CN108355927A - Glue-dropping tool, dispenser and mainboard production method - Google Patents

Glue-dropping tool, dispenser and mainboard production method Download PDF

Info

Publication number
CN108355927A
CN108355927A CN201810273162.0A CN201810273162A CN108355927A CN 108355927 A CN108355927 A CN 108355927A CN 201810273162 A CN201810273162 A CN 201810273162A CN 108355927 A CN108355927 A CN 108355927A
Authority
CN
China
Prior art keywords
glue
cover board
support plate
mainboard
dropping tool
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810273162.0A
Other languages
Chinese (zh)
Inventor
覃华平
郭雄武
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen Huantai Technology Co Ltd
Original Assignee
Guangdong Oppo Mobile Telecommunications Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Oppo Mobile Telecommunications Corp Ltd filed Critical Guangdong Oppo Mobile Telecommunications Corp Ltd
Priority to CN201810273162.0A priority Critical patent/CN108355927A/en
Publication of CN108355927A publication Critical patent/CN108355927A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B05SPRAYING OR ATOMISING IN GENERAL; APPLYING FLUENT MATERIALS TO SURFACES, IN GENERAL
    • B05CAPPARATUS FOR APPLYING FLUENT MATERIALS TO SURFACES, IN GENERAL
    • B05C13/00Means for manipulating or holding work, e.g. for separate articles
    • B05C13/02Means for manipulating or holding work, e.g. for separate articles for particular articles

Landscapes

  • Coating Apparatus (AREA)

Abstract

The invention discloses a kind of glue-dropping tool, dispenser and mainboard production method, glue-dropping tools to include:Support plate and cover board, support plate are equipped at least one storage tank for placing single mainboard, and storage tank is corresponded with mainboard;Cover board is located at the side of support plate so that mainboard to be clamped between cover board and support plate, and mainboard adjacent to a side surface of cover board there is the first dispensing region, cover board to be equipped with multiple first dispensing hollow slots, and the first dispensing hollow slots are opposite with the first dispensing region.Glue-dropping tool according to the ... of the embodiment of the present invention, it can filter out underproof product in time before carrying out dispensing to mainboard, fundamentally avoid mainboard semi-finished product before test caused by after dispensing the problems such as maintenance difficult, the maintenanceability of product is improved, and reduces and scraps probability.

Description

Glue-dropping tool, dispenser and mainboard production method
Technical field
The present invention relates to gluing process fields, more particularly, to a kind of glue-dropping tool, dispenser and mainboard production method.
Background technology
In the production of mainboard, a bottom is needed for part large size BGA (Ball Grid Array, welded ball array encapsulation) Filler reinforces device, enhances the anti-dropping capability of chip bga, while in order to which waterproof needs, needing on mainboard Exposed device do whole plate coating waterproof.
In the mainboard semi-finished product procedure for producing for having a glue process, what promotion and dispensing generally for producing line efficiency produced Ease for operation, point glue process are placed in before dividing techniques, and production procedure is:Patch downloads software, dispensing, scoreboard, survey Examination, assembling.The mode of production has the following disadvantages:In the defective products that test phase tests out, by the upper glue of point, cause Maintenance difficult can not even repair.
Invention content
The application is made to the discovery of following facts and problem and understanding based on inventor:In the master for having a glue process In boards half-finished product procedure for producing, production procedure is:Patch downloads software, dispensing, scoreboard, test, assembling.The mode of production It has the following disadvantages:In the defective products that test phase tests out, by the upper glue of point, cause maintenance difficult even without Faville It repaiies.
It, can be by mainboard for this purpose, the present invention proposes that a kind of glue-dropping tool, the glue-dropping tool may be implemented to veneer dispensing Jigsaw carries out dispensing after being divided into veneer.
The present invention also proposes a kind of dispenser including above-mentioned glue-dropping tool.
The present invention also proposes a kind of mainboard production method.
The glue-dropping tool of embodiment according to a first aspect of the present invention, including:Support plate, the support plate are equipped at least one use In the storage tank for placing single mainboard, the storage tank is corresponded with the mainboard;And cover board, the cover board are located at the load The side of plate is the mainboard to be clamped between the cover board and the support plate, side table of the mainboard adjacent to the cover board There is the first dispensing region, the cover board to be equipped with the first dispensing hollow slots opposite with first dispensing region in face.
Glue-dropping tool according to the ... of the embodiment of the present invention, can the dispensing after mainboard jigsaw to be divided into veneer, make the life of mainboard Flow is produced by patch → download software → dispensing → scoreboard → test → assembling, becomes patch → download software → scoreboard → test → dispensing → assembling, so as to before carrying out dispensing to mainboard, filter out underproof product in time, fundamentally avoid Mainboard semi-finished product improve the maintenanceability of product before test caused by after dispensing the problems such as maintenance difficult, and reduce Scrap probability.
According to some embodiments of the present invention, further include location structure, the location structure includes being located at the storage tank Interior locating piece, the locating piece are arranged in the hole on the mainboard to realize positioning.
According to some embodiments of the present invention, the cover board is connected with the support plate magnetic.
In some embodiments of the invention, the cover board is equipped with the first magnetic absorption member, and the support plate is equipped with the second magnetic Part is inhaled, first magnetic absorption member coordinates with the second magnetic absorption member magnetic the cover board to be connected on the support plate.
Specifically, first magnetic absorption member and second magnetic absorption member are respectively in the circumferential direction of the cover board and the support plate It is spaced apart.
Optionally, the spacing d between two neighboring first magnetic absorption member meets:6mm≤d≤10mm.
It is magnetic one of in some embodiments of the present invention, first magnetic absorption member and second magnetic absorption member Iron, another is the magnetic material pieces that can be connected with magnet magnetic.
In other embodiments of the present invention, first magnetic absorption member and second magnetic absorption member are magnet.
In the still other embodiments of the present invention, magnet is equipped with one of in the cover board and the support plate, separately One is the magnetic material pieces that can be connected with magnet magnetic.
Some further embodiments according to the present invention, the support plate and the cover board are limited by position limiting structure to be coordinated.
Specifically, the position limiting structure include limited post on one of being located in the support plate and the cover board, Be formed in the support plate and the cover board another on limit hole.
In some embodiments of the invention, the support plate and the position of cover board limit cooperation are the support plate and institute State the intersection corner position of cover board.
Some further embodiments according to the present invention, a side surface of the mainboard far from the cover board have second point Glue region, the support plate are equipped with the second dispensing hollow slots opposite with second dispensing region.
Further, the edge of at least one of the support plate and described cover board, which inwardly concaves to be formed, picks and places slot.
Specifically, the storage tank is multiple, multiple storage tank rectangular array arrangements.
In some embodiments of the invention, the spacing L between two adjacent storage tanks meets:2mm≤L≤ 4mm。
The dispenser of embodiment according to a second aspect of the present invention includes the point according to the above-mentioned first aspect embodiment of the present invention Glue jig.
The dispenser of embodiment according to a second aspect of the present invention, by setting according to the above-mentioned first aspect embodiment of the present invention Glue-dropping tool, can the dispensing after mainboard jigsaw to be divided into veneer, make the production procedure of mainboard by patch → download software → Dispensing → scoreboard → test → assembling becomes patch → download software → scoreboard → test → dispensing → assembling, so as to To mainboard carry out dispensing before, filter out underproof product in time, fundamentally avoid mainboard semi-finished product before test by Caused by after dispensing the problems such as maintenance difficult, the maintenanceability of product is improved, and reduces and scraps probability.
The mainboard production method of embodiment according to a third aspect of the present invention, includes the following steps:S10:Patch process;S20: Dividing techniques;S30:Point glue process, wherein described glue process is located at after the dividing techniques.
The mainboard production method of embodiment according to a third aspect of the present invention, by will put glue process be placed on dividing techniques it Afterwards, mainboard semi-finished product can be effectively prevented from before test caused by dispensing the problems such as maintenance difficult, improve product Maintenanceability, and reduce and scrap probability.
According to some embodiments of the present invention, further include step before described glue process, after the dividing techniques S21:Test step.
According to some embodiments of the present invention, further include that step S11 downloads software process before the dividing techniques.
According to some embodiments of the present invention, implement using according to the above-mentioned first aspect of the present invention in described glue process The glue-dropping tool of example carries out dispensing.
The additional aspect and advantage of the present invention will be set forth in part in the description, and will partly become from the following description Obviously, or practice through the invention is recognized.
Description of the drawings
The above-mentioned and/or additional aspect and advantage of the present invention will become in the description from combination following accompanying drawings to embodiment Obviously and it is readily appreciated that, wherein:
Fig. 1 is the stereogram of glue-dropping tool according to the ... of the embodiment of the present invention;
Fig. 2 is the explosive view of glue-dropping tool according to the ... of the embodiment of the present invention;
Fig. 3 is the flow chart of mainboard production method according to the ... of the embodiment of the present invention.
Reference numeral:
Glue-dropping tool 100,
Support plate 1, storage tank 11, locating piece 111, the second magnetic absorption member 12 pick and place slot 13,
Cover board 2, the first dispensing hollow slots 21,
Position limiting structure 3, limited post 31, limit hole 32.
Specific implementation mode
The embodiment of the present invention is described below in detail, examples of the embodiments are shown in the accompanying drawings, wherein from beginning to end Same or similar label indicates same or similar element or element with the same or similar functions.Below with reference to attached The embodiment of figure description is exemplary, and is only used for explaining the present invention, and is not considered as limiting the invention.
In the description of the present invention, it is to be understood that, term "center", " longitudinal direction ", " transverse direction ", " length ", " width ", " thickness ", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom" "inner", "outside", " axial direction ", The orientation or positional relationship of the instructions such as " radial direction ", " circumferential direction " is to be based on the orientation or positional relationship shown in the drawings, merely to just In the description present invention and simplify description, do not indicate or imply the indicated device or element must have a particular orientation, with Specific azimuth configuration and operation, therefore be not considered as limiting the invention.In addition, defining " first ", " second " Feature can explicitly or implicitly include one or more this feature.In the description of the present invention, unless otherwise indicated, The meaning of " plurality " is two or more.
In the description of the present invention, it should be noted that unless otherwise clearly defined and limited, term " installation ", " phase Even ", " connection " shall be understood in a broad sense, for example, it may be being fixedly connected, may be a detachable connection, or be integrally connected;It can Can also be electrical connection to be mechanical connection;It can be directly connected, can also indirectly connected through an intermediary, Ke Yishi Connection inside two elements.For the ordinary skill in the art, above-mentioned term can be understood at this with concrete condition Concrete meaning in invention.
Glue-dropping tool 100 according to the ... of the embodiment of the present invention is described below with reference to Fig. 1-Fig. 2.Point according to the ... of the embodiment of the present invention Glue jig 100 can be used for the dispensing work production of mainboard semi-finished product.
As depicted in figs. 1 and 2, glue-dropping tool 100 according to the ... of the embodiment of the present invention, including:Support plate 1 and cover board 2.Support plate 1 It can be formed as rectangular slab with cover board 2.
Specifically, support plate 1 is equipped at least one storage tank 11 for placing single mainboard.Wherein, storage tank 11 can Think one or more.A mainboard can be placed in each storage tank 11.Preferably, storage tank 11 is multiple, Duo Gerong Slot 11 is set to correspond with multiple mainboards.Multiple storage tanks 11 can be arranged with rectangular array formula.The particular number of storage tank 11 It can be adjusted, be subject to the arrangement of support plate 1 is full according to the specific size of support plate 1.It, can be with for example, according to the apparent size of support plate 1 Arrangement 8 veneers (i.e. single mainboard), 6 veneers, 4 veneers etc..
Cover board 2 is located at the side (for example, upside in Fig. 1) of support plate 1 so that mainboard to be clamped between cover board 2 and support plate 1, Mainboard adjacent to a side surface (for example, uper side surface in Fig. 1) for cover board 2 there is the first dispensing region, cover board 2 to be equipped with and the The first opposite dispensing hollow slots 21 of one dispensing region.After cover board 2 is covered on support plate 1 as a result, the first dispensing hollow slots 21 can With opposite with the first dispensing region, so as to be carried out a little to the first dispensing region of mainboard by the first dispensing hollow slots 21 Glue.
Specifically, when carrying out dispensing using glue-dropping tool 100, the single mainboard after scoreboard can be placed on holding tank It is interior, then the lid of cover board 2 is located on support plate 1, mainboard is clamped between mainboard and cover board 2, and makes first point on cover board 2 Glue hollow slots 21 are opposite with the first dispensing region on mainboard.Hereafter, mainboard can be carried out by the first dispensing hollow slots 21 Dispensing is handled.
Glue-dropping tool 100 according to the ... of the embodiment of the present invention as a result, can the dispensing after mainboard jigsaw to be divided into veneer, make The production procedure of mainboard by patch → download software → dispensing → scoreboard → test → assembling, become patch → download software → point Plate → test → dispensing → assembling, so as to before carrying out dispensing to mainboard, filter out underproof product in time, from basic On avoid mainboard semi-finished product before test caused by after dispensing the problems such as maintenance difficult, improve repairing for product Property, and reduce and scrap probability.
According to some embodiments of the present invention, glue-dropping tool 100 further includes location structure, and location structure is accommodating including being located at Locating piece 111 in slot 11, locating piece 111 are arranged in the hole on mainboard to realize positioning.Locating piece 111 can be formed as column Shape or convex structure.Specifically, when mainboard to be embedded in storage tank 11, locating piece 111 can take advantage of a situation and penetrate on mainboard Hole.Thus, it is possible to further increase the reliability of positioning, it is ensured that first waits for that dispensing region is opposite with the first dispensing hollow slots 21 Accuracy.Further, it is to be appreciated that location structure whether include locating piece 111 and locating piece 111 installation position, It is required to basis and waits for that mainboard for dispensing glue carries out actual design, that is to say, that if waiting for not having hole on mainboard for dispensing glue, this When, there is no need to locating piece 111 is arranged in storage tank 11.
According to some embodiments of the present invention, cover board 2 is connected with 1 magnetic of support plate.That is, support plate 1 passes through with cover board 2 Magnetic attraction is connected with each other.Thus, it is possible to quickly and easily cover board 2 is connected on support plate 1, operating efficiency is improved, while can be with The cooperation reliability for improving support plate 1 and cover board 2, so as to will wait for mainboard for dispensing glue be clamped securely to support plate 1 and cover board 2 it Between, prevent board falling (preventing support plate 1 from being detached with cover board 2).
For example, in some embodiments of the invention, support plate 1 and the position that is connected with 2 magnetic of cover board are along support plate 1 and cover board 2 intersection periphery is uniformly distributed.That is, the thickness direction (i.e. the thickness direction of cover board 2) along support plate 1 projects, support plate 1 and cover board The profile complete cycle of 2 overlapping regions is evenly distributed with the connected position of magnetic.Thus, it is possible to avoid waiting for that mainboard for dispensing glue bears to answer Power, it is ensured that the safety of mainboard, and can be slipped between support plate 1 and cover board 2 to avoid mainboard.
In some embodiments of the invention, cover board 2 is equipped with the first magnetic absorption member (not shown), and support plate 1 is equipped with the Two magnetic absorption members 12, the first magnetic absorption member coordinate with 12 magnetic of the second magnetic absorption member cover board 2 to be connected on support plate 1.In this way, when that will lead After plate is placed on support plate 1 and fastens cover board 2, mainboard can be clipped in load by the first magnetic absorption member and the second mutually absorption of magnetic absorption member 12 Among plate 1 and cover board 2.
Specifically, the first magnetic absorption member and the second magnetic absorption member 12 are respectively in the circumferentially-spaced distribution of cover board 2 and support plate 1. That is circumferentially-spaced distribution of first magnetic absorption member in cover board 2, circumferentially-spaced distribution of second magnetic absorption member 12 in support plate 1. Optionally, the first magnetic absorption member is evenly spaced in the circumferential direction of cover board 2, and the second magnetic absorption member 12 is uniform in the circumferential direction of support plate 1 It is spaced apart.First magnetic absorption member and the second magnetic absorption member 12 can be at the profile complete cycle intervals of support plate 1 Yu 2 overlapping region of cover board point Cloth.It, can be to avoid waiting for a little as a result, by the way that the first magnetic absorption member and the second magnetic absorption member 12 to be located to the peripheral region of support plate 1 and cover board 2 The mainboard of glue meets with stresses, it is ensured that waits for the safety of dispensing mainboard, and can be to avoid waiting for mainboard for dispensing glue from support plate 1 and cover board 2 Between slip.
Specifically, support plate 1 is equipped with the first fitting groove, and the first magnetic absorption member is in the first fitting groove.Cover board 2 is equipped with the Two fitting grooves, the second magnetic absorption member 12 is in the second fitting groove.Thus, it is possible to improve the first magnetic absorption member and the second magnetic absorption member 12 The stability set improves the reliability of magnetic cooperation.
Further, multiple first magnetic absorption members are equipped between two adjacent row storage tanks 11 at interval.With reference to Fig. 2, carry Plate 1 is rectangular slab with cover board 2, and the frame position of " saying " font of rectangular slab is equipped with the first magnetic absorption member.Thus, it is possible to further Ground avoids waiting for that mainboard for dispensing glue meets with stresses, it is ensured that waits for the safety of dispensing mainboard, and can be to avoid waiting for mainboard for dispensing glue from load It is slipped between plate 1 and cover board 2.
Optionally, the spacing d between two neighboring first magnetic absorption member meets:6mm≤d≤10mm.For example, two neighboring Spacing d between one magnetic absorption member can further meet:D=6mm, d=8mm, d=10mm etc..Thus, it is possible to ensure support plate 1 There is sufficiently large magnetic attraction between cover board 2.
It is magnetic in some alternative embodiments of the present invention, one of in the first magnetic absorption member and the second magnetic absorption member 12 Iron, another is magnetic material pieces (such as ferrous material part, the mixing material of the magnetic powder containing opposite magnetic pole that can be connected with magnet magnetic Materials and parts).Facilitate processing as a result, and the effect that magnetic is connected is good.
In other alternative embodiments of the present invention, the first magnetic absorption member and the second magnetic absorption member 12 are magnet.It can manage The magnetic pole of solution, the first magnetic absorption member and the second magnetic absorption member 12 is opposite.Facilitate processing as a result, and the effect that magnetic is connected is good.
In still other alternative embodiment of the present invention, magnet is equipped with one of in cover board 2 and support plate 1, it is another A magnetic material pieces (such as ferrous material part, the mixing material materials and parts of the magnetic powder containing opposite magnetic pole) for that can be connected with magnet magnetic. Facilitate processing as a result, and the effect that magnetic is connected is good.
Some further embodiments according to the present invention, support plate 1 and cover board 2 are limited by position limiting structure 3 to be coordinated.Namely It says, support plate 1 other than magnetic is connected, is also limited by position limiting structure 3 and coordinated with cover board 2.Thus, it is possible to ensure 1 He of support plate The connected position face of 2 magnetic of cover board is accurate, to improve magnetic connected reliability, stability and validity.
Specifically, position limiting structure 3 includes limited post 31 on one of being located in support plate 1 and cover board 2 and is formed in Limit hole 32 on another in support plate 1 and cover board 2.For example, when support plate 1 be equipped with limited post 31 when, cover board 2 be equipped with The limit hole 32 that limited post 31 coordinates.When cover board 2 is equipped with limited post 31, support plate 1 is equipped with the limit coordinated with limited post 31 Position hole 32.Position limiting structure 3 is simple as a result, easy to process, and convenient for limit cooperation.Certainly, the specific composition of position limiting structure 3 is not It is limited to this, position limiting structure 3 can also include positive stop lug boss on one of being located in support plate 1 and cover board 2 and be formed in load Limiting groove etc. on another in plate 1 and cover board 2.
In some embodiments of the invention, the position of support plate 1 and the limit cooperation of cover board 2 is the intersection of support plate 1 and cover board 2 Corner position.That is, the thickness direction (i.e. the thickness direction of cover board 2) along support plate 1 projects, support plate 1 overlaps area with cover board 2 The corner position in domain, which is the position of limit cooperation, (such as in specific example shown in Fig. 1, can be arranged in the corner position and limit Position column 31 and limit hole 32).Thus, it is possible to improve the validity of limit, the reliability of support plate 1 and 2 magnetic of cover board and steady is improved It is qualitative.
Some further embodiments according to the present invention, a side surface of the mainboard far from cover board 2 is (for example, the following table in Fig. 1 Face) there is the second dispensing region, support plate 1 to be equipped with the second dispensing hollow slots corresponding with the second dispensing region.Work as support plate as a result, 1 upward when, the second dispensing hollow slots that can lead on support plate 1 treat the second dispensing region on mainboard and carry out dispensing processing, from And on the one hand it may be implemented to treat the two-sided dispensing of dispensing mainboard so that the manufacturing cost of glue-dropping tool 100 is greatly lowered.Separately On the one hand, due to a set of glue-dropping tool 100 only with the embodiment of the present invention, you can realize the two-sided dispensing for waiting for dispensing mainboard, So as to effectively save the parking space of glue-dropping tool 100.In another aspect, during dispensing, turned over by switching mechanism Turn glue-dropping tool 100, you can realize two-sided dispensing, the reduction disengaging orbit time of glue-dropping tool 100 is primary, effectively promotes production and imitates Rate.In addition, can unify while cross Reflow Soldering after completing two-sided dispensing, so as to effectively save electric energy, promotes Reflow Soldering and cross stove Efficiency.
Further, the edge of at least one of support plate 1 and cover board 2, which inwardly concaves to be formed, picks and places slot 13.Pick and place slot 13 can be formed as arc groove.Specifically, the edge of support plate 1 can be made to inwardly concave to be formed and pick and place slot 13, or make cover board 2 Edge inwardly concave to be formed and pick and place slot 13, or make the edge of support plate 1 and recessed formation picks and places respectively inwards the edge of cover board 2 Slot 13.It is understood that when be equipped on support plate 1 and cover board 2 pick and place slot 13 when, picking and placeing on slot 13 and cover board 2 on support plate 1 The slot 13 that picks and places offset one from another setting.Slot 13 is picked and placeed by setting as a result, to be convenient for separating support plate 1 and cover board 2.
The dispenser of embodiment according to a second aspect of the present invention includes the point according to the above-mentioned first aspect embodiment of the present invention Glue jig 100.Dispenser according to the ... of the embodiment of the present invention other constitute and operate for those of ordinary skill in the art and Speech is all known, is not detailed herein.
The dispenser of embodiment according to a second aspect of the present invention, by setting according to the above-mentioned first aspect embodiment of the present invention Glue-dropping tool 100, can the dispensing after mainboard jigsaw to be divided into veneer, make the production procedure of mainboard by patch → download software → dispensing → scoreboard → test → assembling becomes patch → download software → scoreboard → test → dispensing → assembling, so as to Before carrying out dispensing to mainboard, underproof product is filtered out in time, fundamentally avoids mainboard semi-finished product before test Caused by after dispensing the problems such as maintenance difficult, the maintenanceability of product is improved, and reduces and scraps probability.
The mainboard production method of embodiment according to a third aspect of the present invention, includes the following steps:
S10:Patch process;
S20:Dividing techniques;
S30:Point glue process.
Wherein, mainboard production method according to the ... of the embodiment of the present invention can be used for the production of mainboard finished product.Specifically, ginseng According to Fig. 3, mainboard production method according to the ... of the embodiment of the present invention carries out dividing techniques, and in scoreboard work after completing patch process Dispensing process is carried out after sequence.That is, a glue process is placed on after dividing techniques.Thus, it is possible to be effectively prevented from mainboard Semi-finished product improve the maintenanceability of product before test caused by dispensing the problems such as maintenance difficult, and reduce and scrap Probability.
Specifically, in the point glue process of the embodiment of the present invention, dispensing according to the above embodiment of the present invention can be used Jig 100 carries out dispensing, and dispensing is carried out to the mainboard after scoreboard so as to easily realize.
According to some embodiments of the present invention, further include step S21 before glue process, after dividing techniques:Test Process.Product can be assembled after test step.Thus, it is possible to filter out underproof product in time, fundamentally Mainboard semi-finished product are avoided before test caused by after dispensing the problems such as maintenance difficult, improve the maintenanceability of product, And it reduces and scraps probability.
According to some embodiments of the present invention, further include that step S11 downloads software process before dividing techniques.
Mainboard production method according to the ... of the embodiment of the present invention can be effectively after a glue process is placed on dividing techniques It avoids mainboard semi-finished product before test caused by dispensing the problems such as maintenance difficult, improves the maintenanceability of product, and drop It is low to scrap probability.
In the description of this specification, reference term " one embodiment ", " some embodiments ", " illustrative examples ", The description of " example ", " specific example " or " some examples " etc. means specific features described in conjunction with this embodiment or example, knot Structure, material or feature are included at least one embodiment or example of the invention.In the present specification, to above-mentioned term Schematic representation may not refer to the same embodiment or example.Moreover, specific features, structure, material or the spy of description Point can be combined in any suitable manner in any one or more of the embodiments or examples.
Although an embodiment of the present invention has been shown and described, it will be understood by those skilled in the art that:Not In the case of being detached from the principle of the present invention and objective a variety of change, modification, replacement and modification can be carried out to these embodiments, this The range of invention is limited by claim and its equivalent.

Claims (21)

1. a kind of glue-dropping tool, which is characterized in that including:
Support plate, the support plate are equipped at least one storage tank for placing single mainboard, the storage tank and the mainboard It corresponds;With
Cover board, the cover board are located at the side of the support plate so that the mainboard to be clamped between the cover board and the support plate, The mainboard adjacent to a side surface of the cover board there is the first dispensing region, the cover board to be equipped with and first glue application region The first opposite dispensing hollow slots of domain.
2. glue-dropping tool according to claim 1, which is characterized in that further include location structure, the location structure includes The locating piece being located in the storage tank, the locating piece are arranged in the hole on the mainboard to realize positioning.
3. glue-dropping tool according to claim 1, which is characterized in that the cover board is connected with the support plate magnetic.
4. glue-dropping tool according to claim 3, which is characterized in that the cover board is equipped with the first magnetic absorption member, the load Plate is equipped with the second magnetic absorption member, and first magnetic absorption member coordinates with the second magnetic absorption member magnetic the cover board is connected to institute It states on support plate.
5. glue-dropping tool according to claim 4, which is characterized in that first magnetic absorption member and second magnetic absorption member point Not in the circumferentially-spaced distribution of the cover board and the support plate.
6. glue-dropping tool according to claim 5, which is characterized in that the spacing between two neighboring first magnetic absorption member D meets:6mm≤d≤10mm.
7. glue-dropping tool according to claim 4, which is characterized in that in first magnetic absorption member and second magnetic absorption member One of be magnet, another is the magnetic material pieces that can be connected with magnet magnetic.
8. glue-dropping tool according to claim 4, which is characterized in that first magnetic absorption member and second magnetic absorption member are equal For magnet.
9. glue-dropping tool according to claim 3, which is characterized in that on one of in the cover board and the support plate Equipped with magnet, another is the magnetic material pieces that can be connected with magnet magnetic.
10. glue-dropping tool according to claim 1, which is characterized in that the support plate and the cover board pass through position limiting structure Limit cooperation.
11. glue-dropping tool according to claim 10, which is characterized in that the position limiting structure include be located at the support plate and Limited post on one of in the cover board and be formed in the support plate and the cover board another on limit Hole.
12. glue-dropping tool according to claim 10, which is characterized in that the position of the support plate and cover board limit cooperation It is set to the intersection corner position of the support plate and the cover board.
13. glue-dropping tool according to claim 1, which is characterized in that a side surface of the mainboard far from the cover board With the second dispensing region, the support plate is equipped with the second dispensing hollow slots opposite with second dispensing region.
14. glue-dropping tool according to claim 1, which is characterized in that at least one of the support plate and the cover board Edge inwardly concave to be formed and pick and place slot.
15. glue-dropping tool according to claim 1, which is characterized in that the storage tank is multiple, multiple storage tanks Rectangular array is arranged.
16. glue-dropping tool according to claim 15, which is characterized in that the spacing between two adjacent storage tanks L meets:2mm≤L≤4mm.
17. a kind of dispenser, which is characterized in that include the glue-dropping tool according to any one of claim 1-16.
18. a kind of mainboard production method, which is characterized in that include the following steps:
S10:Patch process;
S20:Dividing techniques;
S30:Point glue process, wherein described glue process is located at after the dividing techniques.
19. mainboard production method according to claim 18, which is characterized in that before described glue process, described minute Further include step S21 after plate process:Test step.
20. mainboard production method according to claim 18, which is characterized in that further include step before the dividing techniques Rapid S11:Download software process.
21. the mainboard production method according to any one of claim 18-20, which is characterized in that in described glue process The middle glue-dropping tool using according to any one of claim 1-16 carries out dispensing.
CN201810273162.0A 2018-03-29 2018-03-29 Glue-dropping tool, dispenser and mainboard production method Pending CN108355927A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810273162.0A CN108355927A (en) 2018-03-29 2018-03-29 Glue-dropping tool, dispenser and mainboard production method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810273162.0A CN108355927A (en) 2018-03-29 2018-03-29 Glue-dropping tool, dispenser and mainboard production method

Publications (1)

Publication Number Publication Date
CN108355927A true CN108355927A (en) 2018-08-03

Family

ID=63001354

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810273162.0A Pending CN108355927A (en) 2018-03-29 2018-03-29 Glue-dropping tool, dispenser and mainboard production method

Country Status (1)

Country Link
CN (1) CN108355927A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109239958B (en) * 2018-11-27 2022-03-08 深圳创维-Rgb电子有限公司 Plate part pasting device and process

Citations (20)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6195881B1 (en) * 1997-10-08 2001-03-06 The Erie Ceramic Arts Company Multiple coated substrates
CN102836808A (en) * 2011-06-23 2012-12-26 苏州五方光电科技有限公司 Glue dispensing universal fixture
CN103447194A (en) * 2013-08-29 2013-12-18 东莞市冠佳电子设备有限公司 Automatic dispensing curing equipment and automatic production line for chargers
CN203695348U (en) * 2013-12-12 2014-07-09 淳华科技(昆山)有限公司 Double-sided dispensing vehicle
CN103957666A (en) * 2014-04-30 2014-07-30 上海美维电子有限公司 Jig and carrier plate used for attaching circuit board strength reinforcing pieces
CN104384081A (en) * 2014-11-21 2015-03-04 苏州赛腾精密电子有限公司 Overturning adhesive dispensing fixture
CN204194245U (en) * 2014-10-10 2015-03-11 深圳市智立方自动化设备有限公司 A kind of vacuum absorption device of FPC and there is the point gum machine of this device
CN104883869A (en) * 2015-05-26 2015-09-02 科思技术(滁州)有限公司 LED module light bar production system
WO2016078002A1 (en) * 2014-11-19 2016-05-26 何素华 Led glue dispensing auxiliary fixture
CN205587258U (en) * 2016-04-14 2016-09-21 东莞市微科光电科技有限公司 Extension clamp tool
CN106313521A (en) * 2016-08-11 2017-01-11 上海斐讯数据通信技术有限公司 Dispensing and pressure holding jig
CN106455338A (en) * 2016-11-30 2017-02-22 江苏正桥影像科技股份有限公司 Special jig for automatic board attaching and automatic board attaching device
CN206122100U (en) * 2016-10-11 2017-04-26 东莞市幸森光电科技有限公司 Be used for gummed frock clamp of mobile phone motherboard
CN106612590A (en) * 2016-12-22 2017-05-03 惠州市蓝微电子有限公司 Battery protective plate packaging technology
CN206251451U (en) * 2016-12-14 2017-06-13 腾捷(厦门)电子有限公司 The magnetic carrier plate jig of carry magnet
CN206341490U (en) * 2016-12-29 2017-07-18 深圳市恒湖科技有限公司 The double-face spray painting masking frock of polylith circuit board
CN206650932U (en) * 2017-03-31 2017-11-17 江西合力泰科技有限公司 A kind of flexible PCB SMT patch jigs
CN206935708U (en) * 2017-05-31 2018-01-30 深圳市路路通线路板有限公司 One kind is applied to FPCA glue-dropping tools for dispensing glue and point glue equipment
CN107801369A (en) * 2017-11-29 2018-03-13 东莞铭普光磁股份有限公司 A kind of power supply automatic production process
CN208373474U (en) * 2018-03-29 2019-01-15 Oppo广东移动通信有限公司 Glue-dropping tool and dispenser

Patent Citations (20)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6195881B1 (en) * 1997-10-08 2001-03-06 The Erie Ceramic Arts Company Multiple coated substrates
CN102836808A (en) * 2011-06-23 2012-12-26 苏州五方光电科技有限公司 Glue dispensing universal fixture
CN103447194A (en) * 2013-08-29 2013-12-18 东莞市冠佳电子设备有限公司 Automatic dispensing curing equipment and automatic production line for chargers
CN203695348U (en) * 2013-12-12 2014-07-09 淳华科技(昆山)有限公司 Double-sided dispensing vehicle
CN103957666A (en) * 2014-04-30 2014-07-30 上海美维电子有限公司 Jig and carrier plate used for attaching circuit board strength reinforcing pieces
CN204194245U (en) * 2014-10-10 2015-03-11 深圳市智立方自动化设备有限公司 A kind of vacuum absorption device of FPC and there is the point gum machine of this device
WO2016078002A1 (en) * 2014-11-19 2016-05-26 何素华 Led glue dispensing auxiliary fixture
CN104384081A (en) * 2014-11-21 2015-03-04 苏州赛腾精密电子有限公司 Overturning adhesive dispensing fixture
CN104883869A (en) * 2015-05-26 2015-09-02 科思技术(滁州)有限公司 LED module light bar production system
CN205587258U (en) * 2016-04-14 2016-09-21 东莞市微科光电科技有限公司 Extension clamp tool
CN106313521A (en) * 2016-08-11 2017-01-11 上海斐讯数据通信技术有限公司 Dispensing and pressure holding jig
CN206122100U (en) * 2016-10-11 2017-04-26 东莞市幸森光电科技有限公司 Be used for gummed frock clamp of mobile phone motherboard
CN106455338A (en) * 2016-11-30 2017-02-22 江苏正桥影像科技股份有限公司 Special jig for automatic board attaching and automatic board attaching device
CN206251451U (en) * 2016-12-14 2017-06-13 腾捷(厦门)电子有限公司 The magnetic carrier plate jig of carry magnet
CN106612590A (en) * 2016-12-22 2017-05-03 惠州市蓝微电子有限公司 Battery protective plate packaging technology
CN206341490U (en) * 2016-12-29 2017-07-18 深圳市恒湖科技有限公司 The double-face spray painting masking frock of polylith circuit board
CN206650932U (en) * 2017-03-31 2017-11-17 江西合力泰科技有限公司 A kind of flexible PCB SMT patch jigs
CN206935708U (en) * 2017-05-31 2018-01-30 深圳市路路通线路板有限公司 One kind is applied to FPCA glue-dropping tools for dispensing glue and point glue equipment
CN107801369A (en) * 2017-11-29 2018-03-13 东莞铭普光磁股份有限公司 A kind of power supply automatic production process
CN208373474U (en) * 2018-03-29 2019-01-15 Oppo广东移动通信有限公司 Glue-dropping tool and dispenser

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109239958B (en) * 2018-11-27 2022-03-08 深圳创维-Rgb电子有限公司 Plate part pasting device and process

Similar Documents

Publication Publication Date Title
US7278193B2 (en) Device for coupling PCB sheet
CN103124038B (en) Flexible automatic assembling machine of mobile communication radio frequency coaxial connector
CN208373474U (en) Glue-dropping tool and dispenser
KR20100129025A (en) Novel process for molding composite inductors
CN108355927A (en) Glue-dropping tool, dispenser and mainboard production method
US8618423B2 (en) Mounting board including a flat-type electrical element and capable of being reduced in size, and lead-attached electric element that is flat in shape and has a lead bonded to each electrode face
CN102764943B (en) Battery welding combined clamping fixture and welding method thereof
US9281224B2 (en) Apparatus for positioning power semiconductor modules and method for surface treatment thereof
CN207410603U (en) A kind of jig for attaching mounted for LED component with wiring board
CN202655830U (en) Welding mould for manufacturing of photoelectric mould
CN211708330U (en) Welding tool for copper-clad ceramic substrate inside power semiconductor module
CN101556391A (en) Apparatus and method for providing, bonding drive circuit board and cassette case thereof
CN207925442U (en) It applies cream tooling and plants ball jig
CN110572561A (en) production process of VCM mobile phone camera module
CN206366772U (en) A kind of spot welding tool for being applicable lithium battery module
CN206869273U (en) A kind of tin soldering machine pcb board fixed mechanism
CN114284160A (en) IGBT module power terminal welding positioning assembly and method
CN206253839U (en) Key for musical instrument post fixed structure
CN208373470U (en) Glue-dropping tool and two-sided dispenser with it
CN102361537A (en) Reinforced mounting jig and mounting method thereof
CN116900735B (en) Wireless charger baby, assembly production line and assembly process thereof
CN206118192U (en) Pressfitting position sleeve installation tool
CN107105581A (en) The method and tool of stainless steel reinforcing chip automatic attaching are carried out to FPC using SMT chip mounters
CN110293385A (en) Hot and cold water ceramic cartridge automatic assembling machine
CN205812532U (en) A kind of SMT carrier controlling tin cream thickness

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information

Address after: Changan town in Guangdong province Dongguan 523860 usha Beach Road No. 18

Applicant after: GUANGDONG OPPO MOBILE TELECOMMUNICATIONS Corp.,Ltd.

Address before: Changan town in Guangdong province Dongguan 523860 usha Beach Road No. 18

Applicant before: GUANGDONG OPPO MOBILE TELECOMMUNICATIONS Corp.,Ltd.

CB02 Change of applicant information
TA01 Transfer of patent application right

Effective date of registration: 20211202

Address after: 518057 Fuan Science and Technology Building, Block B, No. 13, Yuehai Street, Nanshan District, Shenzhen City, Guangdong Province, 207-2

Applicant after: Shenzhen Huantai Technology Co.,Ltd.

Address before: Changan town in Guangdong province Dongguan 523860 usha Beach Road No. 18

Applicant before: GUANGDONG OPPO MOBILE TELECOMMUNICATIONS Corp.,Ltd.

TA01 Transfer of patent application right
RJ01 Rejection of invention patent application after publication

Application publication date: 20180803