CN108130862A - 过隧运梁车 - Google Patents
过隧运梁车 Download PDFInfo
- Publication number
- CN108130862A CN108130862A CN201810094189.3A CN201810094189A CN108130862A CN 108130862 A CN108130862 A CN 108130862A CN 201810094189 A CN201810094189 A CN 201810094189A CN 108130862 A CN108130862 A CN 108130862A
- Authority
- CN
- China
- Prior art keywords
- beams
- trolley
- tunnel
- inner longitudinal
- support
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000006243 chemical reaction Methods 0.000 claims abstract description 18
- 230000000712 assembly Effects 0.000 claims abstract description 9
- 238000000429 assembly Methods 0.000 claims abstract description 9
- 230000007246 mechanism Effects 0.000 claims description 52
- 238000010276 construction Methods 0.000 description 8
- 238000010586 diagram Methods 0.000 description 6
- 238000000034 method Methods 0.000 description 4
- 229910000831 Steel Inorganic materials 0.000 description 3
- 238000012840 feeding operation Methods 0.000 description 3
- 239000010959 steel Substances 0.000 description 3
- 239000002689 soil Substances 0.000 description 2
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 2
- 238000005516 engineering process Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000009417 prefabrication Methods 0.000 description 1
- 238000005096 rolling process Methods 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Bridges Or Land Bridges (AREA)
- Lining And Supports For Tunnels (AREA)
Abstract
Description
Claims (8)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201810094189.3A CN108130862B (zh) | 2018-01-31 | 2018-01-31 | 过隧运梁车 |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201810094189.3A CN108130862B (zh) | 2018-01-31 | 2018-01-31 | 过隧运梁车 |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN108130862A true CN108130862A (zh) | 2018-06-08 |
| CN108130862B CN108130862B (zh) | 2024-02-06 |
Family
ID=62430277
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201810094189.3A Active CN108130862B (zh) | 2018-01-31 | 2018-01-31 | 过隧运梁车 |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN108130862B (zh) |
Cited By (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN109610319A (zh) * | 2018-07-08 | 2019-04-12 | 中铁十局集团汉江重工有限公司 | 一种低位运梁车及桥梁架设施工方法 |
| CN112356759A (zh) * | 2020-11-20 | 2021-02-12 | 中铁十一局集团汉江重工有限公司 | 一种低位运梁车 |
| CN113403955A (zh) * | 2021-06-30 | 2021-09-17 | 保利长大工程有限公司 | 一种适用于节段箱梁空间姿态调整的三维运输台车 |
| CN115125853A (zh) * | 2022-07-04 | 2022-09-30 | 中铁十四局集团青岛工程有限公司 | 装梁工装及装梁方法 |
Citations (8)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN201610102U (zh) * | 2010-01-10 | 2010-10-20 | 秦皇岛天业通联重工股份有限公司 | 一种超低运梁车 |
| CN201745475U (zh) * | 2010-06-09 | 2011-02-16 | 中铁科工集团有限公司 | 山岭地区超低位过隧道的运梁车 |
| CN102019960A (zh) * | 2010-12-02 | 2011-04-20 | 秦皇岛天业通联重工股份有限公司 | 凹体型轮胎式运梁车 |
| CN102029937A (zh) * | 2010-12-15 | 2011-04-27 | 武桥重工集团股份有限公司 | 一种适应单双线梁和有限空间通道的轮胎式运梁车 |
| CN203144904U (zh) * | 2013-02-01 | 2013-08-21 | 上海电力环保设备总厂有限公司 | 组合式运梁车 |
| CN104695338A (zh) * | 2015-03-31 | 2015-06-10 | 中铁工程机械研究设计院有限公司 | 含架梁支撑的多油缸支腿组合式低位运梁车 |
| CN205990588U (zh) * | 2016-08-25 | 2017-03-01 | 中铁工程机械研究设计院有限公司 | 大坡度箱梁架桥机的浮动式后支腿 |
| CN207904776U (zh) * | 2018-01-31 | 2018-09-25 | 中国铁路总公司 | 过隧运梁车 |
-
2018
- 2018-01-31 CN CN201810094189.3A patent/CN108130862B/zh active Active
Patent Citations (8)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN201610102U (zh) * | 2010-01-10 | 2010-10-20 | 秦皇岛天业通联重工股份有限公司 | 一种超低运梁车 |
| CN201745475U (zh) * | 2010-06-09 | 2011-02-16 | 中铁科工集团有限公司 | 山岭地区超低位过隧道的运梁车 |
| CN102019960A (zh) * | 2010-12-02 | 2011-04-20 | 秦皇岛天业通联重工股份有限公司 | 凹体型轮胎式运梁车 |
| CN102029937A (zh) * | 2010-12-15 | 2011-04-27 | 武桥重工集团股份有限公司 | 一种适应单双线梁和有限空间通道的轮胎式运梁车 |
| CN203144904U (zh) * | 2013-02-01 | 2013-08-21 | 上海电力环保设备总厂有限公司 | 组合式运梁车 |
| CN104695338A (zh) * | 2015-03-31 | 2015-06-10 | 中铁工程机械研究设计院有限公司 | 含架梁支撑的多油缸支腿组合式低位运梁车 |
| CN205990588U (zh) * | 2016-08-25 | 2017-03-01 | 中铁工程机械研究设计院有限公司 | 大坡度箱梁架桥机的浮动式后支腿 |
| CN207904776U (zh) * | 2018-01-31 | 2018-09-25 | 中国铁路总公司 | 过隧运梁车 |
Cited By (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN109610319A (zh) * | 2018-07-08 | 2019-04-12 | 中铁十局集团汉江重工有限公司 | 一种低位运梁车及桥梁架设施工方法 |
| CN112356759A (zh) * | 2020-11-20 | 2021-02-12 | 中铁十一局集团汉江重工有限公司 | 一种低位运梁车 |
| CN113403955A (zh) * | 2021-06-30 | 2021-09-17 | 保利长大工程有限公司 | 一种适用于节段箱梁空间姿态调整的三维运输台车 |
| CN115125853A (zh) * | 2022-07-04 | 2022-09-30 | 中铁十四局集团青岛工程有限公司 | 装梁工装及装梁方法 |
Also Published As
| Publication number | Publication date |
|---|---|
| CN108130862B (zh) | 2024-02-06 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN101851898B (zh) | 能通过隧道且实现隧道口架梁的架桥机及其架桥工序 | |
| CN102071650B (zh) | 高速铁路隧道内外通用架桥机 | |
| CN207498755U (zh) | 一种带有水平伸缩和竖向支撑调节的走行小车 | |
| CN107642012A (zh) | 一种城市轨道交通工程新型铺轨机及其施工方法 | |
| CN110130229A (zh) | 一种多幅并置的双悬臂架桥机及其架梁和过孔方法 | |
| CN201474704U (zh) | 针梁式液压钢模台车 | |
| CN207498754U (zh) | 一种城市轨道交通工程新型铺轨机 | |
| CN110273375B (zh) | 一种架桥机 | |
| CN108130862B (zh) | 过隧运梁车 | |
| CN1609342A (zh) | 下导梁式架桥机及其架梁方法 | |
| CN106917360A (zh) | 抬腿式架板机及其架板方法 | |
| CN207904776U (zh) | 过隧运梁车 | |
| CN110747757A (zh) | 整孔梁换架设备 | |
| CN100395411C (zh) | 走行式箱梁架桥机 | |
| CN110804960B (zh) | 整孔梁换架方法 | |
| CN104929056B (zh) | 一种球面轨道液压传动与控制架桥机、架桥系统及架桥方法 | |
| CN216377240U (zh) | 一种钢桁梁内铁路桥面系用桁车 | |
| CN108130864B (zh) | 整体装配式桥梁整跨梁运输架设装备 | |
| CN212202075U (zh) | 一种无轨自行式隧道二次衬砌台车 | |
| CN205368996U (zh) | 组合结构自行栈桥 | |
| CN210599016U (zh) | 一种隧道仰拱衬砌的悬臂式栈桥台车装置 | |
| CN208072215U (zh) | 具有可移动的中导梁支腿的导梁机 | |
| CN207987778U (zh) | 具有可旋转的中导梁支腿的导梁机 | |
| CN207987765U (zh) | 具有可升降的多功能台车的导梁机 | |
| CN110273368A (zh) | 在架梁工位上架梁的方法 |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| GR01 | Patent grant | ||
| GR01 | Patent grant | ||
| CP03 | Change of name, title or address | ||
| CP03 | Change of name, title or address |
Address after: 100844 Fuxing Road 10, Beijing, Haidian District Patentee after: China National Railway Group Co.,Ltd. Country or region after: China Patentee after: CHINA RAILWAY ENGINEERING MACHINERY RESEARCH & DESIGN INSTITUTE Co.,Ltd. Patentee after: CHINA ACADEMY OF RAILWAY SCIENCES Corp.,Ltd. Patentee after: CARS RAILWAY ENGINEERING Research Institute Address before: 100844 Fuxing Road 10, Beijing, Haidian District Patentee before: CHINA RAILWAY Corp. Country or region before: China Patentee before: CHINA RAILWAY ENGINEERING MACHINERY RESEARCH & DESIGN INSTITUTE Co.,Ltd. Patentee before: CHINA ACADEMY OF RAILWAY SCIENCES Patentee before: CHINA ACADEMY OF RAILWAY SCIENCES RAILWAY ENGINEERING Research Institute |