CN108316485A - A kind of anticorrosive workshop wallboard and its bridging method - Google Patents
A kind of anticorrosive workshop wallboard and its bridging method Download PDFInfo
- Publication number
- CN108316485A CN108316485A CN201810246600.4A CN201810246600A CN108316485A CN 108316485 A CN108316485 A CN 108316485A CN 201810246600 A CN201810246600 A CN 201810246600A CN 108316485 A CN108316485 A CN 108316485A
- Authority
- CN
- China
- Prior art keywords
- anticorrosive
- wallboard
- workshop
- wing plate
- plate
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000000034 method Methods 0.000 title claims abstract description 23
- 238000010276 construction Methods 0.000 claims abstract description 21
- 239000000835 fiber Substances 0.000 claims description 14
- 238000010079 rubber tapping Methods 0.000 claims description 14
- 238000009434 installation Methods 0.000 claims description 10
- 239000000463 material Substances 0.000 claims description 9
- 239000002131 composite material Substances 0.000 claims description 6
- 239000003351 stiffener Substances 0.000 claims description 5
- 239000011449 brick Substances 0.000 claims description 3
- 238000005260 corrosion Methods 0.000 abstract description 8
- 230000007797 corrosion Effects 0.000 abstract description 8
- 239000002253 acid Substances 0.000 abstract description 5
- 230000000737 periodic effect Effects 0.000 abstract description 5
- 229910000831 Steel Inorganic materials 0.000 description 9
- 239000010813 municipal solid waste Substances 0.000 description 9
- 239000010959 steel Substances 0.000 description 9
- 239000007789 gas Substances 0.000 description 7
- 239000011347 resin Substances 0.000 description 7
- 229920005989 resin Polymers 0.000 description 7
- 239000004744 fabric Substances 0.000 description 6
- 239000003795 chemical substances by application Substances 0.000 description 5
- 239000004567 concrete Substances 0.000 description 3
- 238000005516 engineering process Methods 0.000 description 3
- 238000004519 manufacturing process Methods 0.000 description 3
- 229920000728 polyester Polymers 0.000 description 3
- 239000002002 slurry Substances 0.000 description 3
- 241000196324 Embryophyta Species 0.000 description 2
- 241000209094 Oryza Species 0.000 description 2
- 235000007164 Oryza sativa Nutrition 0.000 description 2
- 239000000654 additive Substances 0.000 description 2
- 230000000996 additive effect Effects 0.000 description 2
- 238000010586 diagram Methods 0.000 description 2
- 230000005611 electricity Effects 0.000 description 2
- 229920006253 high performance fiber Polymers 0.000 description 2
- 238000009413 insulation Methods 0.000 description 2
- 239000011159 matrix material Substances 0.000 description 2
- 239000002184 metal Substances 0.000 description 2
- 238000012986 modification Methods 0.000 description 2
- 230000004048 modification Effects 0.000 description 2
- 235000009566 rice Nutrition 0.000 description 2
- 238000007789 sealing Methods 0.000 description 2
- 238000007711 solidification Methods 0.000 description 2
- 230000008023 solidification Effects 0.000 description 2
- 238000004056 waste incineration Methods 0.000 description 2
- 229920000742 Cotton Polymers 0.000 description 1
- 230000003712 anti-aging effect Effects 0.000 description 1
- 239000000470 constituent Substances 0.000 description 1
- 238000010924 continuous production Methods 0.000 description 1
- 238000005520 cutting process Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 239000011152 fibreglass Substances 0.000 description 1
- 239000012530 fluid Substances 0.000 description 1
- 239000011381 foam concrete Substances 0.000 description 1
- 239000012634 fragment Substances 0.000 description 1
- 239000003517 fume Substances 0.000 description 1
- 239000011521 glass Substances 0.000 description 1
- 239000003365 glass fiber Substances 0.000 description 1
- 238000005286 illumination Methods 0.000 description 1
- JEIPFZHSYJVQDO-UHFFFAOYSA-N iron(III) oxide Inorganic materials O=[Fe]O[Fe]=O JEIPFZHSYJVQDO-UHFFFAOYSA-N 0.000 description 1
- 238000012423 maintenance Methods 0.000 description 1
- 239000007769 metal material Substances 0.000 description 1
- 238000000465 moulding Methods 0.000 description 1
- 239000004033 plastic Substances 0.000 description 1
- 239000002994 raw material Substances 0.000 description 1
- 238000004064 recycling Methods 0.000 description 1
- 238000010008 shearing Methods 0.000 description 1
- 238000009416 shuttering Methods 0.000 description 1
- 230000003068 static effect Effects 0.000 description 1
- 238000005728 strengthening Methods 0.000 description 1
- 210000002435 tendon Anatomy 0.000 description 1
