CN108330764A - 浅层固化桩承式路堤及施工方法 - Google Patents

浅层固化桩承式路堤及施工方法 Download PDF

Info

Publication number
CN108330764A
CN108330764A CN201810325006.4A CN201810325006A CN108330764A CN 108330764 A CN108330764 A CN 108330764A CN 201810325006 A CN201810325006 A CN 201810325006A CN 108330764 A CN108330764 A CN 108330764A
Authority
CN
China
Prior art keywords
energy
layer
prestressing force
pile
cement soil
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810325006.4A
Other languages
English (en)
Other versions
CN108330764B (zh
Inventor
王新泉
梁建锋
李肖
洪东平
崔允亮
张世民
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang University City College ZUCC
Original Assignee
Zhejiang University City College ZUCC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang University City College ZUCC filed Critical Zhejiang University City College ZUCC
Priority to CN201810325006.4A priority Critical patent/CN108330764B/zh
Publication of CN108330764A publication Critical patent/CN108330764A/zh
Application granted granted Critical
Publication of CN108330764B publication Critical patent/CN108330764B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C3/00Foundations for pavings
    • E01C3/04Foundations produced by soil stabilisation
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/12Pile foundations
    • E02D27/16Foundations formed of separate piles

Abstract

本发明涉及浅层固化桩承式路堤,包括:固化硬壳层、预应力管桩、加筋垫层、路堤、加劲预应力水泥土墙和生态石笼护脚,所述加劲预应力水泥土墙顶部通过预埋螺栓连接盖板;所述加劲预应力水泥土墙设于就地固化范围边界处,加劲预应力水泥土墙进入粉土粉砂层不少于4m;加劲预应力水泥土墙顶部有连接凹槽,与盖板通过预埋螺栓连接,连接凹槽内填充细石混凝土封板;所述固化硬壳层范围为路基以下以及坡脚向外延伸10~15m范围内。本发明的有益效果是:本发明能够解决泥浆池范围内路堤的加固问题,有效减少路堤的不均匀沉降及侧向变形;完善了软土淤泥路堤结构,尤其是浅层固化形成完整的承载体系,改进了施工方法。

Description

浅层固化桩承式路堤及施工方法
技术领域
本发明涉及基础工程施工技术领域,具体涉及浅层固化桩承式路堤及施工方法。
背景技术
由于软土淤泥层的特性,使得软土地区路堤存在沉降、失稳等问题,严重影响了公路的质量与寿命,加大了公路的维护成本。通过软土淤泥换填处理,即在一定范围内,把影响路基稳定性的淤泥软土用挖掘机挖除,用稳定性好的土、石回填并压实或夯实,形成良好的人工地基。但换填处理工作量较大,耗费较多材料,且换填出淤泥的堆放影响市政形象。
为此,通过浅层固化形成硬壳层,形成力学强度更好的土层,解决了换填法带来的弊端。但是,通过单一的浅层固化处理,尚不能形成完整的承载体系,路堤结构依旧不够完善。若在浅层固化区打设预应力管桩,形成浅层固化桩承式路堤,容易出现固化层硬度太大,打设难度大的问题
因此,完善软土淤泥路堤结构,尤其是浅层固化形成完整的承载体系,改进施工方法,具有重要的工程意义。
发明内容
本发明的目的是克服现有技术中的不足,提供一种浅层固化桩承式路堤及施工方法。
这种浅层固化桩承式路堤,包括:固化硬壳层、预应力管桩、加筋垫层、路堤、加劲预应力水泥土墙和生态石笼护脚,所述加劲预应力水泥土墙顶部通过预埋螺栓连接盖板;所述加劲预应力水泥土墙设于就地固化范围边界处,加劲预应力水泥土墙进入粉土粉砂层不少于4m;加劲预应力水泥土墙顶部有连接凹槽,与盖板通过预埋螺栓连接,连接凹槽内填充细石混凝土封板。
作为优选:所述固化硬壳层范围为路基以下以及坡脚向外延伸10~15m范围内。
作为优选:所述预应力管桩桩长14~16m,预应力管桩进入粉土粉砂层不少于4m,桩间距路基以下0.25~0.35m,正三角形布置;路基以外15m范围内的桩,桩间距0.35~0.4m,正三角形布置。
作为优选:所述加筋垫层位于固化硬壳层以上、路堤以下,所述加筋垫层厚0.5~0.7m。
作为优选:所述生态石笼护脚设于加劲预应力水泥土墙外侧,深0.4~0.6m,顶宽0.2~0.4m,坡比1:2;生态石笼护脚由石笼网箱固定件固定。
这种浅层固化桩承式路堤的施工方法,包括以下步骤:
1)填土围堰:在就地固化边界处设置围堰;
2)排水:将围堰范围涌出淤泥吹填至围堰外侧,围堰形成后对围堰内排水;
3)两侧坡脚固化:在路基两侧10m~15m保护区范围就地固化之前先填土,厚度1.5~2m,填土高度至高出水位0.2~0.3m,再对保护区进行固化;
4)加劲预应力水泥土墙施工:紧贴固化层边界处打设一排加劲预应力水泥土墙;
5)路基范围抽水、固化:就地固化厚度至泥浆池底部,固化宽度为路堤坡脚向外延伸2~4m,形成固化硬壳层;
6)安放留置模具:固化完成后,在管桩位置打入留置模具作为管桩孔,采用整体式带刃口切孔模具钻设桩帽;
7)固化范围整平压实:当固结土的含水率较低时,固结阶段施工完成后整平压实;
8)吊出留置模具;在固化区完全硬化前,吊出带尖头留孔钢管;
9)固化区养护:固化区洒水养护至设计强度;
10)预应力管桩施工:在管桩留置孔处打设预应力管桩,采用锤击式管桩机;
11)生态石笼护脚施工:加劲预应力水泥土墙外侧施工生态石笼护脚,深0.4~0.6m,顶宽0.2~0.4m,坡比1:2;
12)加筋垫层施工:铺设0.2~0.3m厚碎石作为第一层土工格室,铺设0.3~0.4m厚清砼渣作为第二层土工格室;
13)路堤施工:采用超载预压,超载高度1~1.2m,预压期5~7个月;
14)路基保护区绿化:路基保护区植被绿化。
作为优选:步骤6)中留置模具由带尖头留孔钢管、钢管顶封板、夹板、夹板上的夹板拔管孔、带丝双套筒及后装带丝定位杆组成;夹板拔管孔用于吊装留置模具,带丝双套筒上安装后装带丝定位杆,后装带丝定位杆用于调整打设角度。
作为优选:步骤6)中整体式带刃口切孔模具由带槽口模具骨架、槽口、旋柄、固定式带刃口切孔板及分离式带刃口切孔板组成;槽口用于安装分离式带刃口切孔板,旋柄用于调整打设角度。
本发明的有益效果是:
(1)本发明能够解决泥浆池范围内路堤的加固问题,有效减少路堤的不均匀沉降及侧向变形。
(2)完善了软土淤泥路堤结构,尤其是浅层固化形成完整的承载体系,改进了施工方法。
(3)该施工方法安全、工期短,施工过程对周边环境影响小,可实现零清淤零换填,具有节能、环保、造价低的优势,适于推广应用。
附图说明
图1是浅层固化桩承式路堤结构示意图;
图2是留置模具构件示意图;
图3是整体式带刃口切孔模具示意图;
图4是施工工艺流程图;
附图标记说明:1.泥浆;2.粉土层;3.粉砂层;4.淤泥质黏土;5.固化硬壳层;6.加劲预应力水泥土墙;7.预应力管桩;8.桩帽;9.连接凹槽;10.预埋螺栓;11.细石混凝土封板;12.钢垫板;13.盖板;14.生态石笼护脚;15.石笼网箱固定件;16.雨水管;17.加筋垫层;18.路堤;19.路基保护区;20.带尖头留孔钢管;21.钢管顶封板;22.夹板;23.夹板拔管孔;24.带丝双套筒;25.后装带丝定位杆;26.整体式带刃口切孔模具;27.带槽口模具骨架;28.槽口;29.旋柄;30.固定式带刃口切孔板;31.分离式带刃口切孔板。
具体实施方式
下面结合实施例对本发明做进一步描述。下述实施例的说明只是用于帮助理解本发明。应当指出,对于本技术领域的普通技术人员来说,在不脱离本发明原理的前提下,还可以对本发明进行若干改进和修饰,这些改进和修饰也落入本发明权利要求的保护范围内。
如图1至图3所示,所示浅层固化桩承式路堤包括固化硬壳层5、预应力管桩7、加筋垫层17、路堤18、加劲预应力水泥土墙6和生态石笼护脚14,所述加劲预应力水泥土墙6顶部通过预埋螺栓10连接盖板13;所述加劲预应力水泥土墙6设于就地固化范围边界处,加劲预应力水泥土墙6进入粉土粉砂层不少于4m;加劲预应力水泥土墙6顶部有连接凹槽9,与盖板13通过预埋螺栓10连接,连接凹槽9内填充细石混凝土封板11。
所述固化硬壳层5范围为路基以下以及坡脚向外延伸10~15m范围内。
所述预应力管桩7桩长14~16m,预应力管桩7进入粉土粉砂层不少于4m,桩间距路基以下0.25~0.35m,正三角形布置;路基以外15m范围内的桩,桩间距0.35~0.4m,正三角形布置。
所述加筋垫层17位于固化硬壳层5以上、路堤18以下,所述加筋垫层17厚0.5~0.7m。
所述生态石笼护脚14设于加劲预应力水泥土墙6外侧,深0.4~0.6m,顶宽0.2~0.4m,坡比1:2;生态石笼护脚14由石笼网箱固定件15固定。
所述浅层固化桩承式路堤的施工方法,包括以下步骤:
1)填土围堰:在就地固化边界处设置围堰;
2)排水:将围堰范围涌出淤泥吹填至围堰外侧,围堰形成后对围堰内排水;
3)两侧坡脚固化:在路基两侧10m~15m保护区范围就地固化之前先填土,厚度1.5~2m,填土高度至高出水位0.2~0.3m,再对保护区进行固化;
4)加劲预应力水泥土墙6施工:紧贴固化层边界处打设一排加劲预应力水泥土墙6;
5)路基范围抽水、固化:就地固化厚度至泥浆池底部,固化宽度为路堤坡脚向外延伸2~4m,形成固化硬壳层5;
6)安放留置模具:固化完成后,在管桩位置打入留置模具作为管桩孔,采用整体式带刃口切孔模具26钻设桩帽8;
7)固化范围整平压实:当固结土的含水率较低时,固结阶段施工完成后整平压实;
8)吊出留置模具;在固化区完全硬化前,吊出带尖头留孔钢管20;
9)固化区养护:固化区洒水养护至设计强度;
10)预应力管桩7施工:在管桩留置孔处打设预应力管桩7,采用锤击式管桩机;
11)生态石笼护脚14施工:加劲预应力水泥土墙6外侧施工生态石笼护脚14,深0.4~0.6m,顶宽0.2~0.4m,坡比1:2;
12)加筋垫层17施工:铺设0.2~0.3m厚碎石作为第一层土工格室,铺设0.3~0.4m厚清砼渣作为第二层土工格室;
13)路堤18施工:采用超载预压,超载高度1~1.2m,预压期5~7个月;
14)路基保护区19绿化:路基保护区19植被绿化。
留置模具由带尖头留孔钢管20、钢管顶封板21、夹板22、夹板22上的夹板拔管孔23、带丝双套筒24及后装带丝定位杆25组成;夹板拔管孔23用于吊装留置模具,带丝双套筒24上安装后装带丝定位杆25,后装带丝定位杆25用于调整打设角度。
整体式带刃口切孔模具26由带槽口模具骨架27、槽口28、旋柄29、固定式带刃口切孔板30及分离式带刃口切孔板31组成;槽口28用于安装分离式带刃口切孔板31,旋柄29用于调整打设角度。

Claims (8)

1.浅层固化桩承式路堤,其特征在于包括:固化硬壳层(5)、预应力管桩(7)、加筋垫层(17)、路堤(18)、加劲预应力水泥土墙(6)和生态石笼护脚(14),所述加劲预应力水泥土墙(6)顶部通过预埋螺栓(10)连接盖板(13);所述加劲预应力水泥土墙(6)设于就地固化范围边界处,加劲预应力水泥土墙(6)进入粉土粉砂层不少于4m;加劲预应力水泥土墙(6)顶部有连接凹槽(9),与盖板(13)通过预埋螺栓(10)连接,连接凹槽(9)内填充细石混凝土封板(11)。
2.根据权利要求1所述的浅层固化桩承式路堤,其特征在于所述固化硬壳层(5)范围为路基以下以及坡脚向外延伸10~15m范围内。
3.根据权利要求1所述的浅层固化桩承式路堤,其特征在于所述预应力管桩(7)桩长14~16m,预应力管桩(7)进入粉土粉砂层不少于4m,桩间距路基以下0.25~0.35m,正三角形布置;路基以外15m范围内的桩,桩间距0.35~0.4m,正三角形布置。
4.根据权利要求1所述的浅层固化桩承式路堤,其特征在于所述加筋垫层(17)位于固化硬壳层(5)以上、路堤(18)以下,所述加筋垫层(17)厚0.5~0.7m。
5.根据权利要求1所述的浅层固化桩承式路堤,其特征在于所述生态石笼护脚(14)设于加劲预应力水泥土墙(6)外侧,深0.4~0.6m,顶宽0.2~0.4m,坡比1:2;生态石笼护脚(14)由石笼网箱固定件(15)固定。
6.一种根据权利要求1所述的浅层固化桩承式路堤的施工方法,其特征在于包括以下步骤:
1)填土围堰:在就地固化边界处设置围堰;
2)排水:将围堰范围涌出淤泥吹填至围堰外侧,围堰形成后对围堰内排水;
3)两侧坡脚固化:在路基两侧10m~15m保护区范围就地固化之前先填土,厚度1.5~2m,填土高度至高出水位0.2~0.3m,再对保护区进行固化;
4)加劲预应力水泥土墙(6)施工:紧贴固化层边界处打设一排加劲预应力水泥土墙(6);
5)路基范围抽水、固化:就地固化厚度至泥浆池底部,固化宽度为路堤坡脚向外延伸2~4m,形成固化硬壳层(5);
6)安放留置模具:固化完成后,在管桩位置打入留置模具作为管桩孔,采用整体式带刃口切孔模具(26)钻设桩帽(8);
7)固化范围整平压实:当固结土的含水率较低时,固结阶段施工完成后整平压实;
8)吊出留置模具;在固化区完全硬化前,吊出带尖头留孔钢管(20);
9)固化区养护:固化区洒水养护至设计强度;
10)预应力管桩(7)施工:在管桩留置孔处打设预应力管桩(7),采用锤击式管桩机;
11)生态石笼护脚(14)施工:加劲预应力水泥土墙(6)外侧施工生态石笼护脚(14),深0.4~0.6m,顶宽0.2~0.4m,坡比1:2;
12)加筋垫层(17)施工:铺设0.2~0.3m厚碎石作为第一层土工格室,铺设0.3~0.4m厚清砼渣作为第二层土工格室;
13)路堤(18)施工:采用超载预压,超载高度1~1.2m,预压期5~7个月;
14)路基保护区(19)绿化:路基保护区(19)植被绿化。
7.根据权利要求6所述的浅层固化桩承式路堤的施工方法,其特征在于步骤6)中留置模具由带尖头留孔钢管(20)、钢管顶封板(21)、夹板(22)、夹板(22)上的夹板拔管孔(23)、带丝双套筒(24)及后装带丝定位杆(25)组成;夹板拔管孔(23)用于吊装留置模具,带丝双套筒(24)上安装后装带丝定位杆(25),后装带丝定位杆(25)用于调整打设角度。
8.根据权利要求6所述浅层固化桩承式路堤的施工方法,其特征在于步骤6)中整体式带刃口切孔模具(26)由带槽口模具骨架(27)、槽口(28)、旋柄(29)、固定式带刃口切孔板(30)及分离式带刃口切孔板(31)组成;槽口(28)用于安装分离式带刃口切孔板(31),旋柄(29)用于调整打设角度。
CN201810325006.4A 2018-04-12 2018-04-12 浅层固化桩承式路堤及施工方法 Active CN108330764B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810325006.4A CN108330764B (zh) 2018-04-12 2018-04-12 浅层固化桩承式路堤及施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810325006.4A CN108330764B (zh) 2018-04-12 2018-04-12 浅层固化桩承式路堤及施工方法

Publications (2)

Publication Number Publication Date
CN108330764A true CN108330764A (zh) 2018-07-27
CN108330764B CN108330764B (zh) 2023-09-26

Family

ID=62933020

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810325006.4A Active CN108330764B (zh) 2018-04-12 2018-04-12 浅层固化桩承式路堤及施工方法

Country Status (1)

Country Link
CN (1) CN108330764B (zh)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110144784A (zh) * 2019-06-13 2019-08-20 福建工程学院 基于预应力混凝土板桩构筑的市政道路及其施工方法
CN110886287A (zh) * 2019-09-29 2020-03-17 中交第一航务工程勘察设计院有限公司 一种浅层软土地基固化结构及其施工方法
CN111321742A (zh) * 2020-03-08 2020-06-23 华中科技大学 一种高含水率淤泥的一体化处理与填料装置及方法
CN113463457A (zh) * 2021-05-17 2021-10-01 衡阳公路桥梁建设有限公司 一种用于穿越泥浆地段的路基结构及其施工方法
CN114508011A (zh) * 2022-01-13 2022-05-17 中国水利水电第七工程局有限公司 一种桩承式软土路基加固结构和加固方法

Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003268790A (ja) * 2002-03-15 2003-09-25 Taisei Corp 軟弱地盤の沈下低減方法
JP2010209571A (ja) * 2009-03-10 2010-09-24 East Japan Railway Co 線路下横断構造物の構築用支持杭施工方法
JP2011202427A (ja) * 2010-03-26 2011-10-13 Railway Technical Research Institute パイルスラブ盛土及びその工法
CN102493472A (zh) * 2011-12-13 2012-06-13 中交第二公路工程局有限公司 一种桥梁深水软土地基逆作法低桩承台复合基础施工工艺
CN104929108A (zh) * 2015-03-23 2015-09-23 重庆大学 一种硬质土场地pcc桩的施工方法
CN206173757U (zh) * 2016-11-09 2017-05-17 上海汇壹土木工程技术有限公司 一种泥浆池的保护路基
CN206428541U (zh) * 2017-01-24 2017-08-22 华中科技大学 一种路堤结构
CN107419630A (zh) * 2017-06-13 2017-12-01 华中科技大学 一种有效控制工后沉降的软土地基高填方路堤及施工方法
CN107447613A (zh) * 2017-07-31 2017-12-08 浙江大学城市学院 一种深厚超软土路堤及施工方法
CN206902488U (zh) * 2017-06-13 2018-01-19 华中科技大学 一种有效控制工后沉降的软土地基高填方路堤
CN208136652U (zh) * 2018-04-12 2018-11-23 浙江大学城市学院 浅层固化桩承式路堤

Patent Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003268790A (ja) * 2002-03-15 2003-09-25 Taisei Corp 軟弱地盤の沈下低減方法
JP2010209571A (ja) * 2009-03-10 2010-09-24 East Japan Railway Co 線路下横断構造物の構築用支持杭施工方法
JP2011202427A (ja) * 2010-03-26 2011-10-13 Railway Technical Research Institute パイルスラブ盛土及びその工法
CN102493472A (zh) * 2011-12-13 2012-06-13 中交第二公路工程局有限公司 一种桥梁深水软土地基逆作法低桩承台复合基础施工工艺
CN104929108A (zh) * 2015-03-23 2015-09-23 重庆大学 一种硬质土场地pcc桩的施工方法
CN206173757U (zh) * 2016-11-09 2017-05-17 上海汇壹土木工程技术有限公司 一种泥浆池的保护路基
CN206428541U (zh) * 2017-01-24 2017-08-22 华中科技大学 一种路堤结构
CN107419630A (zh) * 2017-06-13 2017-12-01 华中科技大学 一种有效控制工后沉降的软土地基高填方路堤及施工方法
CN206902488U (zh) * 2017-06-13 2018-01-19 华中科技大学 一种有效控制工后沉降的软土地基高填方路堤
CN107447613A (zh) * 2017-07-31 2017-12-08 浙江大学城市学院 一种深厚超软土路堤及施工方法
CN208136652U (zh) * 2018-04-12 2018-11-23 浙江大学城市学院 浅层固化桩承式路堤

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
朱明双;王金昌;朱向荣;: "路堤荷载下现浇筒桩复合地基性状分析", 浙江大学学报(工学版), no. 12 *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110144784A (zh) * 2019-06-13 2019-08-20 福建工程学院 基于预应力混凝土板桩构筑的市政道路及其施工方法
CN110886287A (zh) * 2019-09-29 2020-03-17 中交第一航务工程勘察设计院有限公司 一种浅层软土地基固化结构及其施工方法
CN111321742A (zh) * 2020-03-08 2020-06-23 华中科技大学 一种高含水率淤泥的一体化处理与填料装置及方法
CN113463457A (zh) * 2021-05-17 2021-10-01 衡阳公路桥梁建设有限公司 一种用于穿越泥浆地段的路基结构及其施工方法
CN114508011A (zh) * 2022-01-13 2022-05-17 中国水利水电第七工程局有限公司 一种桩承式软土路基加固结构和加固方法

Also Published As

Publication number Publication date
CN108330764B (zh) 2023-09-26

Similar Documents

Publication Publication Date Title
CN108330764A (zh) 浅层固化桩承式路堤及施工方法
CN208136652U (zh) 浅层固化桩承式路堤
CN204059124U (zh) 一种砂桩排水强夯后注浆地基加固结构
CN106703050A (zh) 膨胀土路堑边坡加筋土反压防渗支护结构及其施工方法
CN107419630A (zh) 一种有效控制工后沉降的软土地基高填方路堤及施工方法
CN108560542B (zh) 一种废旧轮胎包覆建渣的双向增强体及其施工方法
CN206902488U (zh) 一种有效控制工后沉降的软土地基高填方路堤
CN102888834B (zh) 一种大直径碎石桩的施工方法
CN111594232A (zh) 大型充填型溶洞地质隧道地基加固结构及其施工方法
CN212404676U (zh) 一种软土地基防沉降结构
CN107724401A (zh) 桥墩基坑的施工方法
CN106836244A (zh) 一种抗滑桩与格宾高挡墙联合防护陡坡路基的方法
CN106592608A (zh) 一种地下综合管廊新地基与老路基差异沉降控制方法
CN110144783A (zh) 一种路基施工方法
CN110241695A (zh) 一种碎石土超高填方地基加固方法
CN104358196A (zh) 已通车公路路堤沉降处置结构的施工方法
CN103334450B (zh) 一种带排水沟的桩柱预制板挡土墙的施工方法
CN106013178A (zh) 一种浅埋型岩溶地区岩溶地面塌陷的充填方法
CN102966109A (zh) 软土地基带状深基坑封底施工方法
CN108708364A (zh) Ddc桩基施工工艺
CN106869153A (zh) 一种井点降水快速处理软地基的方法
CN206220108U (zh) 膨胀土路堑边坡加筋土反压防渗支护结构
CN214993514U (zh) 一种景观河堤加固挡墙
CN112144425B (zh) 一种位于高水位且砂性土质环境的箱涵排水沟浇筑方法
CN210658236U (zh) 一种堆渣结构

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant