CN108149709A - 地下综合管廊预制拼装施工方法 - Google Patents
地下综合管廊预制拼装施工方法 Download PDFInfo
- Publication number
- CN108149709A CN108149709A CN201711463195.3A CN201711463195A CN108149709A CN 108149709 A CN108149709 A CN 108149709A CN 201711463195 A CN201711463195 A CN 201711463195A CN 108149709 A CN108149709 A CN 108149709A
- Authority
- CN
- China
- Prior art keywords
- piping lane
- buried
- nail
- reinforcement cage
- steel reinforcement
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/045—Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/10—Tunnels or galleries specially adapted to house conduits, e.g. oil pipe-lines, sewer pipes ; Making conduits in situ, e.g. of concrete ; Casings, i.e. manhole shafts, access or inspection chambers or coverings of boreholes or narrow wells
Abstract
本发明公开了一种地下综合管廊预制拼装施工方法,包括以下步骤,(1)制作模具和钢筋笼,(2)混凝土浇筑及振捣,(3)蒸汽养护及脱模、(4)提吊及运输、(5)拼装,在步骤(1)之前先进行BIM建模;钢筋笼施工采用钢筋定型胎膜辅助绑扎成型;钢筋笼入模以后,预埋吊钉和螺栓;混凝土浇筑完成后,在预制管廊内壁转角位置处带有加腋角,在加腋角的中部设置有张拉槽;从坡度最低处开始拼装首节预制管廊,两节管廊拼装时结合千斤顶进行对角张拉,直到四个角部均张拉完成。能确保钢筋笼一次顺利入模,吊装及安装支架时不需要在管廊内打孔破坏管廊结构,并能有效防止地面沉降对管廊造成的影响,提高施工效率和施工质量。
Description
技术领域
本发明涉及城市地下管网系统的管廊技术领域,具体涉及一种地下综合管廊的预制及拼装施工方法。
背景技术
相对于现浇管廊而言,预制管廊施工成品外观质量好,施工效率高,对环境污染少、材料浪费少。现有管廊预制拼装施工方法,主要包括制作模具和钢筋笼、混凝土浇筑及振捣、蒸汽养护、提吊及运输、拼装几个步骤。
该施工方法存在的主要问题是:
(1)在钢筋笼绑扎成型过程中,尺寸误差大,不能确保钢筋笼一次顺利入模;(2)吊装时需要在管廊上打吊顶,加载安装支架时需要在管廊内打螺钉,破坏管廊结构造成渗水;(3)管廊拼装位置为薄弱环形,不能有效防止地面沉降对管廊造成的影响;(4)施工效率低,施工质量和进度有待提高。因此,地下管廊预制拼装施工目前处于摸索阶段,尚未有一套科学、合理的综合施工方法。
发明内容
本发明旨在提供一种地下综合管廊预制拼装施工方法,能确保钢筋笼一次顺利入模,吊装及安装支架时不需要在管廊内打孔破坏管廊结构,并能有效防止地面沉降对管廊造成的影响,提高施工效率和施工质量。
为此,本发明所采用的技术方案为:一种地下综合管廊预制拼装施工方法,包括以下步骤,(1)制作模具和钢筋笼,(2)混凝土浇筑及振捣,(3)蒸汽养护及脱模、(4)提吊及运输、(5)拼装,其中:
在步骤(1)之前先进行BIM建模,对整个工程进行了模拟预施工,进行各专业的碰撞检查,及时优化施工图;
在步骤(1)中,模具采用卧式模具并带有承插口和附着式振动板;先用钢板加工成方体钢筋定型胎膜,钢筋笼施工采用钢筋定型胎膜辅助绑扎成型,以确保钢筋笼从上到下一次性顺利放入卧式模具中;钢筋笼入模以后,预埋吊钉和螺栓,使浇筑成的预制管廊顶部带用预埋吊钉、内壁带有预埋螺栓;
在步骤(2)中,混凝土浇筑完成后,在预制管廊内壁转角位置处带有加腋角,在加腋角的中部设置有张拉槽,在加腋角内设置有沿管廊长度方向贯通的钢绞线预留孔;
在步骤(5)中,从坡度最低处开始拼装首节预制管廊,两节管廊拼装时,钢绞线的端头铆固在张拉槽内,钢绞线穿过钢绞线预留孔,并结合千斤顶进行对角张拉,直到四个角部均张拉完成。
作为上述方案的优选,在步骤(2)中,预制管廊浇筑成型时,所述预埋吊钉通过半球形橡胶罩住,半球形橡胶正好将预埋吊钉的“T”型端头罩住,成型后再将半球形橡胶去掉使预埋吊钉的“T”型端头露出,且预埋吊钉的端头不得高出预制管廊的外表面;通过预设半球形橡胶将预埋吊钉的“T”型端头罩住,确保浇筑混凝土不会进入半球形缺槽的空间,拆模时再将半球形橡胶去掉,使预埋吊钉的“T”型端头裸露在外,方便吊具进入半球形缺槽并将“T”型端头夹住进行吊装。预埋吊钉共四个,并呈矩形布置,保证吊装平稳,避免吊装过程中出现偏摆。
步骤(3)中,蒸汽养护采用生物燃料锅炉产生的蒸汽进行,并结合增氧罩覆盖,缩短混凝土凝结时间,达到设计强度75%后进行拆模、吊装及存放。
步骤(4)中,采用龙门吊垂直提吊,管廊运输选用平板拖车,且每次运输2—4个管节,管廊存放时安装RFID芯片,输入管廊参数信息。预埋吊钉并结合垂直提吊,使管廊在提吊过程中垂直受力,防止内部破损。平板车运输,两侧无阻挡,方便管廊装卸。管廊存放时安装RFID芯片,确保安装无误。
步骤(5)中,管廊拼装前先对底部垫层进行精平,满足平整度要求,确定中心轴线和边线,使拼装后平整度高。
步骤(5)中,管廊拼装承口贴中空式遇水膨胀橡胶止水条,管廊张拉完成后,先在张拉槽和预埋吊钉的槽内分别灌入环氧胶泥,防止钢绞线及预埋吊钉锈蚀;再对管廊的承插口处进行内外防水处理,采用双组分密封胶对承插口进行封堵,两侧各宽出承插口4—6mm;最后对管廊进行整体外防水施工,采用满铺3mm后湿铺防水卷材进行处理。
本发明的有益效果是:
(1)施工前先进行BIM建模,对整个工程进行了模拟预施工,解决了各专业施工图纸碰撞问题,对施工安全隐患及工期进行了预判,较以往常规施工工艺可显著提高施工效率、节约施工成本;
(2)预制管廊钢筋笼施工采用钢筋定型胎膜辅助绑扎成型,较常规钢筋绑扎,能确保每个钢筋笼均能满足设计要求,顺利入模,保证混凝土保护层厚度;管廊模具采用卧式模具并带有承插口,便于管廊后期拼装完成施工防水;管廊模具安装附着式振动板,便于混凝土振捣,排出气泡。
(3)设置预埋吊钉和预埋螺栓,减少在管廊上开孔,降低了管廊的破损率,提高施工效率和质量;
(4)预制管廊浇筑完成后自带加腋角以增加管廊转角位置处的强度,并增设张拉槽、钢绞线进行对角张拉,确保拼装时均匀施加张力,且拼装后留置的钢绞线能有效防止管廊接缝处薄弱造成地面下沉;
(5)从坡度最低处开始拼装首节预制管廊,相比由高向低的拼装方式,能有效防止管廊拼装移位。
附图说明
图1是方体钢筋定型胎膜。
图2是预制管廊的成品图。
图3是钢绞线在张拉槽中的锚固状态。
具体实施方式
下面通过实施例并结合附图,对本发明作进一步说明:
一种地下综合管廊预制拼装施工方法,包括以下步骤:
(1)制作模具和钢筋笼;
(2)混凝土浇筑及振捣;
(3)蒸汽养护及脱模;
(4)提吊及运输;
(5)拼装。以上步骤为地下综合管廊预制拼装施工方法的必要步骤,本发明的关键在于:
在步骤(1)之前先进行BIM建模,对整个工程进行了模拟预施工,进行各专业的碰撞检查,及时优化施工图,实现项目成本的精细化管理和动态管理,显著提高施工效率、节约施工成本;
在步骤(1)中,模具采用卧式模具并带有承插口和附着式振动板;先用钢板加工成方体钢筋定型胎膜(如图1所示),最好是,钢筋定型胎膜采用镀锌钢板焊接而成,镀锌钢板做成锯齿形,把半成品钢筋摆放在镀锌钢板锯齿内,校正钢筋,采用二氧化碳保护焊焊接密实。钢筋笼施工采用钢筋定型胎膜辅助绑扎成型,以确保尺寸准确,钢筋笼从上到下一次性顺利放入卧式模具中。钢筋笼入模以后,预埋吊钉和螺栓,使浇筑成的预制管廊顶部带用预埋吊钉、内壁带有预埋螺栓。
在步骤(2)中,混凝土应连续灌注,一次成型,保证良好的密实性,采用斜向分段、水平分层,侧震为主插入式振捣为辅。振捣时不得碰撞模板、钢筋和预应力管道及预埋件。混凝土浇筑完成后,在预制管廊(如图2所示)内壁转角位置处带有加腋角a以增加强度,在加腋角a的中部设置有张拉槽b,在加腋角a内设置有沿管廊长度方向贯通的钢绞线预留孔c,且钢绞线预留孔c经过张拉槽b。
最好是,在步骤(2)中,预制管廊浇筑成型时,所述预埋吊钉通过半球形橡胶罩住,半球形橡胶正好将预埋吊钉的“T”型端头罩住,成型后再将半球形橡胶去掉使预埋吊钉的“T”型端头露出,且预埋吊钉的端头不得高出预制管廊的外表面;预埋吊钉共四个,并呈矩形布置。
步骤(3)中,蒸汽养护最好采用生物燃料锅炉产生的蒸汽进行,并结合增氧罩覆盖,缩短混凝土凝结时间,达到设计强度75%后进行拆模、吊装及存放。
步骤(4)中,采用龙门吊垂直提吊,管廊运输选用平板拖车,且每次运输2—4个管节,管廊存放时安装RFID芯片,输入管廊参数信息。
在步骤(5)中,从坡度最低处开始拼装首节预制管廊,两节管廊拼装时,钢绞线的端头铆固在张拉槽b内,钢绞线d穿过钢绞线预留孔c(结合图2、图3所示),并结合千斤顶进行对角张拉,所谓对角张拉为左下角与右上角同时张拉,左上角与右下角同时张拉,直到四个角部均张拉完成。
最好是,步骤(5)中,管廊拼装前先对底部垫层进行精平,满足平整度要求,确定中心轴线和边线。
另外,在步骤(5)中,管廊拼装承口贴中空式遇水膨胀橡胶止水条,再将下一节管廊的插口套入上一节管廊的承口即可。管廊张拉完成后,先在张拉槽和预埋吊钉的槽内分别灌入环氧胶泥,防止钢绞线及吊顶锈蚀;再对管廊的承插口处进行内外防水处理,采用双组分密封胶对承插口进行封堵,两侧各宽出承插口4—6mm;最后对管廊进行整体外防水施工,采用满铺3mm后湿铺防水卷材进行处理。
Claims (6)
1.一种地下综合管廊预制拼装施工方法,包括以下步骤,(1)制作模具和钢筋笼,(2)混凝土浇筑及振捣,(3)蒸汽养护及脱模、(4)提吊及运输、(5)拼装,其特征在于:
在步骤(1)之前先进行BIM建模,对整个工程进行了模拟预施工,进行各专业的碰撞检查,及时优化施工图;
在步骤(1)中,模具采用卧式模具并带有承插口和附着式振动板;先用钢板加工成方体钢筋定型胎膜,钢筋笼施工采用钢筋定型胎膜辅助绑扎成型,以确保钢筋笼从上到下一次性顺利放入卧式模具中;钢筋笼入模以后,预埋吊钉和螺栓,使浇筑成的预制管廊顶部带用预埋吊钉、内壁带有预埋螺栓;
在步骤(2)中,混凝土浇筑完成后,在预制管廊内壁转角位置处带有加腋角,在加腋角的中部设置有张拉槽,在加腋角内设置有沿管廊长度方向贯通的钢绞线预留孔;
在步骤(5)中,从坡度最低处开始拼装首节预制管廊,两节管廊拼装时,钢绞线的端头锚固在张拉槽内,钢绞线穿过钢绞线预留孔,并结合千斤顶进行对角张拉,直到四个角部均张拉完成。
2.根据权利要求1所述的地下综合管廊预制拼装施工方法,其特征在于:在步骤(2)中,预制管廊浇筑成型时,所述预埋吊钉通过半球形橡胶罩住,半球形橡胶正好将预埋吊钉的“T”型端头罩住,成型后再将半球形橡胶去掉使预埋吊钉的“T”型端头露出,且预埋吊钉的端头不得高出预制管廊的外表面;预埋吊钉共四个,并呈矩形布置。
3.根据权利要求1所述的地下综合管廊预制拼装施工方法,其特征在于:步骤(3)中,蒸汽养护采用燃烧生物质燃料产生的蒸汽进行,并结合增氧罩覆盖。
4.根据权利要求1所述的地下综合管廊预制拼装施工方法,其特征在于:步骤(4)中,采用龙门吊垂直提吊,管廊运输选用平板拖车,且每次运输2—4个管节,管廊存放时安装RFID芯片,输入管廊参数信息。
5.根据权利要求1所述的地下综合管廊预制拼装施工方法,其特征在于:步骤(5)中,管廊拼装前先对底部垫层进行精平,满足平整度要求,确定中心轴线和边线。
6.根据权利要求1或5所述的地下综合管廊预制拼装施工方法,其特征在于:步骤(5)中,管廊拼装承口贴中空式遇水膨胀橡胶止水条,管廊张拉完成后,先在张拉槽和预埋吊钉的槽内分别灌入环氧胶泥;再对管廊的承插口处进行内外防水处理,采用双组分密封胶对承插口进行封堵,两侧各宽出承插口4—6mm;最后对管廊进行整体外防水施工,采用满铺3mm后湿铺防水卷材进行处理。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711463195.3A CN108149709A (zh) | 2017-12-28 | 2017-12-28 | 地下综合管廊预制拼装施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711463195.3A CN108149709A (zh) | 2017-12-28 | 2017-12-28 | 地下综合管廊预制拼装施工方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108149709A true CN108149709A (zh) | 2018-06-12 |
Family
ID=62462755
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201711463195.3A Pending CN108149709A (zh) | 2017-12-28 | 2017-12-28 | 地下综合管廊预制拼装施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108149709A (zh) |
Cited By (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109024681A (zh) * | 2018-09-03 | 2018-12-18 | 江苏金贸科技发展有限公司 | 一种地下管廊拉紧绳接头保护盒 |
CN109098207A (zh) * | 2018-09-21 | 2018-12-28 | 中建局集团第二建筑有限公司 | 一种地下综合管廊预制燃气舱、模板体系及施工方法 |
CN109183847A (zh) * | 2018-11-12 | 2019-01-11 | 北京建工新型建材科技股份有限公司 | 一种地下预制管廊 |
CN109183843A (zh) * | 2018-10-31 | 2019-01-11 | 长沙小如信息科技有限公司 | 预制装配整体式混凝土综合管廊及施工工法 |
CN109605567A (zh) * | 2018-12-25 | 2019-04-12 | 上海公路桥梁(集团)有限公司 | 预制管廊的制造方法 |
CN109811793A (zh) * | 2019-03-22 | 2019-05-28 | 中冶京诚工程技术有限公司 | 预制管节用移动工厂及预制管节生产方法 |
CN110714481A (zh) * | 2019-08-16 | 2020-01-21 | 中电建十一局工程有限公司 | 一种预制装配式电力管廊施工方法 |
CN112171850A (zh) * | 2020-10-09 | 2021-01-05 | 湖南楚怀建材有限公司 | 一种用于预制混凝土方涵制造的振捣装置 |
CN113378256A (zh) * | 2020-12-30 | 2021-09-10 | 中国二十冶集团有限公司 | 综合管廊筏板与墙内角加腋bim建模及其钢筋精细化调整 |
CN114809075A (zh) * | 2022-04-29 | 2022-07-29 | 中国铁建港航局集团有限公司 | 地下预制管廊综合防水施工方法 |
CN115674558A (zh) * | 2022-12-21 | 2023-02-03 | 山东工程职业技术大学 | 一种避免飞边的碳纤维成型机 |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR0140333B1 (ko) * | 1993-12-24 | 1999-02-18 | 박병무 | 조립식 암거설비 및 그 설치방법 |
CN102303369A (zh) * | 2011-08-31 | 2012-01-04 | 沈阳市政地铁管片有限公司 | 预制方涵的工艺方法 |
CN206748720U (zh) * | 2017-03-21 | 2017-12-15 | 中铁工程装备集团有限公司 | 地下管廊用槽型混凝土管节模具 |
-
2017
- 2017-12-28 CN CN201711463195.3A patent/CN108149709A/zh active Pending
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR0140333B1 (ko) * | 1993-12-24 | 1999-02-18 | 박병무 | 조립식 암거설비 및 그 설치방법 |
CN102303369A (zh) * | 2011-08-31 | 2012-01-04 | 沈阳市政地铁管片有限公司 | 预制方涵的工艺方法 |
CN206748720U (zh) * | 2017-03-21 | 2017-12-15 | 中铁工程装备集团有限公司 | 地下管廊用槽型混凝土管节模具 |
Non-Patent Citations (5)
Title |
---|
[匈]L.莫克等: "《钢筋混凝土装配式建筑》", 28 February 1985, 中国建筑工业出版社 * |
中铁四局集团有限公司: "《客运专线预应力混凝土简支箱梁施工技术》", 30 November 2010, 中国铁道出版社 * |
揭海荣: "城市综合管廊预制拼装施工技术", 《低温建筑技术》 * |
杨晓东等: "基于物联网和BIM技术在地下综合管廊建设运维中的应用", 《建设科技》 * |
石立国等: "上下分体装配式预制管廊施工技术", 《施工技术》 * |
Cited By (15)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109024681A (zh) * | 2018-09-03 | 2018-12-18 | 江苏金贸科技发展有限公司 | 一种地下管廊拉紧绳接头保护盒 |
CN109024681B (zh) * | 2018-09-03 | 2024-01-05 | 江苏金贸科技发展有限公司 | 一种地下管廊拉紧绳接头保护盒 |
CN109098207B (zh) * | 2018-09-21 | 2023-09-08 | 中建一局集团第二建筑有限公司 | 一种地下综合管廊预制燃气舱的模板体系及施工方法 |
CN109098207A (zh) * | 2018-09-21 | 2018-12-28 | 中建局集团第二建筑有限公司 | 一种地下综合管廊预制燃气舱、模板体系及施工方法 |
CN109183843A (zh) * | 2018-10-31 | 2019-01-11 | 长沙小如信息科技有限公司 | 预制装配整体式混凝土综合管廊及施工工法 |
CN109183847A (zh) * | 2018-11-12 | 2019-01-11 | 北京建工新型建材科技股份有限公司 | 一种地下预制管廊 |
CN109183847B (zh) * | 2018-11-12 | 2023-10-31 | 北京建工新型建材科技股份有限公司 | 一种地下预制管廊 |
CN109605567A (zh) * | 2018-12-25 | 2019-04-12 | 上海公路桥梁(集团)有限公司 | 预制管廊的制造方法 |
CN109811793A (zh) * | 2019-03-22 | 2019-05-28 | 中冶京诚工程技术有限公司 | 预制管节用移动工厂及预制管节生产方法 |
CN109811793B (zh) * | 2019-03-22 | 2024-02-06 | 中冶京诚工程技术有限公司 | 预制管节用移动工厂及预制管节生产方法 |
CN110714481A (zh) * | 2019-08-16 | 2020-01-21 | 中电建十一局工程有限公司 | 一种预制装配式电力管廊施工方法 |
CN112171850A (zh) * | 2020-10-09 | 2021-01-05 | 湖南楚怀建材有限公司 | 一种用于预制混凝土方涵制造的振捣装置 |
CN113378256A (zh) * | 2020-12-30 | 2021-09-10 | 中国二十冶集团有限公司 | 综合管廊筏板与墙内角加腋bim建模及其钢筋精细化调整 |
CN114809075A (zh) * | 2022-04-29 | 2022-07-29 | 中国铁建港航局集团有限公司 | 地下预制管廊综合防水施工方法 |
CN115674558A (zh) * | 2022-12-21 | 2023-02-03 | 山东工程职业技术大学 | 一种避免飞边的碳纤维成型机 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108149709A (zh) | 地下综合管廊预制拼装施工方法 | |
CN104895092B (zh) | 一种内支撑临时格构柱用作永久结构柱的方法 | |
CN108360370B (zh) | 一种预制钢管约束钢筋混凝土桥墩与承台连接节点 | |
CN111042185B (zh) | 一种带塔吊基础的地下室筏板基础施工方法 | |
CN103410317A (zh) | 采用墙体预制构件现场拼装并浇筑的整体墙体施工方法 | |
CN113481931B (zh) | 一种模块化装配式高桩码头结构及其施工方法 | |
CN102383628A (zh) | 筒仓结构后施工减压锥的施工装置及施工方法 | |
CN108118890A (zh) | 剪力墙变形缝中的待浇筑墙体模板体系及其支设方法 | |
CN105128131A (zh) | 用聚苯乙烯泡沫芯模制作预应力空心板梁的方法 | |
CN108487630A (zh) | 混凝土坎台预制装配施工方法 | |
CN109208790A (zh) | 圆弧剪力墙单侧支模施工方法 | |
US20160376756A1 (en) | Precast concrete bridge unit and headwall assembly and method of production | |
CN108726348A (zh) | 一种管廊节段平卧预制翻转起吊方法 | |
JP2020117902A (ja) | 支柱用組立て基礎およびその構築方法 | |
CN213741571U (zh) | 装配式混凝土建筑结构预留钢筋穿孔的预制柱及梁柱节点 | |
CN109098207A (zh) | 一种地下综合管廊预制燃气舱、模板体系及施工方法 | |
CN112323635A (zh) | 一种现浇湿接缝的施工方法及桥梁结构 | |
CN107237448A (zh) | 一种预制内填充混凝土墙板及其制造方法 | |
CN216131033U (zh) | 风电塔和塔筒 | |
CN207376882U (zh) | 一种装配式混凝土变截面端柱型剪力墙构件及其制作模具 | |
CN214992799U (zh) | 一种预制便道 | |
CN206245467U (zh) | 一种预制框架连接装置 | |
CN107152111A (zh) | 多水房间使用的凹凸式素混凝土导墙施工工艺 | |
CN211547797U (zh) | 一种适用于地下室筏板基础的塔吊基础结构 | |
CN113062236A (zh) | 一种护壁一体化管涵及其施工方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20180612 |