- 239000004753 textile Substances 0.000 description 1
- 238000009966 trimming Methods 0.000 description 1
- 210000001364 upper extremity Anatomy 0.000 description 1
- 238000004078 waterproofing Methods 0.000 description 1
- 238000009941 weaving Methods 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/62—Insulation or other protection; Elements or use of specified material therefor
- E04B1/66—Sealings
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/38—Connections for building structures in general
- E04B1/61—Connections for building structures in general of slab-shaped building elements with each other
- E04B1/6108—Connections for building structures in general of slab-shaped building elements with each other the frontal surfaces of the slabs connected together
- E04B1/612—Connections for building structures in general of slab-shaped building elements with each other the frontal surfaces of the slabs connected together by means between frontal surfaces
- E04B1/6166—Connections for building structures in general of slab-shaped building elements with each other the frontal surfaces of the slabs connected together by means between frontal surfaces with protrusions on both frontal surfaces
- E04B1/6175—Connections for building structures in general of slab-shaped building elements with each other the frontal surfaces of the slabs connected together by means between frontal surfaces with protrusions on both frontal surfaces with two or more protrusions on each frontal surface
Abstract
The invention discloses a kind of anticorrosive workshop wallboard and its bridging methods, wallboard includes wallboard main body, wallboard main body includes top plate and bottom plate relatively disposed in parallel and the first panel and second panel that are connected between top plate and bottom plate, top plate, bottom plate, first panel and second panel surround the internal enclosed construction for cavity, it is provided with the first wing plate below bottom plate, second wing plate and the first lug boss, bottom plate, first wing plate and the second wing plate surround link slot, it is provided with push pedal and third wing plate above top plate, push pedal can be formed with the link slot and be cooperated, the upper end of third wing plate is provided with can be with mutually matched second lug boss of the first lug boss.The anticorrosive workshop wallboard of the present invention is lightweight construction, is connected using periodic tongue-and-groove, and shape is clean and tidy, beautiful, rain-proof, has many advantages, such as that the corrosion resistance of strong alkali-acid resistance, heat insulating ability, durability, wind resistance, air-tightness is good, intensity is high, service life is long.
Description
Technical field
The present invention relates to the wall board material fields of steel-structure factory building building, and in particular to a kind of anticorrosive workshop wallboard and its
Bridging method.
Background technology
In recent years " garbage-surrounded city " the situation is tense, waste incineration and generating electricity is current " minimizing, innoxious, recycling " disposition life
The best mode of rubbish living, during waste incineration and generating electricity, rubbish will first be stored in Kukeng, constantly ferment, rot, go mouldy,
Then it is just incinerated, the gas evaporated, complicated component, there is very strong corrosivity.The incinerator of early stage uses fresh sky
Gas is combustion-supporting, though and garbage storing hole suffers week repeatly often using open or have the no sealing structure of workshop rain cover, foul smell to escape
Side resident complains, protests that state-of-the-art technology requires corrosive gas introducing incinerator as combustion-supporting gas, not only together by foul smell
It burns totally, and the combustible constituent in foul smell is fully used.The workshop lower part in garbage storing hole uses mixed mud wall, and
Close to the wall of roof parts, using steel construction wallboard, the workshop in garbage storing hole is closed, is chronically at negative pressure state, in workshop
Portion's corrosive gas concentration is high, and corrosive gas constitutes serious threat to the service life of wall board structure, it is therefore desirable to wall
Panel has preferable corrosion resistance, and also there is anticorrosive requirement in matched incineration plants, fume treatment workshop etc., in addition
Also requiring shingle nail has a preferable leakproofness, overlapped gap also more demanding sealing performance, to prevent corrosive gas
It leaks.
Since garbage storing hole needs to do large span, the design of large space, the mill construction headroom in garbage storing hole is very high,
Wallboard design is mostly steel construction wallboard, and about wall system, the prior art has following several:1, using double-layer heat insulation coloured silk steel clamp core
Plate, but because color steel anticorrosive aspect limited capacity, usual longest use 3~5 years after with regard to corrosion failure, have through hole
Hole, it is necessary to carry out shingle nail integral replacing;Refuse-burning plant in operation replaces shingle nail, and not only difficulty of construction is high, Er Qiean
Full hidden danger is very big, and later maintenance cost is high;2, plastic wall panel, is only applicable to a lower height of workshop, and garbage incinerating power plant
Workshop generally all in 40 meters high left and right, intensity and wind loading rating cannot all reach requirement;3, also have at present using cast-in-place mixed
Concrete board takes this way that must set up the steel pipe frame support shuttering ability cast-in-place concrete operation of full hall, factory from ground
For room head room at 30~40 meters or more, construction cost is of high cost, and difficulty of construction and security risk are also larger;4, the prior art is also
Using a kind of foamed concrete prefabricated slab, but one of waterproofing work must be done in metope inner cord, otherwise can not solve waterproof and ooze
Leakage problem increases construction cost and duration.
A kind of anticorrosive workshop wallboard and its bridging method proposed by the present invention, wallboard are hollow light structures, are used
Periodic tongue-and-groove connection, material are fibre reinforced composites, and shape is clean and tidy, beautiful, rain-proof, anti-with strong alkali-acid resistance
The advantages that corrosivity, heat insulating ability, durability, wind resistance, air-tightness are good, intensity is high, service life is long.
Invention content
The purpose of the present invention is to provide a kind of anticorrosive workshop wallboard and its bridging methods, to solve existing be used for
Garbage storing cheat the wallboard poor corrosion resistance of workshop, difficulty of construction and it is of high cost, intensity is low, service life is short the problems such as.
To achieve the above object, the technical scheme is that:The anticorrosive workshop wallboard includes wallboard main body, described
Wallboard main body includes top plate and bottom plate relatively disposed in parallel and the first panel being connected between top plate and bottom plate and second
Panel, the top plate and bottom plate, first panel and second panel surround the internal enclosed construction for cavity, are set below the bottom plate
It is equipped with the first wing plate, the second wing plate and the first lug boss, the first wing plate connection first panel lower end, first protrusion
Portion connects second panel lower end, and second wing plate is between the first wing plate and the first lug boss and opposite with the first wing plate
It is arranged in parallel, the bottom plate, the first wing plate and the second wing plate surround link slot, and push pedal and the third wing are provided with above the top plate
Plate, the push pedal can be formed with the link slot and be cooperated, third wing plate connection second panel upper end, the third
The upper end of wing plate is provided with can be with mutually matched second lug boss of the first lug boss.
Preferably, several stiffener plates are provided in the cavity of the wallboard main body, the cavity of the wallboard main body is logical
It crosses several stiffener plates and is separated into several chambers.
Preferably, the height of the push pedal is less than the height of third wing plate.
Preferably, the height of first wing plate is less than the height of the second wing plate, two pieces of anticorrosive workshop wallboard phase interconnections
When connecing, it is formed between the first wing plate and the first panel of another block of anticorrosive workshop wallboard of one block of anticorrosive workshop wallboard
Decorative groove.
Preferably, the third wing plate is fixedly connected by the tapping screw that several uniform intervals are arranged with wall frame.
Preferably, the material of the anticorrosive workshop wallboard is fibre reinforced composites.
Preferably, the width of the anticorrosive workshop wallboard is 10-20m.
Preferably, the thickness of the first panel and second panel is 2.5-8mm.
The invention also provides a kind of bridging method of anticorrosive workshop wallboard, the bridging method includes:
The wall frame of workshop is installed;
Several blocks of anticorrosive workshop wallboards are provided, first piece of anticorrosive workshop wall is installed in Brick wall base of frame first
The two sides of first block of anticorrosive workshop wallboard and bottom edge are embedded in the "u"-shaped groove structure on wall frame by plate;
The tapping screw and wall that the third wing plate of first block of anticorrosive workshop wallboard is arranged by several uniform intervals
Fixed link on frame is fixedly connected;
Second block of anticorrosive workshop wallboard is mounted on to the top of first block of anticorrosive workshop wallboard, second piece of anticorrosive factory
Push pedal above link slot and first piece of anticorrosive workshop wallboard top plate below room wallboard bottom plate cooperates, second piece of anti-corruption
Lose the first lug boss below workshop wallboard bottom plate and the second lug boss above first block of anticorrosive workshop wallboard third wing plate
It cooperates, makes to form stable overlap joint cooperation between first block of anticorrosive workshop wallboard and second block of anticorrosive workshop wallboard;
The two sides of second block of anticorrosive workshop wallboard are embedded in the "u"-shaped groove structure on wall frame;
According to erection sequence from the bottom to top, remaining anticorrosive workshop wallboard is installed successively using same method, it will
The two sides of the anticorrosive workshop wallboard of last block and top margin are embedded in the "u"-shaped groove structure on wall frame, complete anti-corruption
Lose overlap joint and the installation of workshop wallboard entirety.
Preferably, the spacing about 0.5- on every block of anticorrosive workshop wallboard third wing plate between two neighboring tapping screw
2m。
The invention has the advantages that:
A kind of anticorrosive workshop wallboard and its bridging method proposed by the present invention, wallboard are hollow light structures, are often put down
Rice from focus on 10kg hereinafter, be convenient for construction and installation, reduce the load requirement to support steel, reduce metope steel construction at
This;Using periodic tongue-and-groove connect, air-tightness is good, and working procedure is simple, wallboard installation is complete i.e. construction finish, only one of work
Sequence substantially reduces construction cost;Material is fibre reinforced composites, has the corrosion resistance of strong alkali-acid resistance, heat insulating ability, resistance to
Long property, wind resistance, air-tightness is good, intensity is high, service life is long;Shape is clean and tidy, beautiful, rain-proof, highly practical.
Description of the drawings
Fig. 1 is a kind of structural schematic diagram of anticorrosive workshop wallboard of the embodiment of the present invention 1.
Fig. 2 is a kind of bridging arrangement schematic diagram of anticorrosive workshop wallboard of the embodiment of the present invention 1.
Fig. 3 is a kind of mounting structure front view of anticorrosive workshop wallboard of the embodiment of the present invention 1.
Fig. 4 is a kind of mounting structure side view of anticorrosive workshop wallboard of the embodiment of the present invention 1.
Fig. 5 is a kind of mounting structure vertical view of anticorrosive workshop wallboard of the embodiment of the present invention 1.
Specific implementation mode
The following examples are used to illustrate the present invention, but are not intended to limit the scope of the present invention..
Embodiment 1
As shown in Figure 1, a kind of anticorrosive workshop wallboard that the present embodiment proposes includes wallboard main body 1, wallboard main body 1 includes
Top plate 11 and bottom plate 12 relatively disposed in parallel and the first panel 13 being connected between top plate 11 and bottom plate 12 and the second face
Plate 14, when in use, first panel 13 is towards outside workshop, and second panel 14 is towards inside workshop, top plate 11, bottom plate 12,
One panel 13 and second panel 14 surround the internal enclosed construction for cavity, and being provided with several in the cavity of wallboard main body 1 adds
The cavity of strengthening tendons plate 15, wallboard main body 1 is separated into several chambers 16 by several stiffener plates 15, and intensity is high, structure is light
Matter, and using static air as insulating layer, have the function of good insulation.
As depicted in figs. 1 and 2,12 lower section of bottom plate is provided with the first wing plate 121, the second wing plate 122 and the first lug boss
123, the first wing plate 121 connects 13 lower end of first panel, and the first lug boss 123 connects 14 lower end of second panel, second wing
Plate 122 between the first wing plate 121 and the first lug boss 123 and it is opposite with the first wing plate 121 be arranged in parallel, bottom plate 12, the
One wing plate 121 and the second wing plate 122 surround link slot 2, and 11 top of top plate is provided with push pedal 111 and third wing plate 112, push pedal
111 can form mutual cooperation with the link slot 2, and third wing plate 112 connects 14 upper end of second panel, third wing plate 112
Upper end is provided with can be with 123 mutually matched second lug boss 113 of the first lug boss, and the height of the first wing plate 121 is less than the
The height of two wing plates 122, the height of push pedal 111 are less than the height of third wing plate 112, third wing plate 112 by it is several uniformly between
It is fixedly connected with the fixed link 4 on wall frame 6 every the tapping screw 3 of setting, as shown in Fig. 3, Fig. 4 and Fig. 5.
