CN108286210A - A kind of rapid constructing method of embedded railway points system - Google Patents
A kind of rapid constructing method of embedded railway points system Download PDFInfo
- Publication number
- CN108286210A CN108286210A CN201810216788.8A CN201810216788A CN108286210A CN 108286210 A CN108286210 A CN 108286210A CN 201810216788 A CN201810216788 A CN 201810216788A CN 108286210 A CN108286210 A CN 108286210A
- Authority
- CN
- China
- Prior art keywords
- plate
- rail
- points system
- top surface
- railway points
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000000034 method Methods 0.000 title claims abstract description 26
- NJPPVKZQTLUDBO-UHFFFAOYSA-N novaluron Chemical compound C1=C(Cl)C(OC(F)(F)C(OC(F)(F)F)F)=CC=C1NC(=O)NC(=O)C1=C(F)C=CC=C1F NJPPVKZQTLUDBO-UHFFFAOYSA-N 0.000 claims abstract description 30
- 241001669679 Eleotris Species 0.000 claims abstract description 28
- 238000010276 construction Methods 0.000 claims abstract description 27
- 241000283707 Capra Species 0.000 claims abstract description 21
- 239000002131 composite material Substances 0.000 claims abstract description 17
- 229920000642 polymer Polymers 0.000 claims abstract description 15
- 238000009434 installation Methods 0.000 claims abstract description 14
- 230000010412 perfusion Effects 0.000 claims abstract description 10
- 238000000926 separation method Methods 0.000 claims abstract description 10
- 238000013016 damping Methods 0.000 claims abstract description 5
- 239000004570 mortar (masonry) Substances 0.000 claims abstract description 4
- 239000004567 concrete Substances 0.000 claims description 18
- 239000000463 material Substances 0.000 claims description 16
- 239000010410 layer Substances 0.000 claims description 12
- 238000003825 pressing Methods 0.000 claims description 9
- 238000003466 welding Methods 0.000 claims description 7
- 239000011440 grout Substances 0.000 claims description 4
- 230000002787 reinforcement Effects 0.000 claims description 4
- 239000000853 adhesive Substances 0.000 claims description 3
- 230000001070 adhesive effect Effects 0.000 claims description 3
- 239000002313 adhesive film Substances 0.000 claims description 3
- 239000002390 adhesive tape Substances 0.000 claims description 3
- 238000005266 casting Methods 0.000 claims description 3
- 238000002360 preparation method Methods 0.000 claims description 3
- 238000007789 sealing Methods 0.000 claims description 3
- 238000005507 spraying Methods 0.000 claims description 3
- 238000003756 stirring Methods 0.000 claims description 3
- 230000003014 reinforcing effect Effects 0.000 claims description 2
- 239000002344 surface layer Substances 0.000 claims description 2
- 210000002105 tongue Anatomy 0.000 description 16
- 238000005516 engineering process Methods 0.000 description 4
- 210000005182 tip of the tongue Anatomy 0.000 description 3
- 229910000831 Steel Inorganic materials 0.000 description 2
- 238000010586 diagram Methods 0.000 description 2
- 230000000694 effects Effects 0.000 description 2
- 239000010959 steel Substances 0.000 description 2
- 241000269350 Anura Species 0.000 description 1
- 244000025254 Cannabis sativa Species 0.000 description 1
- 230000003044 adaptive effect Effects 0.000 description 1
- 239000010426 asphalt Substances 0.000 description 1
- 238000009833 condensation Methods 0.000 description 1
- 230000005494 condensation Effects 0.000 description 1
- 229920002521 macromolecule Polymers 0.000 description 1
- 238000012423 maintenance Methods 0.000 description 1
- 239000011150 reinforced concrete Substances 0.000 description 1
- 239000002689 soil Substances 0.000 description 1
- 229910000679 solder Inorganic materials 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01B—PERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
- E01B7/00—Switches; Crossings
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01B—PERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
- E01B7/00—Switches; Crossings
- E01B7/02—Tongues; Associated constructions
Landscapes
- Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Machines For Laying And Maintaining Railways (AREA)
Abstract
The invention discloses a kind of rapid constructing methods of embedded railway points system, include the following steps:Pedestal is poured into a mould at the construction field (site), marks line midline, switching turnout plate profile and plate stitch outline position in base top surface, and be laid with separation layer in base top surface;The laying a switch plate in pre-fabricated factory, tuned plate tooling of the installation for adjusting horizontal position and elevation at Hoisting Position;Resilient sleeper-bearing, height adjusting cushion plate are installed in the rail support groove of switching turnout plate;Rail part is placed in switching turnout plate rail support groove and completion group is welded;After the rail part web of the rail is bonded damping block, track geometry is adjusted, is fixed temporarily;Tongue is installed;Pour into a mould polymer composite;Goat is connected by screw rod with the towing point of the point of switch;Embedded railway points system is being positioned and is being fixed;Perfusion mortar layer.Most of step of the method for the present invention is completed in factory, and site operation speed is extremely quick, and entire construction process is scientific and reasonable.
