CN108193906A - 一种核岛厂房布置结构 - Google Patents

一种核岛厂房布置结构 Download PDF

Info

Publication number
CN108193906A
CN108193906A CN201710928881.7A CN201710928881A CN108193906A CN 108193906 A CN108193906 A CN 108193906A CN 201710928881 A CN201710928881 A CN 201710928881A CN 108193906 A CN108193906 A CN 108193906A
Authority
CN
China
Prior art keywords
building
nuclear island
arrangement
reactor
nuclear
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710928881.7A
Other languages
English (en)
Inventor
谷振杰
刘文学
王振中
薛静
吴巧英
贾小攀
王莞珏
贝晨
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Nuclear Power Engineering Co Ltd
Original Assignee
China Nuclear Power Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Nuclear Power Engineering Co Ltd filed Critical China Nuclear Power Engineering Co Ltd
Priority to CN201710928881.7A priority Critical patent/CN108193906A/zh
Publication of CN108193906A publication Critical patent/CN108193906A/zh
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H5/00Buildings or groups of buildings for industrial or agricultural purposes
    • E04H5/02Buildings or groups of buildings for industrial purposes, e.g. for power-plants or factories

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Structure Of Emergency Protection For Nuclear Reactors (AREA)

Abstract

本发明涉及一种核岛厂房布置结构,包括反应堆厂房、核辅助厂房、电气厂房和燃料厂房;所述核辅助厂房、电气厂房和燃料厂房位围绕所述反应堆厂房设置;所述反应堆厂房的操作大厅平台设置于±0.00m标高层。本发明的有益效果为:本发明通过将燃料厂房、辅助厂房和电气厂房围绕反应堆厂房建设,能够保障布局紧凑,减少占地面积,实现经济性能;2、本发明的核岛厂房布置通过将操作大厅布置于±0.00m标高层,可以减少附属设施的配建,简化主要设备安装运输的工艺流程,缩短安装、检修、维修时间;3、根据物项的安全级别分别进行布置,有助于核岛安全生产;4、反应堆厂房的壳体为双层结构,顶层设有水箱,能够有效抵御突发情况,保障生产安全。