The material of anticorrosive workshop wallboard be fibre reinforced composites (FRP), have strong alkali-acid resistance corrosion resistance,
The advantages that heat insulating ability, durability, wind resistance, air-tightness be good, high intensity, and since material is non-metallic material, avoid existing
Have technology use Metal wall caused by trimming metal fragment rest on metope, cause corrosion of the rust spot to wallboard, effectively
The service life for extending wallboard.The width of the anticorrosive workshop wallboard of monolithic is 10-20m, most preferably 16m, first panel 13
Thickness with second panel 14 is 2.5-8mm.
A kind of bridging method of anticorrosive workshop wallboard of the present embodiment includes:The wall frame 6 of workshop is installed;If providing
The anticorrosive workshop wallboard of dry block installs first block of anticorrosive workshop wallboard in Brick wall base of frame first, anti-by first piece
The two sides and bottom edge for corroding workshop wallboard are embedded in the "u"-shaped groove structure 7 on wall frame;By first piece of anticorrosive workshop
The third wing plate 112 of wallboard, which is fixed by the tapping screw 3 that several uniform intervals are arranged with the fixed link 4 on wall frame, to be connected
It connects, the spacing between two neighboring tapping screw 3 about 0.5-2m, preferably 1m or so, as shown in Figure 4 and Figure 5;By second piece of anti-corruption
Lose the top that workshop wallboard is mounted on first block of anticorrosive workshop wallboard, the connection below second piece of anticorrosive workshop wallboard bottom plate
Push pedal 111 above slot 2 and first piece of anticorrosive workshop wallboard top plate cooperates, second piece of anticorrosive workshop wallboard bottom plate 12
The 113 phase interworking of the second lug boss of first lug boss 123 of lower section, 112 top of anticorrosive workshop wallboard third wing plate with first piece
It closes, makes to form stable overlap joint cooperation between first block of anticorrosive workshop wallboard and second block of anticorrosive workshop wallboard;By second
The two sides of the anticorrosive workshop wallboard of block are embedded in the "u"-shaped groove structure 7 on wall frame;It is suitable according to installation from the bottom to top
Sequence installs remaining anticorrosive workshop wallboard, by the both sides of the anticorrosive workshop wallboard of last block successively using same method
Side and top margin are embedded in the "u"-shaped groove structure 7 on wall frame 6, complete overlap joint and the installation of anticorrosive workshop wallboard entirety,
As shown in Figure 3.
As shown in Figure 1, Figure 2 and Figure 4, when two blocks of anticorrosive workshop wallboards mutually overlap cooperation, link slot 2 and push pedal 111
It cooperates, the first lug boss 123 and the second lug boss 113 cooperate, and are connected by this periodic tongue-and-groove, one piece of wall
The upper limb of plate and the lower edge of another block of wallboard are fitted close, and have preferable seal;Has preferable leakproofness;First wing plate
121 are located at the outside of push pedal 111, can dredge rainwater outside wallboard, have certain thin rain function;Due to the first wing plate
121 height is less than the height of the second wing plate 122, decorative groove 5 is formed between two blocks of anticorrosive workshop wallboards, illumination is reflected in day
Under, the shaded bar band of a transverse direction can be formed, makes entire metope that there is shadows cast by the sun effect and have preferable decorative and aesthetics;
Since the height of push pedal 111 is less than the height of third wing plate 112, tool operation space is left, screw can be very easily used
Knife installation tapping screw 3 makes third wing plate 112 be fixedly connected with the fixed link 4 on wall frame 6, and tapping screw 3 is by the
One wing plate 121 and the second wing plate 122 block, though entire metope is fixed with tapping screw 3, can't see self tapping completely from the outside
Screw 3, it is neat and artistic;Since use tongue-and-groove connects, it is used in combination tapping screw 3 to be fixed on wall frame 6, is not necessarily to other connectors,
Installation method is simple.
A kind of anticorrosive workshop wallboard of the present embodiment is prepared using pultrusion method moulding process, and any type is medium-sized or large-scale
FRP extruding equipments can complete pultrude process, and typical pultrusion production line designation Model is:Fiberglass fluid pressure type extruding equipment-
30T;Mold is molded according to design width, thickness, the concrete structure of wallboard by mould factory, has certain designability, pultrusion
Mold be one limitation product cross-sectional shape mold, length direction can be arbitrarily long, general continuous production, according to required
Position is blocked in length setting, can be automatically performed and be blocked by production line, also can blanking at the scene;Wallboard is designed to cross-section plate, just
It is mass produced in pultrusion assembly line.
The inner core of pultrusion part is parallel longitudinal fiber, therefore longitudinal strength and modulus are all higher, in order to reinforce lateral performance,
On pultrusion part surface using two layers of two-way cloth as surface felt, the material of two-way cloth is identical as longitudinal fiber.It is two-way to be meant that
Latitude and longitude all use the high-performance fiber to weave, and in contrast, it is high-performance fiber that unidirectional cloth, which only has warp, and weft is cheap
And it is easier to the cotton yarn of weaving, broadwise does not have intensity at this time, and weft is only to maintain the form of textile.Two-way cloth conduct
The horizontal mechanical performance of component is greatly improved in surface felt.The mode of cutting out of two-way cloth can be 45 degree of directions, therefore arrange
Fiber on pultrusion part surface is in positive and negative 45 degree of directional spredings, strengthens transverse direction, the longitudinal shear resistance shearing stress of component.
In order to achieve the above object, it needs to implement pultrude process, the wherein formula rate (weight of fiber and resin slurry
Than) as follows:Fiber 65-85%, slurry 15-35%.It is anti-aging comprising resin matrix and curing agent and uvioresistant in slurry
Additive, ratio are prepared according to raw material specification, by using for polyester, representative formula is (weight ratio):Resin matrix
95.5-98.5%, curing agent 1-3%, additive 0.5-1.5%.Fiber uses high-elastic mould glass fibre and high-elastic mould glass
The two-way cloth of fiber, its usual fiber Young's modulus are 50-60GPa, ensure pultrusion finished product Young's modulus between 40-45GPa.It draws
Solidification temperature is squeezed, according to resin specific requirement used, depending on resin, curing agent operation instructions, by taking polyester as an example, solidification
Temperature is 150-160 degrees Celsius, is preferred with 155 degrees Celsius.Pultrusion rate, according to the different and different of resin and curing agent, according to
Resin, curing agent specification depending on, by taking polyester as an example, usually may be set in 0.2m-0.6m/min, be with 0.45m/min
It is good.The drawing force of pultrusion production line determines that then pulling tension requirements are big greatly for size, needed for guarantee according to the size of the wallboard drawn
Pull-out speed subject to.
A kind of anticorrosive workshop wallboard and its bridging method proposed by the present invention, wallboard are hollow light structures, are often put down
Rice from focus on 10kg hereinafter, be convenient for construction and installation, reduce the load requirement to support steel, reduce metope steel construction at
This;Using periodic tongue-and-groove connect, air-tightness is good, and working procedure is simple, wallboard installation is complete i.e. construction finish, only one of work
Sequence substantially reduces construction cost;Material is fibre reinforced composites, has the corrosion resistance of strong alkali-acid resistance, heat insulating ability, resistance to
Long property, wind resistance, air-tightness is good, intensity is high, service life is long;Shape is clean and tidy, beautiful, rain-proof, highly practical.
Although above having used general explanation and specific embodiment, the present invention is described in detail, at this
On the basis of invention, it can be made some modifications or improvements, this will be apparent to those skilled in the art.Therefore,
These modifications or improvements without departing from theon the basis of the spirit of the present invention belong to the scope of protection of present invention.
Claims (10)
1. a kind of anticorrosive workshop wallboard, which is characterized in that the anticorrosive workshop wallboard includes wallboard main body, the wallboard master
Body includes top plate and bottom plate relatively disposed in parallel and the first panel and second panel that are connected between top plate and bottom plate, institute
It states top plate and bottom plate, first panel and second panel and surrounds the internal enclosed construction for cavity, first is provided with below the bottom plate
Wing plate, the second wing plate and the first lug boss, first wing plate connection first panel lower end, the first lug boss connection the
Two panel lower ends, second wing plate between the first wing plate and the first lug boss and with the first wing plate is relatively parallel sets
It sets, the bottom plate, the first wing plate and the second wing plate surround link slot, and push pedal and third wing plate, institute are provided with above the top plate
Mutual cooperation, third wing plate connection second panel upper end, the third wing plate can be formed with the link slot by stating push pedal
Be provided with can be with mutually matched second lug boss of the first lug boss for upper end.
2. a kind of anticorrosive workshop wallboard according to claim 1, which is characterized in that set in the cavity of the wallboard main body
Several stiffener plates are equipped with, the cavity in the wallboard main body is separated into several chambers by several stiffener plates.
3. a kind of anticorrosive workshop wallboard according to claim 1, which is characterized in that the height of the push pedal is less than third
The height of wing plate.
4. a kind of anticorrosive workshop wallboard according to claim 1, which is characterized in that the height of first wing plate is less than
The height of second wing plate, when two blocks of anticorrosive workshop wallboards mutually overlap, one block of anticorrosive workshop wallboard the first wing plate and
It is formed with decorative groove between the first panel of another block of anticorrosive workshop wallboard.
5. a kind of anticorrosive workshop wallboard according to claim 1, which is characterized in that the third wing plate passes through several equal
Even spaced tapping screw is fixedly connected with wall frame.
6. a kind of anticorrosive workshop wallboard according to claim 1, which is characterized in that the material of the anticorrosive workshop wallboard
Matter is fibre reinforced composites.
7. a kind of anticorrosive workshop wallboard according to claim 1, which is characterized in that the width of the anticorrosive workshop wallboard
Degree is 10-20m.
8. a kind of anticorrosive workshop wallboard according to claim 1, which is characterized in that the first panel and second panel
Thickness be 2.5-8mm.
9. according to a kind of bridging method of anticorrosive workshop wallboard according to any one of claims 1-8, which is characterized in that described
Bridging method includes:
The wall frame of workshop is installed;
Several blocks of anticorrosive workshop wallboards are provided, first block of anticorrosive workshop wallboard is installed in Brick wall base of frame first,
The two sides of first block of anticorrosive workshop wallboard and bottom edge are embedded in the "u"-shaped groove structure on wall frame;
The tapping screw and wall frame that the third wing plate of first block of anticorrosive workshop wallboard is arranged by several uniform intervals
On fixed link be fixedly connected;
Second block of anticorrosive workshop wallboard is mounted on to the top of first block of anticorrosive workshop wallboard, second piece of anticorrosive workshop wall
Push pedal above link slot and first piece of anticorrosive workshop wallboard top plate below board bottom plate cooperates, second piece of anticorrosive factory
The first lug boss below room wallboard bottom plate and the second lug boss above first block of anticorrosive workshop wallboard third wing plate are mutual
Cooperation makes to form stable overlap joint cooperation between first block of anticorrosive workshop wallboard and second block of anticorrosive workshop wallboard;
The two sides of second block of anticorrosive workshop wallboard are embedded in the "u"-shaped groove structure on wall frame;
According to erection sequence from the bottom to top, remaining anticorrosive workshop wallboard is installed successively using same method, it will be last
The two sides of one block of anticorrosive workshop wallboard and top margin are embedded in the "u"-shaped groove structure on wall frame, complete anticorrosive factory
The overlap joint of room wallboard entirety and installation.
10. a kind of anticorrosive workshop wallboard according to claim 9, which is characterized in that every block of anticorrosive workshop wallboard
Spacing about 0.5-2m on three wing plates between two neighboring tapping screw.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810246600.4A CN108316485A (en) | 2018-03-23 | 2018-03-23 | A kind of anticorrosive workshop wallboard and its bridging method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810246600.4A CN108316485A (en) | 2018-03-23 | 2018-03-23 | A kind of anticorrosive workshop wallboard and its bridging method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108316485A true CN108316485A (en) | 2018-07-24 |
Family
ID=62899219
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810246600.4A Pending CN108316485A (en) | 2018-03-23 | 2018-03-23 | A kind of anticorrosive workshop wallboard and its bridging method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108316485A (en) |
Citations (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2571866Y (en) * | 2002-09-04 | 2003-09-10 | 严丹 | Bidirectional hollow internal locking type multi-function compound wall panel |
CN101581121A (en) * | 2008-01-18 | 2009-11-18 | 王广武 | Wooden plastic combined wall body internally fixed through tenon-groove connection and method for manufacturing same |
CN202227514U (en) * | 2011-08-08 | 2012-05-23 | 罗钦平 | High sound-insulation wall |
CN202672802U (en) * | 2012-06-20 | 2013-01-16 | 广州市泰阳通信设备有限公司 | Shield burglary-preventing communication machine room |
CN103866902A (en) * | 2013-12-31 | 2014-06-18 | 河北金源建材科技有限公司 | Insertion type heat-preservation rock wool wallboard formed by compounding stone and aluminium alloy |
CN203891232U (en) * | 2014-05-22 | 2014-10-22 | 徐永权 | Acoustic wall |
CN104264851A (en) * | 2014-09-16 | 2015-01-07 | 福建九鼎建设集团有限公司 | Sound-proof steel structure wall |
CN205171822U (en) * | 2015-12-07 | 2016-04-20 | 朱效伟 | Board house structural slab |
CN205917917U (en) * | 2016-08-04 | 2017-02-01 | 四川鸥克建设工程有限公司 | Steel frame structure's panel house wall |
CN208280328U (en) * | 2018-03-23 | 2018-12-25 | 湖北中复能新型材料有限公司 | A kind of anticorrosive workshop wallboard |
-
2018
- 2018-03-23 CN CN201810246600.4A patent/CN108316485A/en active Pending
Patent Citations (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2571866Y (en) * | 2002-09-04 | 2003-09-10 | 严丹 | Bidirectional hollow internal locking type multi-function compound wall panel |
CN101581121A (en) * | 2008-01-18 | 2009-11-18 | 王广武 | Wooden plastic combined wall body internally fixed through tenon-groove connection and method for manufacturing same |
CN202227514U (en) * | 2011-08-08 | 2012-05-23 | 罗钦平 | High sound-insulation wall |
CN202672802U (en) * | 2012-06-20 | 2013-01-16 | 广州市泰阳通信设备有限公司 | Shield burglary-preventing communication machine room |
CN103866902A (en) * | 2013-12-31 | 2014-06-18 | 河北金源建材科技有限公司 | Insertion type heat-preservation rock wool wallboard formed by compounding stone and aluminium alloy |
CN203891232U (en) * | 2014-05-22 | 2014-10-22 | 徐永权 | Acoustic wall |
CN104264851A (en) * | 2014-09-16 | 2015-01-07 | 福建九鼎建设集团有限公司 | Sound-proof steel structure wall |
CN205171822U (en) * | 2015-12-07 | 2016-04-20 | 朱效伟 | Board house structural slab |
CN205917917U (en) * | 2016-08-04 | 2017-02-01 | 四川鸥克建设工程有限公司 | Steel frame structure's panel house wall |
CN208280328U (en) * | 2018-03-23 | 2018-12-25 | 湖北中复能新型材料有限公司 | A kind of anticorrosive workshop wallboard |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US10808396B2 (en) | Building based on large-space structure and freestanding external envelope as well as construction method | |
CN207878960U (en) | A kind of construction material for installing high-strength durable fiber cloth or/and plastic film | |
CN106869539A (en) | A kind of assembled factory building | |
CN103352569A (en) | Construction method of integrally-poured architecture building | |
CN202214829U (en) | Vertical seam of external wallboards | |
CN208280328U (en) | A kind of anticorrosive workshop wallboard | |
CN108316485A (en) | A kind of anticorrosive workshop wallboard and its bridging method | |
CN203270856U (en) | Building wall | |
CN211279058U (en) | Prefabricated assembled concrete structure fast-assembling sleeve built-in fitting | |
CN107975163A (en) | A kind of mountable double-deck Side fascia and mounting structure and horizontal vertical waterproof construction | |
CN204163203U (en) | For waterproof construction and the box-body movable house thereof of mobile house | |
CN206158255U (en) | Prefabricated assembled communication machinery room | |
CN203412312U (en) | Thermal-insulating integrated template wallboard construction building | |
CN110080471A (en) | A kind of ventilating heat-proof structural water-proof roof system and production method | |
CN207620229U (en) | A kind of roof boarding for garbage incinerating power plant | |
CN210713208U (en) | Transformer substation's assembled integration guard room | |
CN107989259A (en) | The mountable double-deck Side fascia and mounting structure and waterproof construction of band mo(u)lding panel | |
CN107476592A (en) | A kind of construction material for installing high-strength durable fiber cloth or/and plastic sheeting | |
CN213062528U (en) | High-performance enclosure wall | |
CN114059707A (en) | High strength building engineering concrete wallboard | |
CN202706483U (en) | Glass fiber and magnesium flue | |
CN209457213U (en) | A kind of easy-to-mount autoclaved aerated concrete slab interior wall | |
CN208950182U (en) | Wall with waterproof construction | |
CN203320751U (en) | Formwork thermal insulation integrated wall body | |
CN204728764U (en) | A kind of container-type plant maintenance structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |