in that institute
The steel bushing stated(3)Lower end is provided with convex angle(6).
4. the positioning device of scene binding foundation bolt in steel construction according to claim 3, which is characterized in that described
Steel bushing(3)Inner wall is equipped with interior screw thread(5).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810229215.9A CN108360551A (en) | 2018-03-20 | 2018-03-20 | The positioning device of scene binding foundation bolt in steel construction |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810229215.9A CN108360551A (en) | 2018-03-20 | 2018-03-20 | The positioning device of scene binding foundation bolt in steel construction |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108360551A true CN108360551A (en) | 2018-08-03 |
Family
ID=63000614
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810229215.9A Pending CN108360551A (en) | 2018-03-20 | 2018-03-20 | The positioning device of scene binding foundation bolt in steel construction |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108360551A (en) |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN201826437U (en) * | 2010-09-29 | 2011-05-11 | 上海市机械施工有限公司 | Structure for accurately embedding column pin bolts for steel structures |
CN103276899A (en) * | 2013-06-05 | 2013-09-04 | 中国建筑第八工程局有限公司 | Construction method of steel bars surrounding steel column base |
CN103469732A (en) * | 2013-09-22 | 2013-12-25 | 中建八局第三建设有限公司 | Construction method of preformed holes for foundation bolts of bridge support |
CN105696800A (en) * | 2016-01-21 | 2016-06-22 | 中建钢构有限公司 | Temporary fixed sleeve frame for preventing relative displacement generated during construction of steel-structured anchor bolts |
CN105887917A (en) * | 2016-04-13 | 2016-08-24 | 中国十七冶集团有限公司 | Quick processing, mounting and alignment method for foundation bolt sleeve |
CN206245763U (en) * | 2016-12-07 | 2017-06-13 | 南京兴华建筑设计研究院股份有限公司 | The positioner of live assembling reinforcement in precast construction |
-
2018
- 2018-03-20 CN CN201810229215.9A patent/CN108360551A/en active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN201826437U (en) * | 2010-09-29 | 2011-05-11 | 上海市机械施工有限公司 | Structure for accurately embedding column pin bolts for steel structures |
CN103276899A (en) * | 2013-06-05 | 2013-09-04 | 中国建筑第八工程局有限公司 | Construction method of steel bars surrounding steel column base |
CN103469732A (en) * | 2013-09-22 | 2013-12-25 | 中建八局第三建设有限公司 | Construction method of preformed holes for foundation bolts of bridge support |
CN105696800A (en) * | 2016-01-21 | 2016-06-22 | 中建钢构有限公司 | Temporary fixed sleeve frame for preventing relative displacement generated during construction of steel-structured anchor bolts |
CN105887917A (en) * | 2016-04-13 | 2016-08-24 | 中国十七冶集团有限公司 | Quick processing, mounting and alignment method for foundation bolt sleeve |
CN206245763U (en) * | 2016-12-07 | 2017-06-13 | 南京兴华建筑设计研究院股份有限公司 | The positioner of live assembling reinforcement in precast construction |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107299683B (en) | Compound concrete-filled tubular column assembled docks node and connection method | |
CN108560716B (en) | Steel pipe concrete column beam joint structure and construction method thereof | |
CN206174146U (en) | Assembly type structure's assembly node | |
CN205421616U (en) | Assemble integral shear force wall with steel pipe concrete edge member | |
CN106760054B (en) | Prefabricated reinforced concrete shear wall | |
CN206245763U (en) | The positioner of live assembling reinforcement in precast construction | |
CN104929279B (en) | Pre-cast shear wall vertical rebar centralized restraint lap joint construction | |
CN205875206U (en) | Utility tunnel lateral wall built -in fitting fixing device | |
CN107130703A (en) | A kind of double steel plate shear wall vertically splices node | |
CN205444968U (en) | Bar planting anchor structure | |
CN104831832B (en) | Assembly of shear wall structure and its installation method | |
CN108360551A (en) | The positioning device of scene binding foundation bolt in steel construction | |
CN202131676U (en) | Quake-proof steel tie bar embedded part | |
CN215594765U (en) | Auxiliary tool for forming setting slurry between component and ground | |
CN212053436U (en) | Strenghthened type precast concrete wallboard and connection structure with from structure of taking one's place | |
CN103352568A (en) | Method for building constructional column on foundation pad | |
CN108468388A (en) | A kind of built-in fitting and its construction method | |
CN210597655U (en) | Connecting joint between vertical stressed components | |
CN207568074U (en) | A kind of secondary structure member reinforcing steel bar connecting node | |
CN104264992B (en) | The construction method of skyscraper pipeline enclosure | |
CN202284291U (en) | Concrete overflowing surface template shaped like Chinese character ba | |
CN206571057U (en) | A kind of UPVC roofings c-type tile | |
CN206368433U (en) | A kind of built-in fitting attachment structure | |
CN109137982B (en) | Slurry base sleeve for underground comprehensive pipe gallery and construction method of comprehensive pipe gallery | |
CN201560579U (en) | Device for arranging preformed hole on concrete structural slab |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WD01 | Invention patent application deemed withdrawn after publication | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20180803 |