CN105867321A - Scene visualization intelligent construction site management system based three-dimensional model - Google Patents

Scene visualization intelligent construction site management system based three-dimensional model Download PDF

Info

Publication number
CN105867321A
CN105867321A CN201610173074.4A CN201610173074A CN105867321A CN 105867321 A CN105867321 A CN 105867321A CN 201610173074 A CN201610173074 A CN 201610173074A CN 105867321 A CN105867321 A CN 105867321A
Authority
CN
China
Prior art keywords
building site
management
information
data
site
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610173074.4A
Other languages
Chinese (zh)
Other versions
CN105867321B (en
Inventor
王琳
王作峰
张启锡
宫俊亭
张鲁鹰
董长竹
潘清波
孙晓峰
张宝
樊俊怀
陈文刚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong Electric Power Engineering Consulting Institute Corp Ltd
Original Assignee
Shandong Electric Power Engineering Consulting Institute Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong Electric Power Engineering Consulting Institute Corp Ltd filed Critical Shandong Electric Power Engineering Consulting Institute Corp Ltd
Publication of CN105867321A publication Critical patent/CN105867321A/en
Application granted granted Critical
Publication of CN105867321B publication Critical patent/CN105867321B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G05CONTROLLING; REGULATING
    • G05BCONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
    • G05B19/00Programme-control systems
    • G05B19/02Programme-control systems electric
    • G05B19/418Total factory control, i.e. centrally controlling a plurality of machines, e.g. direct or distributed numerical control [DNC], flexible manufacturing systems [FMS], integrated manufacturing systems [IMS], computer integrated manufacturing [CIM]
    • G05B19/41865Total factory control, i.e. centrally controlling a plurality of machines, e.g. direct or distributed numerical control [DNC], flexible manufacturing systems [FMS], integrated manufacturing systems [IMS], computer integrated manufacturing [CIM] characterised by job scheduling, process planning, material flow
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction
    • GPHYSICS
    • G05CONTROLLING; REGULATING
    • G05BCONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
    • G05B2219/00Program-control systems
    • G05B2219/30Nc systems
    • G05B2219/31From computer integrated manufacturing till monitoring
    • G05B2219/31457Factory remote control, monitoring through internet

Abstract

The invention discloses a scene visualization intelligent construction site management system based a three-dimensional model, and the system obtains the data of a person and a vehicle according to the card swiping information of an access control system, and obtains the scanning data of a corresponding fixed person and set mechanical equipment through scanning a bar code. A plurality of cameras disposed on a construction site are used for obtaining the real-time video monitoring data of the construction side. An environment monitoring device disposed on the construction site is used for obtaining the corresponding environment data. An information real-time broadcasting system enables the obtained public broadcast data to be transmitted to an information broadcast database. Based on the technology of intelligent construction site management, the visualized scene of the system is displayed and integrated on the basis of the three-dimensional model, and the display, analysis, processing and analysis of the obtained data of the system are carried out. Meanwhile, the system is integrated with the existing project management system and database, thereby achieving the decision support for project management, the bias early warning for a project, and the feedback of project experience and information.

Description

Outdoor scene based on threedimensional model visual wisdom building site management system
Technical field
The present invention relates to intelligent field, building site, be specifically related to outdoor scene based on threedimensional model visual wisdom building site management system System.
Background technology
Mostly traditional construction management information system is the needs according to project management, the project management flow process of the online circulation of exploitation and table Single, it is impossible to automatically, Real-time Collection or from system directly, automatically extract Various types of data that job site produces and data carried out Working process, is provided without threedimensional model and outdoor scene visualization technique, is also not integrated on unified information platform, it is impossible to for engineering Personnel provide effective decision support.
In existing patent, application number: 201220675601.9, apply for entitled: wisdom building site management system, specifically disclose : include digital camera, gps satellite locator, weighbridge meter, IR intrusion detector, card system, tower crane CAS, environmental protection dust investigating, all kinds of building machinery accident warning device, automobile unmanned device, automobile Tyre cleaning machine, above-mentioned parts are connected to signal and launch WAP, and described signal is launched WAP and passed through nothing Line transmission is connected to signal and receives WAP, and described signal receives WAP and is connected to wireless exchange board, described nothing Connect on line switch and have described storage server, Surveillance center, video server, wisdom fielded system server and data Center.Said system does not has outdoor scene visual presentation based on threedimensional model, and operating personnel can not be comprehensive when monitoring Understand on-the-spot Practical Project progress, the data obtained are not analyzed and profound application, intelligent not.
Application number: 201310324645.6, applies for entitled: a kind of building site digital management system and application process thereof, specifically Disclose: described management system includes five big subsystems: personnel location system, gate control system, material Management System, shield System is followed the tracks of in structure operating system and section of jurisdiction, and each described subsystem is all set up with remote database server and is connected, at remotely number According to having the five big subdata bases corresponding with five big subsystems in the server of storehouse, each described subsystem utilizes RFID less radio-frequency Technology the main management object in site boundary is written and read operation, and read data are gone up in real time incoming corresponding each greatly In subdata base, verified by the data cross between each big subdata base, to obtain the operating rights of handheld RFID read head Limit and the operating right of shield machine.It is an advantage of the invention that improvement current traditional extensive property management, specify management responsibility, carry High-level management, it is achieved engineering information management, digital management, visualized management.Above-mentioned patent disclosure of that is also It is not based on the outdoor scene visual presentation of threedimensional model, acquisition data is not analyzed and profound application, intelligent not.
In a word, prior art cannot meet current demand, it is impossible to realize on threedimensional model intuitively engineering based on outdoor scene prison Control, is mainly manifested in following several aspect:
1. it is not provided with three-dimensional display system, not according to the threedimensional model that building site project build is corresponding, people's car is not managed system, work Ground video monitoring system, environmental data collecting and application system and information real-time broadcasting system are distinguished the data acquisition unit of correspondence Carry out outdoor scene deployment in the three-dimensional model and represent, not outdoor scene exhibition by the way of wisdom building site three-dimensional display system is with 3-D view Show the real time data of building-site, the various application of non-integrated project management, unrealized realize item with project threedimensional model for core Mesh manages the mutual of multiple data and application, the intellectuality of unrealized project management, wisdom.
2. gate control system gets personnel, the statistics of the unrealized data of information of vehicles, analysis and the degree of depth are excavated and application, not Data-interface is provided to other functional modules.
3. building site video monitoring is not integrated on project threedimensional model, and the position that video frequency pick-up head is arranged does not standardizes yet.
4. be not provided with site environment data acquisition unit, the most not in the way of 3-D view outdoor scene show harvester position is set, The data intervals such as the related data obtained is not provided with normally, pays close attention to, warning, alarm free or the hand of warning during the superscalar data of collection Section is the most single.
The information at the most unrealized scene is reported immediately, and unrealized every day, self-timing was reported and lower immediately the reporting that be in an emergency, The emergent report not triggered by phone realizes on-the-spot emergency command, fails report content is carried out automatic record.
The project datas such as the most unrealized technological document, management file associate with physical model, it is impossible to real time inspection model is correlated with Technology, management file.
7. be not provided with being exclusively used in the on-the-spot safety of project, Quality training examination system, safety, Quality training examination system the most not with The systems such as people's car management carry out data interaction, association with interactive.
Summary of the invention
For solving the deficiency that prior art exists, manage with the invention discloses the visual wisdom chemical industry of outdoor scene based on threedimensional model Reason system, the present invention is regarded by the exhibition of visual outdoor scene on the basis of threedimensional model, it is achieved integrated, process and issue all kinds of work Number of passes evidence, it is achieved the intelligentized management functions such as project management decision support, project implementation deviation pre-alert, project experiences information feedback.
For achieving the above object, the concrete scheme of the present invention is as follows:
Outdoor scene based on threedimensional model visual wisdom building site management system, including:
People's car management system, the entrance guard device arranged according to building-site, swiped the card acquisition personnel and vehicle by all-purpose card technology Information data, obtains corresponding fixed personnel and the information data of specific plant equipment by scan stripes shape code;The information obtained Data are all analyzed by wisdom building site three-dimensional display system, are shown;
Building site video monitoring system, obtains the real-time video monitoring number of building-site by being arranged on multiple video cameras of building-site According to, video monitoring data is shown by wisdom building site three-dimensional display system and multiple terminal;
Environmental data collecting and application system, obtain corresponding environmental data also by the environment monitoring device being arranged on building-site Environmental data is shown by wisdom building site three-dimensional display system in real time;
Information real-time broadcasting system, the information that the public broadcasting data of acquisition is sent to is reported database and passes through wisdom in real time Building site three-dimensional display system is reported;
Field network hardware facility automated intelligent cruising inspection system, will take the photograph in building site video monitoring system, people's car management system accordingly As fault message automatically can be distributed to corresponding operation maintenance personnel by head, people track lock when breaking down;
Wisdom building site three-dimensional display system, according to the threedimensional model that building site project build is corresponding, regards people's car management system, building site Frequently monitoring system, environmental data collecting and application system and information real-time broadcasting system are distinguished the device of correspondence in the three-dimensional model Carry out outdoor scene mark, to visualize the real time data of outdoor scene displaying building-site.
Described intelligent building site management system supports mobile office, can carry out answering by terminal, mobile phone, PAD kinds of platform With, and realize the issue of overall strange land by cloud distribution technology.
Described people's car management system includes that at least one is arranged on the gate control system at scene, and gate control system is right by card according to card using information People's car management database that the personnel answered and information of vehicles transmit to all-purpose card server, being consolidated corresponding by scan stripes shape code People's car management database that the plant equipment information of fix the number of workers and setting is transmitted to all-purpose card server.
The described gate control system being arranged on scene includes being arranged on the turnover field gate control system of on-the-spot gateway and being arranged on important area Zonule gate control system.The zonule gate control system of important area is provided in some because of requirement need such as safety, environment, constructions The region of personnel to be limited turnover.
Described building site video monitoring system includes the multiple video cameras being arranged on building-site, and described video camera is arranged on by The Cloud Terrace The ad-hoc location of job site, video camera is used for monitoring the monitored object that can cover in real time and real-time monitor video data being uploaded To wisdom building site three-dimensional display system.
Described environmental data collecting and application system include the environment monitoring device being arranged on warehouse district and are arranged on the gas of building-site As monitoring device, be arranged on Temperature Humidity Sensor that the environment monitoring device of warehouse district includes being connected with environmental monitoring main frame respectively, Smog alarm sensor, naked light detection sensor and water sensor, the weather monitoring device being arranged on building-site includes and gas Temperature sensor, sensor noise and the wind direction and wind velocity sensor being respectively connected with as monitoring main frame, environmental monitoring main frame and meteorological prison Surveying main frame and respectively the data of monitoring are sent to databank for environmental monitoring in real time, the data of databank for environmental monitoring are by wisdom building site collection One-tenth system processes, and informs related management personnel in time when exceeding setting threshold value by the way of note and mail.
Described information real-time broadcasting system includes public broadcast host, and public broadcast host is connected with phone incoming call answering machine, public Phone call-in message corresponding for phone incoming call answering machine and public broadcasting data are uploaded to information and report database, factory by broadcast host According to general layout, sound column is set at ad-hoc location, sound column is connected with public broadcast host, and information real-time broadcasting system is used for Realize timing report, real-time broadcast, emergent prompting and report.
Described field network hardware facility automated intelligent cruising inspection system includes intelligent patrol detection server, in the video monitoring system of building site Camera hardware, the people track lock in people's car management system is monitored, and above-mentioned camera hardware and people track lock break down Time can notify corresponding operation maintenance personnel in time by note, and remind accordingly in the three-dimensional display system of wisdom building site.
Further, above-mentioned outdoor scene based on threedimensional model visual wisdom building site management system also includes safe mass training Examination system, tower crane safety monitoring system, Engineering Documents Management Systems and management file management system.
Described safe mass training examination system includes the examination system main frame being arranged in Classroom, is arranged on Office Area meeting room Machine of registering, meeting attendance check brushing card data is sent to examination system main frame, includes safe matter in examination system main frame by machine of registering Amount database and training examination data storehouse, the performance information of the examination personnel of examination system main frame collection is uploaded to the management of people's car is The all-purpose card server of system, links the information of the performance information of examination personnel with people's car management system, the one-tenth of examination personnel Invalid then will be unable to is carried out job site less than card corresponding to personnel setting threshold value by achievement information.
Described technological document and management file management system include Engineering Documents Management Systems and management file management system, technology literary composition Part management system is connect by management class document with literary composition control communication, management file management system by technology class document interface Mouth and literary composition control communication, use the information correlation method towards 3D solid object, in civilian keyholed back plate reason system and wisdom work Ground three-dimensional display portal entity object realizes Attribute Association, it is achieved having access to of various management under 3-D view and technical documentation.
Described tower crane safety monitoring system includes that multiple beacon, each beacon are provided with the tower crane minor exchange of correspondence, and tower crane is divided Switch is connected with corresponding video camera and beacon wireless bridge respectively, by the existing real-time monitoring to tower crane state of video camera.
The present invention is by carrying out integrated to said system, it is possible to synthesis display also processes relevant data and information, it is possible at hand The different terminals such as machine, PAD, notebook computer operate, the reserved interface with PMIS, for improving further With lifting slot milling.
Beneficial effects of the present invention:
The present invention is integrated on unified three-dimensional model information platform, process and issue all kinds of project management data, according to item The needs of mesh management, integrated, to process and issue data mode is optional.Project management needed for utilizing all kinds of terminal device to obtain Information and date, transfers required Project Management Data by native system at any time, everywhere at engineering site, improves project management Intelligent level.Based on this wisdom chemical industry ground administrative skill, can develop with integrated diversified engineering data management subsystem also Constantly extension, simultaneously with existing PMIS and geo-database integration, it is achieved project management decision support, project are in fact Execute the intelligentized management function such as deviation pre-alert, project experiences information feedback.
Accompanying drawing explanation
Fig. 1 embodiments of the invention hardware structure figure;
Fig. 2 embodiments of the invention core switch region hardware structure figure;
Fig. 3 embodiments of the invention subfunction Organization Chart.
Detailed description of the invention:
The present invention is described in detail below in conjunction with the accompanying drawings:
Wisdom building site three-dimensional display system: the three-dimensional entity model of construction project, manages system, building site video monitoring system by people's car System, safe mass training examination system, environmental data collecting and application system, information real-time broadcasting system and technical file management The management systems such as system, management file management system carry out integrated in the three-dimensional model, it is possible to realized the intelligence in building site by this system Energyization, wisdomization manage, and outdoor scene shows the real-time management information and date of building-site in the way of 3-D view.
People's car management system: obtain personnel and the turnover field information of vehicle according to the card using information of gate control system, and to acquired Information carries out collecting, processing, and shows that the data of acquisition, to meet project management demand, are sent out by acquired data in many ways Carry out market demand to sundry item management information system, and obtain the data of sundry item management information with to people, the turnover of car License etc. is managed;Site construction management and operating personnel, main mechanical is obtained by building-site scan stripes shape code Relevant information is also managed;
Building site video monitoring system: to comprehensively show that what power construction engineering progress needed to arrange camera position is standardized, The real-time video monitoring data of building-site are obtained by these video cameras, and by video monitoring data by the three-dimensional exhibition of wisdom building site Show that system carries out outdoor scene displaying;
Safe mass training examination system: the safety of construction project level and Quality training and examination system, the project personnel that take part in building are permissible Participate in the management needed for post and professional training by this system, and participate in relevant examination to determine the management possessing be engaged in post Skill set requirements, and decide whether to allow related personnel to be engaged in relevant work on-site depending on appraisal result.
Environmental data collecting and application system: obtain corresponding environmental data by the environment monitoring device being arranged on building-site, And environmental data is shown by wisdom building site three-dimensional display system in real time, arrange data normal, note and warn three kinds Interval, requires to arrange each interval numerical value of various environmental data according to building site project management, when data reach to warn interval, passes through The modes such as data interface, SMS, sound and light alarm are reported to the police;
Information real-time broadcasting system: be integrated into wisdom building site three-dimensional display by being arranged on building-site, networking broadcasting system System, it is achieved every day, weather forecast, safe mass information etc. were reported in timing, and when project is in an emergency, passed through mobile phone Realize reporting notice, it is achieved emergent real-time broadcasting;Technology, management file management system: by technology, the pipe of project management formation Reason file is associated with the realistic model in threedimensional model, can by the corresponding threedimensional model of click check relevant technology, Management file.
Wisdom building site three-dimensional display system also communicates with cloud delivery system, by cloud delivery system by wisdom building site three-dimensional display system Information carry out cloud issue.
As shown in Figure 1-2, people's car management system includes the first Layer 2 switch being arranged at gate sentry, and the first Layer 2 switch is respectively With gate sentry video camera, gate sentry wireless bridge, gate sentry wireless aps, gate sentry cart banister, the outlet of gate sentry dolly banister, gate sentry dolly Banister entrance, gate sentry triroller gate, Bailey bridge video camera and user client communication, client respectively with LED display and managing caller System communicates.
People's car management system also includes the second Layer 2 switch of being arranged at another gate sentry, the second Layer 2 switch respectively with dolly The outlet of banister entrance, dolly banister, pendulum lock, gate sentry minor exchange, client and the first video camera communication, described gate sentry divides friendship Change planes respectively with cart banister and the second video camera communication, client respectively with LED display and visitor management system communication.
Environmental data collecting and application system include warehouse district minor exchange, described warehouse district minor exchange respectively with warehouse district hard disk Video recorder, the first warehouse district big warehouse video camera and constant-temperature and constant humidity store minor exchange communication, constant-temperature and constant humidity store minor exchange respectively with Environmental monitoring main frame, constant-temperature and constant humidity store video camera, the second warehouse district big warehouse video camera, special material storehouse video camera, warehouse district Front door video camera is connected, and described environmental monitoring main frame passes with Temperature Humidity Sensor, smog alarm sensor, naked light detection respectively Sensor, water sensor are connected.
Building site video monitoring system includes circulating pump room beacon minor exchange, described circulating pump room beacon minor exchange respectively with Circulating pump room beacon wireless bridge, circulating pump room video camera and wireless bridge communication, wireless bridge, zonule gate inhibition is wireless Bridge, zonule gate inhibition's minor exchange, wireless aps are sequentially connected with communication, described zonule gate inhibition's minor exchange also with water circulating pump Room triroller gate is connected.
Building site video monitoring system also includes beacon Layer 2 switch, described beacon Layer 2 switch respectively with beacon wireless aps, set Put video camera, beacon outdoor water-proof sound column and the first beacon wireless bridge at main building southeast corner to be connected, the first beacon wireless network The second beacon wireless bridge that bridge is corresponding with another one beacon is connected, and the second beacon wireless bridge is connected with beacon minor exchange, Beacon minor exchange respectively with corresponding beacon outdoor water-proof sound column and be arranged on the video camera at boiler room be connected.
It is arranged on the first Layer 2 switch at gate sentry, is arranged on the second Layer 2 switch at another gate sentry and beacon Layer2 switching Machine all with wisdom chemical industry ground host exchange be connected, wisdom chemical industry ground host exchange the most respectively with first outdoor transmitting antenna, the second Room Emission antenna, the first wireless aps, the second wireless aps, wireless bridge, be arranged on maintenance the minor exchange of roof, all-purpose card clothes Business device, Environment Monitoring Service device, monitoring DVR public broadcast host electric arc incoming call answering machine are connected.
Be arranged on the minor exchange of maintenance roof respectively with weather monitoring main frame, be arranged on the video camera at a tube hub, be arranged on Waterproof sound column at tube hub is connected, described weather monitoring main frame respectively with Temperature Humidity Sensor, sensor noise, wind direction wind Speed sensor is connected.
Second exterior aerial is connected with administration quarter wireless bridge, and administration quarter wireless bridge, administration quarter minor exchange, administration quarter image Machine is sequentially connected, and administration quarter minor exchange is also connected with administration quarter triroller gate.
The wireless bridge being connected with wisdom chemical industry ground host exchange is connected with boiler tower crane wireless bridge, and boiler tower crane wireless bridge depends on Secondary being connected with boiler tower crane minor exchange, the boiler tower crane minor exchange video camera that takes a crane shot with multiple boiler rooms respectively is connected.
First exterior aerial respectively with corresponding multiple beacon wireless bridges be connected, each beacon wireless bridge all with corresponding beacon Minor exchange is connected, and each beacon minor exchange is all connected with corresponding video camera.
Wisdom chemical industry ground host exchange is connected with core switch, core switch respectively with and be connected two layers of examination system main frame Switch, Meeting Signature machine, wisdom chemical industry ground router, construction management information system/intelligent inspection system server, EDOC Server, portal site server, CTBS server, desktop cloud system Platform Server, tower crane monitoring server, always monitor Center is connected, and wisdom chemical industry ground router is connected with the client of our department.
As it is shown on figure 3, people's car management system, setup of entrances and exits turnover field gate inhibition, important area set zonule gate control system at the scene, Realize monitoring in real time, it is achieved to turnover Field Force and the management of vehicle, add up and show;
Utilize all-purpose card technology, set turnover field gate inhibition and important area gate inhibition, human and vehicle shunting at project scene, it is achieved people, Che Shi Time monitoring, statistics.
Functional realiey: add up on a time period, situation marched into the arena by analysis personnel, vehicle;Enter by unit statistics, analysis personnel, vehicle Field situation;March into the arena situation by work post statistics, analysis personnel, vehicle;March into the arena feelings by gated area statistics, analysis personnel, vehicle Condition;Integrated condition statistics, analysis personnel, vehicle are marched into the arena situation;Graphically (block diagram, cake chart) analyzes personnel, vehicle March into the arena situation;In detail personnel, vehicle is marched into the arena the retrieval of information and query function.
Building site video monitoring system: arrange multiple video camera according to general layout at ad-hoc location in factory, can monitor project in real time Progress, arranges orientation shooting video camera, boiler and structure of main power house is carried out sequence photography;
Our department of enterprise, project management department all comprehensive, multi-angle can monitor development of projects in real time.Integration exhibition live video monitoring information.
Functional realiey: the monitoring device of position is specified in link, checks on-the-spot real-time pictures;Monitoring device is manipulated by Permission Levels; History monitor video is play online;Integrated with what three-dimensional door was shown.
Environmental data collecting and application system: site setup environment detector, provide in real time temperature, humidity, wind direction, wind speed, The environmental informations such as noise, and stopping construction, warning attention and the interval of normal construction are set;Warehouse district arranges constant-temperature and constant humidity store Temperature and humidity measure, arranges cigarette leaching, water logging, the warning of naked light;
Realize detection site environment data in real time, provide foundation for safely cleaning construction.Integrated building site environmental monitoring data and storage Environmental monitoring data, for important indexs such as temperature, humidity, wind speed, noises, by building-site operator on duty supervision and System detects a series of environmental monitoring system organic combinations such as prompting, alarm automatically, for great alarm can by note and The mode of mail informs related management personnel in time.
Functional realiey: real time temperature, humidity, wind speed, wind direction, noise are shown and early warning;Historical temperature, humidity, wind speed, The inquiry of wind direction, noise, analysis;Realize instrument board display real-time condition;Realize tracing analysis historical data;Relevant in conjunction with country Construction reference and field management, unify Real-time Alarm by three-dimensional display door.
Information real-time broadcasting system: arrange sound column according to general layout at ad-hoc location in factory, builds broadcast system, it is achieved fixed Time report, real-time broadcast, emergent remind and report function;
Realize timing and emergent report, the building site whole audience is issued project information immediately.Independence maintenance broadcast message or real-time exhibition are public Information in broadcast system altogether.Functional realiey: broadcast message represented, play the same day;Historical broadcasts information represents, plays.
Field network hardware facility automated intelligent cruising inspection system: on-the-spot machine room arranges intelligent patrol detection server, to building site video monitoring Camera hardware in system, the people track lock in people's car management system is monitored, and can pass through during above-mentioned hardware generation problem Note notifies corresponding operation maintenance personnel in time, and reminds accordingly in the three-dimensional display system of wisdom building site.
Safe mass training examination system: building-site arranges special safe mass propaganda division, gives safe mass training, And by this system, safety, Quality training effect are estimated;
Realize safe mass online training, examination and training evaluation, examine online according to the safety of site operation personnel simultaneously Examination achievement result, can realize and the linkage of people's car management system, take an examination underproof personnel and vehicle to be prohibited from entering project on-the-spot.
Safe mass training examination system: building-site arranges special safe mass propaganda division, gives safe mass training, And by this system, safety, Quality training effect are estimated;
Office Area meeting room arranges machine of registering, by the data interaction with construction management information system, it is achieved automatically sign by checking card To and go out attendance sheet, it is achieved the management to meeting room;Build the video conferencing system of Intranet special line, be designed by this system Tell somebody what one's real intentions are and drawing joint examination, build mobile video session system as interior lines video conferencing system supplement, it is achieved mobile terminal mobile phone or PAD video conference function;
Realize safe mass online training, examination and training evaluation, examine online according to the safety of site operation personnel simultaneously Examination achievement result, can realize and the linkage of people's car management system, take an examination underproof personnel and vehicle to be prohibited from entering project on-the-spot.
Tower crane safety monitoring system: by tower crane is run the integrated of relevant parameter, it is achieved the real-time monitoring to tower crane state, keeps away Exempt from the security incident caused because of the carelessness of operator or error in judgement, it is ensured that the safe handling of tower crane.
Wisdom building site three-dimensional display system: the unification realizing each systemic-function represents, the unified management of privilege matrix and respectively apply system The unified single-sign-on management of system, can show each application system by the way of 3-D view simultaneously, uses three dimensional object association Mode realize the inquiry of three-dimensional document associations.
Functional realiey: decision-making management center: report form statistics, comprehensive inquiry and managing alarm information;Control of authority center: unified User right matrix management, each system single-sign-on manages;Three-dimensional display center: platform unification is shown, visual information is mutual, Three dimensional object information is checked.
Although the detailed description of the invention of the present invention is described by the above-mentioned accompanying drawing that combines, but not limit to scope System, one of ordinary skill in the art should be understood that on the basis of technical scheme, and those skilled in the art need not pay Go out various amendments or deformation that creative work can make still within protection scope of the present invention.

Claims (10)

1. outdoor scene based on threedimensional model visual wisdom building site management system, is characterized in that, including:
People's car management system, the entrance guard device arranged according to building-site, swiped the card acquisition personnel and vehicle by all-purpose card technology Information data, obtains corresponding fixed personnel and the information data of specific plant equipment by scan stripes shape code;The information obtained Data are all analyzed by wisdom building site three-dimensional display system, are shown;
Building site video monitoring system, obtains the real-time video monitoring number of building-site by being arranged on multiple video cameras of building-site According to, video monitoring data is shown by wisdom building site three-dimensional display system and multiple terminal;
Environmental data collecting and application system, obtain corresponding environmental data also by the environment monitoring device being arranged on building-site Environmental data is shown by wisdom building site three-dimensional display system in real time;
Information real-time broadcasting system, the information that the public broadcasting data of acquisition is sent to is reported database and passes through wisdom in real time Building site three-dimensional display system is reported;
Field network hardware facility automated intelligent cruising inspection system, will take the photograph in building site video monitoring system, people's car management system accordingly As fault message automatically can be distributed to corresponding operation maintenance personnel by head, people track lock when breaking down;
Wisdom building site three-dimensional display system, according to the threedimensional model that building site project build is corresponding, regards people's car management system, building site Frequently monitoring system, environmental data collecting and application system and information real-time broadcasting system are distinguished the device of correspondence in the three-dimensional model Carry out outdoor scene mark, to visualize the real time data of outdoor scene displaying building-site.
2. outdoor scene based on threedimensional model visual wisdom building site management system as claimed in claim 1, is characterized in that, Described intelligent building site management system supports mobile office, can be applied by terminal, mobile phone, PAD kinds of platform, And realize the issue of overall strange land by cloud distribution technology.
3. outdoor scene based on threedimensional model visual wisdom building site management system as claimed in claim 1, is characterized in that, Described people's car management system include at least one be arranged on scene gate control system, gate control system according to card using information by card correspondence People's car management database that personnel and information of vehicles transmit to all-purpose card server, by scan stripes shape code by corresponding fixing people People's car management database that member and the plant equipment information set are transmitted to all-purpose card server.
4. outdoor scene based on threedimensional model visual wisdom building site management system as claimed in claim 3, is characterized in that, The described gate control system being arranged on scene includes being arranged on the turnover field gate control system of on-the-spot gateway and being arranged on the little of important area Region gate control system.The zonule gate control system of important area is provided in some and requires to need limit because of safety, environment, construction etc. The region of personnel processed turnover.
5. outdoor scene based on threedimensional model visual wisdom building site management system as claimed in claim 1, is characterized in that, Described building site video monitoring system includes the multiple video cameras being arranged on building-site, and described video camera is arranged on construction by The Cloud Terrace On-the-spot ad-hoc location, video camera is used for monitoring the monitored object that can cover in real time and real-time monitor video data being uploaded to intelligence Intelligent building site three-dimensional display system.
6. outdoor scene based on threedimensional model visual wisdom building site management system as claimed in claim 1, is characterized in that, Described environmental data collecting and application system include the environment monitoring device being arranged on warehouse district and are arranged on the meteorological prison of building-site Survey device, be arranged on Temperature Humidity Sensor, smog that the environment monitoring device of warehouse district includes being connected with environmental monitoring main frame respectively Alarm sensor, naked light detection sensor and water sensor, the weather monitoring device being arranged on building-site includes and meteorological prison Survey temperature sensor, sensor noise and wind direction and wind velocity sensor that main frame is respectively connected with, environmental monitoring main frame and weather monitoring master The data of monitoring are sent to databank for environmental monitoring by machine respectively in real time, and the data of databank for environmental monitoring are by the integrated system in wisdom building site System processes, and informs related management personnel in time when exceeding setting threshold value by the way of note and mail.
7. outdoor scene based on threedimensional model visual wisdom building site management system as claimed in claim 1, is characterized in that, Described information real-time broadcasting system includes that public broadcast host, public broadcast host are connected with phone incoming call answering machine, public broadcasting Phone call-in message corresponding for phone incoming call answering machine and public broadcasting data are uploaded to information and report database by main frame, press in factory Arranging sound column according to general layout at ad-hoc location, sound column is connected with public broadcast host, and information real-time broadcasting system is used for realizing Timing report, real-time broadcast, emergent prompting and report.
8. outdoor scene based on threedimensional model visual wisdom building site management system as claimed in claim 1, is characterized in that, Described field network hardware facility automated intelligent cruising inspection system includes intelligent patrol detection server, to taking the photograph in the video monitoring system of building site As head hardware, the people track lock in people's car management system is monitored, energy when above-mentioned camera hardware and people track lock break down Enough notified corresponding operation maintenance personnel by note in time, and remind accordingly in the three-dimensional display system of wisdom building site.
9. outdoor scene based on threedimensional model visual wisdom building site management system as claimed in claim 1, is characterized in that, Above-mentioned outdoor scene based on threedimensional model visual wisdom building site management system also includes safe mass training examination system, tower crane Safety monitoring system, Engineering Documents Management Systems and management file management system;
Described safe mass training examination system includes the examination system main frame being arranged in Classroom, is arranged on Office Area meeting room Machine of registering, meeting attendance check brushing card data is sent to examination system main frame, includes safe matter in examination system main frame by machine of registering Amount database and training examination data storehouse, the performance information of the examination personnel of examination system main frame collection is uploaded to the management of people's car is The all-purpose card server of system, links the information of the performance information of examination personnel with people's car management system, the one-tenth of examination personnel Invalid then will be unable to is carried out job site less than card corresponding to personnel setting threshold value by achievement information.
10. outdoor scene based on threedimensional model visual wisdom building site management system as claimed in claim 9, is characterized in that, Described technological document and management file management system include Engineering Documents Management Systems and management file management system, technological document pipe Reason system by technology class document interface with literary composition control communication, management file management system by management class document interface with Literary composition control communication, uses the information correlation method towards 3D solid object, in literary composition keyholed back plate reason system and wisdom building site three Dimension is shown in door entity object and is realized Attribute Association, it is achieved having access to of various management under 3-D view and technical documentation;
Described tower crane safety monitoring system includes that multiple beacon, each beacon are provided with the tower crane minor exchange of correspondence, and tower crane is divided Switch is connected with corresponding video camera and beacon wireless bridge respectively, by the existing real-time monitoring to tower crane state of video camera.
CN201610173074.4A 2015-09-28 2016-03-24 The visual wisdom chemical industry ground management system of outdoor scene based on threedimensional model Active CN105867321B (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN201510628958.XA CN105204470A (en) 2015-09-28 2015-09-28 Live-action visual intelligent construction site managing system based on three-dimensional model
CN201510628958X 2015-09-28

Publications (2)

Publication Number Publication Date
CN105867321A true CN105867321A (en) 2016-08-17
CN105867321B CN105867321B (en) 2017-05-31

Family

ID=54952212

Family Applications (2)

Application Number Title Priority Date Filing Date
CN201510628958.XA Pending CN105204470A (en) 2015-09-28 2015-09-28 Live-action visual intelligent construction site managing system based on three-dimensional model
CN201610173074.4A Active CN105867321B (en) 2015-09-28 2016-03-24 The visual wisdom chemical industry ground management system of outdoor scene based on threedimensional model

Family Applications Before (1)

Application Number Title Priority Date Filing Date
CN201510628958.XA Pending CN105204470A (en) 2015-09-28 2015-09-28 Live-action visual intelligent construction site managing system based on three-dimensional model

Country Status (1)

Country Link
CN (2) CN105204470A (en)

Cited By (25)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106651119A (en) * 2016-11-07 2017-05-10 成都科曦科技有限公司 Engineering security decision system of smart hotel
CN106709655A (en) * 2016-12-28 2017-05-24 南京合智信息技术有限公司 Internet-of-things-based civilized construction site index evaluation system for project construction site
CN107065733A (en) * 2017-06-05 2017-08-18 合肥市闵葵电力工程有限公司 A kind of construction site monitoring system
CN107872648A (en) * 2017-10-06 2018-04-03 湖北聚注通用技术研究有限公司 A kind of interior decoration construction scene monitoring system based on three-dimensional modeling
CN108170079A (en) * 2018-02-16 2018-06-15 广西建工集团智慧制造有限公司 Building site intelligent container comprehensive management platform
CN108334024A (en) * 2018-02-16 2018-07-27 广西建工集团智慧制造有限公司 Building site intelligent container comprehensive management platform control system
CN108898255A (en) * 2018-06-29 2018-11-27 河南聚合科技有限公司 One kind is based on the twinborn intelligence community O&M supervisory control simulation cloud platform of digitlization
CN108961767A (en) * 2018-07-24 2018-12-07 河北德冠隆电子科技有限公司 Highway inspection based on four-dimensional outdoor scene traffic simulation, which is pursued and captured an escaped prisoner, takes alarm system
CN108985714A (en) * 2018-07-04 2018-12-11 江苏南通三建集团股份有限公司 A kind of construction site wisdom control integrated system
CN109635132A (en) * 2018-12-10 2019-04-16 Oppo(重庆)智能科技有限公司 A kind of Automatic Warehouse management method, system and terminal device
TWI662478B (en) * 2018-11-14 2019-06-11 江俊昇 Civil engineering design method with real landscape
CN109885008A (en) * 2019-03-19 2019-06-14 汉锦科技(北京)有限公司 Wisdom construction auxiliary system
CN109917708A (en) * 2019-03-13 2019-06-21 武汉零点视觉数字科技有限公司 A kind of three-dimensional scenic display systems of engineering informationization construction
CN111061928A (en) * 2019-11-25 2020-04-24 上海彤逸电子工程有限公司 Three-dimensional holographic management system and implementation method thereof
CN111125808A (en) * 2019-11-12 2020-05-08 万翼科技有限公司 Intelligent construction site management model construction method and device
CN111401746A (en) * 2020-03-17 2020-07-10 中交第一航务工程局有限公司 Intelligent construction site informatization management system
CN111722575A (en) * 2019-03-22 2020-09-29 江苏海内软件科技有限公司 Intelligent enterprise management system, method and equipment
CN111784280A (en) * 2020-05-28 2020-10-16 浙江舜江建设集团有限公司 Intelligent management system for construction site of building engineering
CN112543314A (en) * 2020-12-04 2021-03-23 众源科技(广东)股份有限公司 Intelligent construction site management system based on AR real scene technology
CN112633785A (en) * 2019-09-24 2021-04-09 北京京东振世信息技术有限公司 Storage visualization method and device
CN112651069A (en) * 2020-12-05 2021-04-13 重庆源道建筑规划设计有限公司 Intelligent construction site management and control method, system and device based on BIM and storage medium
CN113433914A (en) * 2021-07-06 2021-09-24 山东电力工程咨询院有限公司 Intelligent construction site management and control platform and monitoring method thereof
CN114119897A (en) * 2022-01-27 2022-03-01 南京精筑智慧科技有限公司 Intelligent construction site management method and system based on Internet of things
CN114397862A (en) * 2021-11-29 2022-04-26 湖南联合智为信息技术有限公司 Wisdom building site supervision platform
CN115273268A (en) * 2022-07-27 2022-11-01 中建三局集团有限公司 Large-scene construction site inspection method based on tower crane carrying zoom camera

Families Citing this family (19)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105915632A (en) * 2016-06-03 2016-08-31 绵阳九鼎智远知识产权运营有限公司 Building engineering monitoring system based on 3D virtual reality technology
CN106412526A (en) * 2016-11-15 2017-02-15 武汉市公安局公共交通分局 Police oblique-photography real 3D platform system and interface system thereof
CN107038754A (en) * 2017-03-15 2017-08-11 武汉华安科技股份有限公司 A kind of wisdom garden management system and method based on three-dimensional live
CN106973116A (en) * 2017-05-04 2017-07-21 绵阳市川交公路规划勘察设计有限公司 A kind of construction Supervision system of the remote real-time monitoring based on cloud
CN107909001A (en) * 2017-08-04 2018-04-13 国网浙江省电力公司湖州供电公司 A kind of engineering site personnel Vehicular system
CN107544326A (en) * 2017-08-30 2018-01-05 深圳市易联智道科技有限公司 Ensure the multifunction monitoring system of construction site security
CN107678340A (en) * 2017-10-10 2018-02-09 中建八局第二建设有限公司 A kind of intelligent hanging basket monitoring system, comprehensive monitoring system and monitoring method
CN108146966B (en) * 2017-11-22 2019-12-10 余仪琳 logistics vehicle loading control system based on Internet of things
CN108064018A (en) * 2017-12-25 2018-05-22 上海建工集团股份有限公司 A kind of safety management in construction site system and its application method based on location technology
CN109118088A (en) * 2018-08-15 2019-01-01 杨超 A kind of construction management method and system based on wisdom building site
CN109448116B (en) * 2018-10-31 2022-06-28 广西路桥工程集团有限公司 Intelligent construction site system based on BIM model
CN110324584A (en) * 2019-07-15 2019-10-11 广东电网有限责任公司 A kind of monitoring device of quick lock in displacement equipment
CN110691116B (en) * 2019-08-18 2023-04-14 朗德万斯公司 Method, positioning device and system for managing network device
CN111770315A (en) * 2020-07-21 2020-10-13 广西路桥工程集团有限公司 Intelligent building site video online monitoring system
CN111928897A (en) * 2020-08-10 2020-11-13 武汉泛宇科技有限公司 Method for collecting and analyzing temperature, humidity and noise of mechanical workshop
CN115250280A (en) * 2021-04-27 2022-10-28 上海宝信软件股份有限公司 3D intelligent security ring management system, method, device and medium based on BS/CS
CN115100375B (en) * 2022-07-05 2023-04-11 中国人民解放军32039部队 Display platform and method
CN115623031B (en) * 2022-09-20 2023-11-03 中邮通建设咨询有限公司 Three-dimensional intelligent building site operation and maintenance management and control platform
CN115796392B (en) * 2023-01-31 2023-06-13 中交第四航务工程勘察设计院有限公司 Intelligent building display method and system based on 3D visualization

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103795976A (en) * 2013-12-30 2014-05-14 北京正安融翰技术有限公司 Full space-time three-dimensional visualization method
CN103984333A (en) * 2014-06-04 2014-08-13 北京京能高安屯燃气热电有限责任公司 Monitoring and management system for power plant
CN104618694A (en) * 2015-03-02 2015-05-13 国家电网公司 Three-dimensional dynamic monitoring method and system of machine room
CN104808610A (en) * 2015-02-13 2015-07-29 上海同筑信息科技有限公司 Machinery control system and machinery control method based on a BIM (building information model)

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103795976A (en) * 2013-12-30 2014-05-14 北京正安融翰技术有限公司 Full space-time three-dimensional visualization method
CN103984333A (en) * 2014-06-04 2014-08-13 北京京能高安屯燃气热电有限责任公司 Monitoring and management system for power plant
CN104808610A (en) * 2015-02-13 2015-07-29 上海同筑信息科技有限公司 Machinery control system and machinery control method based on a BIM (building information model)
CN104618694A (en) * 2015-03-02 2015-05-13 国家电网公司 Three-dimensional dynamic monitoring method and system of machine room

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
李芳等: "基于GIS的数字工地系统的设计和开发", 《山西建筑》 *

Cited By (28)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106651119A (en) * 2016-11-07 2017-05-10 成都科曦科技有限公司 Engineering security decision system of smart hotel
CN106709655A (en) * 2016-12-28 2017-05-24 南京合智信息技术有限公司 Internet-of-things-based civilized construction site index evaluation system for project construction site
CN107065733A (en) * 2017-06-05 2017-08-18 合肥市闵葵电力工程有限公司 A kind of construction site monitoring system
CN107872648A (en) * 2017-10-06 2018-04-03 湖北聚注通用技术研究有限公司 A kind of interior decoration construction scene monitoring system based on three-dimensional modeling
CN108170079A (en) * 2018-02-16 2018-06-15 广西建工集团智慧制造有限公司 Building site intelligent container comprehensive management platform
CN108334024A (en) * 2018-02-16 2018-07-27 广西建工集团智慧制造有限公司 Building site intelligent container comprehensive management platform control system
CN108898255A (en) * 2018-06-29 2018-11-27 河南聚合科技有限公司 One kind is based on the twinborn intelligence community O&M supervisory control simulation cloud platform of digitlization
CN108985714A (en) * 2018-07-04 2018-12-11 江苏南通三建集团股份有限公司 A kind of construction site wisdom control integrated system
CN108961767A (en) * 2018-07-24 2018-12-07 河北德冠隆电子科技有限公司 Highway inspection based on four-dimensional outdoor scene traffic simulation, which is pursued and captured an escaped prisoner, takes alarm system
CN108961767B (en) * 2018-07-24 2021-01-26 河北德冠隆电子科技有限公司 Highway inspection chases fee alarm system based on four-dimensional outdoor traffic simulation
TWI662478B (en) * 2018-11-14 2019-06-11 江俊昇 Civil engineering design method with real landscape
CN109635132A (en) * 2018-12-10 2019-04-16 Oppo(重庆)智能科技有限公司 A kind of Automatic Warehouse management method, system and terminal device
CN109917708A (en) * 2019-03-13 2019-06-21 武汉零点视觉数字科技有限公司 A kind of three-dimensional scenic display systems of engineering informationization construction
CN109885008A (en) * 2019-03-19 2019-06-14 汉锦科技(北京)有限公司 Wisdom construction auxiliary system
CN111722575A (en) * 2019-03-22 2020-09-29 江苏海内软件科技有限公司 Intelligent enterprise management system, method and equipment
CN112633785A (en) * 2019-09-24 2021-04-09 北京京东振世信息技术有限公司 Storage visualization method and device
CN111125808A (en) * 2019-11-12 2020-05-08 万翼科技有限公司 Intelligent construction site management model construction method and device
CN111061928A (en) * 2019-11-25 2020-04-24 上海彤逸电子工程有限公司 Three-dimensional holographic management system and implementation method thereof
CN111401746A (en) * 2020-03-17 2020-07-10 中交第一航务工程局有限公司 Intelligent construction site informatization management system
CN111784280A (en) * 2020-05-28 2020-10-16 浙江舜江建设集团有限公司 Intelligent management system for construction site of building engineering
CN112543314A (en) * 2020-12-04 2021-03-23 众源科技(广东)股份有限公司 Intelligent construction site management system based on AR real scene technology
CN112651069A (en) * 2020-12-05 2021-04-13 重庆源道建筑规划设计有限公司 Intelligent construction site management and control method, system and device based on BIM and storage medium
CN113433914A (en) * 2021-07-06 2021-09-24 山东电力工程咨询院有限公司 Intelligent construction site management and control platform and monitoring method thereof
CN113433914B (en) * 2021-07-06 2022-09-30 山东电力工程咨询院有限公司 Intelligent construction site management and control platform and monitoring method thereof
CN114397862A (en) * 2021-11-29 2022-04-26 湖南联合智为信息技术有限公司 Wisdom building site supervision platform
CN114119897A (en) * 2022-01-27 2022-03-01 南京精筑智慧科技有限公司 Intelligent construction site management method and system based on Internet of things
CN115273268A (en) * 2022-07-27 2022-11-01 中建三局集团有限公司 Large-scene construction site inspection method based on tower crane carrying zoom camera
CN115273268B (en) * 2022-07-27 2023-05-19 中建三局集团有限公司 Large scene construction site inspection method based on tower crane carrying zoom camera

Also Published As

Publication number Publication date
CN105204470A (en) 2015-12-30
CN105867321B (en) 2017-05-31

Similar Documents

Publication Publication Date Title
CN105867321B (en) The visual wisdom chemical industry ground management system of outdoor scene based on threedimensional model
CN112116503A (en) Smart community cloud platform management system
CN111242574A (en) Intelligent site inspection management system and method based on GPS technology
CN111121862A (en) Air-space-ground integrated atmospheric environment monitoring system and method
CN112116502A (en) Smart community security management system
CN115348247A (en) Forest fire detection early warning and decision-making system based on sky-ground integration technology
CN108508831A (en) A kind of intelligent managing and control system of underground pipe gallery
CN108922188A (en) The four-dimensional outdoor scene traffic of radar tracking positioning perceives early warning monitoring management system
CN113706355A (en) Method for building intelligent emergency system of chemical industry park
CN113298444A (en) Private cloud-based intelligent power safety control platform
CN111784140A (en) Wisdom water affairs management and control scheduling platform based on internet of things
CN116962460B (en) Intelligent park operation management system and method
CN114399265A (en) Electric power engineering construction project overall process management and control system
CN104103153A (en) Flood prevention rainwater information automatic monitoring central system and monitoring method thereof
CN106597966A (en) Security and protection system based on chemical industrial park
CN103995936A (en) Simulation system platform used for practical training of water supply and drainage pump operators
CN102979524A (en) Robot control mining system
KR20160099931A (en) Disaster preventing and managing method for the disaster harzard and interest area
KR20140134457A (en) Safety Accident Management System Of Bridge
CN115940408A (en) Transformer substation operation safety management and control system and method based on indoor and outdoor fusion positioning
CN115022601A (en) IOT deep learning intelligent early warning research and judgment system and method based on big data
CN103760865A (en) Remote monitoring platform based on MSTP special communication network
CN114926314A (en) Ubiquitous autonomous controllable Internet of things equipment system and method
CN114245294A (en) Personnel safety management and control system for 3D personnel positioning
CN113538825A (en) Campus wall-turning event alarm method and system

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant