CN106499070B - The construction method of connecting sewing between assembled architecture component and component - Google Patents

The construction method of connecting sewing between assembled architecture component and component Download PDF

Info

Publication number
CN106499070B
CN106499070B CN201510563573.XA CN201510563573A CN106499070B CN 106499070 B CN106499070 B CN 106499070B CN 201510563573 A CN201510563573 A CN 201510563573A CN 106499070 B CN106499070 B CN 106499070B
Authority
CN
China
Prior art keywords
sleeper
component
grouting
concrete
stirrup
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510563573.XA
Other languages
Chinese (zh)
Other versions
CN106499070A (en
Inventor
范振江
姜云剑
武克辰
姜顺
刘峰
梁府
姚树国
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Baoye Group Corp Ltd
Original Assignee
Shanghai Baoye Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Baoye Group Corp Ltd filed Critical Shanghai Baoye Group Corp Ltd
Priority to CN201510563573.XA priority Critical patent/CN106499070B/en
Publication of CN106499070A publication Critical patent/CN106499070A/en
Application granted granted Critical
Publication of CN106499070B publication Critical patent/CN106499070B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The present invention relates to the realm of building construction, the construction method of connecting sewing between specifically a kind of assembled architecture component and component;It is characterized in that: including the following steps;Step 1, the binding of sleeper reinforcing bar;Step 2 buries electric wire box and spool in sleeper reinforcing bar;Step 3, installation sleeper formwork for placing: step 4, sleeper concreting;Step 5, prefabricated panel grouting;Step 6, precast facade are horizontal, vertical joint waterproofing is constructed.This construction method is easy to implement, can effectively ensure that the construction quality in gap between assembled architecture component, and then ensures the waterproof construction quality of assembled architecture.

Description

The construction method of connecting sewing between assembled architecture component and component
Technical field
The present invention relates to the realm of building construction, the construction party of connecting sewing between specifically a kind of assembled architecture component and component Method.
Background technique
The vertical member of assembled-type house precast construction is combined by prefabricated panel and cast-in-place shear wall by cast-in-place node At there is gap problem, junction construction technology between prefabricated components since assembled architecture is made of splicing prefabricated components The performances such as the waterproof to subsequent building are even more important.
Summary of the invention
It is an object of the invention to improve the connection for the horizontal direction between assembled architecture component and component/vertically stitch Locate construction quality and then guarantees the waterproof construction quality of assembled architecture.
In order to achieve the above object, the present invention is implemented as follows:
The construction method of connecting sewing between a kind of assembled architecture component and component;It is characterized in that: including the following steps;
Step 1, the binding of sleeper reinforcing bar;
Step 1.1 lifts panels in place;
Step 1.2, binding sleeper stirrup and sleeper indulge muscle: according to stirrup spacing, stirrup temporarily being bound to the envelope in component It closes on hoop, sleeper is indulged into muscle and is vertically penetrated in stirrup from top, and is connect with the reserved joint bar of next layer of sleeper;Between adjustment stirrup Away from stirrup and vertical muscle are reliably bound;
Step 1.3, binding sleeper lacing wire;
Step 2 buries electric wire box and spool in sleeper reinforcing bar;Wire box, spool and the binding of sleeper reinforcing bar position;
Step 3, installation sleeper formwork for placing: line-styled or the cast-in-place sleeper of " L " type between two module component plates, using interior Side single side formwork, outboard template is using prefabricated outer wall panel as exterior sheathing;Wherein, inner side template left and right sides and prefabricated components Foam strip joint seal is used between plate, bottom edge gap is tamped with cement mortar, prevents running pulp;Counter screw shuttering uses full thread spiral shell Bar, screw rod one end are screwed into the sleeve being embedded on the inside of prefabricated panel, and the other end is fastened using conventional chevron card and nut;Two The gap 20mm tack rubber joint seal between block prefabricated outer wall panel;
Step 4, sleeper concreting;
Step 4.1, the installation quality for checking the template at concreting position, reinforcing bar, built-in fitting and pipeline, it is ensured that meet Design requirement;
Step 4.2, sleeper template bottom pour with it is identical with concrete mix subtract stone cement mortar 30~ 50mm;
Step 4.3, concreting in lifts;Wherein, the layering blanking thickness of production layering scale bar control concrete, point Layer pours thickness and takes 400mm;Upper and lower level interval time cannot be greater than the concrete initial set time;Step 4.4 is layered the coagulation that vibrates Soil, every thickness degree are not more than 30cm;
Step 4.5, concrete are conserved with water law, brush curing agent, package plastic cloth is poured;
After step 4.6, concrete strength reach 70%, dismountable support, and support is transferred to next working face and is used;
Step 5, prefabricated panel grouting;
Step 5.1, after the completion of the cast-in-place sleeper in prefabricated panel two sides and cast-in-situ floor concreting, floor is expired hall frame and is torn open Prefabricated panel grouting operation is carried out after removing;
Step 5.2 is in the milk with grout sleeve: from grout sleeve bottom, PVC grout hole is successively poured into, to its correspondence Top PVC overflow hole emerge grouting material when indicate to have filled in grouting cylinder, overflow hole is blocked after filling using cork Tightly, continue to hold pressure after 30 seconds, then with cork by grouting hole plugging;After the completion of step 5.3, grouting within 4 hours, dry wall Plate must not be vibrated.
Step 6, precast facade are horizontal, vertical joint waterproofing is constructed: one of material waterproofing inside precast wall body is hung in component Panel tops are pasted on before dress dropping place;Another road material waterproofing is carried out after topping out, exterior coating has been constructed using hanging basket Alien invasion waterproof construction.
This construction method is easy to implement, can effectively ensure that the construction quality in gap between assembled architecture component, and then really Protect the waterproof construction quality of assembled architecture.
Detailed description of the invention
Fig. 1 is that wall sleeper builds schematic diagram.
Fig. 2 is that sleeper template builds schematic diagram.
Fig. 3 is prefabricated panel grout sleeve grouting schematic diagram.
Fig. 4 is horizontal joint waterproofing organigram.
Fig. 5 is vertical joint waterproofing organigram.
Specific embodiment
The present invention is further illustrated below by way of specific embodiment.
The construction method of connecting sewing, includes the following steps: between a kind of assembled architecture component and component
1, cast-in-place sleeper reinforcing bar binding
Different according to prefabricated outer wall panel type, Side fascia two sides reserved steel bar has following three kinds: top concealed beam altitude range Reserved concealed beam longitudinal reinforcement (YWQ), wall overall height range reserve horizontal direction closed stirrup (YSQ) and wall overall height range is reserved The binding sequence of vertical closed stirrup (YNQ), the cast-in-place sleeper variety classes reinforcing bar in two sides is also had any different.
The two sides shear wall slab (YSQ) sleeper reinforcement installation
As shown in Figure 1, reinforcement installation sequence: shear wall slab (YSQ) lifts in place → sleeper stirrup installation → sleeper and indulges muscle And lacing wire installation;
After the lifting of precast shear wall plate is in place, the installation for first carrying out sleeper stirrup temporarily ties up stirrup according to stirrup spacing It pricks on the closing ring of component;Sleeper is indulged muscle vertically to penetrate in stirrup from top, and is connected with the reserved joint bar of next layer of sleeper It connects;Stirrup spacing is adjusted, stirrup and vertical muscle are reliably bound;Finally bind the lacing wire of sleeper.
2, electric wire box, spool are embedded
In sleeper reinforcing bar process of binding, cooperation electric wire box, spool it is embedded.Various electromechanical built-in pipes and line in order to prevent Box positional shift when embedded is bound using the additional spacer bar and main reinforcement worn when use secured.
3, cast-in-place sleeper template installation
As shown in Fig. 2, line-styled or the cast-in-place sleeper 1 of " L " type between two pieces of prefabricated panels, using inside unilateral side branch Mould, outboard template is using prefabricated outer wall panel 2 as exterior sheathing.Foam is used between 3 left and right sides of inner side template and prefabricated panel 2 Joint seal, bottom edge gap are tamped with cement mortar, prevent running pulp.Counter screw shuttering 4 uses full thread M14 screw rod, screw rod one End is screwed into the sleeve being embedded on the inside of prefabricated panel, and the other end is fastened using conventional chevron card and nut.
The gap 20mm tack rubber joint seal between two pieces of prefabricated outer wall panels.
4, cast-in-place sleeper concreting
1) template at concreting position, reinforcing bar, built-in fitting and pipeline etc. all install, and meet design on inspection It is required that and finishing hidden, preliminary examination formality.
2) it before sleeper concreting, is first poured in bottom and subtracts stone cement mortar 30 with identical with concrete mix ~50mm, then casting concrete again.
3) when concreting in lifts, the layering blanking thickness of layering scale bar control concrete, placement layer by layer to be made Thickness takes 400mm or so.Upper and lower level interval time cannot be greater than the concrete initial set time;Vibrating head vibration point will be prevented uniformly Leakage.
4) concrete should be layered and vibrate, and every thickness degree is not more than 30cm.Vibrating head is wanted " fast insert is pulled out slowly " when vibrating, fast to insert It is that surface concrete jolt ramming is first generated into laminated segregation with lower part concrete in order to prevent.Slowly pulling out is to enable concrete to fill out Caused cavity when full vibrator extraction, and the bubble in concrete can be drawn.
5) concrete curing
(1) walls concrete uses water seasoning, and irrigation times, which are subject to, guarantees concrete wall surface in dampness.
(2) brush curing agent after the completion of concreting, package plastic cloth are conserved.
(3) normal concrete curing time must not be less than seven days, and water-proof concrete curing time must not be less than fortnight.
(4) summer high temperature weather is too fast to prevent young concrete surface moisture to scatter and disappear, after concreting in time It is conserved, increases water seasoning number according to the actual situation and guarantee surface wettability, covered tightly with plastic cloth when necessary, and protect Holding has condensed water in plastic cloth, prevent the appearance of concrete cracks.
(5) after cast-in-place concrete intensity reaches 70%, dismountable temporary support is transferred to next working face and uses.
5, prefabricated panel is in the milk
As shown in figure 3,
1) grouting operation
(1) the grouting operation time: in prefabricated panel two sides, cast-in-place sleeper and cast-in-situ floor concreting are completed, and floor is full Hall frame carries out grouting operation after removing.
(2) prefabricated panel grout sleeve is in the milk, and successively pours into from grout sleeve bottom PVC grout hole 5, corresponding to its Top PVC overflow hole 6 emerge grouting material when indicate to have filled in grouting cylinder, using cork overflow hole blocked after filling tight It is real, continue after holding pressure 30s, then with cork by grouting hole plugging.It is as shown below:
(3) during grouting construction, test cube in the same condition and test specimen need to be made.Grouting material needs indwelling test cube in the same condition, every building One group of test block of every layer of indwelling, every group 3 pieces, test block specification is 40*40*160mm;Grouting operation is every to complete 500 reinforcing bars companies Female connector cylinder makees one group of test specimen, 3 connectors of every group of test specimen, when test specimen indwelling, completion grouting need to be operated on dispenser, and carry out Mark is supported 28 days and is conserved.As shown in the figure following figure:
(4) utensils such as blender, agitator, grouting cylinder are cleaned after being in the milk immediately, in order to avoid grouting material solidifies, cleaning is tired Difficulty, paying attention to being in the milk, it is primary to clean after cylinder needs every perfusion to complete one, can reuse after cleaning.So in each teams and groups Three grouting cylinders should at least be prepared when grouting operation, wherein one spare.
(5) after the completion of being in the milk within 4 hours, prefabricated panel must not be vibrated.
6, precast facade level, vertical joint waterproofing construction
As shown in figure 4, precast facade horizontal joint waterproofing construction adds the form of twice material waterproofing using one of constructional waterproofing. One of material waterproofing (hollow rubber waterstop 7) inside precast wall body, is pasted on panel tops before lifting component dropping place;Separately One of material waterproofing (elastoplastic stick and synthesis polymeric seal cream 8) is after topping out, exterior coating has been constructed, using hanging Basket carries out alien invasion waterproof construction.
As shown in figure 5, precast facade is vertically sewn on cast-in-place sleeper position, water proof structure uses one of material waterproofing (PE Stick 8+ sealant 9) form, constructed using hanging basket.