Description
Technical field
The present invention relates to a kind of rapid constructing methods of embedded railway points system, belong to rail traffic road construction technology neck
Domain.
Background technology
Embedded tracks are continuously supported using high molecular material and locking rail part, have good damping noise reduction effect,
The vibration and noise generated when train operation influences very little to the living environment of resident near circuit, and track switch is as entire circuit
In the weakest one of link, construction quality is to the safety of the service efficiency of circuit and train operation, stationarity and relaxes
Adaptive has a significant impact, and section especially larger in vehicle flowrate and the volume of the flow of passengers, the construction efficiency of circuit also has attracted much attention.Existing
In patent document, the associated construction method about embedded tracks railway points system there is no.At present only application No. is
201310311983.6, the patent document of entitled " a kind of rapid constructing method of embedded tracks system " elaborates
The constructions of embedded tracks main tracks, but the patent does not illustrate the construction method of embedded tracks railway points system,
Therefore it is very to study rational embedded railway points system construction technology to ensure embedded track switch construction quality and construction efficiency
It is necessary.
Invention content
The goal of the invention of the present invention is:In view of the above problems, a kind of the quick of embedded railway points system is provided
Construction method, with the blank on remedy technology.
Embedded railway points system according to the present invention is as shown in Figure 1, 2, including pedestal 1, separation layer 2, screed 3 and road
Trouble system, the railway points system include that switching turnout plate 4, rail part 8, goat 14, resilient sleeper-bearing 5, height adjusting cushion plate 5 and macromolecule are multiple
Condensation material 7, the switching turnout plate 4 are prefabricated, which is provided with rail support groove 41, the steel member installation by adhering in rail support groove 41 simultaneously
Uniform restraint is carried out by polymer composite 7, the steel member includes stock rail 81, curve rail 83, goat 14, tongue
82 and railway frog 84, combined guardrail 85, institute are installed between 84 corresponding stock rail of the railway frog, 81 inside and 41 side wall of rail support groove
It states 82 butt of tongue to be located on tongue pedestal and can rotate around positioning pin by a vertical positioning pin, 82 tip of tongue is set
There are towing point, the goat 14 to be embedded in a manner of sinking on switching turnout plate 4 and connect with the towing point at 82 tip of tongue,
The pedestal 1 is rubble sandy soil structure or reinforced concrete structure.
The polymer composite 7 includes elastomeric pad and elastic filling material, and the elastomeric pad is in rail support groove 41
Bottom continuous laying, remaining gap is to stock rail 81,83 and of curve rail in elastic filling material filling rail support groove 41
Railway frog 84 is constrained.Osculum is opened up on the tongue pedestal, osculum is always downward through switching turnout plate 4.The tongue 82
Butt upper surface has recessed area, wedge block pressing to be mounted on tongue pedestal in the recessed area and by bolt by working edge
On, 82 upper surface of tongue is less than at the top of wedge block and bolt.The guard rail 85 is realized and stock rail 81 by the support base of bottom
It is contour and be fixedly mounted in rail support groove 41 by vertical bolt.
Rapid constructing method provided by the present invention is specific as follows:
A kind of rapid constructing method of embedded railway points system, includes the following steps:
1), preparation of construction:Unwrapping wire is carried out using CPIII unwrapping wire mode and CPIII control nets measure, then at the construction field (site)
Pedestal is poured into a mould, marks line midline, switching turnout plate profile and plate stitch outline position in base top surface, and be laid with and be isolated in base top surface
Layer;
2), laying a switch plate:In pre-fabricated factory, to being segmented prefabricated switching turnout plate outline position unwrapping wire, sleeper pair is then utilized
Switching turnout plate slightly spreads positioning, then tuned plate tooling is installed at the Hoisting Position of switching turnout plate, finally removes sleeper, utilizes tuned plate tooling tune
The horizontal position of whole switching turnout plate and elevation;
3), in the rail support groove of switching turnout plate install resilient sleeper-bearing, height adjusting cushion plate;
4), assembling track switch:The group mounted welder welded to rail part is installed in switching turnout plate support rail groove location, at switching turnout plate plate end
The adjustment holder of positioning adjustment is carried out to rail part with the installation of plate stitch position, then rail part is hung in group mounted welder, and adjustment is fixed
Behind position, it is welded as a whole;
5), laying a switch:After the rail part web of the rail is bonded damping block, remove group mounted welder puts rail part by adjusting holder
Enter in rail support groove and adjust track geometry, is then fixed temporarily rail part with temporary locking tooling;
6), installation tongue:Tongue is put into rail support groove, tongue butt is mounted on tongue pedestal by bolt and wedge block;
7), cast polymer composite:It properly protects measure to track switch plate top surface and rail part top surface, then in rail support groove
Polymer composite is poured into a mould, then pours into a mould skin-material, after material reaches design strength, removes adjustment holder and temporary locking work
Dress;
8), installation goat:On switching turnout plate reserve goat installed position install goat, goat by screw rod with
The towing point of the point of switch is connected, and is assembled in the factory to complete embedded railway points system;
9), embedded railway points system positioning and fixed:The embedded railway points system that group installs in factory is transported existing to construction
, according to step 1)In switch area unwrapping wire as a result, unwrapping wire longitudinal extension place sleeper, be then by embedded track switch
System is lifted into coarse positioning on sleeper, and utilizes tuned plate tooling accurate adjustment center line and elevation, finally utilizes tuned plate tooling and pressing plate work
Dress fixes embedded railway points system;
10), perfusion mortar layer:After the pre-buried drainpipe in goat position bottom, to embedded railway points system and pedestal it
Between gap concrete perfusion screed remove tuned plate tooling and pressing plate tooling after concrete strength reaches design strength.
Feature possessed by above-mentioned technical proposal is:
1, step 2)Step 8)The step of completing in factory, really constructing at the scene only has step 1), step 9), step
10), reduce the workload of construction site, site operation speed is extremely quick, and entire construction process is scientific and reasonable, when construction pair
Traffic impact is minimum.
2, the track geometry of switching turnout plate and rail can accurately be adjusted in work progress, ensure that gauge, the flange of rail
Elevation and central lines of track etc. meet the high-precision requirement of circuit design, it is ensured that train is safely and smoothly run.
3, between each switching turnout plate, it is preset with plate stitch, is convenient for the later maintenance of switching turnout plate and rail part.
It can also carry out construction procedure 11 again based on the above technical solution), road top application work:It is to embedded track switch
The circuit surface of system is laid with.
Further preferred, the step 1 to above-mentioned technical proposal)In, go out pedestal using CPIII control net line-putting method setting-outs
Edge positions simultaneously determine reinforcement installation position, then assembling reinforcement, carry out pass mould to pedestal using baffle, pour into a mould concrete,
When band concrete strength reaches design strength 75%, template is removed;It is marked using CPIII control net setting-outs on base top surface
Then the outline position of line midline, switching turnout plate and plate stitch is laid with separation layer in base top surface.
It is further preferred to above-mentioned technical proposal, limiting groove, limiting groove bottom paving are also set up on the base top surface
If separation layer, four side of limiting groove is laid with resilient sleeper-bearing.Limiting groove can reinforce the cross spacing to embedded railway points system
Effect.
Further preferred, the step 3 to above-mentioned technical proposal)In, in the roads switching turnout plate support rail trench bottom adhesive for spraying Hou Yan
Longitudinal extension of branching off is laid with resilient sleeper-bearing, and total powerstation is then used to carry out elevation side every a distance to resilient sleeper-bearing top surface
Beam calculates the height adjusting cushion plate thickness under each point according to flange of rail designed elevation, and by the height adjusting cushion plate of respective thickness and elasticity
Backing plate is bonded as one.The resilient sleeper-bearing in different cross section region selects different rigidity according to actual needs.Height adjusting cushion plate and height
Molecular composite material has consistent elasticity modulus.
Further preferred, the step 4 to above-mentioned technical proposal)In, between stock rail and curve rail, between stock rail and railway frog
It is previously-completed welding in processing, reduces the welding job in embedded railway points system assembling process, improves assembling
Efficiency shortens construction period.
Further preferred, the step 7 to above-mentioned technical proposal)In, baffle is placed at switching turnout plate rail support groove both ends, and in track switch
Plate top surface and rail part top surface jointing tape paper or film, polymer composite are slowly injected into right in rail support groove after stirring evenly
Gap is filled, and after polymer composite starts hardening, in its surface casting skin-material, band skin-material, which reaches, to be set
After counting intensity, adjustment holder and temporary locking tooling are removed, removes the adhesive tape or film of track switch plate top surface and rail part top surface.
Further preferred, the step 10 to above-mentioned technical proposal)In, it will be between embedded railway points system and pedestal with baffle
After gap sealing, the grout hole by being reserved on switching turnout plate waits for that concrete strength reaches towards concrete perfusion screed in gap
Baffle, tuned plate tooling and pressing plate tooling are removed after design strength.
Description of the drawings
Fig. 1 is the cross-sectional structure schematic diagram of embedded railway points system of the present invention.
Fig. 2 is the vertical structure schematic diagram of embedded railway points system of the present invention.
Fig. 3 is the construction process figure of the method for the present invention.
It is identified in figure:1- pedestals, 2- separation layers, 3- screeds, 4- switching turnout plates, 41- rail support grooves, 42- grout holes, 43- plates
Seam, 5- resilient sleeper-bearings, 6- height adjusting cushion plates, 7- polymer composites, 8- rail parts, 81- stock rails, 82- tongues, 83- curves
Rail, 84- railway frogs, 85- guard rails, 86- weld seams, 9- adjust holder, 10- group mounted welders, 11-PVC pipes, 12- drainpipes, 13- limits
Groove, 14- goats.
Specific implementation mode
Below in conjunction with the accompanying drawings, the present invention is described in detail.
Embodiment:As shown in figure 3, a kind of rapid constructing method of embedded railway points system, includes the following steps:
1), preparation of construction:Unwrapping wire is carried out using CPIII unwrapping wire mode and CPIII control nets measure, then at the construction field (site)
Pedestal 1 is poured into a mould, marks line midline, 43 outline position of 4 profile of switching turnout plate and plate stitch in 1 top surface of pedestal, and spread in 1 top surface of pedestal
If separation layer 2.Step 1)In, go out the edge positions of pedestal 1 using CPIII control net line-putting method setting-outs and determines that reinforcing bar is pacified
Holding position, then assembling reinforcement carry out pass mould using baffle to pedestal 1, pour into a mould concrete, it is strong that band concrete strength reaches design
When spending 75%, template is removed;Line midline, switching turnout plate 4 and plate stitch are marked using CPIII control net setting-outs on 1 top surface of pedestal
Then 43 outline position is laid with separation layer 2 in 1 top surface of pedestal.Limiting groove 13 is also set up on 1 top surface of the pedestal, is limited
13 bottom of groove is laid with separation layer 2, and 13 4 side of limiting groove is laid with resilient sleeper-bearing 5.
2), laying a switch plate 4:In pre-fabricated factory, to being segmented prefabricated 4 outline position unwrapping wire of switching turnout plate, then utilize
Sleeper is to the slightly paving positioning of switching turnout plate 4, then tuned plate tooling is installed at the Hoisting Position of switching turnout plate 4, finally removes sleeper, utilizes tune
Plate tooling adjusts horizontal position and the elevation of switching turnout plate 4.
3), switching turnout plate 4 rail support groove 41 in installation resilient sleeper-bearing 5, height adjusting cushion plate 6.Step 3)In, in switching turnout plate 4
It is laid with resilient sleeper-bearing 5 along track switch longitudinal extension after 41 bottom adhesive for spraying of rail support groove, then uses total powerstation to elasticity
5 top surface of backing plate carries out elevation curb girder every a distance, and the thickness of the height adjusting cushion plate under each point is calculated according to flange of rail designed elevation
Degree, and the height adjusting cushion plate of respective thickness 6 and resilient sleeper-bearing 5 are bonded as one.
