CN106499070A - The construction method of connecting sewing between assembled architecture component and component - Google Patents

The construction method of connecting sewing between assembled architecture component and component Download PDF

Info

Publication number
CN106499070A
CN106499070A CN201510563573.XA CN201510563573A CN106499070A CN 106499070 A CN106499070 A CN 106499070A CN 201510563573 A CN201510563573 A CN 201510563573A CN 106499070 A CN106499070 A CN 106499070A
Authority
CN
China
Prior art keywords
sleeper
component
grouting
concrete
colligation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510563573.XA
Other languages
Chinese (zh)
Other versions
CN106499070B (en
Inventor
范振江
姜云剑
武克辰
姜顺
刘峰
梁府
姚树国
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Baoye Group Corp Ltd
Original Assignee
Shanghai Baoye Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Baoye Group Corp Ltd filed Critical Shanghai Baoye Group Corp Ltd
Priority to CN201510563573.XA priority Critical patent/CN106499070B/en
Publication of CN106499070A publication Critical patent/CN106499070A/en
Application granted granted Critical
Publication of CN106499070B publication Critical patent/CN106499070B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The present invention relates to the realm of building construction, the construction method of connecting sewing between specifically a kind of assembled architecture component and component;It is characterized in that:Comprise the steps;Step 1, sleeper reinforcing bar colligation;Step 2, electric wire box and spool is buried in the sleeper reinforcing bar;Step 3, installation sleeper formwork for placing:Step 4, sleeper concreting;Step 5, prefabricated panel grouting;Step 6, precast facade level, vertical joint waterproofing construction.This construction method is easy to implement, can effectively ensure that the construction quality in gap between assembled architecture component, and then guarantees the waterproof construction quality of assembled architecture.

