CN108331525A CN201810063357.2A CN201810063357A CN108331525A CN 108331525 A CN108331525 A CN 108331525A CN 201810063357 A CN201810063357 A CN 201810063357A CN 108331525 A CN108331525 A CN 108331525A
Authority
CN
China
Prior art keywords
cavity
water pipe
guide runner
guide
slider guide
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810063357.2A
Other languages
Chinese (zh)
Other versions
CN108331525B (en
Inventor
洪杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xuzhou Juke Mechanical And Electrical Equipment Co Ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201810063357.2A priority Critical patent/CN108331525B/en
Publication of CN108331525A publication Critical patent/CN108331525A/en
Application granted granted Critical
Publication of CN108331525B publication Critical patent/CN108331525B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B1/00Percussion drilling
    • CCHEMISTRY; METALLURGY
    • C22METALLURGY; FERROUS OR NON-FERROUS ALLOYS; TREATMENT OF ALLOYS OR NON-FERROUS METALS
    • C22BPRODUCTION AND REFINING OF METALS; PRETREATMENT OF RAW MATERIALS
    • C22B3/00Extraction of metal compounds from ores or concentrates by wet processes
    • C22B3/02Apparatus therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B15/00Supports for the drilling machine, e.g. derricks or masts
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P10/00Technologies related to metal processing
    • Y02P10/20Recycling

Landscapes

  • Engineering & Computer Science (AREA)
  • Geology (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Mechanical Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Physics & Mathematics (AREA)
  • Chemical & Material Sciences (AREA)
  • Fluid Mechanics (AREA)
  • Materials Engineering (AREA)
  • Metallurgy (AREA)
  • Organic Chemistry (AREA)
  • Manufacturing & Machinery (AREA)
  • Earth Drilling (AREA)

Abstract

Mine device is soaked on the spot the invention discloses a kind of, including ore soaking machine body and articulated connection, the boring the ground mechanism in the ore soaking machine body left end is set, the first pedestal to be articulated and connected with the first support arm other end is installed on the ore soaking machine body right end end face, the second pedestal is equipped at the top of first pedestal, the first guide runner is equipped in the ore soaking machine body, it is slidably connected with the first slider guide in first guide runner, it is embedded with the first motor in the first guide runner left end inner wall, the first slider guide screw-internal thread fit is connected with the adjusting threaded rod that left and right extends, the adjusting threaded rod left end extending end and the first motor right end end be connected by power, what transition mating connection extended downwardly in first slider guide has multiple-segment telescopic tube;The configuration of the present invention is simple, it is easy to operate, convenient for storage, it is moved easily and carries, meanwhile, improve mineral leaching efficiency and effect.

Description

It is a kind of to soak mine device on the spot
Technical field
It is specifically a kind of to soak mine device on the spot the present invention relates to leaching mine equipment technical field.
Background technology
Novel species substance is all being sought in the whole world at present, constantly extracts various new elements from ore kind, is then tested, But there are bottlenecks for current mining technique on the spot, since required ore is all to carry general large size positioned at remote mountain area It is time-consuming and laborious to soak mine equipment, and general leaching mine equipment is all several equipment work in combination, required operating personnel's quantity is more, behaviour Make complexity, it is more to soak the required liquid slag inclusion quantity extracted after mine, it is difficult to it extracts, a major problem is brought to leaching mine overall work, Therefore, it is badly in need of a kind of leaching mine device on the spot at present.
Invention content
Mine device is soaked on the spot technical problem to be solved by the invention is to provide a kind of, can solve above-mentioned present technology The problems in.
The present invention is achieved through the following technical solutions:The a kind of of the present invention soaks mine device, including ore soaking machine on the spot Body and articulated connection are arranged boring the ground mechanism in the ore soaking machine body left end, the boring the ground mechanism be equipped with the first support arm, Second support arm and electric hammer head body, first support arm one end are articulated and connected with second support arm one end, institute The second support arm other end is stated to be fixedly connected with electric hammer head body left end end face, it is solid on the ore soaking machine body right end end face Equipped with the first pedestal to be articulated and connected with the first support arm other end, crus secunda is equipped at the top of first pedestal Seat, the ore soaking machine body is interior to be equipped with the first guide runner, and the first slider guide is slidably connected in first guide runner, described The first motor is embedded in first guide runner left end inner wall, the first slider guide screw-internal thread fit is connected with what left and right extended Adjust threaded rod, the adjustings threaded rod left end extending end and the first motor right end end be connected by power, described the What transition mating connection extended downwardly in one slider guide has multiple-segment telescopic tube, the multiple-segment telescopic tube to run through first slider guide Bottom end face, be embedded in first slider guide at the top of the multiple-segment telescopic tube being connected to the multiple-segment telescopic tube and The first water pipe upwardly extended is also embedded with to be connected to first water pipe and to the left extend in first slider guide Second water pipe, the second water pipe left end extending end is in the first slider guide left end end face, first guide runner It is communicated in the left end inner wall at the top of first motor equipped with the third water pipe extended to the left, first guide runner position In being equipped with metal hose for being connected to second water pipe and third water pipe, the third water in the first slider guide left end Pipe left end extending end is communicated equipped with the 4th water pipe that upwardly extends, is communicated in the middle part of the 4th water pipe equipped with the extended to the right Five water pipes, the 5th water pipe right end extending end are communicated equipped with water outlet pump, are equipped with barrier gate in the middle part of the 5th water pipe, it is described go out Suction pump at the top of water pump, suction pump left end end are communicated equipped with being connected with extending end at the top of the 4th water pipe 7th water pipe, suction pump right end end are communicated equipped with the 8th water pipe extended to the right, and the first guide runner top is equipped with First cavity, the first cavity top inner wall are connected with the 8th water pipe, and rectangle mistake is equipped in the middle part of first cavity Filter frame, top cap frame outside are fixedly connected with the first cavity vertical inner wall, the top cap frame It is fixedly provided with filter screen, described first cavity or so end is communicated equipped with symmetrical storage slag chamber, first cavity rear end inner wall Interior connection is equipped with the second guide runner, and driving scraping mechanism is equipped in second guide runner.
Preferably technical solution, the first support arm top end surface are installed with third pedestal, the third pedestal It is hingedly connected with the first hydraulically extensible column between second pedestal, the 4th is installed on the first support arm bottom end face Pedestal is installed with the 5th pedestal on the second support arm bottom end face, is cut with scissors between the 4th pedestal and the 5th pedestal It is connected to the second hydraulic column in succession.
Preferably technical solution, the metal hose have enough surpluses in the first guide runner.
Preferably technical solution, the drilling machine body is interior to be equipped with the second cavity that Open Side Down, second cavity Bottom is sequentially communicated from top to bottom is equipped with the third guide runner extended downwardly, the third cavity that Open Side Down, the third cavity Left end top inner wall is communicated equipped with the 4th cavity, and the second cavity left end is equipped with the 5th cavity extended up and down, and described second It is rotatably assorted in inner wall between cavity and the 5th cavity and is connected with the first rotation axis that left and right extends, described first turn Moving axis right end extending end puts in second cavity and is installed with the first cam, and first cam grows section right end end face hinge It is connected to the connecting rod extended downwardly in succession, the connecting rod bottom end is put in the third guide runner, the third slide guide It is slidably connected with the second slider guide of top end surface and the connecting rod articulated connection in slot, position in the third guide runner It is connected with piston in the second slider guide basal sliding, is rotatably assorted in the third cavity and is connected with outer cone flute profile set Cylinder, the outer cone flute profile sleeve is interior to be equipped with the 6th cavity, and third slider guide is slidably connected in the 6th cavity, described The first push rod upwardly extended is equipped at the top of third slider guide, first push rod is put in the third guide runner, and described the It is slidably connected with the auger spindle extended up and down in six cavity bottom inner walls, extending end puts in described the at the top of the shaft It is fixedly connected in six cavitys and with the third slider guide bottom end face, shaft bottom extending end stretches out the drilling machine Outside body bottom end face, the first rotation axis left end extending end puts in the 5th cavity and has the in end be connected by power Two motor, second motor outer surface is embedded in the 5th cavity left end inner wall and connection fixed thereto, described First rotation axis is located at the part in the 5th cavity and is equipped with the first sprocket wheel, and the first sprocket wheel cochain, which is connected to, extends downwardly chain Item is rotatably assorted between the 4th cavity and the 5th cavity and is connected with the second rotation axis of left and right extension, described second turn Moving axis left end extending end puts in the 5th cavity and is installed with the second sprocket wheel to be connect with the chain, and described the Two rotation axis right end extending ends are put in the 4th cavity and are installed with to ratcheting with the outer cone tooth form sleeve the One bevel gear.
Preferably technical solution, the scraper driving mechanism include being slided with top cap frame roof end face The slide plate being slidably connected in the scraper plate and second guide runner being connected with, the slide plate front end surface It is fixedly connected with scraper plate rear end end, the sliding slot extended up and down, second guide runner rear end is equipped in the slide plate Third motor is embedded in inner wall, the third motor front end be connected by power has the second cam, second cam Front end surface is equipped with the supporting rod to be slidably connected with the sliding slot.
Preferably technical solution, the multiple-segment telescopic tube are slidably connected between respectively saving.
Preferably technical solution, there are four wheels for the setting of ore soaking machine body bottom.
The beneficial effects of the invention are as follows:The configuration of the present invention is simple, it is easy to operate, it is hingedly connected with by ore soaking machine body left end Boring the ground mechanism may be implemented effectively the progress that boring the ground punches on the spot, and follow-up leaching miner is convenient for make, solve the maximum for soaking mine on the spot Problem is slidably connected with the further through opening the first guide runner to the right is provided in ore soaking machine body in the first guide runner One slider guide, the first slider guide screw-internal thread fit are connected with the adjusting threaded rod that left and right extends, and adjust threaded rod left end and extend end End be connected by power has the first motor, the first motor outer surface to be embedded in the first guide runner left end inner wall, and fixed thereto Connection, the first slider guide is interior to be equipped with the multiple-segment telescopic tube that Open Side Down, communicates at the top of multiple-segment telescopic tube and runs through equipped with left end end Second water pipe of the first slider guide left end end face, the interior perforation of the first guide runner left end inner wall are embedded with the third water that left and right extends Pipe, the interior metal being connected with second water pipe and third water pipe being equipped with positioned at the first slider guide left end of the first guide runner Hose, third water pipe left end end are connected the 4th water pipe extended up and down, and right end is equipped with water outlet pump in the middle part of the 4th water pipe, goes out It is communicated between water pump and the 4th water pipe equipped with the 5th water pipe, the 5th water pipe is equipped with barrier gate, and the 4th water pipe top end right end is set There are suction pump, suction pump left end end to be connected with the 4th water pipe end, suction pump right end is communicated equipped with the 7th water pipe, and first The first cavity is equipped at the top of guide runner, the first cavity top inner wall is connected with the 7th water pipe right end end, in the first cavity Equipped with rectangular sieve frame, it is equipped with filter screen in rectangular sieve frame, is communicated equipped with the second slide guide in the first cavity rear end inner wall Slot, the second guide runner is interior to be equipped with driving screeding device, is communicated equipped with symmetrical storage slag chamber in the first cavity both ends inner wall, to It realizes automatic note ore leachate and absorbs the solution after leaching mine, required solution obtains purer extracting solution by filtering, can be with It carries out leaching miner in maximum magnitude to make, time saving and energy saving, cheap, easy to remove, high degree of automation, meanwhile, it improves just Soak the efficiency and effect of mine in ground.
Description of the drawings
The present invention is described in detail by following specific embodiment and attached drawing for ease of explanation,.
Fig. 1 is that a kind of of the present invention soaks mine device overall structure diagram on the spot;
Fig. 2 is the structural schematic diagram of A in Fig. 1;
Fig. 3 is the structural schematic diagram of B in Fig. 2;
Fig. 4 is the structural schematic diagram of the drilling body of the present invention.
Specific implementation mode
As Figure 1-Figure 4, a kind of leaching mine device on the spot of the invention, including ore soaking machine body 2 and articulated connection setting In the boring the ground mechanism of 2 left end of ore soaking machine body, the boring the ground mechanism is equipped with the first support arm 4, the second support arm 5 and electricity Tup portion body 6, described first support arm, 4 one end are articulated and connected with described second support arm, 5 one end, second support arm 5 The other end is fixedly connected with 6 left end end face of electric hammer head body, be installed on 2 right end end face of the ore soaking machine body to First pedestal 28 of 4 other end of the first support arm articulated connection, first pedestal, 28 top are equipped with the second pedestal 29, institute It states and is equipped with the first guide runner 21 in ore soaking machine body 2, the first slider guide 3, institute are slidably connected in first guide runner 21 It states and is embedded with the first motor 211 in 21 left end inner wall of the first guide runner, 3 screw-internal thread fit of the first slider guide is connected with a left side The adjusting threaded rod 212 of right extension, the 212 left end extending end of adjusting threaded rod and 211 right end of the first motor end Hold be connected by power, in first slider guide 3 transition be connected extend downwardly have multiple-segment telescopic tube 32, the multi-joint telescoping Pipe 32 runs through 3 bottom end face of the first slider guide, is embedded in first slider guide 3 at 32 top of the multiple-segment telescopic tube To the first water pipe 31 for being connected to and upwardly extending with the multiple-segment telescopic tube 32, also it is embedded in first slider guide 3 useful With the second water pipe 33 for being connected to first water pipe 31 and extending to the left, second water pipe, 33 left end extending end runs through institute 3 left end end face of the first slider guide is stated, is located in first guide runner 21 in the left end inner wall at first motor, 211 top It communicates equipped with the third water pipe 214 extended to the left, first guide runner 21, which is located to be equipped in 3 left end of the first slider guide, to be used In the metal hose 213 for being connected to second water pipe 33 and third water pipe 214,214 left end extending end phase of the third water pipe Logical to be equipped with the 4th water pipe 26 upwardly extended, 26 middle part of the 4th water pipe is communicated equipped with the 5th water pipe 241 extended to the right, institute It states 241 right end extending end of the 5th water pipe to communicate equipped with water outlet pump 24,241 middle part of the 5th water pipe is equipped with barrier gate 242, described 24 top suction pump 25 of water outlet pump, 25 left end end of the suction pump, which communicates, to be equipped with and 26 top extending end of the 4th water pipe The 7th water pipe 252 being connected, 25 right end end of the suction pump is communicated equipped with the 8th water pipe 252 extended to the right, described First guide runner, 21 top is equipped with the first cavity 22, and 22 top inner wall of the first cavity is connected with the 8th water pipe 252, First cavity, 22 middle part is equipped with top cap frame 221, the outer outside of the top cap frame 221 and first cavity 22 vertical inner walls are fixedly connected, and the top cap frame 221 is fixedly provided with filter screen 224, first cavity 22 or so End is communicated equipped with symmetrical storage slag chamber 23, in first cavity, 22 rear end inner wall connection be equipped with the second guide runner 27, described the Driving scraping mechanism is equipped in two guide runners 27.
Valuably, 4 top end surface of the first support arm is installed with third pedestal 41, the third pedestal 41 and described the It is hingedly connected with the first hydraulically extensible column 42 between two pedestals 29, the 4th foot is installed on 4 bottom end face of the first support arm Seat 43 is installed with the 5th pedestal 51, the 4th pedestal 43 and the 5th pedestal 51 on second support arm, 5 bottom end face Between be hingedly connected with the second hydraulic column 44, realization automatically controls the arbitrary activity of drilling body 6, is beaten for leaching mine in maximum magnitude The effect of leaching mine is improved in hole.
Valuably, the metal hose 213 has enough surpluses in the first guide runner 21, wear-resisting and prevent from being drawn It is disconnected.
Valuably, it is equipped with the second cavity 61 that Open Side Down in the drilling body 6,61 bottom of the second cavity is from upper It is sequentially communicated under and and is equipped with the third guide runner 63 extended downwardly, the third cavity 64 that Open Side Down, the third cavity 64 is left End top inner wall is communicated equipped with the 4th cavity 65, and 61 left end of the second cavity is equipped with the 5th cavity 62 extended up and down, described It is rotatably assorted in inner wall between second cavity 61 and the 5th cavity 62 and is connected with the first rotation axis that left and right extends 611, first rotation axis, 611 right end extending end puts in second cavity 61 and is installed with the first cam 612, described First cam 612 grows section right end end face and is hingedly connected with the connecting rod 613 extended downwardly, and 613 bottom end of the connecting rod is stretched Into in the third guide runner 63, top end surface and the connecting rod 613 are slidably connected in the third guide runner 63 Second slider guide 631 of articulated connection, the third guide runner 63 is interior to be located at 631 basal sliding of the second slider guide cooperation company It is connected to piston 632, is rotatably assorted in the third cavity 64 and is connected with outer cone flute profile sleeve 641, the outer cone flute profile sleeve 641 It is inside equipped with the 6th cavity 642, third slider guide 6421, the third slide guide are slidably connected in the 6th cavity 643 6421 top of block is equipped with the first push rod 643 upwardly extended, and first push rod 643 is put in the third guide runner 63, institute It states and is slidably connected with the auger spindle 644 extended up and down in 642 bottom interior wall body of the 6th cavity, 644 top of the shaft extends End puts in the 6th cavity 642 and is fixedly connected with 6421 bottom end face of third slider guide, 644 bottom of the shaft Portion extending end stretches out outside 6 bottom end face of drilling body, and first rotation axis, 611 left end extending end puts in described the There is the second motor 622 in five cavitys 62 and in end be connected by power, 622 outer surface of the second motor is embedded at described the In five cavitys, 62 left end inner wall and connection fixed thereto, first rotation axis 611 are located at the part in the 5th cavity 62 Equipped with the first sprocket wheel 621,621 cochain of the first sprocket wheel, which is connected to, extends downwardly chain 623, the 4th cavity 65 and described the It is rotatably assorted between five cavitys 62 and is connected with the second rotation axis 624 of left and right extension, second rotation axis, 624 left end extending end It puts in the 5th cavity 62 and is installed with the second sprocket wheel 625 to be connect with the chain 623, second rotation axis 624 right end extending ends are put in the 4th cavity 65 and are installed with to ratcheting with the outer cone tooth form sleeve 641 the One bevel gear 651 increases drilling efficiency to realize vertical tremor and the rotation of auger spindle.
Valuably, the scraper driving mechanism includes being slidably connected with 221 top end surface of top cap frame The slide plate 273 being slidably connected in some scraper plates 222 and second guide runner 27,273 front end of the slide plate End face is fixedly connected with 222 rear end end of the scraper plate, and the sliding slot 2731 extended up and down is equipped in the slide plate 273, described Third motor 272 is embedded in second guide runner, 27 rear end inner wall, 272 front end be connected by power of the third motor has Second cam 271,271 front end surface of the second cam are equipped with the supporting rod to be slidably connected with the sliding slot 2731 274, it realizes the left and right working in reciprocating mode for automatically controlling scraper plate, prevents filter screen from blocking.
Valuably, the multiple-segment telescopic tube 32 is slidably connected between respectively saving, and realizes etchant depth capacity soaking mine.
Valuably, there are four wheel, devices easy to remove for 2 bottom of the ore soaking machine body setting.
When original state, the first support arm 4 is located at vertical position, and the second support arm 5 is horizontally situated, the first slider guide 3 are located at 21 right end of the first guide runner, and multiple-segment telescopic tube 32 is shunk completely in the first slider guide, and supporting rod 274 is located at second Above 271 center line of cam, slide plate 273 is located at 27 middle part of the second guide runner, and scraper plate 222 is made to be located at 22 middle part of the first cavity, the One cam 612 grows section and is located at center line back end, at this point, the second slider guide 631 is located at the middle part of sliding stroke, third slider guide 6421 are located at 642 top of the 6th cavity, and 643 depth capacity of the first push rod stretches into third guide runner 63, at this point, piston 632 643 top end of the first push rod of bottom top pressure.
When needing leaching miner to make, device is moved integrally to the position of required leaching mine, at this point, automatically controlling the first hydraulic pressure Telescopic mast 4 and the second hydraulically extensible column 5 freely stretch, and drilling body 6 is made to contact the required ore position to drill, meanwhile, control Second motor 622 drives the rotation of the first rotation axis 611, the first rotation axis 611 to drive the first sprocket wheel 621 and the first cam 612 Rotation, the first cam 612 drives connecting rod 613 that the second slider guide 631 is pushed to move back and forth up and down, when the first cam 612 grows section When positioned at bottom, the second slider guide 631 is located at the bottommost of sliding stroke, and 631 impact piston 632 of the second slider guide makes piston 632 form huge impact force, so that the first push rod 643 is quickly moved down and third slider guide 6421 is driven to move down, third slider guide 6421 drive auger spindles 644 quickly move down, and when the first cam 612, which grows section, is located at top, the second slider guide 631 is located at sliding and goes The top of journey at this point, 6422 top pressure third slider guide 6421 of top pressure spring quickly moves up, and drives the first push rod 643 and bores Axis 644 quickly moves up, 643 impact piston 632 of the first push rod, makes piston 632 that there is mobile inertia to move up a distance, according to Boring the ground work is realized in secondary reciprocating motion, meanwhile, the first sprocket wheel 621 drives chain 623 to rotate, and chain 623 drives the second sprocket wheel 625 rotations, the second sprocket wheel 625 drive the rotation of the second rotation axis 624, the second rotation axis 624 that first bevel gear 651 is driven to rotate, First bevel gear 651 drives external tooth type sleeve 641 to rotate, and external tooth type sleeve 641 drives auger spindle 644 to rotate, to accelerate boring the ground First support arm 4 and the second support arm 5 are restored to initial position, at this point, control first by speed when completing boring the ground work Motor 211, which drives, adjusts the rotation of threaded rod 212, so that the first slider guide 3 is moved to right and skids off outside the first guide runner 21, works as multi-joint telescoping When pipe 32 is located at the top of institute bore position, the first motor 211 of control shuts down, by the elongation of multiple-segment telescopic tube 32 to being drilled Bottom, at this point, opening barrier gate 242, the control operating of water outlet pump 24 fills solvent into drilling, when soaking mine completion, closes barrier gate 242, control suction pump 25 extracts the solution in drilling out, and solution, which enters in the first cavity 22, to be sprinkling upon on filter screen 224, at this point, Controlling third motor 272 drives the rotation of the second cam 271, the second cam 271 that supporting rod 274 is driven to rotate, and keeps slide plate 273 left It moves right, slide plate 273 drives scraper plate 222 to move left and right, and the indissoluble composition granule on filter screen 224 is blown into storage slag chamber 23.
The beneficial effects of the invention are as follows:The configuration of the present invention is simple, it is easy to operate, it is hingedly connected with by ore soaking machine body left end Boring the ground mechanism may be implemented effectively the progress that boring the ground punches on the spot, and follow-up leaching miner is convenient for make, solve the maximum for soaking mine on the spot Problem is slidably connected with the further through opening the first guide runner to the right is provided in ore soaking machine body in the first guide runner One slider guide, the first slider guide screw-internal thread fit are connected with the adjusting threaded rod that left and right extends, and adjust threaded rod left end and extend end End be connected by power has the first motor, the first motor outer surface to be embedded in the first guide runner left end inner wall, and fixed thereto Connection, the first slider guide is interior to be equipped with the multiple-segment telescopic tube that Open Side Down, communicates at the top of multiple-segment telescopic tube and runs through equipped with left end end Second water pipe of the first slider guide left end end face, the interior perforation of the first guide runner left end inner wall are embedded with the third water that left and right extends Pipe, the interior metal being connected with second water pipe and third water pipe being equipped with positioned at the first slider guide left end of the first guide runner Hose, third water pipe left end end are connected the 4th water pipe extended up and down, and right end is equipped with water outlet pump in the middle part of the 4th water pipe, goes out It is communicated between water pump and the 4th water pipe equipped with the 5th water pipe, the 5th water pipe is equipped with barrier gate, and the 4th water pipe top end right end is set There are suction pump, suction pump left end end to be connected with the 4th water pipe end, suction pump right end is communicated equipped with the 7th water pipe, and first The first cavity is equipped at the top of guide runner, the first cavity top inner wall is connected with the 7th water pipe right end end, in the first cavity Equipped with rectangular sieve frame, it is equipped with filter screen in rectangular sieve frame, is communicated equipped with the second slide guide in the first cavity rear end inner wall Slot, the second guide runner is interior to be equipped with driving screeding device, is communicated equipped with symmetrical storage slag chamber in the first cavity both ends inner wall, to It realizes automatic note ore leachate and absorbs the solution after leaching mine, required solution obtains purer extracting solution by filtering, can be with It carries out leaching miner in maximum magnitude to make, time saving and energy saving, cheap, floor space is small, easy to remove, high degree of automation, together When, improve the efficiency and effect for soaking mine on the spot.
The above description is merely a specific embodiment, but scope of protection of the present invention is not limited thereto, any The change or replacement expected without creative work, should be covered by the protection scope of the present invention.Therefore, of the invention Protection domain should be determined by the scope of protection defined in the claims.

Claims (7)

1. a kind of soaking mine device on the spot, including the boring the ground machine in the ore soaking machine body left end is arranged in ore soaking machine body and articulated connection Structure, it is characterised in that:The boring the ground mechanism is equipped with the first support arm, the second support arm and electric hammer head body, and described the One support arm one end is articulated and connected with second support arm one end, the second support arm other end and electric hammer head machine Body left end end face is fixedly connected, and is installed on the ore soaking machine body right end end face to hinged with the first support arm other end First pedestal of connection, the first pedestal top are equipped with the second pedestal, and the first guide runner is equipped in the ore soaking machine body, described The first slider guide is slidably connected in first guide runner, it is electronic to be embedded with first in the first guide runner left end inner wall Machine, the first slider guide screw-internal thread fit are connected with the adjusting threaded rod that left and right extends, and the adjusting threaded rod left end extends End and the first motor right end end be connected by power, in first slider guide transition be connected having of extending downwardly Multiple-segment telescopic tube, the multiple-segment telescopic tube runs through the first slider guide bottom end face, described at the top of the multiple-segment telescopic tube The first water pipe to be connected to and upwardly extend with the multiple-segment telescopic tube, first slider guide are embedded in first slider guide Inside also it is embedded with the second water pipe to be connected to first water pipe and extend to the left, the second water pipe left end extending end In the first slider guide left end end face, first guide runner in the left end inner wall at the top of first motor It communicates equipped with the third water pipe extended to the left, first guide runner, which is located in the first slider guide left end, to be equipped with for being connected to The metal hose of second water pipe and third water pipe, the third water pipe left end extending end are communicated equipped with the upwardly extended Four water pipes, the 4th water pipe middle part are communicated equipped with the 5th water pipe extended to the right, the 5th water pipe right end extending end phase It is logical to be equipped with water outlet pump, barrier gate, water outlet pump top suction pump, suction pump left end end are equipped in the middle part of the 5th water pipe It communicates equipped with the 7th water pipe being connected with extending end at the top of the 4th water pipe, suction pump right end end, which communicates, to be set There is the 8th water pipe extended to the right, the first cavity, the first cavity top inner wall and institute are equipped at the top of first guide runner It states the 8th water pipe to be connected, top cap frame, the outer outside of the top cap frame and institute is equipped in the middle part of first cavity It states the first cavity vertical inner wall to be fixedly connected, the top cap lower portion is installed with filter screen, first cavity or so End is communicated equipped with symmetrical storage slag chamber, and inner wall interior connection in first cavity rear end is equipped with the second guide runner, second slide guide Driving scraping mechanism is equipped in slot.
2. a kind of leaching mine device on the spot according to claim 1, it is characterised in that:The first support arm top end surface is solid Equipped with third pedestal, it is hingedly connected with the first hydraulically extensible column between the third pedestal and second pedestal, described first It is installed with the 4th pedestal on support arm bottom end face, is installed with the 5th pedestal on the second support arm bottom end face, described It is hingedly connected with the second hydraulic column between four pedestals and the 5th pedestal.
3. a kind of leaching mine device on the spot according to claim 1, it is characterised in that:The metal hose is in the first guide runner Inside there are enough surpluses.
4. a kind of leaching mine device on the spot according to claim 1, it is characterised in that:Be equipped in the drilling machine body opening to Under the second cavity, second cavity bottom be sequentially communicated from top to bottom equipped with extend downwardly third guide runner, be open to Under third cavity, the third cavity left end top inner wall communicates equipped with the 4th cavity, and the second cavity left end is equipped with upper 5th cavity of lower extension, being rotatably assorted in the inner wall between second cavity and the 5th cavity is connected with left and right and prolongs The first rotation axis stretched, the first rotation axis right end extending end put in second cavity and are installed with the first cam, First cam grows section right end end face and is hingedly connected with the connecting rod extended downwardly, and the connecting rod bottom end puts in described In third guide runner, the second of top end surface and connecting rod articulated connection is slidably connected in the third guide runner Slider guide, the third guide runner is interior to be connected with piston, the third cavity positioned at the second slider guide basal sliding It is inside rotatably assorted and is connected with outer cone flute profile sleeve, the 6th cavity is equipped in the outer cone flute profile sleeve, is slided in the 6th cavity It is dynamic to be connected with third slider guide, it is equipped with the first push rod upwardly extended, first push rod at the top of the third slider guide It puts in the third guide runner, is slidably connected with the auger spindle extended up and down in the 6th cavity bottom inner wall, institute Extending end at the top of shaft is stated to put in the 6th cavity and be fixedly connected with the third slider guide bottom end face, described turn Axis bottom extending end stretches out outside the drilling body bottom end face, and the first rotation axis left end extending end puts in described the There is the second motor in five cavitys and in end be connected by power, it is left that second motor outer surface is embedded at the 5th cavity It holds in inner wall and connection fixed thereto, first rotation axis is located at the part in the 5th cavity and is equipped with the first sprocket wheel, institute It states the first sprocket wheel cochain and is connected to and extend downwardly chain, be rotatably assorted between the 4th cavity and the 5th cavity and be connected with a left side The second rotation axis of right extension, the second rotation axis left end extending end put in the 5th cavity and be installed with to institute State the second sprocket wheel of chain connection, the second rotation axis right end extending end put in the 4th cavity and be installed with to The ratcheting first bevel gear with the outer cone tooth form sleeve.
5. a kind of leaching mine device on the spot according to claim 1, it is characterised in that:The scraper driving mechanism includes and institute It states and is slidably connected in the scraper plate and second guide runner that top cap frame roof end face is slidably connected with Slide plate, the slide plate front end surface is fixedly connected with scraper plate rear end end, is equipped in the slide plate upper downward The sliding slot stretched is embedded with third motor, the third motor front end power in the inner wall of second guide runner rear end It is connected with the second cam, the second cam front end surface is equipped with the supporting rod to be slidably connected with the sliding slot.
6. a kind of leaching mine device on the spot according to claim 1, it is characterised in that:The multiple-segment telescopic tube is sliding between respectively saving It is dynamic to be connected.
7. a kind of leaching mine device on the spot according to claim 1, it is characterised in that:Ore soaking machine body bottom is provided with four A wheel, device easy to remove.
CN201810063357.2A 2018-01-23 2018-01-23 It is a kind of to soak mine device on the spot Active CN108331525B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810063357.2A CN108331525B (en) 2018-01-23 2018-01-23 It is a kind of to soak mine device on the spot

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810063357.2A CN108331525B (en) 2018-01-23 2018-01-23 It is a kind of to soak mine device on the spot

Publications (2)

Publication Number Publication Date
CN108331525A true CN108331525A (en) 2018-07-27
CN108331525B CN108331525B (en) 2019-01-22

Family

ID=62925615

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810063357.2A Active CN108331525B (en) 2018-01-23 2018-01-23 It is a kind of to soak mine device on the spot

Country Status (1)

Country Link
CN (1) CN108331525B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110259372A (en) * 2019-06-19 2019-09-20 嘉兴缔华贸易有限公司 A kind of oil content exploring equipment

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4221433A (en) * 1978-07-20 1980-09-09 Occidental Minerals Corporation Retrogressively in-situ ore body chemical mining system and method
CN101915073A (en) * 2010-08-03 2010-12-15 江西稀有金属钨业控股集团有限公司 In situ leaching injection process
CN102392129A (en) * 2011-11-17 2012-03-28 五矿(北京)稀土研究院有限公司 Method and system of in-situ ore leaching and leachate discharge of ion adsorption type ore
CN203655249U (en) * 2013-12-23 2014-06-18 新疆中核天山铀业有限公司 In-situ leaching uranium mining process well
CN104694746A (en) * 2015-03-25 2015-06-10 江西理工大学 Ion-adsorption-type rare earth in-situ leaching method and leaching system thereof

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4221433A (en) * 1978-07-20 1980-09-09 Occidental Minerals Corporation Retrogressively in-situ ore body chemical mining system and method
CN101915073A (en) * 2010-08-03 2010-12-15 江西稀有金属钨业控股集团有限公司 In situ leaching injection process
CN102392129A (en) * 2011-11-17 2012-03-28 五矿(北京)稀土研究院有限公司 Method and system of in-situ ore leaching and leachate discharge of ion adsorption type ore
CN203655249U (en) * 2013-12-23 2014-06-18 新疆中核天山铀业有限公司 In-situ leaching uranium mining process well
CN104694746A (en) * 2015-03-25 2015-06-10 江西理工大学 Ion-adsorption-type rare earth in-situ leaching method and leaching system thereof

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110259372A (en) * 2019-06-19 2019-09-20 嘉兴缔华贸易有限公司 A kind of oil content exploring equipment

Also Published As

Publication number Publication date
CN108331525B (en) 2019-01-22

Similar Documents

Publication Publication Date Title
CN105804764B (en) One kind bores the formula development machine that rises
CN106677699B (en) A kind of coal mine automatic liquid drilol press
CN201714392U (en) Rock drilling device
CN106150382B (en) It bores anchor and visits Multi Role Aircraft
CN107130656B (en) Integrated mining loader with functions of underground drilling, anchoring and rock breaking
CN108222931B (en) A kind of rotary rock drill splits all-in-one machine
CN104033168B (en) From moving platform-type brill anchor car
CN105840100A (en) Self-moving type water jet drilling machine
CN214616516U (en) Multifunctional mining manipulator
CN115075728B (en) Petroleum geological exploration drill rod device
CN108331525B (en) It is a kind of to soak mine device on the spot
CN203756080U (en) Automatic pipe racker of drilling platform
CN107762402B (en) A kind of efficient rock drill
CN108331526B (en) It is a kind of to soak mine equipment on the spot
CN211173964U (en) Pile machine suitable for drilling in rock block soil
CN206174866U (en) Bore anchor and visit multifunctional machine
CN106854881A (en) Rig on excavator with quartering hammer
CN108729850A (en) A kind of novel leaching mine device on the spot
CN110513039A (en) The both arms roofboltier of primary positioning tunneling boring construction
CN216841455U (en) Be applied to wear-resisting baffle of machine of digging soon
CN113153160B (en) Roller bit drill rod for roller bit rig
CN112796358A (en) Underground mining prying scraper and mining method thereof
CN214424409U (en) Drilling mechanism for mine exploitation blasting
CN206428738U (en) Rig on excavator with quartering hammer
CN209723079U (en) A kind of sled hair excavates and loads all-in-one machine

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20181211

Address after: 221000 North Longitudinal Third Road, No. 3, Third Industrial Park, Xuzhou High-tech Industrial Development Zone, Jiangsu Province

Applicant after: Xuzhou Juke Mechanical and Electrical Equipment Co., Ltd.

Address before: 441100 Xiangyang, Hubei, Xiangzhou District, central China, 24 of the bright market 5

Applicant before: Hong Jie

GR01 Patent grant
GR01 Patent grant