4), assembling track switch:The group mounted welder 10 welded to rail part 8 is installed in 41 position of rail support groove of switching turnout plate 4,
The adjustment holder 9 of positioning adjustment is carried out to rail part 8 at the plate end of switching turnout plate 4 and the installation of 43 position of plate stitch, then rail part 8 is hung
To group mounted welder 10, after adjustment positioning, it is welded as a whole.Step 4)In, between stock rail 81 and curve rail 83, stock rail
Between 81 and railway frog 84 welding is previously-completed in processing.4 contact positions at solder joint 86-3 are welded using exothermic welding
It connects, connector polishes flat after the completion of welding.In this step, pad 86-1,86-2,86-4 and 86-5 of rail part 8 are advance
Complete welding.
5), laying a switch:After 8 web of the rail of rail part is bonded damping block, remove group mounted welder 10 will by adjusting holder 9
Rail part 8 is put into rail support groove 41 and adjusts track geometry, is then fixed temporarily rail part 8 with temporary locking tooling.
6), installation tongue:Tongue 82 is put into rail support groove 41,82 butt of tongue is mounted on tongue by bolt and wedge block
Pedestal.
7), cast polymer composite 7:It properly protects measure to 4 top surface of switching turnout plate and 8 top surface of rail part, then exists
Polymer composite 7 is poured into a mould in rail support groove 41, then pours into a mould skin-material, after material reaches design strength, removes adjustment holder 9
With temporary locking tooling.Step 7)In, baffle is placed at 41 both ends of rail support groove of switching turnout plate 4, and in 4 top surface of switching turnout plate and rail
8 top surface jointing tape paper of part or film, polymer composite 7 are slowly injected into rail support groove 41 after stirring evenly and are carried out to gap
Filling, after polymer composite 7 starts hardening, in its surface casting skin-material, band skin-material reaches design strength
Afterwards, adjustment holder 9 and temporary locking tooling are removed, the adhesive tape or film of 4 top surface of switching turnout plate and 8 top surface of rail part are removed.
8), installation goat:The goat installed position reserved on switching turnout plate 4 installs goat 14, goat 14
It is connected with the towing point at 82 tip of tongue by screw rod, is assembled in the factory to complete embedded railway points system.Goat 14
Power supply and signal cable passed through from the two φ 50mmPVC pipes 11 reserved on switching turnout plate 4, drawn from plate stitch 43 with it is extraneous
Power supply and the connected of signal source
9), embedded railway points system positioning and fixed:The embedded railway points system that group installs in factory is transported existing to construction
, according to step 1)In switch area unwrapping wire as a result, unwrapping wire longitudinal extension place sleeper, be then by embedded track switch
System is lifted into coarse positioning on sleeper, and utilizes tuned plate tooling accurate adjustment center line and elevation, finally utilizes tuned plate tooling and pressing plate work
Dress fixes embedded railway points system.
10), perfusion mortar layer:After the pre-buried drainpipe 12 in goat position bottom, to embedded railway points system with
Gap concrete perfusion screed 3 between pedestal 1 removes tuned plate tooling and pressure after concrete strength reaches design strength
Plate tooling.Step 10)In, with baffle by after the gap sealing between embedded railway points system and pedestal, by pre- on switching turnout plate 4
The grout hole 42 stayed removes baffle, tuned plate towards concrete perfusion screed 3 in gap after concrete strength reaches design strength
Tooling and pressing plate tooling.
11), road top application work:The circuit surface of embedded railway points system is laid with, the grass planting that such as bankets, asphalt or
Sandstone.
Claims (8)
1. a kind of rapid constructing method of embedded railway points system, it is characterised in that include the following steps:
1), preparation of construction:Unwrapping wire is carried out using CPIII unwrapping wire mode and CPIII control nets measure, then at the construction field (site)
Pedestal is poured into a mould, marks line midline, switching turnout plate profile and plate stitch outline position in base top surface, and be laid with and be isolated in base top surface
Layer;
2), laying a switch plate:In pre-fabricated factory, to being segmented prefabricated switching turnout plate outline position unwrapping wire, sleeper pair is then utilized
Switching turnout plate slightly spreads positioning, then tuned plate tooling is installed at the Hoisting Position of switching turnout plate, finally removes sleeper, utilizes tuned plate tooling tune
The horizontal position of whole switching turnout plate and elevation;
3), in the rail support groove of switching turnout plate install resilient sleeper-bearing, height adjusting cushion plate;
4), assembling track switch:The group mounted welder welded to rail part is installed in switching turnout plate support rail groove location, at switching turnout plate plate end
The adjustment holder of positioning adjustment is carried out to rail part with the installation of plate stitch position, then rail part is hung in group mounted welder, and adjustment is fixed
Behind position, it is welded as a whole;
5), laying a switch:After the rail part web of the rail is bonded damping block, remove group mounted welder puts rail part by adjusting holder
Enter in rail support groove and adjust track geometry, is then fixed temporarily rail part with temporary locking tooling;
6), installation tongue:Tongue is put into rail support groove, tongue butt is mounted on tongue pedestal by bolt and wedge block;
7), cast polymer composite:It properly protects measure to track switch plate top surface and rail part top surface, then in rail support groove
Polymer composite is poured into a mould, then pours into a mould skin-material, after material reaches design strength, removes adjustment holder and temporary locking work
Dress;
8), installation goat:On switching turnout plate reserve goat installed position install goat, goat by screw rod with
The towing point of the point of switch is connected, and is assembled in the factory to complete embedded railway points system;
9), embedded railway points system positioning and fixed:The embedded railway points system that group installs in factory is transported existing to construction
, according to step 1)In switch area unwrapping wire as a result, unwrapping wire longitudinal extension place sleeper, be then by embedded track switch
System is lifted into coarse positioning on sleeper, and utilizes tuned plate tooling accurate adjustment center line and elevation, finally utilizes tuned plate tooling and pressing plate work
Dress fixes embedded railway points system;
10), perfusion mortar layer:After the pre-buried drainpipe in goat position bottom, to embedded railway points system and pedestal it
Between gap concrete perfusion screed remove tuned plate tooling and pressing plate tooling after concrete strength reaches design strength.
2. a kind of rapid constructing method of embedded railway points system according to claim 1, it is characterised in that further include step
Suddenly:
11), road top application work:The circuit surface of embedded railway points system is laid with.
3. a kind of rapid constructing method of embedded railway points system according to claim 1 or 2, it is characterised in that:Step
1)In, go out the edge positions of pedestal using CPIII control net line-putting method setting-outs and determine reinforcement installation position, then binds
Reinforcing bar carries out pass mould using baffle to pedestal, pours into a mould concrete and removes mould when band concrete strength reaches design strength 75%
Plate;The outline position of line midline, switching turnout plate and plate stitch is marked using CPIII control net setting-outs on base top surface, then
It is laid with separation layer in base top surface.
4. a kind of rapid constructing method of embedded railway points system according to claim 3, it is characterised in that:The pedestal
Limiting groove is also set up on top surface, limiting groove bottom is laid with separation layer, and four side of limiting groove is laid with resilient sleeper-bearing.
5. a kind of rapid constructing method of embedded railway points system according to claim 1, it is characterised in that:Step 3)
In, it is laid with resilient sleeper-bearing along track switch longitudinal extension after switching turnout plate support rail trench bottom adhesive for spraying, then uses whole station
Instrument carries out elevation curb girder to resilient sleeper-bearing top surface every a distance, and the height-regulating under each point is calculated according to flange of rail designed elevation
Plate thickness, and the height adjusting cushion plate of respective thickness is bonded as one with resilient sleeper-bearing.
6. a kind of rapid constructing method of embedded railway points system according to claim 1, it is characterised in that:Step 4)
In, between stock rail and curve rail, welding is previously-completed in processing between stock rail and railway frog.
7. a kind of rapid constructing method of embedded railway points system according to claim 1, it is characterised in that:Step 7)
In, baffle is placed at switching turnout plate rail support groove both ends, and in track switch plate top surface and rail part top surface jointing tape paper or film, high score
Sub- composite material is slowly injected into rail support groove after stirring evenly and is filled to gap, waits for that polymer composite starts to harden
Afterwards, adjustment holder and temporary locking tooling are removed after band skin-material reaches design strength in its surface casting skin-material,
Remove the adhesive tape or film of track switch plate top surface and rail part top surface.
8. a kind of rapid constructing method of embedded railway points system according to claim 1, it is characterised in that:Step 10)
In, with baffle by after the gap sealing between embedded railway points system and pedestal, by the grout hole reserved on switching turnout plate towards seam
Concrete perfusion screed in gap removes baffle, tuned plate tooling and pressing plate tooling after concrete strength reaches design strength.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810216788.8A CN108286210B (en) | 2018-03-16 | 2018-03-16 | A kind of rapid constructing method of embedded railway points system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810216788.8A CN108286210B (en) | 2018-03-16 | 2018-03-16 | A kind of rapid constructing method of embedded railway points system |
Publications (2)
Publication Number | Publication Date |
---|---|
CN108286210A true CN108286210A (en) | 2018-07-17 |
CN108286210B CN108286210B (en) | 2019-05-07 |
Family
ID=62833785
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810216788.8A Active CN108286210B (en) | 2018-03-16 | 2018-03-16 | A kind of rapid constructing method of embedded railway points system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108286210B (en) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110029535A (en) * | 2019-04-01 | 2019-07-19 | 成都市新筑路桥机械股份有限公司 | A kind of slidably slight drag embedded tracks structure |
CN111663375A (en) * | 2020-06-18 | 2020-09-15 | 成都市新筑路桥机械股份有限公司 | Novel beam type embedded track system and construction and maintenance process thereof |
CN112064424A (en) * | 2020-08-07 | 2020-12-11 | 上海远通路桥工程有限公司 | Quick construction method for road section track at level crossing |
CN113699835A (en) * | 2021-10-26 | 2021-11-26 | 中国土木工程集团有限公司 | Integral type turnout drainage structure of railway track bed in cargo yard of port area and construction method |
CN113737579A (en) * | 2021-09-17 | 2021-12-03 | 芜湖中铁科吉富轨道有限公司 | Site-reconstructed small-radius I-shaped switch rail expansion adjuster and reconstruction construction method thereof |
CN116397465A (en) * | 2023-05-05 | 2023-07-07 | 广州地铁设计研究院股份有限公司 | Embedded continuous support turnout |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
RU203554U1 (en) * | 2020-11-23 | 2021-04-12 | Федеральное государственное автономное образовательное учреждение высшего образования "Российский университет транспорта" (ФГАОУ ВО РУТ (МИИТ), РУТ (МИИТ)) | PLATE BASE OF ROTARY TRANSFERS |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE202006013822U1 (en) * | 2005-10-06 | 2006-11-09 | Scharrenbroich, Eugen | Modular, series-connected heating unit for railway points or switches, includes shaped aluminum casting containing tubes carrying heating fluid |
CN101215812A (en) * | 2007-12-27 | 2008-07-09 | 中铁二局股份有限公司 | Construction method for passenger transport dedicated line bolster embedded large-size ballastless track |
CN103362036A (en) * | 2013-07-24 | 2013-10-23 | 成都市新筑路桥机械股份有限公司 | Quick construction method of embedded rail system |
CN206581083U (en) * | 2017-03-14 | 2017-10-24 | 成都市新筑路桥机械股份有限公司 | A kind of rail support groove adjuster |
-
2018
- 2018-03-16 CN CN201810216788.8A patent/CN108286210B/en active Active
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE202006013822U1 (en) * | 2005-10-06 | 2006-11-09 | Scharrenbroich, Eugen | Modular, series-connected heating unit for railway points or switches, includes shaped aluminum casting containing tubes carrying heating fluid |
CN101215812A (en) * | 2007-12-27 | 2008-07-09 | 中铁二局股份有限公司 | Construction method for passenger transport dedicated line bolster embedded large-size ballastless track |
CN103362036A (en) * | 2013-07-24 | 2013-10-23 | 成都市新筑路桥机械股份有限公司 | Quick construction method of embedded rail system |
CN206581083U (en) * | 2017-03-14 | 2017-10-24 | 成都市新筑路桥机械股份有限公司 | A kind of rail support groove adjuster |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110029535A (en) * | 2019-04-01 | 2019-07-19 | 成都市新筑路桥机械股份有限公司 | A kind of slidably slight drag embedded tracks structure |
CN111663375A (en) * | 2020-06-18 | 2020-09-15 | 成都市新筑路桥机械股份有限公司 | Novel beam type embedded track system and construction and maintenance process thereof |
CN111663375B (en) * | 2020-06-18 | 2022-01-04 | 成都市新筑路桥机械股份有限公司 | Novel beam type embedded track system and construction and maintenance process thereof |
CN112064424A (en) * | 2020-08-07 | 2020-12-11 | 上海远通路桥工程有限公司 | Quick construction method for road section track at level crossing |
CN113737579A (en) * | 2021-09-17 | 2021-12-03 | 芜湖中铁科吉富轨道有限公司 | Site-reconstructed small-radius I-shaped switch rail expansion adjuster and reconstruction construction method thereof |
CN113699835A (en) * | 2021-10-26 | 2021-11-26 | 中国土木工程集团有限公司 | Integral type turnout drainage structure of railway track bed in cargo yard of port area and construction method |
CN113699835B (en) * | 2021-10-26 | 2022-01-28 | 中国土木工程集团有限公司 | Construction method of integral type turnout drainage structure of railway track bed of cargo yard in port area |
CN116397465A (en) * | 2023-05-05 | 2023-07-07 | 广州地铁设计研究院股份有限公司 | Embedded continuous support turnout |
Also Published As
Publication number | Publication date |
---|---|
CN108286210B (en) | 2019-05-07 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108286210B (en) | A kind of rapid constructing method of embedded railway points system | |
CN104790970B (en) | A kind of method that use combining structure carries out shield tunnel reinforcing | |
CN101063289B (en) | City-rail steel spring floating slab rail bed railroad switch construction method | |
CN207452594U (en) | A kind of urban track traffic prestressing force slab track | |
CN101215812B (en) | Construction method for passenger transport dedicated line bolster embedded large-size ballastless track | |
CN104018425B (en) | A kind of quick-replaceable bridge expansion joint installation and installation method thereof | |
CN107974935A (en) | A kind of SF combs flute profile telescopic device and its construction method of installation | |
CN101775772B (en) | Sloping tensioning method two-way prestressed concrete pavement construction method | |
RU2148685C1 (en) | Method for construction of railway track structure without crushed-stone ballast | |
CN103321111B (en) | Streetcar track connects the construction method of paving | |
JP2004538401A (en) | Method of continuously supporting rails on fixed tracks, as well as adjusting devices and fixed tracks | |
CN102653931A (en) | Elastic supporting vibration isolation member ballast bed | |
KR101405468B1 (en) | Method for manufacturing concrete block for railway track and method for laying railway track using concrete block manufactured by the same method | |
KR20050108867A (en) | A method for changing plate-girder bridge of railway bridge into slab bridge by using temporary construction bents. | |
CN109098102A (en) | Just beam ruggedized construction for switch section | |
KR101705141B1 (en) | Improved technique of railway track ballast operation | |
WO2017187461A1 (en) | Slab track, arranged in an overlapping manner on a slab foundation | |
JP3566704B2 (en) | Reinforcement structure of existing railway bridge | |
CN105926381A (en) | Method for changing ballast track bed of tunnel to ballastless track under condition of uninterrupted train working | |
CN104532691A (en) | Ballastless track connected-block sleeper | |
CN106283978B (en) | A kind of ore deposit inside slope track failure railway roadbed fast repairing method | |
CN105672172B (en) | A kind of construction method of Dacroment steel highway barrier | |
CN107119568A (en) | A kind of high-level bridge construction method | |
CN110029574A (en) | The novel bridge telescopic device and its installation method that can quickly repair | |
CN111926649A (en) | Reinforced integrally-built crossing plate for railway special line and line rail fixing device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
TR01 | Transfer of patent right |
Effective date of registration: 20240403 Address after: 611400 No. 799, hope road, Wujin street, Xinjin District, Chengdu, Sichuan (Industrial Park) Patentee after: Chengdu Xinzhu Transportation Technology Co.,Ltd. Country or region after: China Address before: 611430 Xinjin Industrial Park, Sichuan, Chengdu Patentee before: CHENGDU XINZHU ROAD & BRIDGE MACHINERY Co.,Ltd. Country or region before: China |
|
TR01 | Transfer of patent right |