CN108170079A - Building site intelligent container comprehensive management platform - Google Patents
Building site intelligent container comprehensive management platform Download PDFInfo
- Publication number
- CN108170079A CN108170079A CN201810152532.5A CN201810152532A CN108170079A CN 108170079 A CN108170079 A CN 108170079A CN 201810152532 A CN201810152532 A CN 201810152532A CN 108170079 A CN108170079 A CN 108170079A
- Authority
- CN
- China
- Prior art keywords
- building site
- monitoring
- management platform
- comprehensive management
- intelligent container
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000012544 monitoring process Methods 0.000 claims abstract description 62
- 230000005540 biological transmission Effects 0.000 claims abstract description 10
- 238000009434 installation Methods 0.000 claims abstract description 5
- DMBHHRLKUKUOEG-UHFFFAOYSA-N diphenylamine Chemical compound C=1C=CC=CC=1NC1=CC=CC=C1 DMBHHRLKUKUOEG-UHFFFAOYSA-N 0.000 claims description 12
- QVFWZNCVPCJQOP-UHFFFAOYSA-N chloralodol Chemical compound CC(O)(C)CC(C)OC(O)C(Cl)(Cl)Cl QVFWZNCVPCJQOP-UHFFFAOYSA-N 0.000 claims description 10
- 238000004378 air conditioning Methods 0.000 claims description 8
- 230000007613 environmental effect Effects 0.000 claims description 7
- 238000004891 communication Methods 0.000 claims description 3
- 238000012806 monitoring device Methods 0.000 claims description 3
- 239000004973 liquid crystal related substance Substances 0.000 claims description 2
- 238000013461 design Methods 0.000 abstract description 2
- 238000010276 construction Methods 0.000 description 4
- 230000006870 function Effects 0.000 description 2
- 230000002265 prevention Effects 0.000 description 2
- 230000008054 signal transmission Effects 0.000 description 2
- 239000005955 Ferric phosphate Substances 0.000 description 1
- 230000033228 biological regulation Effects 0.000 description 1
- 239000013078 crystal Substances 0.000 description 1
- 238000001514 detection method Methods 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 239000000428 dust Substances 0.000 description 1
- 230000005611 electricity Effects 0.000 description 1
- 238000004134 energy conservation Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 229940032958 ferric phosphate Drugs 0.000 description 1
- 230000005764 inhibitory process Effects 0.000 description 1
- WBJZTOZJJYAKHQ-UHFFFAOYSA-K iron(3+) phosphate Chemical compound [Fe+3].[O-]P([O-])([O-])=O WBJZTOZJJYAKHQ-UHFFFAOYSA-K 0.000 description 1
- 229910000399 iron(III) phosphate Inorganic materials 0.000 description 1
- 239000007788 liquid Substances 0.000 description 1
- 229910052744 lithium Inorganic materials 0.000 description 1
- 230000013011 mating Effects 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 230000001105 regulatory effect Effects 0.000 description 1
- 230000000630 rising effect Effects 0.000 description 1
- 229910001220 stainless steel Inorganic materials 0.000 description 1
- 239000010935 stainless steel Substances 0.000 description 1
- 238000012360 testing method Methods 0.000 description 1
- 239000002699 waste material Substances 0.000 description 1
Classifications
-
- G—PHYSICS
- G05—CONTROLLING; REGULATING
- G05B—CONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
- G05B19/00—Programme-control systems
- G05B19/02—Programme-control systems electric
- G05B19/04—Programme control other than numerical control, i.e. in sequence controllers or logic controllers
- G05B19/048—Monitoring; Safety
Landscapes
- Physics & Mathematics (AREA)
- General Physics & Mathematics (AREA)
- Engineering & Computer Science (AREA)
- Automation & Control Theory (AREA)
- Alarm Systems (AREA)
Abstract
The invention discloses building site intelligent container comprehensive management platform, including infrastructure device, personnel channel, monitoring center, transmission control system, environment monitor and energy resource system;All electronic equipments, electrical equipment, mechanical equipment are all connect by wired or wireless network with monitoring center in project building site, the control and management at monitored center.The advantage of the invention is that realizing building site access control system, monitoring system, control system, network system, the mobile design of energy resource system, movement easy for installation is convenient, can be repeated as many times and use.
Description
Technical field
The invention belongs to construction site equipment technical field more particularly to building site intelligent container comprehensive management platforms.
Background technology
At present, the access control system in construction site and building site monitoring control system are all provided separately, and access control system is adopted
It is traditional building structure, often changing a building site will reconstruct, and carrying, access control equipment must be removed after the duration
It is often damaged or destroys during dismounting, economic loss can be caused in this way, it may be said that be to waste man power and money.Door
Access control system and building site monitoring control system are provided separately the United Dispatching management being unfavorable for building site, during assembling and disassembling
It will appear the problem of similar to access control system.
Invention content
The present invention in view of the above shortcomings of the prior art, has invented building site intelligent container comprehensive management platform.
To achieve these goals, the present invention adopts the following technical scheme that:
Building site intelligent container comprehensive management platform, including infrastructure device, personnel channel, monitoring center, transmission control system
System, environment monitor and energy resource system;The infrastructure device includes container, electrical house, electrical cabinet, heavy current cabinet and entrance guard
Room is provided with entrance guard room on the left of the container, personnel channel is provided on the right side of container, is set in the entrance guard room
Electrical house is equipped with, Electric Appliance Cabinet is laid in electrical house;Heavy current cabinet has been placed beside the Electric Appliance Cabinet;On the personnel channel
Escape truck and bridge-type tripod turnstile are provided with, face recognition device is provided on the bridge-type tripod turnstile and identity card is read
Device;The liquid for showing recognition of face information and identity information by personnel is hung on the left of the personnel channel on wall
Crystal display;The monitoring center includes operation host, background server, video server, monitoring display, monitoring camera
Head, bridge, Beidou positioning module, Big Dipper time service module and PLC control panels, operation host, background server and the video
Server is mounted in electrical cabinet, and the operation host is for the various informatization platform softwares needed for integrated project building site;
The background server is the main control part of intelligent container, carries out the control of internal unit;The video server carries
For h.256 supporting the network hard disk video recorder NVR of onvif agreements, extendible access site safety monitor video, and carried for building site
For real-time video monitoring;The position of the monitoring camera installation is building site doorway, the main thoroughfare in building site and operation and control
Platform;The monitoring display is electrically connected the monitoring environment for showing each place in building site with operation host;The net
Bridge communicates wirelessly passback by bridge mode for the region that cable wiring is not easy to video, control data;The north
Bucket locating module is used to detect the real-time condition of intelligent container circulation, transport;Time service module is by the satellite standard time, to behaviour
Hosted, background server, video server, monitoring camera first-class data equipment synchronization time is the available time of data
It provides safeguard;Operation host, video server, monitoring display, monitoring camera, Beidou positioning module and the Big Dipper is awarded
When module all with background server be electrically connected;The PLC control panels are to container alternating current, accumulator group, solar cell
The state of plate is monitored and alarm module is controlled to ensure that all types of monitoring warnings are conveyed in real time;The transmission control system packet
Core switch, router, high-power WIFI and LORA radio network gateways are included, the interchanger is used to be the net with covering building site
The electronic equipment of network connection provides multiple network interfaces;The router is using more WAN mouthfuls routings, it is ensured that in extreme circumstances
Communication it is smooth;The high-power WIFI is used to cover the signal of item area rank, and mobile monitoring device offer is connect
Enter signal service;The LORA radio network gateways move equipment for building site and carry out remote signal transmission;The environment monitor
It is electrically connected with background server, for monitoring building site government pollution emissions situation;The energy resource system includes solar-electricity
Pond plate, lightning rod, solar charging controller and accumulator group, the solar panel and lightning rod are mounted on container
Top on;The accumulator group provides power supply for whole electrical equipments in container and receives background server
Management;Solar charging controller, the solar charging controller and accumulator group are connected in the accumulator group
In heavy current cabinet.The present invention integrate gate inhibition, monitoring, control, network, the energy mobile building site intelligent management put down
Platform reduces the trouble of repetition construction, installs easy to connect, energy conservation and environmental protection.
Further, air-conditioning and LED screen are also equipped on the container, air-conditioning can be used for the temperature in regulating container
Degree and humidity, LED screen are used to publicize the real time information in building site.
Further, the operation host integrates building site required information platform software and builds cloud quotient platform, logistics for product
Platform, special equipment monitoring system, the monitoring of project security video, environment monitor, one kind in personnel's real-name management or more
Kind, the monitoring or test of corresponding informatization platform software can be checked and controlled on the monitoring display of operation host connection
Data integrate multiple functions.
Further, stereo set, talk back equipment, keyboard, alarm and hard disk are electrically connected on the operation host,
Can make operation host service function that must be more convenient by external input device more humane, alarm can monitoring numerical value be less than or
Supervisor is reminded during higher than what value, hard disk increases the memory space of monitoring data.
Further, the internal unit of background server control has energy resource system, UPS classifications electric power system, the Big Dipper
Position time dissemination system, LORA gateway systems, project wisdom building site platform data scratch system, transmission control system system and long-range
Control system plans as a whole control by background server and forms a complete entirety.
Further, it needs have tower crane or/building site edge zone by the region that bridge communicates wirelessly, makes in building site
Each place and mobile equipment or fixed equipment can even connect to the Net.
Further, the PLC control panels can be also used for the work of control air-conditioning and LED screen, realize automation.
Further, the monitoring camera includes infrared high-speed ball-forming machine and infrared gunlock.
Further, the router is divided into enterprise router and 4G wireless routers, and the enterprise router passes through
Access in radio and 4G wireless routers carry out network redundancy, and network safety prevention and division are realized by multi-stage router.
Further, router division has device network, office network, living network and monitoring network, network
Security level and protection level can be arranged as required to by being divided into four parts, while be mutually independent of each other will not for respective network
Cause congestion.
Further, the network signal of router access is telecommunication signal or/and movable signal, realizes that multi signal connects
It connects, it can be to avoid network interruption.
Further, the core switch is 24 mouthfuls of 6 core interchangers of gigabit, and the equipment for building site connects network and provides net
Network interface.
Further, the environment monitor includes environmental monitoring main control unit, PM2.5 sensors, PM1 sensors, makes an uproar
Sound sensor, air velocity transducer, Temperature Humidity Sensor and LED outdoor display screens, the PM2.5 sensors, PM1 sensors,
Sensor noise, air velocity transducer, Temperature Humidity Sensor and LED outdoor display screens and environmental monitoring main control unit are electrically connected.
Further, the energy resource system is configured with on-Line UPS system and power distribution control system, realization pair
Effective distribution of energy resource system electricity.
Further, the heavy current cabinet is provided with level-one input protection, improves safe class.
Further, the container under be provided with bottom girder frame, conveniently sling or transport container, keep away after mounting
Exempt from container and directly contacted with ground to slow down getting rusty for container and extend the service life of container.
The advantage of the invention is that:
1. realize building site access control system, monitoring system, control system, network system, the mobile design of energy resource system, installation
It is convenient to be moved easily, and can be repeated as many times and use;
2. the product on collection construction site builds cloud quotient system system, logistics system, special equipment monitoring system, project security video monitoring system
System, airborne dust noise monitoring system, personnel's real-name management system, power detection system, UPS classification electric power system, the Big Dipper Big Dipper
Positioning time dissemination system, LORA repeater systems, project wisdom building site platform data are kept in, network controls, tele-control system is equal to
One, which is realized, plans as a whole management and running.
Description of the drawings
Fig. 1 is the principle of the present invention frame diagram;
Fig. 2 is the stereogram of container in the present invention;
Fig. 3 is the vertical view of container in the present invention.
Specific embodiment
Below in conjunction with attached drawing, the present invention is described in detail:
In the description of the present invention, it should be noted that the orientation or position relationship of the instructions such as term " left side ", " right side "
For be based on orientation shown in the drawings or position relationship or the invention product using when the orientation usually put or position close
System is for only for ease of the description present invention and simplifies description rather than instruction or imply that signified device or element must have
Specific orientation, with specific azimuth configuration and operation, therefore be not considered as limiting the invention.
As shown in Figure 1, building site intelligent container comprehensive management platform, including infrastructure device, personnel channel, monitoring center,
Transmission control system, environment monitor and energy resource system;All electronic equipments, electrical equipment, machinery are set in project building site
It is standby all to be connect by wired or wireless network with monitoring center, the control and management at monitored center.
As shown in Figure 2 or Figure 3, the infrastructure device includes container 1, electrical house 2, electrical cabinet 3, heavy current cabinet 4, entrance guard
Room 5, air-conditioning and LED screen, the left side of the container 1 are provided with entrance guard room 5, and the right side of container 1 is provided with personnel channel;
Electrical house 2 and air-conditioning are provided in the entrance guard room 5, Electric Appliance Cabinet 3 is laid in electrical house 2, table is additionally provided in entrance guard room 5
Chair;Heavy current cabinet 4 is placed in 3 side of Electric Appliance Cabinet;LED screen for publicizing building site information is arranged on the front of container 1
Top;The monitored middle gains in depth of comprehension control of the air-conditioning and LED screen.
Escape truck 6 and the bridge-type tripod turnstile 7 of JX-T510 models, the bridge-type are provided on the personnel channel
Face recognition device 8, identity card reader 9, fingerprint identification device and ID identification equipments, the bridge are provided on tripod turnstile 7
A face recognition device 8 is each provided with before and after each channel of formula tripod turnstile 7.It is hanged on wall on the left of the personnel channel
It hangs with to show the liquid crystal display 10 by the recognition of face information of personnel and 42 cun of the Philip of identity information.
The monitoring center includes operation host, background server, video server, monitoring display, monitoring camera
Head, bridge, Beidou positioning module, Big Dipper time service module and PLC control panels, operation host, background server and the video
Server is mounted in electrical cabinet 3, and electrical cabinet plays the role of protecting lightning protection.The operation host is used for integrated project building site institute
The various informatization platform softwares needed, as product builds cloud quotient platform, logistics platform, special equipment monitoring system, project security video
Monitoring, environment monitor, personnel's real-name management platform etc., realize the unified management to multi-platform multisystem;In operation host
On be also associated with being conducive to facilitate control or operate to obtain stereo set, talk back equipment, keyboard, alarm and hard disk.The backstage
Server is the main control part of intelligent container, carries out the control of building site internal unit, such as to energy resource system, UPS classification power supplies
System, Big Dipper positioning time dissemination system, LORA gateway systems, project wisdom building site platform data scratch system, transmission control system
System and tele-control system.The video server provides the network hard disk video recorder NVR for h.256 supporting onvif agreements,
Extendible access site safety monitor video, and provide real-time video monitoring for building site;The position of the monitoring camera installation
Building site doorway, the main thoroughfare in building site and operating console are set to, the Haikang prestige that monitoring camera includes 200W regards infrared high-speed
Ball and Haikang prestige regard the 200/5000000 infrared gunlocks of starlight grade network H265;The monitoring display electrically connects with operation host
The monitoring environment for showing each place in building site is connect, monitoring display is mounted on the metope in entrance guard room 5 before tables and chairs;It is described
Bridge for the region that is not easy of cable wiring, passback is communicated wirelessly to video, control data by bridge mode, such as
The data information of tower crane or building site edge zone returns;The Beidou positioning module circulates for detecting intelligent container, fortune
Defeated real-time condition;Time service module takes the photograph operation host, background server, video server, monitoring by the satellite standard time
As first-class data equipment synchronization time, the available time for data provides safeguard;The operation host, video server,
Display, monitoring camera, Beidou positioning module and Big Dipper time service module is monitored all to be electrically connected with background server;Described
PLC control panels are monitored container alternating current, accumulator group, the state of solar panel and alarm module are controlled to ensure respectively
Type monitoring warning is conveyed in real time;PLC control panels are the control panel of included gateway external member and are electrically connected with operation host.
The core switch of the transmission control system including 24 mouthfuls of 6 core of gigabit of core, router, high-power WIFI and
LORA radio network gateways, the interchanger connect for providing multiple networks for the electronic equipment of the network connection with covering building site
Mouthful;The router is using more WAN mouthfuls routings, it is ensured that communication in extreme circumstances is smooth, and router is divided into enterprise's routing
Device and 4G wireless routers, the two carry out network redundancy, and network be divided into device network, office network, living network and
Network is monitored, forms network safety prevention;The high-power WIFI is used to cover the signal of item area rank, to movement
Monitoring device provides access signal service;The LORA radio network gateways move equipment for building site and carry out remote signal transmission.
More 433M exterior aerials and outdoor WIFI antennas are also associated on transmission control system.
The environment monitor using statutory regulation environment monitor, and with background server be electrically connected,
For monitoring building site government pollution emissions situation.The environment monitor includes environmental monitoring main control unit, PM2.5 is sensed
Device, PM1 sensors, sensor noise, air velocity transducer, Temperature Humidity Sensor and LED outdoor display screens, environmental monitoring master control list
Member has PM2.5 sensors, PM1 sensors, sensor noise, air velocity transducer, Temperature Humidity Sensor and LED outdoor display screens
Control and gathered data permission.
The energy resource system includes solar panel, lightning rod, solar charging controller, accumulator group, online
Formula uninterruptible power system and power distribution control system, the solar panel and lightning rod are mounted on the top of container 1,
Lightning rod is also mating to be connected with the general antenna lightning protection device of the east rising sun;The solar panel is connect with accumulator group;It is described
Accumulator group provide power supply for whole electrical equipments in container and receive the management of background server;Described
Solar charging controller, on-Line UPS system and power distribution control system are connected in accumulator group.It is described too
Positive energy charge controller and accumulator group are mounted in heavy current cabinet 4, and heavy current cabinet 4 is provided with level-one input protection.The sun
Can solar panel using A grade of 200W monocrystalline 24V solar panel, lightning rod be stainless steel lightning rod, accumulator group
Ferric phosphate lithium cell for 12V/100Ah.
Although specific embodiments of the present invention are described in detail and are illustrated above, it should be noted that
We can make various changes and modifications the embodiment above, but these spirit without departure from the present invention and appended power
The recorded range of profit requirement.
Claims (16)
1. building site intelligent container comprehensive management platform, which is characterized in that including infrastructure device, personnel channel, monitoring center, biography
Defeated control system, environment monitor and energy resource system;
The infrastructure device includes container (1), electrical house (2), electrical cabinet (3), heavy current cabinet (4) and entrance guard room (5), described
Container (1) on the left of be provided with entrance guard room (5), personnel channel, the entrance guard room are provided on the right side of container (1)
(5) electrical house (2) is provided in, Electric Appliance Cabinet (3) is laid in electrical house (2);Forceful electric power has been placed beside the Electric Appliance Cabinet (3)
Cabinet (4);
Escape truck (6) and bridge-type tripod turnstile (7) are provided on the personnel channel, is set on the bridge-type tripod turnstile (7)
It is equipped with face recognition device (8) and identity card reader (9);It is hung on wall on the left of the personnel channel logical for showing
Cross the recognition of face information of personnel and the liquid crystal display (10) of identity information;
The monitoring center includes operation host, background server, video server, monitoring display, monitoring camera, net
Bridge, Beidou positioning module, Big Dipper time service module and PLC control panels, operation host, background server and the video server
In electrical cabinet (3), the operation host is for the various informatization platform softwares needed for integrated project building site;It is described
Background server be intelligent container main control part, carry out the control of internal unit;The video server provides
H.256 the network hard disk video recorder NVR of onvif agreements, extendible access site safety monitor video are supported, and is provided for building site
Real-time video monitoring;The position of the monitoring camera installation is building site doorway, the main thoroughfare in building site and operating console;
The monitoring display is electrically connected the monitoring environment for showing each place in building site with operation host;The bridge pair
Passback is communicated wirelessly to video, control data by bridge mode in the region that cable wiring is not easy;The Big Dipper is determined
Position module is used to detect the real-time condition of intelligent container circulation, transport;Time service module leads operation by the satellite standard time
Machine, background server, video server, monitoring camera first-class data equipment synchronization time, the available time for data provide
It ensures;Operation host, video server, monitoring display, monitoring camera, Beidou positioning module and the Big Dipper time service mould
Block is all electrically connected with background server;The PLC control panels are to container alternating current, accumulator group, solar panel
State is monitored and alarm module is controlled to ensure that all types of monitoring warnings are conveyed in real time;
The transmission control system includes core switch, router, high-power WIFI and LORA radio network gateways, the friendship
It changes planes to provide multiple network interfaces for the electronic equipment of the network connection with covering building site;The router is using more
WAN mouthfuls of routings, it is ensured that communication in extreme circumstances is smooth;The high-power WIFI is used for the signal to item area rank
Covering provides mobile monitoring device access signal service;The LORA radio network gateways move equipment for building site and carry out remotely
Signal transmits;
The environment monitor is electrically connected with background server, for monitoring building site government pollution emissions situation;
The energy resource system include solar panel, lightning rod, solar charging controller and accumulator group, it is described too
Positive energy solar panel and lightning rod are mounted on the top of container (1);The accumulator group is the whole in container
Electrical equipment provides power supply and receives the management of background server;Solar charging electric control is connected in the accumulator group
Device, the solar charging controller and accumulator group are mounted in heavy current cabinet (4).
2. intelligent container comprehensive management platform in building site according to claim 1, which is characterized in that the container
(1) air-conditioning and LED screen are also equipped on.
3. intelligent container comprehensive management platform in building site according to claim 1, which is characterized in that the operation host
Integrated building site required information platform software builds cloud quotient platform, logistics platform, special equipment monitoring system, project safety for product
It is one or more in video monitoring, environment monitor, personnel's real-name management.
4. intelligent container comprehensive management platform in building site according to claim 1, which is characterized in that the operation host
On be electrically connected with stereo set, talk back equipment, keyboard, alarm and hard disk.
5. intelligent container comprehensive management platform in building site according to claim 1, which is characterized in that the background service
The internal unit of device control has energy resource system, UPS classifications electric power system, Big Dipper positioning time dissemination system, LORA gateway systems, project
Wisdom building site platform data scratch system, transmission control system system and tele-control system.
6. intelligent container comprehensive management platform in building site according to claim 1, which is characterized in that need by bridge into
There are tower crane or/building site edge zone in the region of row wireless telecommunications.
7. intelligent container comprehensive management platform in building site according to claim 2, which is characterized in that the PLC controls
Plate is used to control the work of air-conditioning and LED screen.
8. intelligent container comprehensive management platform in building site according to claim 1, which is characterized in that the monitoring camera
Head includes infrared high-speed ball-forming machine and infrared gunlock.
9. intelligent container comprehensive management platform in building site according to claim 1, which is characterized in that the router point
For enterprise router and 4G wireless routers, the enterprise router carries out network by access in radio and 4G wireless routers
Redundancy.
10. intelligent container comprehensive management platform in building site according to claim 9, which is characterized in that the router
Division has device network, office network, living network and monitoring network.
11. intelligent container comprehensive management platform in building site according to claim 10, which is characterized in that the router
The network signal of access is telecommunication signal or/and movable signal.
12. intelligent container comprehensive management platform in building site according to claim 1, which is characterized in that the core is handed over
It changes planes as 24 mouthfuls of 6 core interchangers of gigabit.
13. intelligent container comprehensive management platform in building site according to claim 1, which is characterized in that the environment prison
It surveys instrument and includes environmental monitoring main control unit, PM2.5 sensors, PM1 sensors, sensor noise, air velocity transducer, humiture biography
Sensor and LED outdoor display screens, the PM2.5 sensors, PM1 sensors, sensor noise, air velocity transducer, humiture
Sensor and LED outdoor display screens are electrically connected with environmental monitoring main control unit.
14. intelligent container comprehensive management platform in building site according to claim 1, which is characterized in that the energy system
It is under unified central planning to be equipped with on-Line UPS system and power distribution control system.
15. intelligent container comprehensive management platform in building site according to claim 1, which is characterized in that the heavy current cabinet
(4) it is provided with level-one input protection.
16. intelligent container comprehensive management platform in building site according to claim 1, which is characterized in that the container
(1) bottom girder frame is provided under.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810152532.5A CN108170079A (en) | 2018-02-16 | 2018-02-16 | Building site intelligent container comprehensive management platform |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810152532.5A CN108170079A (en) | 2018-02-16 | 2018-02-16 | Building site intelligent container comprehensive management platform |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108170079A true CN108170079A (en) | 2018-06-15 |
Family
ID=62510651
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810152532.5A Pending CN108170079A (en) | 2018-02-16 | 2018-02-16 | Building site intelligent container comprehensive management platform |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108170079A (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109035533A (en) * | 2018-08-31 | 2018-12-18 | 上海华工安全技术服务有限公司 | Container-type access control system |
CN110852909A (en) * | 2019-09-01 | 2020-02-28 | 成都建工第五建筑工程有限公司 | Building engineering information management system |
CN112187897A (en) * | 2020-09-18 | 2021-01-05 | 山西省工业设备安装集团有限公司 | Wisdom building site assembled management and control integrated device based on IOT and AI video fusion |
CN112698678A (en) * | 2020-12-29 | 2021-04-23 | 中建科技集团有限公司 | Monitoring system for building site |
CN115019430A (en) * | 2022-06-09 | 2022-09-06 | 江西大正智能信息技术有限公司 | Intelligent construction site management and control platform and monitoring method thereof |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105867321A (en) * | 2015-09-28 | 2016-08-17 | 山东电力工程咨询院有限公司 | Scene visualization intelligent construction site management system based three-dimensional model |
CN105974870A (en) * | 2016-06-30 | 2016-09-28 | 上海海事大学 | Wireless remote monitoring system and method for refrigerated container |
CN205809612U (en) * | 2016-06-13 | 2016-12-14 | 深圳中集智能科技有限公司 | The container monitoring communication equipment of redundancy mutually |
CN206034967U (en) * | 2016-08-30 | 2017-03-22 | 北京爱必优得科技发展有限公司 | Place function device integration's system of real name passageway container |
-
2018
- 2018-02-16 CN CN201810152532.5A patent/CN108170079A/en active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105867321A (en) * | 2015-09-28 | 2016-08-17 | 山东电力工程咨询院有限公司 | Scene visualization intelligent construction site management system based three-dimensional model |
CN205809612U (en) * | 2016-06-13 | 2016-12-14 | 深圳中集智能科技有限公司 | The container monitoring communication equipment of redundancy mutually |
CN105974870A (en) * | 2016-06-30 | 2016-09-28 | 上海海事大学 | Wireless remote monitoring system and method for refrigerated container |
CN206034967U (en) * | 2016-08-30 | 2017-03-22 | 北京爱必优得科技发展有限公司 | Place function device integration's system of real name passageway container |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109035533A (en) * | 2018-08-31 | 2018-12-18 | 上海华工安全技术服务有限公司 | Container-type access control system |
CN110852909A (en) * | 2019-09-01 | 2020-02-28 | 成都建工第五建筑工程有限公司 | Building engineering information management system |
CN112187897A (en) * | 2020-09-18 | 2021-01-05 | 山西省工业设备安装集团有限公司 | Wisdom building site assembled management and control integrated device based on IOT and AI video fusion |
CN112698678A (en) * | 2020-12-29 | 2021-04-23 | 中建科技集团有限公司 | Monitoring system for building site |
CN115019430A (en) * | 2022-06-09 | 2022-09-06 | 江西大正智能信息技术有限公司 | Intelligent construction site management and control platform and monitoring method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108170079A (en) | Building site intelligent container comprehensive management platform | |
CN104052151B (en) | Intelligent substation aided synthesis is monitored and D5000 cooler interlock platforms | |
CN110707810B (en) | Auxiliary comprehensive monitoring system for transformer substation | |
CN204925783U (en) | Indoor long -range fortune dimension information system that patrols and examines of control protection of transformer substation | |
CN105867321B (en) | The visual wisdom chemical industry ground management system of outdoor scene based on threedimensional model | |
CN206132978U (en) | Office building personnel positioning system based on bluetooth | |
CN107544326A (en) | Ensure the multifunction monitoring system of construction site security | |
CN205892393U (en) | Closed monitored control system of construction elevator guard gate | |
CN202513670U (en) | Auxiliary control system of intelligent transformer substation | |
CN107991999A (en) | Power cable tunnel comprehensive monitoring system and method | |
CN107333113A (en) | A kind of pipe gallery wireless supervisory control system | |
CN110158648A (en) | A kind of Urban Underground pipe gallery O&M monitoring management system | |
CN107659645A (en) | A kind of integrated intelligence community system based on Internet of Things | |
CN206992800U (en) | A kind of monitoring system of the intelligent substation of Internet of Things | |
CN210536814U (en) | Unified supervision platform for fire-fighting internet of things | |
CN211908986U (en) | Intelligent operation and maintenance early warning management platform for high-speed electromechanical system | |
CN110798344A (en) | Intelligent power distribution operation and maintenance system | |
CN103576650A (en) | Operation security monitoring and managing system for airport ground equipment | |
CN110674957A (en) | Intelligent charging management system and method | |
CN107947362A (en) | Electric railway traction supply intelligent auxiliary system | |
CN102566519A (en) | Setting method for power tunnel monitoring system | |
CN207511622U (en) | A kind of elevator monitoring system based on Internet of Things and cloud service | |
CN208820537U (en) | A kind of box-type substation integrated information monitoring system based on Internet of Things | |
CN107193244A (en) | A kind of communication comprehensive monitoring system | |
CN108596811A (en) | A kind of intelligent micro fire-fighting station administration system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20180615 |