A kind of multi-functional bar of lying prone of the assembled being connect with structure
Technical field
The present invention relates to technical field of engineering machinery, especially a kind of multi-functional bar of lying prone of the assembled being connect with structure.
Background technology
More and more construction sites are all the dismountings for carrying out tower crane again after curtain wall completion at present, and more and more
The tower crane of project will use long draw, in addition the particularity of building structure, attached wall embedded part is such often within curtain wall vertical plane
In the case of, depend merely on tied up using cucurbit dismantled in tower crane wall-attaching equipment be it is difficult to ensure that dismounting process without impinging on curtain wall
's.Furthermore the last dismounting of more and more skyscrapers, which is required for using roofing, lifts up into capable dismounting, and roofing, which is hung, to be torn open to the end,
Small roofing, which is hung, to be required for manually directly removed and now often in roofing layer, structure can all be shunk, and without building
Ladder goes directly structure sheaf from terrace layer, and artificial is difficult to be transported to the floor of construction elevator to be transported through.
Invention content
The purpose of the present invention is to provide a kind of multi-functional bars of lying prone of assembled being connect with structure, pass through turning for rotary shaft
It is dynamic, it realizes the lifting in the range of the 180 degree of arm, is lifted by crane by secondary suspension centre, be replaced with main hook after being turned back to midline position, then
By elevator operation, to solve the problems mentioned in the above background technology.
To achieve the above object, the present invention provides following technical solution:A kind of assembled being connect with structure is multi-functional to lie prone
Bar, including floor and bar of lying prone, the bar of lying prone is separately installed with hoist engine, shape steel plate, shaped steel on floor on the floor
Stirrup one, diagonal brace one, shaped steel stirrup two, diagonal brace two and shaped steel stirrup three, the upper left of the floor are equipped with hoist engine, volume
It raises and chemical bolt is equipped between machine and floor, hoist engine bottom end both sides are fixed on by chemical bolt on floor, the volume
It raises and shaped steel stirrup one is installed on the right side of machine, shape steel plate is connected between hoist engine and shaped steel stirrup one, shape steel plate is jointly mounted to
On floor, the right side of shaped steel stirrup one is equipped with diagonal brace one, and the right side of the diagonal brace one is equipped with shaped steel stirrup two, the shaped steel
Stirrup one, diagonal brace one and shaped steel stirrup two are mounted on the middle part of floor, and the right side of the shaped steel stirrup two is equipped with diagonal brace two, institute
The right side for stating diagonal brace two is provided with shaped steel stirrup three, and the diagonal brace two and shaped steel stirrup three are mounted on the upper right of floor, institute
The upper support for stating shaped steel stirrup one, diagonal brace one, shaped steel stirrup two, diagonal brace two and shaped steel stirrup three is connected with shaped steel mobile jib, institute
That states shaped steel mobile jib passes on left shaped steel stirrup one, diagonal brace one, shaped steel stirrup two, diagonal brace two and shaped steel stirrup three mounted on floor
Top, be provided with fixed pulley above the left side of the shaped steel mobile jib, institute's fixed pulley is corresponding with shaped steel stirrup one mounted on shaped steel
Above mobile jib, shaped steel stirrup four is installed above the middle part of the shaped steel mobile jib, shaped steel stirrup four is corresponding with shaped steel stirrup three,
The top of shaped steel stirrup four is equipped with fixed pulley, and the right of the shaped steel stirrup four is equipped with shaft, and shaft is by rotary shaft and locking
Axis forms, and is connected with flanged joint pattern two between shaft on the left of the shaped steel mobile jib, shaft passes through flanged joint pattern two
It is fixed on the right side of shaped steel mobile jib, the right side for passing on left shaft connection shaped steel mobile jib of the shaped steel mobile jib, the shaped steel master
Floor is extended by shaft on the right side of bar, on the right side of shaped steel mobile jib on installation there are three flanged joint pattern two, the shaped steel mobile jibs
It is separately installed with the identical fixed pulley of size above right top and right end, the fixed pulley above right end is equipped with anti-drop device, institute
It states and is provided with secondary suspension centre below shaped steel mobile jib right end.
As further embodiment of the present invention:The diagonal brace one and diagonal brace two are respectively by the identical shaped steel diagonal brace of two sizes
Composition.
As further embodiment of the present invention:The shaped steel stirrup one, diagonal brace one, shaped steel stirrup two, diagonal brace two and shaped steel
The bottom side of stirrup three is equipped with billet, and billet both ends are equipped with expansion bolt, the shaped steel stirrup one, diagonal brace one, shaped steel horse
Stirrup two, diagonal brace two and shaped steel stirrup three are fixed on by billet and expansion bolt on floor.
As further embodiment of the present invention:Flange company is connected between fixed pulley on the left of the shaped steel mobile jib and mobile jib
Pattern one is connect, flanged joint pattern one is connected between the fixed pulley of four top of the shaped steel stirrup four and shaped steel stirrup, it is described
Flanged joint pattern two, shaped steel stirrup are provided between shaped steel stirrup one, shaped steel stirrup two and shaped steel stirrup three and shaped steel mobile jib
First, shaped steel stirrup two and shaped steel stirrup three fix support shaped steel mobile jib by flanged joint pattern two, the shaped steel stirrup four with
Flanged joint pattern two is provided between shaped steel mobile jib, shaped steel stirrup four is fixed on shaped steel mobile jib by flanged joint pattern two
On.
As further embodiment of the present invention:The right end of the floor be floor parapet, the outer side edges of floor parapet
For glass curtain wall outer boundary.
As further embodiment of the present invention:It is set between three flanged joint patterns two on the right side of the shaped steel mobile jib
There are fixation holes, and fixation holes are provided on the right side of shaped steel stirrup four, steel wire rope is connected between the fixation holes
It is fixed.
As further embodiment of the present invention:It is in series with lifting rope from left to right between the hoist engine and four fixed pulleys.
Compared with prior art, advantageous effect of the present invention:
This multi-functional bar of lying prone of assembled being connect with structure by the rotation of rotary shaft, realizes rising in the range of the 180 degree of arm
It hangs, the length combination of arm can be easily replaced using this function, and be avoided that will be because of the weight to be hung in different positions
It puts and the repositioning installation for the bar that causes to lie prone, secondary suspension centre lifting can be first passed through when rotating hanging object, is turned back to after midline position more
Change main hook into, then by elevator operation, the multi-functional bar of lying prone of assembled that should connect with structure, have light, assembling simply, remove
The features such as fortune is convenient, freight is low, recycling.Installation cost of labor can be saved using the design, improve work efficiency.
Description of the drawings
Fig. 1 is the overall structure figure of the present invention;
Fig. 2 is the inclined support structure figure of the present invention;
Fig. 3 is the flanged joint pattern two devices figure of the present invention;
Fig. 4 is one installation drawing of flanged joint pattern of the present invention;
Fig. 5 is the pivot structure figure of the present invention.
In figure:1- floors;2- hoist engines;3- shape steel plates;4- shaped steel stirrup one;5- diagonal braces one;6- shaped steel stirrup two;7- is oblique
Support two;8- shaped steel stirrup three;9- chemical bolts;10- shaped steel mobile jibs;11- fixed pulleys;12- shaped steel stirrup four;13- shafts;14-
Rotary shaft;15- lock shafts;16- flanged joints pattern one;17- flanged joints pattern two;18- anti-drop devices;19- pair suspension centres;
20- shaped steel diagonal braces;21- billets;22- expansion bolts;23- floor parapets;24- glass curtain wall outer boundaries;25- mounting holes
Hole;26- steel wire ropes;27- lifting ropes;28- lies prone bar.
Specific embodiment
Below in conjunction with the attached drawing in the embodiment of the present invention, the technical solution in the embodiment of the present invention is carried out clear, complete
Site preparation describes, it is clear that described embodiment is only part of the embodiment of the present invention, instead of all the embodiments.It is based on
Embodiment in the present invention, those of ordinary skill in the art are obtained every other without making creative work
Embodiment shall fall within the protection scope of the present invention.
Please refer to Fig.1-5, in the embodiment of the present invention, a kind of multi-functional bar of lying prone of the assembled being connect with structure, including floor 1
With bar 28 of lying prone, bar 28 of lying prone include a hoist engine 2, four shaped steel stirrups, four shaped steel diagonal braces, a segment type steel mobile jib 10, three sections
Shaped steel combination bar, four fixed pulleys 11 and nine sets of fixed flanged joint systems, seven sets are bar of lying prone with being fixedly connected for floor 1
28 are mounted on floor 1, and hoist engine 2, shape steel plate 3, shaped steel stirrup 1, diagonal brace 1, shaped steel stirrup are separately installed on floor 1
26, diagonal brace 27 and shaped steel stirrup 38, the upper left of floor 1 are equipped with hoist engine 2, are equipped between hoist engine 2 and floor 1
Chemical bolt 9,2 bottom end both sides of hoist engine are fixed on by chemical bolt 9 on floor 1, and 2 right side of hoist engine is equipped with shaped steel stirrup
One 4, shape steel plate 3 is connected between hoist engine 2 and shaped steel stirrup 1, shape steel plate 3 is jointly mounted on floor 1, shaped steel stirrup one
4 right side is equipped with diagonal brace 1, and the right side of diagonal brace 1 is equipped with shaped steel stirrup 26, shaped steel stirrup 1, diagonal brace 1 and shaped steel
Stirrup 26 is mounted on the middle part of floor 1, and the right side of shaped steel stirrup 26 is equipped with diagonal brace 27, and the right side of diagonal brace 27 is provided with type
Steel stirrup 38, diagonal brace 27 and shaped steel stirrup 38 are mounted on the upper right of floor 1, and the right end of floor 1 is floor parapet
23, the outer side edges of floor parapet 23 are glass curtain wall outer boundary 24, and diagonal brace 1 is identical by two sizes respectively with diagonal brace 27
Shaped steel diagonal brace 20 form, shaped steel stirrup 1, diagonal brace 1, shaped steel stirrup 26, diagonal brace 27 and shaped steel stirrup 38 bottom side peace
Equipped with billet 21,21 both ends of billet are equipped with expansion bolt 22, shaped steel stirrup 1, diagonal brace 1, shaped steel stirrup 26, diagonal brace
27 and shaped steel stirrup 38 be fixed on floor 1 by billet 21 and expansion bolt 22, shaped steel stirrup 1, diagonal brace 1, type
The upper support of steel stirrup 26, diagonal brace 27 and shaped steel stirrup 38 is connected with shaped steel mobile jib 10, and shaped steel mobile jib 10 passes on left
Shaped steel stirrup 1, diagonal brace 1, shaped steel stirrup 26, diagonal brace 27 and shaped steel stirrup 38 are mounted on the top of floor 1, shaped steel master
Fixed pulley 11 is provided with above the left side of bar 10, institute's fixed pulley 11 is corresponding with shaped steel stirrup 1 to be mounted on 10 top of shaped steel mobile jib,
Shaped steel stirrup 4 12 is installed above the middle part of shaped steel mobile jib 10, shaped steel stirrup 4 12 is corresponding with shaped steel stirrup 38, shaped steel horse
The top of stirrup 4 12 is equipped with fixed pulley 11, and flanged joint pattern is connected between the fixed pulley 11 on the left of shaped steel mobile jib 10 and mobile jib
One 16, it is connected with flanged joint pattern 1, shaped steel between shaped steel stirrup 4 12 and the fixed pulley 11 of the top of shaped steel stirrup 4 12
Flanged joint pattern 2 17, shaped steel horse are provided between stirrup 1, shaped steel stirrup 26 and shaped steel stirrup 38 and shaped steel mobile jib 10
Stirrup 1, shaped steel stirrup 26 and shaped steel stirrup 38 fix support shaped steel mobile jib 10, shaped steel stirrup by flanged joint pattern 2 17
Flanged joint pattern 2 17 is provided between 4 12 and shaped steel mobile jib 10, shaped steel stirrup 4 12 is solid by flanged joint pattern 2 17
It is scheduled on shaped steel mobile jib 10, the right of shaped steel stirrup 4 12 is equipped with shaft 13, and shaft 13 is by 15 groups of rotary shaft 14 and lock shaft
Flanged joint pattern 2 17 is connected between 10 left side of, shaped steel mobile jib and shaft 13, shaft 13 passes through flanged joint pattern two
17 are fixed on the right side of shaped steel mobile jib 10, the right side for passing on left shaft 13 and connecting shaped steel mobile jib 10 of shaped steel mobile jib 10, shaped steel
Floor 1 is extended in 10 right side of mobile jib by shaft 13, by the rotation of rotary shaft, realizes the lifting in the range of the 180 degree of arm,
Can easily replace the length combination of arm using this function, and can to avoid will because of the weight to be hung in different positions and
Cause to lie prone the repositioning installation of bar, and there are three flanged joint pattern 2 17, shaped steel mobile jibs 10 for installation on 10 right side of shaped steel mobile jib
Fixation holes 25 are provided with, and set on the right side of shaped steel stirrup 4 12 between three flanged joint patterns 2 17 on right side
There are fixation holes 25, steel wire rope 26 is connected between fixation holes 25 and is fixed, above 10 right top of shaped steel mobile jib and right end
It is separately installed with the identical fixed pulley 11 of size, the fixed pulley 11 above right end is equipped with anti-drop device 18, hoist engine 2 and four
Lifting rope 27 is in series between fixed pulley 11 from left to right, secondary suspension centre 19 is provided with below 10 right end of shaped steel mobile jib, to rotate hanging object
When can first pass through secondary suspension centre 19 and lift by crane, be replaced with main hook after being turned back to midline position, then by elevator operation, this assembled is more
Function bar of lying prone can require to select the combination of the specification and arm of each building block according to different hanging objects, all using can
The assembled design of detachable, is readily transported and manually carries, have light, assembling is simple, convenient in carrying, freight are low,
The features such as recycling, and installation cost of labor can be saved using the design, improve work efficiency.
In summary:This multi-functional bar of lying prone of assembled being connect with structure by the rotation of rotary shaft 14, realizes arm
Lifting in the range of 180 degree can easily replace the length combination of arm using this function, and be avoided that will be because of being hung
Weight causes to lie prone in different positions the repositioning installation of bar, and secondary suspension centre 19 can be first passed through when rotating hanging object and is lifted by crane, is returned
Main hook is replaced with after going to midline position, then by elevator operation, the multi-functional bar of lying prone of assembled that should be connect with structure has
It is light, assembling is simple, convenient in carrying, freight is low, the features such as recycling, and it is artificial using the design can to save installation
Cost improves work efficiency.
It is obvious to a person skilled in the art that the present invention is not limited to the details of above-mentioned exemplary embodiment, Er Qie
In the case of without departing substantially from spirit or essential attributes of the invention, the present invention can be realized in other specific forms.Therefore, no matter
From the point of view of which point, the present embodiments are to be considered as illustrative and not restrictive, and the scope of the present invention is by appended power
Profit requirement rather than above description limit, it is intended that all by what is fallen within the meaning and scope of the equivalent requirements of the claims
Variation is included within the present invention.Any reference numeral in claim should not be considered as to the involved claim of limitation.
In addition, it should be understood that although this specification is described in terms of embodiments, but not each embodiment is only wrapped
Containing an independent technical solution, this description of the specification is merely for the sake of clarity, and those skilled in the art should
It considers the specification as a whole, the technical solutions in each embodiment can also be properly combined, forms those skilled in the art
The other embodiment being appreciated that.