CN108104166A - A kind of ground well body structure and construction method - Google Patents

A kind of ground well body structure and construction method Download PDF

Info

Publication number
CN108104166A
CN108104166A CN201710787082.2A CN201710787082A CN108104166A CN 108104166 A CN108104166 A CN 108104166A CN 201710787082 A CN201710787082 A CN 201710787082A CN 108104166 A CN108104166 A CN 108104166A
Authority
CN
China
Prior art keywords
prefabricated block
well body
groove
ground
waterproof material
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710787082.2A
Other languages
Chinese (zh)
Inventor
胡世金
李青林
李飞
李国伟
魏丽
刘洪亮
翟佳
王洪超
宋健
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Co Ltd Of Bjrb Ruitong Maintenance Center
BEIJING MUNICIPAL BRIDGE MANAGEMENT MAINTENANCE GROUP Co Ltd
Original Assignee
Co Ltd Of Bjrb Ruitong Maintenance Center
BEIJING MUNICIPAL BRIDGE MANAGEMENT MAINTENANCE GROUP Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Co Ltd Of Bjrb Ruitong Maintenance Center, BEIJING MUNICIPAL BRIDGE MANAGEMENT MAINTENANCE GROUP Co Ltd filed Critical Co Ltd Of Bjrb Ruitong Maintenance Center
Priority to CN201710787082.2A priority Critical patent/CN108104166A/en
Publication of CN108104166A publication Critical patent/CN108104166A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/12Manhole shafts; Other inspection or access chambers; Accessories therefor
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/12Manhole shafts; Other inspection or access chambers; Accessories therefor
    • E02D29/121Manhole shafts; Other inspection or access chambers; Accessories therefor characterised by the connection between shaft elements, e.g. of rings forming said shaft
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/12Manhole shafts; Other inspection or access chambers; Accessories therefor
    • E02D29/125Manhole shafts; Other inspection or access chambers; Accessories therefor characterised by the lining of the shaft
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/02Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F5/00Sewerage structures
    • E03F5/02Manhole shafts or other inspection chambers; Snow-filling openings; accessories
    • E03F5/025Manhole shafts or other inspection chambers; Snow-filling openings; accessories provided with a liner
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F5/00Sewerage structures
    • E03F5/02Manhole shafts or other inspection chambers; Snow-filling openings; accessories
    • E03F5/027The bottom made of prefabricated segments
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0004Synthetics
    • E02D2300/0018Cement used as binder
    • E02D2300/002Concrete
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/20Miscellaneous comprising details of connection between elements
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F5/00Sewerage structures
    • E03F5/02Manhole shafts or other inspection chambers; Snow-filling openings; accessories
    • E03F2005/028Sealing joints between manhole segments

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Environmental & Geological Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • Health & Medical Sciences (AREA)
  • Road Paving Structures (AREA)

Abstract

The present invention relates to well body construction technique fields, more particularly to a kind of ground well body structure and construction method, including multilayer Prefabricated block, adjacent two layers Prefabricated block is connected by concave-convex tenon portion, concave-convex tenon portion includes the groove to cooperate and protrusion, between groove and protrusion there is gap, waterproof material is filled in gap.The present invention is using concave-convex tenon portion structure as the jointing between levels Prefabricated block, waterproof material is placed in groove, it falls in the Prefabricated block installation process of upper strata, protrude out into groove, squeezing waterproof material makes it full of the gap between protrusion and groove, waterproof material can also pass through crimping section and overflow, reach the surface on the outside of Prefabricated block fovea superior tenon portion, it effectively prevents waterproof material lack of fill and generates crack, the cooperation of the construction and waterproof material of concave-convex tenon portion, it prevents the inside and outside infiltration of well body, further improves the water resistance for the well body that Prefabricated block connects and composes.

Description

A kind of ground well body structure and construction method
Technical field
The present invention relates to well body construction technique field more particularly to a kind of ground well body structure and construction methods.
Background technology
In building process, the Prefabricated block of generally use is stepped for inspection shaft or this kind of ground well body of inlet for stom water at present Top surface and stepped bottom surface, the Prefabricated block top surface of lower floor is engaged with the bottom shape of the Prefabricated block on upper strata, in lower floor Prefabricated block top surface smears slurry, and the Prefabricated block on upper strata then is put down compacting, but since step surface and slurry itself flow The limitation of property, two layers of Prefabricated block can not be fully connected closely, and slurry can not be realized good between two layers of Prefabricated block Filling effect is susceptible to crack, makes permeable inside and outside well body.
The content of the invention
(1) technical problems to be solved
It can not hold in connection the technical problem to be solved by the present invention is to solve existing ground well body Prefabricated block structure The problem of easily there is crack, cause well body permeable.
(2) technical solution
In order to solve the above technical problem, the present invention provides a kind of structure of ground well body, including multilayer Prefabricated block, Prefabricated block described in adjacent two layers is connected by concave-convex tenon portion, and the bumps tenon portion includes the groove to cooperate and protrusion, institute Stating has gap between groove and the protrusion, waterproof material is filled in the gap.
Wherein, the waterproof material includes water-proof strip and waterproof mortar.
Wherein, the surface that wall in surface well body is formed on the Prefabricated block is equipped with multigroup reserving for installs connector Hole, preformed hole described in every group include two blind holes laterally arranged side by side, the preformed hole pair described in adjacent two layers on Prefabricated block It is neat to set.
Wherein, the connector includes turnbarrel and two connecting rods, and the connecting rod is right angle bending, including water Flat bar and vertical bar, the inner wall of the turnbarrel have two sections of reverse threads, and two vertical bars are inserted into the rotation respectively The both ends of rotaring sleeve, and be threadedly coupled with the turnbarrel, two horizon bars are inserted into prefabricated described in adjacent two layers respectively In module in the corresponding preformed hole.
Wherein, Prefabricated block described in multilayer includes top-level module, bottom module and one or more layers middle level module.
Wherein, it is additionally provided with hole for hoist in the bottom module.
The present invention also provides a kind of construction methods of ground well body, comprise the following steps:
S1 is positioned at the Prefabricated block of lower floor;
S2 places steel plate in the top surface of Prefabricated block;
S3, making rolls same layer road structure layer around Prefabricated block;
S4 removes steel plate, and water-proof strip is placed in the groove of Prefabricated block and fills waterproof mortar;
S5, by the groove of the Prefabricated block of the embedded lower floor of protrusion of the Prefabricated block on upper strata, and by the prefabricated molds on upper strata Block leveling;
S6 repeats step S2 to step S5, until reaching the establishment height of ground well body.
Wherein, it is further comprising the steps of between step S5 and step S6:
Two connecting rods of connector are inserted into the preformed hole of Prefabricated block on upper strata and the prefabricated molds of lower floor by S51 respectively In the preformed hole of block;
S52, the turnbarrel of rotary connector further the Prefabricated block of the Prefabricated block on upper strata and lower floor fastening.
Wherein, after step S4, when the Prefabricated block of connector connection is three layers, after step S5, tear open Except the connector positioned at lower floor.
(3) advantageous effect
The above-mentioned technical proposal of the present invention has the following advantages that:Well body structure in ground of the present invention is made using concave-convex tenon portion structure For the jointing between levels Prefabricated block, waterproof material is placed in groove, is fallen in the Prefabricated block installation process of upper strata, protrusion Into groove, the gap that waterproof material makes it be full of between protrusion and groove is squeezed, waterproof material can also pass through crimping section and overflow, arrive Surface up on the outside of Prefabricated block fovea superior tenon portion effectively prevents waterproof material lack of fill and generates crack, the structure of concave-convex tenon portion It makes and the cooperation of waterproof material, prevents the inside and outside infiltration of well body, further improve the water proofing property for the well body that Prefabricated block connects and composes Energy.
Except it is described above present invention solves the technical problem that, form technical solution technical characteristic and have this Outside advantage caused by the technical characteristic of a little technical solutions, what other technical characteristics of the invention and these technical characteristics were brought Advantage will be further illustrated with reference to attached drawing.
Description of the drawings
Fig. 1 is the structure diagram of the middle level module of ground of embodiment of the present invention well body structure;
Fig. 2 is the structure diagram of the top-level module of ground of embodiment of the present invention well body structure;
Fig. 3 is the structure diagram of the bottom module of ground of embodiment of the present invention well body structure;
Fig. 4 is the structure diagram of ground of embodiment of the present invention well body structure;
Fig. 5 is the preformed hole of ground of embodiment of the present invention well body structure and the structure diagram of connector;
Fig. 6 is the structure diagram of the waterproof material of ground of embodiment of the present invention well body structure;
Fig. 7 is the structural representation after the completion of the step S1 to step S3 of the construction method of ground of embodiment of the present invention well body Figure;
Fig. 8 is the structural representation after the completion of the step S4 to step S5 of the construction method of ground of embodiment of the present invention well body Figure;
Fig. 9 is the structure diagram after the completion of the step S6 of the construction method of ground of embodiment of the present invention well body;
Figure 10 is the structure diagram of inspection shaft of the embodiment of the present invention.
In figure:1:Prefabricated block;2:Concave-convex tenon portion;3:Waterproof material;4:Connector;5:Top-level module;6:Bottom module;7: Middle level module;8:Steel plate;10:Road structure layer;11:Preformed hole;21:Groove;22:Protrusion;31:Water-proof strip;32:Waterproof sand Slurry;41:Turnbarrel;42:Connecting rod;61:Hole for hoist;111:Blind hole;101:Well head;102:Base course;103:It goes to a grassroots level; 104:Cutting optimal bituminous concrete;105:Superficial layer bituminous concrete;106:Base course pit shaft upper module;107:Well room cover board mould Block.
Specific embodiment
To make the purpose, technical scheme and advantage of the embodiment of the present invention clearer, below in conjunction with the embodiment of the present invention In attached drawing, the technical solution in the embodiment of the present invention is clearly and completely described, it is clear that described embodiment is The part of the embodiment of the present invention, instead of all the embodiments.Based on the embodiments of the present invention, ordinary skill people Member's all other embodiments obtained on the premise of creative work is not made, belong to the scope of protection of the invention.
In the description of the present invention, it is necessary to illustrate, unless otherwise clearly defined and limited, term " installation ", " phase Even ", " connection " should be interpreted broadly, for example, it may be being fixedly connected or being detachably connected or be integrally connected;It can To be mechanical connection or be electrically connected;It can be directly connected, can also be indirectly connected by intermediary, Ke Yishi Connection inside two elements.For the ordinary skill in the art, with concrete condition above-mentioned term can be understood at this Concrete meaning in invention.
In addition, in the description of the present invention, unless otherwise indicated, " multiple ", " more ", " multigroup " be meant that two or Two or more, " several ", " several ", " several groups " are meant that one or more.
As shown in Figure 1, Figure 2, Figure 3 and Figure 4, well body structure in ground provided in an embodiment of the present invention, including multilayer prefabricated molds Block 1, adjacent two layers Prefabricated block 1 are connected by concave-convex tenon portion 2, and concave-convex tenon portion 2 includes the groove 21 to cooperate and protrusion 22, Between groove 21 and protrusion 22 there is gap, waterproof material 3 is filled in gap.
Well body structure in ground of the present invention is using concave-convex tenon portion structure as the jointing between levels Prefabricated block, groove Middle placement waterproof material, falls in the Prefabricated block installation process of upper strata, protrudes out into groove, squeeze waterproof material make its full of protrusion with Gap between groove, waterproof material can also pass through crimping section and overflow, reach the surface on the outside of Prefabricated block fovea superior tenon portion, have Effect avoids waterproof material lack of fill and generates crack, and the cooperation of the construction and waterproof material of concave-convex tenon portion prevents the inside and outside infiltration of well body, Further improve the water resistance for the well body that Prefabricated block connects and composes.
Wherein, as shown in fig. 6, waterproof material 3 includes water-proof strip 31 and waterproof mortar 32.First water-proof strip is inserted in groove, Waterproof mortar is injected into groove again, with groove is protruded out into, waterproof mortar can be extruded full of groove is even overflowed, finally Coagulation forming is fixed levels prefab-form and water-proof strip complete.
Wherein, as shown in figure 5, the surface that wall in surface well body is formed on Prefabricated block 1 is connected equipped with multigroup for installing The preformed hole 11 of device 4, every group of preformed hole 11 include two blind holes 111 laterally arranged side by side, reserved on adjacent two layers Prefabricated block 1 The alignment of hole 11 is set.Prefabricated block is equipped with multigroup equally distributed preformed hole, to prevent from setting up work progress in ground well body In, it causes when rolling supercrust around well body above and below Prefabricated block, double swerve, after two layers of Prefabricated block of completion is piled up, adopts Levels preformed hole is connected with connector, levels Prefabricated block is in clamping connection securely, connector is removed after the completion of construction.In advance It boxes out for two transverse directions blind hole composition arranged side by side, two connectors being staggeredly located and two layers of connection that one group of preformed hole connects Device can fix three layers of Prefabricated block, and blind hole can also prevent leak.
Wherein, connector 4 includes turnbarrel 41 and two connecting rods 42, and connecting rod 42 is right angle bending, including water Flat bar and vertical bar, the inner wall of turnbarrel 41 have two sections of reverse threads, and two vertical bars are inserted into turnbarrel 41 respectively Both ends, and two vertical bars are threadedly coupled with turnbarrel 41, two horizon bars are inserted into phase on adjacent two layers Prefabricated block 1 respectively In corresponding preformed hole 11.In the preformed hole that module is reserved during the connecting rod insertion of connector, turnbarrel, two connections are screwed Bar is respectively along ice cream cone axial direction is opposite or relative motion, therefore drive adjacent two layers Prefabricated block mobile and compress.
Wherein, as shown in figure 4, multilayer Prefabricated block 1 includes top-level module 5, bottom module 6 and one or more layers middle level mould Block 7.The outside of middle level module 7 and bottom module 6 is base course 102, and the outside of top-level module 5 is go to a grassroots level 103, and top layer mould Block 5 has been also connected with multilayer bearing well head 101, and the outside of well head 101 is laid with superficial layer bituminous concrete 105 and cutting optimal pitch mixes Solidifying soil 104, top-level module only have protrusion in bottom surface, and bottom module only has groove in top surface.
Wherein, it is additionally provided with hole for hoist 61 in bottom module 6.Preformed hole on Prefabricated block can be used for lifting and connector, But bottom module volume is big and heavier, so setting up hole for hoist.
In embodiments of the present invention, the bottom surface of Prefabricated block is equipped with protrusion, and top surface is equipped with groove, and protrusion and groove are Inverted trapezoidal is directly embedded into groove convenient for protrusion and squeezes waterproof material.
As shown in Figure 7, Figure 8 and Figure 9, the embodiment of the present invention additionally provides the construction method of ground well body, including following step Suddenly:
S1 is positioned at the Prefabricated block 1 of lower floor;
S2 places steel plate 8 in the top surface of Prefabricated block 1;
S3, making rolls same layer road structure layer 10 around Prefabricated block 1;Roll road structure layer 10 be densified to it is close Solidity requirement, and structural material on steel plate is cleared up at any time;
S4 removes steel plate 8, and water-proof strip is placed in the groove of Prefabricated block 1 and fills waterproof mortar;
S5, by the groove of the Prefabricated block 1 of the embedded lower floor of protrusion of the Prefabricated block 1 on upper strata, and by the prefabricated of upper strata 1 leveling of module;
S6 repeats step S2 to step S5, until reaching the establishment height of ground well body.
The construction method of ground well body of the present invention is in construction by layer of the Prefabricated block upper surface than same layer road structure layer Push up the thickness of a low steel plate, such as 10mm, in order to place steel plate in top surface after installation is complete in Prefabricated block, steel plate can prevent It is fallen into when making rolls same layer road structure layer in the upper surface of crushing Prefabricated block and groove inner channel pipeline material and well After the completion of making, steel plate is opened when placing upper strata Prefabricated block, removes steel plate, clears up groove again for people and sundries, then into groove Water-proof strip and waterproof mortar are placed, can effectively be avoided according to the construction method progress well body construction of ground well body of the present invention prefabricated Intermodule waterproof material lack of fill generates crack, and the cooperation of the construction and waterproof material of concave-convex tenon portion prevents the inside and outside infiltration of well body, into One step improves the water resistance for the well body that Prefabricated block connects and composes.
Wherein, it is further comprising the steps of between step S5 and step S6:
S51, two connecting rods of connector 4 are inserted into respectively the Prefabricated block 1 on upper strata preformed hole and lower floor it is prefabricated In the preformed hole of module 1;
S52, the turnbarrel of rotary connector 4 further the Prefabricated block 1 of the Prefabricated block 1 on upper strata and lower floor fastening.
For prevent ground well body set up work progress in, caused when rolling supercrust around well body Prefabricated block up and down, Double swerve after two layers of Prefabricated block of completion is piled up, connects levels preformed hole, by levels Prefabricated block using connector It is in clamping connection securely, connector is removed after the completion of construction.
Wherein, after step S4, when the Prefabricated block 1 that connector 4 connects is three layers, after step S5, dismounting is located at The connector 4 of lower floor.The connector of dismounting can be used in turn.
It is constructed using the Prefabricated block thickness hierarchical synchronization identical with each structure sheaf lift height of road.According to design or former There is the road practice, determine Prefabricated block height and quantity, so as to carry out Prefabricated block processing.The present invention is suitable for inspection shaft or rain The well body construction at the mouth of a river.As shown in Figure 10, the inspection shaft set up for the Prefabricated block of the application present invention, compared with than in above-mentioned implementation Ground well body structure in example, inspection shaft well body is interted in middle level module 7 as needed adds base course pit shaft upper module 106 and well room cover plate module 107, the wherein structure of base course pit shaft upper module 106 and well room cover plate module 107 and above-mentioned implementation Prefabricated block in example is essentially identical.
In conclusion well body structure in ground of the present invention and construction method use concave-convex tenon portion structure as levels prefabricated molds Jointing between block places waterproof material in groove, falls in the Prefabricated block installation process of upper strata, protrude out into groove, squeezes Waterproof material makes it, and full of the gap between protrusion and groove, waterproof material can also pass through crimping section and overflow, and reach on Prefabricated block Surface on the outside of concave-convex tenon portion effectively prevents waterproof material lack of fill and generates crack, the construction of concave-convex tenon portion and waterproof material Cooperation prevents the inside and outside infiltration of well body, further improves the water resistance for the well body that Prefabricated block connects and composes.
Finally it should be noted that:The above embodiments are merely illustrative of the technical solutions of the present invention, rather than its limitations;Although The present invention is described in detail with reference to the foregoing embodiments, it will be understood by those of ordinary skill in the art that:It still may be used To modify to the technical solution recorded in foregoing embodiments or carry out equivalent substitution to which part technical characteristic; And these modification or replace, do not make appropriate technical solution essence depart from various embodiments of the present invention technical solution spirit and Scope.

Claims (9)

1. a kind of ground well body structure, it is characterised in that:Including multilayer Prefabricated block, Prefabricated block described in adjacent two layers passes through recessed Tenon portion connects, and the bumps tenon portion includes the groove to cooperate and protrusion, between having between the groove and the protrusion Gap fills waterproof material in the gap.
2. well body structure in ground according to claim 1, it is characterised in that:The waterproof material includes water-proof strip and Waterproof sand Slurry.
3. well body structure in ground according to claim 1, it is characterised in that:It is formed on the Prefabricated block in surface well body The surface of wall is equipped with multigroup preformed hole for installs connector, and preformed hole described in every group includes two blind holes laterally arranged side by side, Preformed hole alignment described in adjacent two layers on Prefabricated block is set.
4. well body structure in ground according to claim 3, it is characterised in that:The connector includes turnbarrel and two Connecting rod, the connecting rod is right angle bending, and including horizon bar and vertical bar, the inner wall of the turnbarrel has two sections instead To screw thread, two vertical bars are inserted into the both ends of the turnbarrel respectively, and are threadedly coupled with the turnbarrel, two The horizon bar is inserted into described in adjacent two layers on Prefabricated block respectively in the corresponding preformed hole.
5. the ground well body structure according to claim 1-4 any one, it is characterised in that:Prefabricated block bag described in multilayer Include top-level module, bottom module and one or more layers middle level module.
6. well body structure in ground according to claim 5, it is characterised in that:Hole for hoist is additionally provided in the bottom module.
7. a kind of construction method of ground well body, it is characterised in that:Comprise the following steps:
S1 is positioned at the Prefabricated block of lower floor;
S2 places steel plate in the top surface of Prefabricated block;
S3, making rolls same layer road structure layer around Prefabricated block;
S4 removes steel plate, and water-proof strip is placed in the groove of Prefabricated block and fills waterproof mortar;
S5, by the groove of the Prefabricated block of the embedded lower floor of protrusion of the Prefabricated block on upper strata, and by the Prefabricated block tune on upper strata It is flat;
S6 repeats step S2 to step S5, until reaching the establishment height of ground well body.
8. the construction method of ground well body according to claim 1, it is characterised in that:Between step S5 and step S6, It is further comprising the steps of:
Two connecting rods of connector are inserted into the preformed hole of the Prefabricated block on upper strata and the Prefabricated block of lower floor by S51 respectively In preformed hole;
S52, the turnbarrel of rotary connector further the Prefabricated block of the Prefabricated block on upper strata and lower floor fastening.
9. the construction method of ground well body according to claim 7, it is characterised in that:After step S4, when the connection When the Prefabricated block of device connection is three layers, after step S5, the connector positioned at lower floor is removed.
CN201710787082.2A 2017-09-04 2017-09-04 A kind of ground well body structure and construction method Pending CN108104166A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710787082.2A CN108104166A (en) 2017-09-04 2017-09-04 A kind of ground well body structure and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710787082.2A CN108104166A (en) 2017-09-04 2017-09-04 A kind of ground well body structure and construction method

Publications (1)

Publication Number Publication Date
CN108104166A true CN108104166A (en) 2018-06-01

Family

ID=62206674

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710787082.2A Pending CN108104166A (en) 2017-09-04 2017-09-04 A kind of ground well body structure and construction method

Country Status (1)

Country Link
CN (1) CN108104166A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109435023A (en) * 2018-11-29 2019-03-08 北京市政路桥管理养护集团有限公司 For ground well body structure Prefabricated block mold and method is applied in combination
CN114960747A (en) * 2022-06-13 2022-08-30 北京韩建河山管业股份有限公司 Large-diameter PCCP exhaust valve chamber and construction process thereof

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0791692A1 (en) * 1996-02-21 1997-08-27 Colle S.P.A. Method for manufacturing a manhole and manhole made by the method
CN202324159U (en) * 2011-11-17 2012-07-11 天津永壮水泥制品有限公司 Combined prefabricated reinforced concrete sewage and rainwater inspection well
CN103469825A (en) * 2013-09-04 2013-12-25 中建三局第一建设工程有限责任公司 Prefabricated water-resistant post-pouring belt formwork and installation method
CN103850437A (en) * 2014-01-27 2014-06-11 广西矿建集团有限公司 Detachable stair step template and installing method thereof
CN104358337A (en) * 2014-10-11 2015-02-18 安徽湖滨建设集团有限公司 Light-weight composite floor slab structure for assembling integral prefabricated double thin plates, and construction method
CN104831752A (en) * 2015-04-16 2015-08-12 北京市政路桥管理养护集团有限公司 Prefabricated inspection well and construction method thereof
CN105544976A (en) * 2015-12-29 2016-05-04 国家电网公司 Gallery side wall formwork positioning device and method
CN205444893U (en) * 2016-02-24 2016-08-10 中国建筑第二工程局有限公司 Template system is pour to rectangle post structure
CN205617425U (en) * 2016-05-10 2016-10-05 湖南恒致工程技术有限公司 Prefabricated structure of assembling of utility tunnel
CN207714376U (en) * 2017-09-04 2018-08-10 北京市政路桥管理养护集团有限公司 A kind of ground well body structure

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0791692A1 (en) * 1996-02-21 1997-08-27 Colle S.P.A. Method for manufacturing a manhole and manhole made by the method
CN202324159U (en) * 2011-11-17 2012-07-11 天津永壮水泥制品有限公司 Combined prefabricated reinforced concrete sewage and rainwater inspection well
CN103469825A (en) * 2013-09-04 2013-12-25 中建三局第一建设工程有限责任公司 Prefabricated water-resistant post-pouring belt formwork and installation method
CN103850437A (en) * 2014-01-27 2014-06-11 广西矿建集团有限公司 Detachable stair step template and installing method thereof
CN104358337A (en) * 2014-10-11 2015-02-18 安徽湖滨建设集团有限公司 Light-weight composite floor slab structure for assembling integral prefabricated double thin plates, and construction method
CN104831752A (en) * 2015-04-16 2015-08-12 北京市政路桥管理养护集团有限公司 Prefabricated inspection well and construction method thereof
CN105544976A (en) * 2015-12-29 2016-05-04 国家电网公司 Gallery side wall formwork positioning device and method
CN205444893U (en) * 2016-02-24 2016-08-10 中国建筑第二工程局有限公司 Template system is pour to rectangle post structure
CN205617425U (en) * 2016-05-10 2016-10-05 湖南恒致工程技术有限公司 Prefabricated structure of assembling of utility tunnel
CN207714376U (en) * 2017-09-04 2018-08-10 北京市政路桥管理养护集团有限公司 A kind of ground well body structure

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
杨嗣信等: "建筑工程模板施工手册", 中国建筑工业出版社, pages: 208 - 212 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109435023A (en) * 2018-11-29 2019-03-08 北京市政路桥管理养护集团有限公司 For ground well body structure Prefabricated block mold and method is applied in combination
CN109435023B (en) * 2018-11-29 2023-11-21 北京市政路桥管理养护集团有限公司 Die for ground well body structure prefabricated module and combined use method
CN114960747A (en) * 2022-06-13 2022-08-30 北京韩建河山管业股份有限公司 Large-diameter PCCP exhaust valve chamber and construction process thereof
CN114960747B (en) * 2022-06-13 2024-02-27 北京韩建河山管业股份有限公司 Large-caliber PCCP (prestressed concrete cylinder pipe) exhaust valve chamber and construction process thereof

Similar Documents

Publication Publication Date Title
CN104563288B (en) Reinforced concrete frame gridding slab prefabricated energy-saving house
CN105926804B (en) A kind of reinforcement means of 3D printing reinforced masonry shear wall
CN104358337B (en) Light-weight composite floor slab structure for assembling integral prefabricated double thin plates, and construction method
CN106677440A (en) Roofing parapet water-floating structure and construction method thereof
CN208266618U (en) A kind of road and bridge crack construction reinforcing connection structure
CN102041845A (en) United draining system for effectively lowering seepage lines in fill dam of tailing reservoir
CN208072809U (en) A kind of whole perception type stair of raising
CN105297685B (en) Base concrete panel rock-fill dam and construction method thereof
CN106499070A (en) The construction method of connecting sewing between assembled architecture component and component
CN111764522A (en) Anti-leakage building floor post-cast strip structure and pouring method
CN107165177A (en) A kind of side slope supporting construction method
CN108797636A (en) A kind of upper font retaining wall structure and its construction method
CN108104166A (en) A kind of ground well body structure and construction method
CN105089072B (en) Anti-seepage structure of basement bottom board and construction method
CN108104287B (en) Concrete structure and the segmentation casting method for utilizing the concrete structure
CN108240045A (en) A kind of compound late poured band structure of outer wall precast slab and its construction method
CN207714376U (en) A kind of ground well body structure
CN105133619A (en) Construction method for deep foundation pit of elevator shaft
CN207348229U (en) A kind of connection structure of caisson and partition wall
CN204825545U (en) Make things convenient for prepackage type cement road structure of drainage
CN104631393B (en) A kind of rock-fill dams asphalt concrete face slab structure based on steel wire
CN104314047B (en) Water-bag type concrete works movement joint sealing swaging die and its manufacture and construction method
CN207525736U (en) Diaphram wall connection structure
CN207145004U (en) A kind of constructing structure of tunnel arch wall pin anti-seep water
CN207144477U (en) The clear-water concrete exposed joint strip template of Measurement of Elevator tower

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20180601

RJ01 Rejection of invention patent application after publication