Description

一种核岛厂房布置结构
技术领域
本发明属于核工程领域,具体涉及一种核岛厂房布置结构。
背景技术
在低碳发展模式下,核电是解决我国经济重工业化而导致的高能耗、高电力需求与碳减排压力之间矛盾的最佳选择。
经济性和安全性是影响核电站投资的重要因素。为改善核能发电的经济性,主要是通过增大单机容量和电站的规模来降低建造成本,目前最大单机容量己达1650MWe。常见的核岛厂房反应堆厂房和燃料厂房操作大厅在进行主设备运输及燃料操作时,需要增设的龙门架等设施,增加了工程成本。
发明内容
针对现有技术中存在的缺陷,本发明的目的是提供一种核岛厂房布置结构,降低主设备运输及燃料操作时的工程成本,布局紧凑、适用于各种厂址,安全经济性好。
本发明的技术方案如下:
一种核岛厂房布置结构,包括反应堆厂房、核辅助厂房、电气厂房和燃料厂房;所述核辅助厂房、电气厂房和燃料厂房位围绕所述反应堆厂房设置;所述反应堆厂房的操作大厅平台设置于±0.00m标高层。
进一步地,上述的核岛厂房布置结构,所述燃料厂房的操作大厅平台设置于±0.00m标高层。
进一步地,上述的核岛厂房布置结构,所述燃料厂房内设置有主泵清洗及原AC仓库两大源项。
进一步地,上述的核岛厂房布置结构,所述电气厂房中,安全级物项设置于靠近所述反应堆厂房的位置,非安全级物项设置于远离所述反应堆厂房的位置。
进一步地,上述的核岛厂房布置结构,所述安全级物项包括保护序列机柜,所述非安全级物项包括NC电子机柜。
进一步地,上述的核岛厂房布置结构,所述燃料厂房上层布置整层通风设备。
进一步地,上述的核岛厂房布置结构,反应堆厂房的壳体为双层结构,其中内层安全壳为钢制安全壳,外层安全壳为钢筋混凝土壳。
进一步地,上述的核岛厂房布置结构,所述反应堆厂房的外层安全壳顶部设有非能动安全水箱;所述非能动安全水箱与所述内层安全壳内的、布置高度低于所述非能动安全水箱的换热器通过管线相连。
进一步地,上述的核岛厂房布置结构,所述反应堆厂房的主控室设置有双层墙体。
本发明的有益效果如下:
1、本发明通过将燃料厂房、辅助厂房和电气厂房围绕反应堆厂房建设,能够保障布局紧凑,减少占地面积,实现经济性能;
2、本发明的核岛厂房布置通过将操作大厅布置于±0.00m标高层,可以减少附属设施的配建,简化主要设备安装运输的工艺流程,缩短安装、检修、维修时间;
3、根据物项的安全级别分别进行布置,有助于核岛安全生产;
4、反应堆厂房的壳体为双层结构,顶层设有水箱,能够有效抵御突发情况,保障生产安全。
附图说明
图1为本发明一个实施例的核岛厂房布置结构的示意图。
图2为图1中横向的剖面结构示意图。
图3为图1中纵向的剖面结构示意图。
上述附图中,1、反应堆厂房;2、核辅助厂房;3、电气厂房;4、燃料厂房。
具体实施方式
下面结合附图和实施例对本发明进行详细的描述。
如图1所示,本发明公开了一种核岛厂房布置结构,包括反应堆厂房1、核辅助厂房2、电气厂房3和燃料厂房4;所述核辅助厂房2、电气厂房3和燃料厂房4位围绕所述反应堆厂房1设置;所述反应堆厂房1的操作大厅平台设置于±0.00m标高层。同样,所述燃料厂房4的操作大厅平台设置于±0.00m标高层(如图2所示)。如此,在进行主设备运输及燃料操作时,可以减少附属设施(例如龙门架等)的配建,简化主要设备安装运输的工艺流程,缩短安装、检修、维修时间。所述燃料厂房4内设置有主泵清洗及原AC仓库两大源项,可以缩短核岛主工艺系统设备的维修时间。
如图3所示,所述电气厂房3中,安全级物项设置于靠近所述反应堆厂房1的位置,非安全级物项设置于远离所述反应堆厂房1的位置。例如,所述安全级物项包括保护序列机柜,所述非安全级物项包括NC电子机柜。如此设置能够保证外部事故发生时,安全级物项能够得到最大程度的保护。
本实施例中,所述燃料厂房4上层布置整层通风设备,可以提高燃料厂房4抵御外部突发事件的能力。反应堆厂房1的壳体为双层结构,其中内层安全壳为钢制壳,作为第三道安全屏障防止放射性物质外逸;外层安全壳为钢筋混凝土壳,用于支撑非能动安全水箱及乏池补水箱,并保证事故时紧邻安全壳区域的温度不会过高。所述外层安全壳顶部设有非能动安全水箱,与钢壳(内层安全壳)内的换热器(其布置高度低于安全水箱)间通过管线相连,依靠重位差和温差作为驱动力;事故时,乏池补水箱内的水则依靠重力驱动沿补水管线进入乏池。所述反应堆厂房1顶层设有非能动安全水箱作为专设安全设施,事故工况下为反应堆提供导出堆芯热量的非能动安全手段。所述反应堆厂房1的主控室设置有双层墙体,来实现对于飞机撞击的防护。
显然,本领域的技术人员可以对本发明进行各种改动和变型而不脱离本发明的精神和范围。这样,倘若对本发明的这些修改和变型属于本发明权利要求及其同等技术的范围之内,则本发明也意图包含这些改动和变型在内。

Claims (9)

1.一种核岛厂房布置结构,其特征在于:包括反应堆厂房(1)、核辅助厂房(2)、电气厂房(3)和燃料厂房(4);所述核辅助厂房(2)、电气厂房(3)和燃料厂房(4)位围绕所述反应堆厂房(1)设置;所述反应堆厂房(1)的操作大厅平台设置于±0.00m标高层。
2.如权利要求1所述的核岛厂房布置结构,其特征在于:所述燃料厂房(4)的操作大厅平台设置于±0.00m标高层。
3.如权利要求1所述的核岛厂房布置结构,其特征在于:所述燃料厂房(4)内设置有主泵清洗及原AC仓库两大源项。
4.如权利要求1所述的核岛厂房布置结构,其特征在于:所述电气厂房(3)中,安全级物项设置于靠近所述反应堆厂房的位置,非安全级物项设置于远离所述反应堆厂房的位置。
5.如权利要求4所述的核岛厂房布置结构,其特征在于:所述安全级物项包括保护序列机柜,所述非安全级物项包括NC电子机柜。
6.如权利要求1所述的核岛厂房布置结构,其特征在于:所述燃料厂房(4)上层布置整层通风设备。
7.如权利要求1所述的核岛厂房布置结构,其特征在于:反应堆厂房(1)的壳体为双层结构,其中内层安全壳为钢制壳,外层安全壳为钢筋混凝土壳。
8.如权利要求7所述的核岛厂房布置结构,其特征在于:所述反应堆厂房(1)的外层安全壳顶部设有非能动安全水箱;所述非能动安全水箱与所述内层安全壳内的、布置高度低于所述非能动安全水箱的换热器通过管线相连。
9.如权利要求1-8任一所述的核岛厂房布置结构,其特征在于:所述反应堆厂房(1)的主控室设置有双层墙体。
CN201710928881.7A 2017-10-09 2017-10-09 一种核岛厂房布置结构 Pending CN108193906A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710928881.7A CN108193906A (zh) 2017-10-09 2017-10-09 一种核岛厂房布置结构

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710928881.7A CN108193906A (zh) 2017-10-09 2017-10-09 一种核岛厂房布置结构

Publications (1)

Publication Number Publication Date
CN108193906A true CN108193906A (zh) 2018-06-22

Family

ID=62572858

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710928881.7A Pending CN108193906A (zh) 2017-10-09 2017-10-09 一种核岛厂房布置结构

Country Status (1)

Country Link
CN (1) CN108193906A (zh)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112746758A (zh) * 2020-12-28 2021-05-04 岭东核电有限公司 一种核岛厂房布置结构
CN115045544A (zh) * 2022-06-08 2022-09-13 中国核电工程有限公司 一种新型核岛非抗震附属厂房布置结构

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1790552A (zh) * 2004-12-16 2006-06-21 中国核动力研究设计院 直行式核反应堆燃料组件换料装卸工艺
EP2287856A2 (en) * 2009-08-21 2011-02-23 Kabushiki Kaisha Toshiba Construction of nuclear power plant building and construction method thereof
CN103850483A (zh) * 2013-04-02 2014-06-11 中国核电工程有限公司 一种核电厂主厂房群布置方法
WO2015188695A1 (zh) * 2014-06-13 2015-12-17 长江勘测规划设计研究有限责任公司 地下核电站组合洞室群沿山体纵深方向的施工布置
US9312035B2 (en) * 2011-11-14 2016-04-12 Westinghouse Electric Company Llc Semi-portable emergency cooling system for removing decay heat from a nuclear reactor

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1790552A (zh) * 2004-12-16 2006-06-21 中国核动力研究设计院 直行式核反应堆燃料组件换料装卸工艺
EP2287856A2 (en) * 2009-08-21 2011-02-23 Kabushiki Kaisha Toshiba Construction of nuclear power plant building and construction method thereof
US9312035B2 (en) * 2011-11-14 2016-04-12 Westinghouse Electric Company Llc Semi-portable emergency cooling system for removing decay heat from a nuclear reactor
CN103850483A (zh) * 2013-04-02 2014-06-11 中国核电工程有限公司 一种核电厂主厂房群布置方法
WO2015188695A1 (zh) * 2014-06-13 2015-12-17 长江勘测规划设计研究有限责任公司 地下核电站组合洞室群沿山体纵深方向的施工布置

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
核电秦山联营有限公司编著: "《秦山核电二期扩建工程项目管理实践 设计篇》", 31 December 2012, 中国原子能出版社 *
邹树梁: "《核电厂安全评价与分析》", 30 August 2016, 中国原子能出版社 *
钮新强 罗琦: "《地下核电厂概论》", 31 July 2016, 中国原子能出版社 *
闫昌琪 曹夏昕: "《核反应堆安全传热》", 31 March 2010, 哈尔滨工业大学出版社 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112746758A (zh) * 2020-12-28 2021-05-04 岭东核电有限公司 一种核岛厂房布置结构
CN115045544A (zh) * 2022-06-08 2022-09-13 中国核电工程有限公司 一种新型核岛非抗震附属厂房布置结构

Similar Documents

Publication Publication Date Title
CN103850483B (zh) 一种核电厂主厂房群布置方法
CA1049665A (en) Nuclear reactor apparatus
CN102412000B (zh) 一种核电站乏燃料贮存竖井系统
CN103065696B (zh) 乏燃料干式贮存装置
CN110047606B (zh) 一种核电站燃料厂房的布置结构
CN102287062B (zh) 核电站布置结构
CN206460782U (zh) 高温气冷堆核电站乏燃料贮存库竖井热屏筒安装装置
CN108193906A (zh) 一种核岛厂房布置结构
CN108597629A (zh) 一种核电站安全厂房的布置结构
CN103474105A (zh) 一种反应堆压力容器模块式支座支承
US3929568A (en) Nuclear power plant containment construction
EP3364420B1 (en) Dry storage facility with waste heat exhaust and ventilation system for spent nuclear fuel
KR20230041796A (ko) 핵연료 재충전 장치
CN106531265A (zh) 一种地下核电站主厂房群全埋式布置设计方法
CN202650562U (zh) 一种反应堆压力容器模块式支座支承
CN104210930A (zh) 一种用于核聚变装置颈管内部件转运的保护机构
CN202170656U (zh) 核电站布置结构
Ricotti et al. Small modular reactors
CN106373626B (zh) 一种地下核电站主厂房群下埋式布置设计方法
CN106340330B (zh) 一种地下核电站主厂房群台阶式布置设计方法
CN204880472U (zh) 一种安全壳冷却机组框架
CN107863167A (zh) 一种模块式小型堆的多堆布置结构
CN204079220U (zh) 一种用于核聚变装置颈管内部件转运的保护机构
CN106469578A (zh) 核电站反应堆冷却剂系统主回路的布置结构
JP5905790B2 (ja) 使用済燃料貯蔵施設

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20180622