CN108360551A - The positioning device of scene binding foundation bolt in steel construction - Google Patents

The positioning device of scene binding foundation bolt in steel construction Download PDF

Info

Publication number
CN108360551A
CN108360551A CN201810229215.9A CN201810229215A CN108360551A CN 108360551 A CN108360551 A CN 108360551A CN 201810229215 A CN201810229215 A CN 201810229215A CN 108360551 A CN108360551 A CN 108360551A
Authority
CN
China
Prior art keywords
steel
foundation bolt
positioning device
scene
plateform
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810229215.9A
Other languages
Chinese (zh)
Inventor
周善来
孙文
李锦红
刘子洁
吴涛
吴荣先
金波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nanjing Xinghua Architecture & Research Institute Co Ltd
Original Assignee
Nanjing Xinghua Architecture & Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nanjing Xinghua Architecture & Research Institute Co Ltd filed Critical Nanjing Xinghua Architecture & Research Institute Co Ltd
Priority to CN201810229215.9A priority Critical patent/CN108360551A/en
Publication of CN108360551A publication Critical patent/CN108360551A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/42Foundations for poles, masts or chimneys

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention belongs to technical field of buildings, the positioning device of scene binding foundation bolt specially in steel construction.Scene binds the positioning device of foundation bolt, including steel plateform in steel construction, offers through-hole on steel plateform, the through-hole upper surface is welded with junction button, and lower surface is welded with steel bushing;Junction button, steel bushing and the through-hole is interconnected.The steel plateform side is also associated with steel knob.The positioning device of scene binding foundation bolt in steel construction provided by the invention, after the completion of factory is by prefabricated steel column, produce the corresponding stationary positioned device of every steel column, the device can be with the column kit, the secondary operation for sending the scene of being decreased to construction site together greatly improves efficiency, reduces the manual synchronizing time, improves accuracy, ensure being smoothed out for engineering, also conforms to the demand for development of steel building.

Description

The positioning device of scene binding foundation bolt in steel construction
Technical field
The invention belongs to technical field of buildings, the positioning device of scene binding foundation bolt specially in steel construction.
Background technology
Nowadays steel building is gradually applied to construction project field, girder steel, profiled sheet, steel in steel building Column can be first prefabricated in the factory, then is transported to construction site and is installed, but since underground foundation part can not also apply this Technology, the problem of connection with pre-erection there is always cast-in-place part when installation at the scene.
Such as foundation platform region, all reinforcing bars in cushion cap are all live bindings, and fall within the steel column on cushion cap in It is produced in factory, therefore the docking of the two connection is not exactly accurate, often occurs the steel column foundation bolt on cushion cap at the scene It can not be fully inserted into the bolt hole that steel column bottom plate is stayed, result in the need for carrying out manual synchronizing again, due on common cushion cap Column foundation bolt diameter is all larger, and old friend's work causes high effort for, and the amount of correction not easy to control.
Invention content
The purpose of the present invention is to provide a kind of positioning devices of binding foundation bolt in scene in steel construction, are a kind of strip The Interal fixation device of muscle sleeve, can be by the bolt hole of reserved column foundation bolt entirely accurate reserved into steel column bottom plate In.
Specific technical solution is:
Scene binds the positioning device of foundation bolt, including steel plateform in steel construction, and multiple through-holes are offered on steel plateform, The through hole upper surface is welded with junction button, and lower surface is welded with steel bushing;The junction button, steel bushing respectively with it is logical Hole is connected to.
The steel plateform side is also associated with steel knob.
The steel bushing lower end is provided with convex angle.
The steel bushing inner wall is equipped with interior screw thread.
The positioning device of scene binding foundation bolt, mating with steel column in steel construction provided by the invention, in factory process After the completion, it produces the corresponding stationary positioned device steel plate of every steel column to be sent together to construction site, decreases the secondary of scene Processing greatly improves efficiency, reduces the manual synchronizing time, improves accuracy, ensures being smoothed out for engineering, also conform to The demand for development of steel building.
Description of the drawings
Fig. 1 is the structural schematic diagram of the present invention;
Fig. 2 is that the present invention uses construction schematic diagram.
Specific implementation mode
Below in conjunction with the accompanying drawings, specific embodiments of the present invention are described in further detail:
As shown in Figure 1, scene binds the positioning device of foundation bolt, including steel plateform 1 in steel construction, opened on steel plateform 1 Equipped with multiple through-holes, the through hole upper surface is welded with junction button 2, and lower surface is welded with steel bushing 3;The junction button 2, steel bushing 3 is connected to through-hole respectively.
1 side of steel plateform is also associated with steel knob 4.
3 lower end of steel bushing is provided with convex angle 6.
3 inner wall of steel bushing is equipped with interior screw thread 5.
The positioning device abbreviation positioning device 15 of scene binding foundation bolt in steel construction.
As shown in Fig. 2, process for using:First foundation bolt 11 is embedded in cushion cap 14 when binding foundation bolt, then should The steel bushing 3 of positioning device 15 is inserted in from 11 top of foundation bolt, adjusts steel bushing 3,1 top of steel plateform and 14 top surface of cushion cap Maintain an equal level, foundation bolt 11 is fixed after whole is in place;After the completion of cushion cap 14, prefabricated steel column 13 can accurately be hung in scheduled position It sets, the steel column end plate 12 of prefabricated steel column 13 is located on steel plateform 1.
In the prefabricated steel column 13 of plant produced, positioning device 15, the positioning device 15 and prefabricated steel column 13 are mating, send together to Construction site decreases the secondary operation at scene, greatly improves efficiency, reduces the manual synchronizing time, improves accuracy, Ensure being smoothed out for engineering, also conforms to the demand for development of steel building.
13 size of prefabricated steel column, the size design of institute's reserving hole first produced according to factory goes out corresponding steel plateform 1 size, and steel plateform 1 carries out trepanning processing according to steel column hole;Design the steel plateform of junction button 2, steel bushing 3 and trepanning 1 welding, junction button 2 are positioned for scene binding.
Wherein, the size of 1 trepanning of steel plateform is 11 diameter+2mm of foundation bolt, to facilitate foundation bolt 11 can be smoothly It passes through.

Claims (4)

1. the positioning device of scene binding foundation bolt in steel construction, which is characterized in that including steel plateform(1), steel plateform (1)On offer multiple through-holes, the through-hole upper surface is welded with junction button(2), lower surface is welded with steel bushing(3);Institute The junction button stated(2), steel bushing(3)It is connected to respectively with through-hole.
2. the positioning device of scene binding foundation bolt in steel construction according to claim 1, which is characterized in that described Steel plateform(1)Side is also associated with steel knob(4).
3. the positioning device of scene binding foundation bolt in steel construction according to claim 1 or 2, which is characterized in that institute The steel bushing stated(3)Lower end is provided with convex angle(6).
4. the positioning device of scene binding foundation bolt in steel construction according to claim 3, which is characterized in that described Steel bushing(3)Inner wall is equipped with interior screw thread(5).
CN201810229215.9A 2018-03-20 2018-03-20 The positioning device of scene binding foundation bolt in steel construction Pending CN108360551A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810229215.9A CN108360551A (en) 2018-03-20 2018-03-20 The positioning device of scene binding foundation bolt in steel construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810229215.9A CN108360551A (en) 2018-03-20 2018-03-20 The positioning device of scene binding foundation bolt in steel construction

Publications (1)

Publication Number Publication Date
CN108360551A true CN108360551A (en) 2018-08-03

Family

ID=63000614

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810229215.9A Pending CN108360551A (en) 2018-03-20 2018-03-20 The positioning device of scene binding foundation bolt in steel construction

Country Status (1)

Country Link
CN (1) CN108360551A (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201826437U (en) * 2010-09-29 2011-05-11 上海市机械施工有限公司 Structure for accurately embedding column pin bolts for steel structures
CN103276899A (en) * 2013-06-05 2013-09-04 中国建筑第八工程局有限公司 Construction method of steel bars surrounding steel column base
CN103469732A (en) * 2013-09-22 2013-12-25 中建八局第三建设有限公司 Construction method of preformed holes for foundation bolts of bridge support
CN105696800A (en) * 2016-01-21 2016-06-22 中建钢构有限公司 Temporary fixed sleeve frame for preventing relative displacement generated during construction of steel-structured anchor bolts
CN105887917A (en) * 2016-04-13 2016-08-24 中国十七冶集团有限公司 Quick processing, mounting and alignment method for foundation bolt sleeve
CN206245763U (en) * 2016-12-07 2017-06-13 南京兴华建筑设计研究院股份有限公司 The positioner of live assembling reinforcement in precast construction

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201826437U (en) * 2010-09-29 2011-05-11 上海市机械施工有限公司 Structure for accurately embedding column pin bolts for steel structures
CN103276899A (en) * 2013-06-05 2013-09-04 中国建筑第八工程局有限公司 Construction method of steel bars surrounding steel column base
CN103469732A (en) * 2013-09-22 2013-12-25 中建八局第三建设有限公司 Construction method of preformed holes for foundation bolts of bridge support
CN105696800A (en) * 2016-01-21 2016-06-22 中建钢构有限公司 Temporary fixed sleeve frame for preventing relative displacement generated during construction of steel-structured anchor bolts
CN105887917A (en) * 2016-04-13 2016-08-24 中国十七冶集团有限公司 Quick processing, mounting and alignment method for foundation bolt sleeve
CN206245763U (en) * 2016-12-07 2017-06-13 南京兴华建筑设计研究院股份有限公司 The positioner of live assembling reinforcement in precast construction

Similar Documents

Publication Publication Date Title
CN107299683B (en) Compound concrete-filled tubular column assembled docks node and connection method
CN108560716B (en) Steel pipe concrete column beam joint structure and construction method thereof
CN206174146U (en) Assembly type structure's assembly node
CN205421616U (en) Assemble integral shear force wall with steel pipe concrete edge member
CN106760054B (en) Prefabricated reinforced concrete shear wall
CN206245763U (en) The positioner of live assembling reinforcement in precast construction
CN104929279B (en) Pre-cast shear wall vertical rebar centralized restraint lap joint construction
CN205875206U (en) Utility tunnel lateral wall built -in fitting fixing device
CN107130703A (en) A kind of double steel plate shear wall vertically splices node
CN205444968U (en) Bar planting anchor structure
CN104831832B (en) Assembly of shear wall structure and its installation method
CN108360551A (en) The positioning device of scene binding foundation bolt in steel construction
CN202131676U (en) Quake-proof steel tie bar embedded part
CN215594765U (en) Auxiliary tool for forming setting slurry between component and ground
CN212053436U (en) Strenghthened type precast concrete wallboard and connection structure with from structure of taking one's place
CN103352568A (en) Method for building constructional column on foundation pad
CN108468388A (en) A kind of built-in fitting and its construction method
CN210597655U (en) Connecting joint between vertical stressed components
CN207568074U (en) A kind of secondary structure member reinforcing steel bar connecting node
CN104264992B (en) The construction method of skyscraper pipeline enclosure
CN202284291U (en) Concrete overflowing surface template shaped like Chinese character ba
CN206571057U (en) A kind of UPVC roofings c-type tile
CN206368433U (en) A kind of built-in fitting attachment structure
CN109137982B (en) Slurry base sleeve for underground comprehensive pipe gallery and construction method of comprehensive pipe gallery
CN201560579U (en) Device for arranging preformed hole on concrete structural slab

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20180803