Description

The construction method of connecting sewing between assembled architecture component and component
Technical field
The present invention relates to the realm of building construction, the construction method of connecting sewing between specifically a kind of assembled architecture component and component.
Background technology
The vertical member of assembled-type house precast construction is combined by cast-in-place node by prefabricated panel and cast-in-place shear wall, as assembled architecture is made up of splicing prefabricated components, there is gap problem between prefabricated components, junction construction technology is even more important to performances such as the waterproofs subsequently built.
Content of the invention
It is an object of the invention to improve to the junction construction quality of/vertical seam and then ensureing the waterproof construction quality of assembled architecture for the level between assembled architecture component and component.
In order to achieve the above object, the present invention is realized in:
The construction method of connecting sewing between a kind of assembled architecture component and component;Comprise the steps;
Step 1, sleeper reinforcing bar colligation;
Step 1.1, panels are lifted in place;
Step 1.2, colligation sleeper stirrup and sleeper indulge muscle:According to stirrup spacing, by interim for stirrup colligation on the closing ring of component, vertical for sleeper muscle is vertically penetrated in stirrup from top, and is connected with the reserved joint bar of next layer of sleeper;Adjustment stirrup spacing, by stirrup and the reliability colligation of vertical muscle;
Step 1.3, colligation sleeper lacing wire;
Step 2, electric wire box and spool is buried in the sleeper reinforcing bar;Line box, spool and the colligation of sleeper reinforcing bar positioning;
Step 3, installation sleeper formwork for placing:" one " font or the cast-in-place sleeper of " L " type between two module component plates, using inner side single side formwork, outboard template is by the use of precast wall panel as exterior sheathing;Wherein, use foam strip joint seal, base gap to be tamped with cement mortar between inner side template left and right sides and precast member board, prevent running pulp;Counter screw shuttering adopts full flight screw, screw rod one end to be screwed in the sleeve being embedded on the inside of prefabricated panel, and the other end is fastened with nut using conventional chevron card;20mm gaps between two pieces of precast wall panels autohension rubber bar joint seal;
Step 4, sleeper concreting;
The installation quality of step 4.1, the template at examination concreting position, reinforcing bar, built-in fitting and pipeline, it is ensured that meet design requirement;
Step 4.2, poured in sleeper template bottom to subtract stone 30~50mm of cement mortar with concrete mix identical;
Step 4.3, concreting in lifts;Wherein, the layering blanking thickness that layering scale bar controls concrete is made, and placement layer by layer thickness takes 400mm;Levels can not be more than the concrete initial set time interval time;Step 4.4, layering vibrated concrete, are not more than 30cm per thickness degree;
Step 4.5, concrete are conserved with water law, brush sealing compound, parcel Polypropylence Sheet is poured;
After step 4.6, concrete strength reach 70%, dismountable support, and support is proceeded to next work surface use;
Step 5, prefabricated panel grouting;
Step 5.1, after the completion of the cast-in-place sleeper in prefabricated panel both sides and cast-in-situ floor concreting, the full hall frame of floor carries out prefabricated panel grouting operation after removing;
Step 5.2, it is in the milk with grout sleeve:From grout sleeve bottom, PVC grout holes are poured into successively, represent when its corresponding top PVC spout hole emerges grouting material and filled in grouting cylinder, spout hole is blocked using cork tight after filling, continue to hold pressure after 30 seconds, then with cork by grouting hole plugging;Within 4 hours after the completion of step 5.3, grouting, prefabricated panel must not be vibrated.
Step 6, precast facade level, vertical joint waterproofing construction:One material waterproofing inside precast wall body, is pasted on panel tops before lifting component dropping place;After another road material waterproofing is topping out, exterior coating has been constructed, alien invasion waterproof construction is carried out using hanging basket.
This construction method is easy to implement, can effectively ensure that the construction quality in gap between assembled architecture component, and then guarantees the waterproof construction quality of assembled architecture.
Description of the drawings
Fig. 1 builds schematic diagram for body of wall sleeper.
Fig. 2 builds schematic diagram for sleeper template.
Fig. 3 is prefabricated panel grout sleeve grouting schematic diagram.
Fig. 4 is horizontal joint waterproofing organigram.
Fig. 5 is vertical joint waterproofing organigram.
Specific embodiment
The present invention is further illustrated below by way of specific embodiment.
Between a kind of assembled architecture component and component, the construction method of connecting sewing, comprises the steps:
1st, cast-in-place sleeper reinforcing bar colligation
Different according to precast wall panel species, Side fascia both sides reserved steel bar has following three kinds:The dark depth of beam scope in top reserves dark beam longitudinal reinforcement(YWQ), the reserved level of body of wall overall height scope is to closed stirrup(YSQ), and body of wall overall height scope reserve vertical closed stirrup (YNQ), the colligation order of the cast-in-place sleeper variety classes reinforcing bar in its both sides is also had any different.
Shear wall slab(YSQ)Both sides sleeper reinforcement installation
As shown in figure 1, reinforcement installation order:Shear wall slab(YSQ)Lift the vertical muscle of in place → sleeper stirrup installation → sleeper and lacing wire is installed;
After the lifting of precast shear wall plate is in place, the installation of sleeper stirrup is first carried out, according to stirrup spacing, by interim for stirrup colligation on the closing ring of component;Vertical for sleeper muscle is vertically penetrated in stirrup from top, and is connected with the reserved joint bar of next layer of sleeper;Adjustment stirrup spacing, by stirrup and the reliability colligation of vertical muscle;The lacing wire of last colligation sleeper.
2nd, electric wire box, spool are buried
In sleeper reinforcing bar process of binding, coordinate electric wire box, spool embedded.In order to prevent position skew when embedded of various electromechanical built-in pipes and line box, firm with cage bar colligation using the additional spacer bar that has worn during use.
3rd, cast-in-place sleeper model sheetinstallat
As shown in Fig. 2 " one " font or the cast-in-place sleeper of " L " type between two pieces of prefabricated panels, using inner side single side formwork, outboard template is by the use of precast wall panel as exterior sheathing.Use foam strip joint seal, base gap to be tamped with cement mortar between inner side template left and right sides and prefabricated panel, prevent running pulp.Counter screw shuttering adopts full thread M14 screw rods, screw rod one end to be screwed in the sleeve being embedded on the inside of prefabricated panel, and the other end is fastened with nut using conventional chevron card.
20mm gaps between two pieces of precast wall panels autohension rubber bar joint seal.
4th, cast-in-place sleeper concreting
1)The template at concreting position, reinforcing bar, built-in fitting and pipeline etc. are all installed, and are met design requirement on inspection, and are finished hidden, preliminary examination formality.
2)Before sleeper concreting, first poured in bottom to subtract stone 30~50mm of cement mortar with concrete mix identical, then casting concrete again.
3)During concreting in lifts, the layering blanking thickness that layering scale bar controls concrete to be made, placement layer by layer thickness takes 400mm or so.Levels can not be more than the concrete initial set time interval time;Vibrating head shakes and a little uniformly will prevent leakage is shaken.
4)Concrete should be layered and vibrate, and be not more than 30cm per thickness degree.When vibrating vibrating head will " fast insert pull out slowly ", fast inserting is to prevent surface concrete jolt ramming is produced laminated segregation with bottom concrete first.Slowly pull out is in order that concrete can fill up caused cavity when vibrator is extracted out, and can draw the bubble in concrete.
5)Concrete curing
(1)Walls concrete adopts water seasoning, irrigation times to be defined in dampness to ensure concrete wall surface.
(2)Brush sealing compound after the completion of concreting, parcel Polypropylence Sheet are conserved.
(3)Normal concrete curing time must not be less than seven days, and water-proof concrete curing time must not be less than fortnight.
(4)Summer high temperature weather is too fast for preventing young concrete surface moisture to scatter and disappear, conserved after concreting in time, water seasoning number of times is increased according to practical situation and ensures surface wettability, covered with Polypropylence Sheet if necessary tight, and keep in Polypropylence Sheet, having condensate, prevent the appearance of concrete cracks.
(5)After cast-in-place concrete intensity reaches 70%, dismountable temporary support proceeds to next work surface and uses.
5th, prefabricated panel grouting
As shown in figure 3,
1)Grouting operation
(1)The grouting operation time:In prefabricated panel both sides, cast-in-place sleeper and cast-in-situ floor concreting are completed, and the full hall frame of floor carries out grouting operation after removing.
(2)Prefabricated panel grout sleeve is in the milk, from grout sleeve bottom, PVC grout holes are poured into successively, represent when its corresponding top PVC spout hole emerges grouting material and filled in grouting cylinder, spout hole is blocked using cork after filling tight, after continuing to hold pressure 30s, then with cork by grouting hole plugging.
(3)During grouting construction, test cube in the same condition and test specimen need to be made.Grouting material needs indwelling test cube in the same condition, and per one group of test block of every layer of building indwelling, 3 pieces per group, test block specification is 40*40*160mm;Grouting operation often completes 500 reinforcing steel bar connecting sleeve tubes and makees one group of test specimen, and 3 joints of every group of test specimen, during test specimen indwelling, need to operate on dispenser and complete to be in the milk, and rower of going forward side by side is supported 28 days and conserved.As shown in figure figure below:
(4)Blender, agitator, the grouting utensil such as cylinder are cleaned in grouting immediately after finishing, in order to avoid grouting material solidification, cleaning is difficult, and the cylinder that notes being in the milk need to often be irrigated after completing one and be cleaned once, clean and can reuse after finishing.So should at least prepare three grouting cylinders in each teams and groups' grouting operation, wherein one standby.
(5)After the completion of grouting within 4 hours, prefabricated panel must not be vibrated.
6th, precast facade level, vertical joint waterproofing construction
As shown in figure 4, precast facade horizontal joint waterproofing is constructed in the form of one constructional waterproofing adds twice material waterproofing.One material waterproofing inside precast wall body(Hollow rubber waterstop), before lifting component dropping place, it is pasted on panel tops;Another road material waterproofing(Elastoplast rod and synthesis polymeric seal cream)Topping out, after exterior coating constructed, alien invasion waterproof construction is carried out using hanging basket.
As shown in figure 5, precast facade is vertically sewn on cast-in-place sleeper position, its water proof structure adopts one material waterproofing(PE rods+fluid sealant)Form, constructed using hanging basket.

Claims (1)

1. between a kind of assembled architecture component and component connecting sewing construction method;It is characterized in that:Comprise the steps;
Step 1, sleeper reinforcing bar colligation;
Step 1.1, panels are lifted in place;
Step 1.2, colligation sleeper stirrup and sleeper indulge muscle:According to stirrup spacing, by interim for stirrup colligation on the closing ring of component, vertical for sleeper muscle is vertically penetrated in stirrup from top, and is connected with the reserved joint bar of next layer of sleeper;Adjustment stirrup spacing, by stirrup and the reliability colligation of vertical muscle;
Step 1.3, colligation sleeper lacing wire;
Step 2, electric wire box and spool is buried in the sleeper reinforcing bar;Line box, spool and the colligation of sleeper reinforcing bar positioning;
Step 3, installation sleeper formwork for placing:" one " font or the cast-in-place sleeper of " L " type between two module component plates, using inner side single side formwork, outboard template is by the use of precast wall panel as exterior sheathing;Wherein, use foam strip joint seal, base gap to be tamped with cement mortar between inner side template left and right sides and precast member board, prevent running pulp;Counter screw shuttering adopts full flight screw, screw rod one end to be screwed in the sleeve being embedded on the inside of prefabricated panel, and the other end is fastened with nut using conventional chevron card;20mm gaps between two pieces of precast wall panels autohension rubber bar joint seal;
Step 4, sleeper concreting;
The installation quality of step 4.1, the template at examination concreting position, reinforcing bar, built-in fitting and pipeline, it is ensured that meet design requirement;
Step 4.2, poured in sleeper template bottom to subtract stone 30~50mm of cement mortar with concrete mix identical;
Step 4.3, concreting in lifts;Wherein, the layering blanking thickness that layering scale bar controls concrete is made, and placement layer by layer thickness takes 400mm;Levels can not be more than the concrete initial set time interval time;Step 4.4, layering vibrated concrete, are not more than 30cm per thickness degree;
Step 4.5, concrete are conserved with water law, brush sealing compound, parcel Polypropylence Sheet is poured;
After step 4.6, concrete strength reach 70%, dismountable support, and support is proceeded to next work surface use;
Step 5, prefabricated panel grouting;
Step 5.1, after the completion of the cast-in-place sleeper in prefabricated panel both sides and cast-in-situ floor concreting, the full hall frame of floor carries out prefabricated panel grouting operation after removing;
Step 5.2, it is in the milk with grout sleeve:From grout sleeve bottom, PVC grout holes are poured into successively, represent when its corresponding top PVC spout hole emerges grouting material and filled in grouting cylinder, spout hole is blocked using cork tight after filling, continue to hold pressure after 30 seconds, then with cork by grouting hole plugging;Within 4 hours after the completion of step 5.3, grouting, prefabricated panel must not be vibrated;
Step 6, precast facade level, vertical joint waterproofing construction:One material waterproofing inside precast wall body, is pasted on panel tops before lifting component dropping place;After another road material waterproofing is topping out, exterior coating has been constructed, alien invasion waterproof construction is carried out using hanging basket.
CN201510563573.XA 2015-09-08 2015-09-08 The construction method of connecting sewing between assembled architecture component and component Active CN106499070B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510563573.XA CN106499070B (en) 2015-09-08 2015-09-08 The construction method of connecting sewing between assembled architecture component and component

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510563573.XA CN106499070B (en) 2015-09-08 2015-09-08 The construction method of connecting sewing between assembled architecture component and component

Publications (2)

Publication Number Publication Date
CN106499070A true CN106499070A (en) 2017-03-15
CN106499070B CN106499070B (en) 2019-03-15

Family

ID=58287729

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510563573.XA Active CN106499070B (en) 2015-09-08 2015-09-08 The construction method of connecting sewing between assembled architecture component and component

Country Status (1)

Country Link
CN (1) CN106499070B (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108035539A (en) * 2018-01-08 2018-05-15 上海建工二建集团有限公司 A kind of sleeper plate device and the method using its construction assembled building sleeper
CN109505368A (en) * 2018-12-25 2019-03-22 湘潭远大住宅工业有限公司 Wallboard connecting node for assembled architecture
CN110409637A (en) * 2019-08-22 2019-11-05 华北理工大学 A kind of grouting of prefabricated construction seams block apparatus
CN110552440A (en) * 2019-08-16 2019-12-10 青岛一建集团有限公司 safe and environment-friendly construction process for high-strength assembled integral type sandwich heat-insulation shear wall
CN110803902A (en) * 2019-12-09 2020-02-18 盛业建设有限公司 Self-leveling environment-friendly ground construction method
CN111946050A (en) * 2020-07-01 2020-11-17 北京住总第六开发建设有限公司 Aluminum alloy formwork construction method applied to assembly type engineering
CN113338476A (en) * 2021-06-16 2021-09-03 重庆渝能建筑安装工程有限公司 Assembled shear force wall concatenation seam waterproof construction
CN114541774A (en) * 2022-03-28 2022-05-27 中建八局第二建设有限公司 Construction method of assembled building outer wall structure
CN115030398A (en) * 2022-06-30 2022-09-09 中铁二十局集团市政工程有限公司 External wallboard embedded structure and construction method thereof
CN115419464A (en) * 2022-08-03 2022-12-02 中铁第四勘察设计院集团有限公司 Separation device, tunnel and tunnel construction method

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2037758U (en) * 1988-10-14 1989-05-17 宁波市机电工业研究设计院 Assembled commodity house
JP2001227119A (en) * 2000-02-18 2001-08-24 Toshin Komu:Kk Roof top construction method for wooden house
CN103147529A (en) * 2013-04-03 2013-06-12 东南大学 Assembly type energy dissipation and seismic mitigation shear wall structure system
CN103556749A (en) * 2013-10-10 2014-02-05 南京工业大学 Suspension type flexible connection for precast concrete infilled wall
CN104264798A (en) * 2014-09-12 2015-01-07 北京首钢建设集团有限公司 Method for constructing prefabricated cladding panel and steel frame column split joint seam
CN104452961A (en) * 2014-12-08 2015-03-25 上海应用技术学院 Rural low-rise assembled damping building structure system

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2037758U (en) * 1988-10-14 1989-05-17 宁波市机电工业研究设计院 Assembled commodity house
JP2001227119A (en) * 2000-02-18 2001-08-24 Toshin Komu:Kk Roof top construction method for wooden house
CN103147529A (en) * 2013-04-03 2013-06-12 东南大学 Assembly type energy dissipation and seismic mitigation shear wall structure system
CN103556749A (en) * 2013-10-10 2014-02-05 南京工业大学 Suspension type flexible connection for precast concrete infilled wall
CN104264798A (en) * 2014-09-12 2015-01-07 北京首钢建设集团有限公司 Method for constructing prefabricated cladding panel and steel frame column split joint seam
CN104452961A (en) * 2014-12-08 2015-03-25 上海应用技术学院 Rural low-rise assembled damping building structure system

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108035539A (en) * 2018-01-08 2018-05-15 上海建工二建集团有限公司 A kind of sleeper plate device and the method using its construction assembled building sleeper
CN109505368A (en) * 2018-12-25 2019-03-22 湘潭远大住宅工业有限公司 Wallboard connecting node for assembled architecture
CN109505368B (en) * 2018-12-25 2024-05-14 湘潭远大住宅工业有限公司 Wallboard connecting node for assembled building
CN110552440A (en) * 2019-08-16 2019-12-10 青岛一建集团有限公司 safe and environment-friendly construction process for high-strength assembled integral type sandwich heat-insulation shear wall
CN110409637A (en) * 2019-08-22 2019-11-05 华北理工大学 A kind of grouting of prefabricated construction seams block apparatus
CN110803902A (en) * 2019-12-09 2020-02-18 盛业建设有限公司 Self-leveling environment-friendly ground construction method
CN111946050A (en) * 2020-07-01 2020-11-17 北京住总第六开发建设有限公司 Aluminum alloy formwork construction method applied to assembly type engineering
CN113338476A (en) * 2021-06-16 2021-09-03 重庆渝能建筑安装工程有限公司 Assembled shear force wall concatenation seam waterproof construction
CN114541774A (en) * 2022-03-28 2022-05-27 中建八局第二建设有限公司 Construction method of assembled building outer wall structure
CN115030398A (en) * 2022-06-30 2022-09-09 中铁二十局集团市政工程有限公司 External wallboard embedded structure and construction method thereof
CN115030398B (en) * 2022-06-30 2024-01-26 中铁二十局集团市政工程有限公司 External wall board embedded structure and construction method thereof
CN115419464A (en) * 2022-08-03 2022-12-02 中铁第四勘察设计院集团有限公司 Separation device, tunnel and tunnel construction method

Also Published As

Publication number Publication date
CN106499070B (en) 2019-03-15

Similar Documents

Publication Publication Date Title
CN106499070A (en) The construction method of connecting sewing between assembled architecture component and component
CN101818527B (en) Assembled integral shear wall structure system and construction method thereof
CN103821364B (en) The construction method of reinforced concrete water pond
CN103410332B (en) A kind of concrete hollow block reinforcement wall construction technology
CN201687102U (en) Assembled integral type shear wall structure system
CN207582663U (en) Connecting elements between concrete folding plate and shear wall Side fascia
CN103410317A (en) Construction method for site assembly and casting integral wall body by adopting wall body prefabricated part
CN106120870B (en) The advanced enclosed construction of poured band of outer wall of basement and construction method
CN104358337B (en) Light-weight composite floor slab structure for assembling integral prefabricated double thin plates, and construction method
CN209482591U (en) Prefabricated molds shell structure column construction structure
CN107476351B (en) The waterproof method of the assembled prefabricated side wall assembling construction seam in station
CN105464396A (en) Reinforcing method for external wall of protective historical building
CN107503450A (en) A kind of cast-in-place hollow armored concrete filling wall and its construction technology
CN209633298U (en) The prefabricated shell mold molding die of constructional column
CN108277820A (en) The construction method of retaining wall structure
CN104358275B (en) Darker elevator shaft or collecting well construction method
CN207110214U (en) A kind of prefabricated interior fill concrete wallboard
CN102433958A (en) Prefabricated wall board construction member
CN112575886A (en) Low-level and multi-level fully-prefabricated assembled concrete structure and design, production and installation method
CN206233560U (en) Wall formwork erecting structure
CN108396761A (en) The non-fully pile foundation cushion cap and production method under precipitation state inside a kind of foundation pit
CN106284653B (en) A kind of construction method that balcony construct capital interspaces in advance
CN108240045A (en) A kind of compound late poured band structure of outer wall precast slab and its construction method
CN107237448B (en) The prefabricated interior fill concrete wallboard of one kind and its manufacturing method
CN211114261U (en) Precast concrete shear force wall panel structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant