CN104264992B - The construction method of skyscraper pipeline enclosure - Google Patents

The construction method of skyscraper pipeline enclosure Download PDF

Info

Publication number
CN104264992B
CN104264992B CN201410463553.0A CN201410463553A CN104264992B CN 104264992 B CN104264992 B CN 104264992B CN 201410463553 A CN201410463553 A CN 201410463553A CN 104264992 B CN104264992 B CN 104264992B
Authority
CN
China
Prior art keywords
support plate
pipeline
floor support
steel bar
bar truss
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201410463553.0A
Other languages
Chinese (zh)
Other versions
CN104264992A (en
Inventor
胡永红
白建勇
杨东升
汪亚忠
王小波
陈洪根
龚铁钾
梅国栋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Fifth Engineering Bureau Co Ltd
Original Assignee
Bengbu Construction Engineering Co Ltd of China Construction Fifth Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Bengbu Construction Engineering Co Ltd of China Construction Fifth Engineering Co Ltd filed Critical Bengbu Construction Engineering Co Ltd of China Construction Fifth Engineering Co Ltd
Priority to CN201410463553.0A priority Critical patent/CN104264992B/en
Publication of CN104264992A publication Critical patent/CN104264992A/en
Application granted granted Critical
Publication of CN104264992B publication Critical patent/CN104264992B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The invention discloses the construction method of skyscraper pipeline enclosure, comprise following step: main structure construction, angle steel is installed, steel bar truss floor support plate or prestressed concrete overlapped slab blanking, the perforate of pipeline installation site, old concrete dabbing, pipeline installation and steel bar truss floor support plate or prestressed concrete overlapped slab are installed, bar planting and assembling reinforcement, casting concrete, this method takes full advantage of steel bar truss floor support plate or prestressed concrete overlapped slab self rigidity, directly be routed on beam, carry out after simple reinforced bar engineering just directly casting concrete, substitute template completely, template erection and demolition works are saved, greatly improve floor slab construction efficiency, on steel bar truss floor support plate or prestressed concrete overlapped slab, unify perforate, and carry out centralized positioning with laser plummet, well ensured the quality that pipeline is installed, do not need to cut off the reinforcing bar on floor, accelerated progress, ensured construction quality.

Description

The construction method of skyscraper pipeline enclosure
Technical field
The invention belongs to building field, specifically the construction method of skyscraper pipeline enclosure.
Background technology
Pipeline enclosure is a requisite function room in building, is mainly used to arrange plumbing, fire-fighting, heating and ventilating pipeline and the cable pipeline etc. that in building, need. Pipeline enclosure is owing to need to laying more pipe laying, and designing unit is generally designed to the floor of pipeline enclosure reinforcing bar and as usual installs, and after pipeline installation, builds with high one-level slightly expanded concrete again. This kind of way, pipeline can bring secondary to set up support for shuttering after installing, install that template difficulty is large, expense is high, and tube circumference easily causes the hidden danger of quality such as seepage, top board out-of-flatness.
Summary of the invention
The technical problem to be solved in the present invention is to overcome the deficiencies in the prior art, a kind of construction method of skyscraper pipeline enclosure is provided, this method makes full use of steel bar truss floor support plate or prestressed concrete overlapped slab self rigidity, directly be routed on beam, carry out after simple reinforced bar engineering just directly casting concrete, substituted template completely, template erection and demolition works are saved, greatly improve floor slab construction efficiency, accelerated progress, ensured construction quality.
For solving the problems of the technologies described above, the invention provides a kind of construction method of skyscraper pipeline enclosure, comprise following concrete steps:
(1) main structure construction: main building when construction, floor is not constructed and made cavity, and pipeline enclosure is made to piping shaft, treats that agent structure form removable, floor cleared up, and carries out next process;
(2) angle steel is installed: on former xoncrete structure, the position from structure floor face toward next thickness of slab, installs equal leg angle, adopts setscrew to fix, and angle steel adopts spirit level to carry out horizontal plane control while installation, and guarantee angle steel is installed level;
(3) steel bar truss floor support plate blanking: according to piping shaft size, carry out the blanking of steel bar truss floor support plate by every limit size reduction 10~20mm, steel bar truss floor support plate lap width on angle steel is 50~75mm;
(4) pipeline installation site perforate: taking the center of pipe laying in construction drawing as the center of circle, increase 5mm again draw circle as radius taking the radius of pipe laying, carry out cut hole on steel bar truss floor support plate, cut hole adopts special circular cutter cutting regular;
(5) old concrete dabbing: because piping shaft periphery concrete is first casting concrete, in order to be combined with pipeline enclosure floorslab concrete, avoid cracking, above angle steel scope concrete must be carried out to dabbing, before secondary casting concrete, also need water moistening, brush by interfacial agents or cement mortar;
(6) pipeline is installed with steel bar truss floor support plate and is installed: pipeline carries out the installation of steel bar truss floor support plate when installation, adopt two laser plummets steel bar truss floor support plate to be positioned simultaneously, guarantee that pipeline center is consistent with steel bar truss floor support plate perforate center, when pipeline can not be installed simultaneously, can stay a floor support plate not install every 3~5 layers, so that pipe laying can be conveniently through floor support plate;
(7) bar planting, assembling reinforcement: after pipeline installation, at the enterprising andante reinforcing steel implant of piping shaft circumferential concrete, reinforcing bar size, bar planting spacing are identical with former designing requirement, are then connected with floor support plate reinforcing bar binding;
(8) concreting: after the hidden acceptance(check) of reinforcing bar, carry out concreting, concrete adopts from mixed concrete, carry out vertical transport by construction elevator, adopting trolley to carry out horizontal transport puts in place, while building, between tube circumference, floor support plate and former concrete, gap vibrating head vibration compacting, prevents percolating water.
For the purpose of describing the problem, below to the construction method of skyscraper pipeline enclosure of the present invention all referred to as this method.
Described in this method, steel bar truss floor support plate is that the reinforcing bar in floor is become to steel bar girder in factory process, and by steel bar girder and the integrally welded gang form of zinc-plated profiled sheet. This method takes full advantage of steel bar truss floor support plate self rigidity, is directly routed on beam, carries out after simple reinforced bar engineering just directly casting concrete, has substituted template completely, has saved template erection and demolition works, has greatly improved floor slab construction efficiency; On steel bar truss floor support plate, unify perforate, carry out centralized positioning with laser plummet, well ensured the quality that pipeline is installed; Do not need to cut off the reinforcing bar on floor, accelerated progress, ensured construction quality.
Steel bar truss floor support plate described in this method can replace with prestressed concrete overlapped slab, prestressed concrete overlapped slab is the prefabricated a kind of version combining with cast-in-place concrete, that cast-in-place concrete layer is made on prestressed thin slab, the cast-in-place concrete layer in prestressed thin slab (thick 5~8cm) and top is combined into as a whole, jointly works. The main muscle of prestressing force of prestressed thin slab is the main muscle of laminated floor slab, and cast-in-place concrete layer in top only configures negative reinforcement and distributing bar. Prestressed thin slab, as the bed die of cast-in-place concrete layer, needn't be cast-in-place concrete layer support shuttering, and prestressed thin slab bottom surface be smooth, and plate stitches after treatment, and ceiling can no longer be plastered.
Brief description of the drawings
Fig. 1 is that piping shaft stays and establishes plane.
Fig. 2 is angle steel scheme of installation.
Fig. 3 is steel bar truss floor support plate perforate schematic diagram.
Fig. 4 is that pipeline is installed and steel bar truss floor support plate erection sequence schematic diagram.
Fig. 5 is the schematic diagram after pipeline and steel bar truss floor support plate are installed.
Fig. 6 is bar planting and floor support plate reinforcing bar connection diagram.
Fig. 7 is the A-A cutaway view of Fig. 6.
Fig. 8 is concreting schematic diagram.
Detailed description of the invention
Below in conjunction with specification drawings and specific embodiments, the invention will be further described.
Embodiment mono-
The construction method of skyscraper pipeline enclosure, comprises following concrete steps:
(1) main structure construction: when main building construction, floor is not constructed and is made cavity, pipeline enclosure is made to piping shaft, piping shaft stays to be established as shown in Figure 1, in figure, 1 is to stay the piping shaft of establishing, the 2nd, beam, the 3rd, shear wall, treat that agent structure form removable, floor cleared up, install before starting and carry out next process;
(2) angle steel 4 is installed: on former xoncrete structure, the position from structure floor face toward next thickness of slab, installs L75 × 5 equal leg angle 4, adopt M12 setscrew to fix, as shown in Figure 2, angle steel 4 adopts spirit level to carry out horizontal plane control while installation, ensures angle steel 4 installation levels;
(3) steel bar truss floor support plate 5 blankings: according to piping shaft size, carry out the blanking of steel bar truss floor support plate 5 by every limit size reduction 20mm, steel bar truss floor support plate 5 lap width on angle steel 4 is 50mm;
(4) pipe hole 6 is opened in pipeline installation site: taking the center of pipe laying in construction drawing as the center of circle, add 5mm draw circle as radius taking the radius of pipe laying, output pipe hole 6, as shown in Figure 3 on steel bar truss floor support plate 5;
(5) old concrete dabbing: because piping shaft 1 periphery concrete is first casting concrete, in order to be combined with pipeline enclosure floorslab concrete, avoid cracking, above angle steel 4 scope concrete is carried out to dabbing, before secondary casting concrete, also need water moistening, brush by interfacial agents or cement mortar;
(6) pipeline 7 and steel bar truss floor support plate 5 are installed: when pipeline 7 is installed, carry out the installation of steel bar truss floor support plate 5, adopt two laser plummets steel bar truss floor support plate 5 to be positioned simultaneously, guarantee that pipeline 7 centers are consistent with steel bar truss floor support plate 5 perforate centers. when pipeline can not be installed simultaneously, can stay a steel bar truss floor support plate 5 not install every 3~5 layers, so that pipeline 7 can be conveniently through the pipe hole 6 of steel bar truss floor support plate 5, concrete erection sequence as shown in Figure 4, for example, after 7 installations of N layer pipeline, carry out the installation of N+1 layer pipeline 7, so first to carry out the installation of N+2 layer steel bar truss floor support plate 5, after steel bar truss floor support plate 5 installations, pipeline 7 inserts downwards and docks with lower floor pipeline 7 from the pipe hole 6 of N+2 layer steel bar truss floor support plate 5, complete the installation of N+1 layer pipeline 7, in like manner, when N+2 layer pipeline 7 installed, first carry out the installation of N+3 layer steel bar truss floor support plate 5, then pipeline 7 docks downwards and with lower floor pipeline 7 through steel bar truss floor support plate 5 from N+3 layer, the like installation, Fig. 5 is the schematic diagram after pipeline 7 and steel bar truss floor support plate 5 are installed,
(7) bar planting, assembling reinforcement: after pipeline 7 installations, in enterprising andante reinforcing bar 8 bar plantings of piping shaft 1 circumferential concrete, slab muscle 8 sizes, bar planting spacing are identical with designing requirement, are then connected with the reinforcing bar binding of steel bar truss floor support plate 5, as shown in Figure 6, Figure 7;
(8) concreting: after the hidden acceptance(check) of reinforcing bar, carry out concreting, as shown in Figure 8, concrete adopts from mixed concrete, carry out vertical transport by construction elevator, adopt trolley to carry out horizontal transport and put in place, while building, between tube circumference, floor support plate and former concrete, gap vibrating head vibration compacting, prevents percolating water.
Embodiment bis-
The construction method of skyscraper pipeline enclosure, comprises following concrete steps:
(1) main structure construction: main building when construction, floor is not constructed and made cavity, and pipeline enclosure is made to piping shaft, treats that agent structure form removable, floor clear up, before installation starts, carries out next process;
(2) angle steel is installed: on former xoncrete structure, the position from structure floor face toward next thickness of slab, installs L75 × 5 equal leg angle, adopts M12 setscrew to fix, and angle steel adopts spirit level to carry out horizontal plane control while installation, and guarantee angle steel is installed level;
(3) prestressed concrete overlapped slab blanking: according to piping shaft size, carry out the blanking of prestressed concrete overlapped slab by every limit size reduction 10mm, prestressed concrete overlapped slab lap width on angle steel is 75mm;
(4) pipe hole is opened in pipeline installation site: taking the center of pipe laying in construction drawing as the center of circle, add 5mm draw circle as radius taking the radius of pipe laying, output pipe hole on prestressed concrete overlapped slab;
(5) old concrete dabbing: because piping shaft periphery concrete is first casting concrete, in order to be combined with pipeline enclosure floorslab concrete, avoid cracking, above angle steel scope concrete is carried out to dabbing, before secondary casting concrete, also need water moistening, brush by interfacial agents or cement mortar;
(6) pipeline and prestressed concrete overlapped slab are installed: pipeline carries out the installation of prestressed concrete overlapped slab when installation, adopt two laser plummets prestressed concrete overlapped slab to be positioned simultaneously, guarantee that pipeline center is consistent with prestressed concrete overlapped slab perforate center. When pipeline can not be installed simultaneously, can stay a prestressed concrete overlapped slab not install every 3~5 layers, so as pipeline can be conveniently through the pipe hole of prestressed concrete overlapped slab;
(7) bar planting, assembling reinforcement: after pipeline installation, at the enterprising andante reinforcing steel implant of piping shaft circumferential concrete, slab muscle size, bar planting spacing are identical with designing requirement, are then connected with the reinforcing bar binding of prestressed concrete overlapped slab;
(8) concreting: after the hidden acceptance(check) of reinforcing bar, carry out concreting, concrete adopts from mixed concrete, carry out vertical transport by construction elevator, adopting trolley to carry out horizontal transport puts in place, while building, between tube circumference, floor support plate and former concrete, gap vibrating head vibration compacting, prevents percolating water.
Application example:
Certain skyscraper, underground 4 layers, 47 layers on the ground, 206.4 meters of maximum heights, overall floorage 148390m2, wherein overall floorage is 89600m on the ground2, underground overall floorage is 58790m2, in this building main building, have between two water pipes, between a heating coil between strong and weak electricity each one, pipeline enclosure floor adopts steel bar truss floor support plate construction, easy construction, operation easier reduce, and pipeline is installed fast, quality is better, all meets design and construction inspection of quality code requirement.
By adopting construction method of the present invention to carry out the construction of pipeline enclosure floor, effectively control construction quality, accelerate construction speed, obtain 10.6 ten thousand yuan of overall economic efficiencies.

Claims (5)

1. the construction method of skyscraper pipeline enclosure, comprises following concrete steps:
(1) main structure construction: when main building construction, floor is not constructed and made cavity, and pipeline enclosure is made to piping shaft;
(2) angle steel is installed: on former xoncrete structure, the position from structure floor towards next thickness of slab, installs equal leg angle, adopts setscrew to fix;
(3) steel bar truss floor support plate blanking: according to piping shaft size, carry out the blanking of steel bar truss floor support plate by every limit size reduction 10~20mm, steel bar truss floor support plate lap width on angle steel is 50~75mm;
(4) pipeline installation site perforate: taking the center of pipe laying in construction drawing as the center of circle, increase again 5mm taking the radius of pipe laying and draw circle as radius, carry out cut hole on steel bar truss floor support plate;
(5) old concrete dabbing: the old concrete of the above scope of angle steel is carried out to dabbing, and water is moistening before secondary casting concrete, brushes by interfacial agents or cement mortar;
(6) pipeline is installed with steel bar truss floor support plate and is installed: pipeline carries out the installation of steel bar truss floor support plate when installation, adopt two laser plummets steel bar truss floor support plate to be positioned simultaneously, make pipeline center consistent with steel bar truss floor support plate perforate center;
(7) bar planting, assembling reinforcement: after pipeline installation, at the enterprising andante reinforcing steel implant of piping shaft circumferential concrete, be then connected with steel bar truss floor support plate reinforcing bar binding;
(8) concreting: after the hidden acceptance(check) of reinforcing bar, carry out concreting.
2. the construction method of skyscraper pipeline enclosure as claimed in claim 1, is characterized in that: described steel bar truss floor support plate prestressed concrete overlapped slab replaces.
3. the construction method of skyscraper pipeline enclosure as claimed in claim 1 or 2, is characterized in that: when angle steel is installed in step (2), adopt spirit level to carry out horizontal plane control.
4. the construction method of skyscraper pipeline enclosure as claimed in claim 1 or 2, is characterized in that: it is regular that in step (4), cut hole adopts special circular cutter cutting.
5. the construction method of skyscraper pipeline enclosure as claimed in claim 1 or 2, is characterized in that: when the middle concreting of step (8), and gap vibrating head vibration compacting between tube circumference, steel bar truss floor support plate and former concrete.
CN201410463553.0A 2014-09-12 2014-09-12 The construction method of skyscraper pipeline enclosure Expired - Fee Related CN104264992B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410463553.0A CN104264992B (en) 2014-09-12 2014-09-12 The construction method of skyscraper pipeline enclosure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410463553.0A CN104264992B (en) 2014-09-12 2014-09-12 The construction method of skyscraper pipeline enclosure

Publications (2)

Publication Number Publication Date
CN104264992A CN104264992A (en) 2015-01-07
CN104264992B true CN104264992B (en) 2016-05-18

Family

ID=52156554

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410463553.0A Expired - Fee Related CN104264992B (en) 2014-09-12 2014-09-12 The construction method of skyscraper pipeline enclosure

Country Status (1)

Country Link
CN (1) CN104264992B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111734133A (en) * 2020-05-21 2020-10-02 青岛海川建设集团有限公司 Narrow space assembly type partition plate pipeline in-well decoration reverse construction method and structure
CN114776032A (en) * 2022-04-29 2022-07-22 中建二局第四建筑工程有限公司 Construction method of combined casing for water heating pipe well

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3800486A (en) * 1972-07-24 1974-04-02 Harvey W Co Pipe spacer
JP3425229B2 (en) * 1994-08-02 2003-07-14 ミサワホーム株式会社 Pipe space construction method of unit type building and pipe space structure
JP2002339450A (en) * 2001-05-11 2002-11-27 Misawa Homes Co Ltd Building construction method, building design system and partition panel
CN103015721B (en) * 2012-12-20 2015-07-15 山东万鑫建设有限公司 Leakage prevention construction method of reserved holes in kitchen and toilet
CN103089014A (en) * 2013-02-05 2013-05-08 浙江新东阳建设集团有限公司 Construction method of through floor pipe
CN203808502U (en) * 2014-03-06 2014-09-03 中国建筑第六工程局有限公司 Formwork device for secondary casting of cement for floor reserved openings

Also Published As

Publication number Publication date
CN104264992A (en) 2015-01-07

Similar Documents

Publication Publication Date Title
US10030792B2 (en) Underground steel-concrete structure pipeline with spiral composite reinforcement ring on inner wall and manufacturing method thereof
CN103981896B (en) The seamless link construction method of a kind of outer wall of basement and fender post
CN109505609B (en) Bracket-free construction method for underground comprehensive pipe rack of shallow-buried underground excavation city and comprehensive pipe rack
CN103643971B (en) Tunnel invert sizing end mould rapid constructing method
CN108331385B (en) Inspection pit precast column structure and construction method thereof
CN104131704A (en) Steel pipe column concrete lateral pouring method and steel pipe column structure used in method
CN204983662U (en) To drawing screw rod and steel pipe framed bent combination unilateral formwork device
CN105525753A (en) Method and structure for simultaneously constructing constructional column and main body structure
CN104594655A (en) Application method for dismantling temporary supports in brick-concrete structure wall
CN104831736A (en) Support changing method and support changing structure of middle wall of foundation trench
JP2017008568A (en) Tunnel joint structure and tunnel construction method
CN106760851A (en) The construction method of the newly-increased Seismic Isolation of Isolation Layer of existing brick mix structure
CN111456025A (en) Combined support replacing and dismantling construction method for ultra-deep foundation pit
CN104264992B (en) The construction method of skyscraper pipeline enclosure
CN206245763U (en) The positioner of live assembling reinforcement in precast construction
CN107083804A (en) A kind of wall structure post joint bar construction method
CN102352690B (en) Construction method of anti-floating locating system of cast-in-place concrete hollow floorslab steel tube
CN103696437A (en) Construction method for cutting latticed column
CN102493488A (en) Construction method for reverse beams and normal plates in foundation pit engineering
CN105350575A (en) Reverse construction method for underground continuous wall
CN105065040A (en) Top-plate-prefabricated underground space underground excavation building method
CN104895221B (en) Assembled shaped steel confined concrete shear wall structure
CN104153451A (en) Construction method for installing concrete pipeline through prefabricated supporting block
CN203834809U (en) Steel pipe column structure for steel pipe column concrete side pouring method
JP2014001550A (en) Slab for connection and construction method thereof

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20170412

Address after: 410116 Changsha Yuhua District, Hunan Zhongyi Road, No. 158

Patentee after: China Construction Fifth Engineering Division Co., Ltd.

Address before: Anhui city of Bengbu Province on the 233099 century iron building homes six four unit 10

Patentee before: In build Bangbu construction work Co., Ltd five innings

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160518

Termination date: 20170912