Claims (1)

1. the construction method of connecting sewing between a kind of assembled architecture component and component;It is characterized in that: including the following steps;
Step 1, the binding of sleeper reinforcing bar;
Step 1.1 lifts panels in place;
Step 1.2, binding sleeper stirrup and sleeper indulge muscle: according to stirrup spacing, stirrup temporarily being bound to the closing ring in component On, sleeper is indulged into muscle and is vertically penetrated in stirrup from top, and is connect with the reserved joint bar of next layer of sleeper;Stirrup spacing is adjusted, Stirrup and vertical muscle are reliably bound;
Step 1.3, binding sleeper lacing wire;
Step 2 buries electric wire box and spool in sleeper reinforcing bar;Wire box, spool and the binding of sleeper reinforcing bar position;
Step 3, installation sleeper formwork for placing: line-styled or the cast-in-place sleeper of " L " type between two module component plates, using inside list Collateral mould, outboard template is using prefabricated outer wall panel as exterior sheathing;Wherein, inner side template left and right sides and precast member board it Between use foam strip joint seal, bottom edge gap tamped with cement mortar, prevents running pulp;Counter screw shuttering uses full flight screw, spiral shell Bar one end is screwed into the sleeve being embedded on the inside of prefabricated panel, and the other end is fastened using conventional chevron card and nut;Two pieces pre- The gap 20mm tack rubber joint seal between Side fascia processed;
Step 4, sleeper concreting;
Step 4.1, the installation quality for checking the template at concreting position, reinforcing bar, built-in fitting and pipeline, it is ensured that meet design It is required that;
Step 4.2 is poured in sleeper template bottom and subtracts 30~50mm of stone cement mortar with identical with concrete mix;
Step 4.3, concreting in lifts;Wherein, the layering blanking thickness of production layering scale bar control concrete, layering are poured It builds thickness and takes 400mm;Upper and lower level interval time cannot be greater than the concrete initial set time;Step 4.4, layering vibrated concrete, often Thickness degree is not more than 30cm;
Step 4.5, concrete are conserved with water law, brush curing agent, package plastic cloth is poured;
After step 4.6, concrete strength reach 70%, dismountable support, and support is transferred to next working face and is used;
Step 5, prefabricated panel grouting;
Step 5.1, after the completion of the cast-in-place sleeper in prefabricated panel two sides and cast-in-situ floor concreting, floor expire hall frame remove after Carry out prefabricated panel grouting operation;
Step 5.2 is in the milk with grout sleeve: from grout sleeve bottom, PVC grout hole is successively poured into, to its it is corresponding on Portion's PVC overflow hole emerge grouting material when indicate to have filled in grouting cylinder, using cork overflow hole blocked after filling it is tight, Continue to hold pressure after 30 seconds, then with cork by grouting hole plugging;After the completion of step 5.3, grouting within 4 hours, prefabricated panel is not It must be vibrated;
Step 6, precast facade are horizontal, vertical joint waterproofing is constructed: one of material waterproofing inside precast wall body is fallen in lifting component Panel tops are pasted on before position;Another road material waterproofing is carried out outer vertical after topping out, exterior coating has been constructed using hanging basket Face waterproof construction.
CN201510563573.XA 2015-09-08 2015-09-08 The construction method of connecting sewing between assembled architecture component and component Active CN106499070B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510563573.XA CN106499070B (en) 2015-09-08 2015-09-08 The construction method of connecting sewing between assembled architecture component and component

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510563573.XA CN106499070B (en) 2015-09-08 2015-09-08 The construction method of connecting sewing between assembled architecture component and component

Publications (2)

Publication Number Publication Date
CN106499070A CN106499070A (en) 2017-03-15
CN106499070B true CN106499070B (en) 2019-03-15

Family

ID=58287729

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510563573.XA Active CN106499070B (en) 2015-09-08 2015-09-08 The construction method of connecting sewing between assembled architecture component and component

Country Status (1)

Country Link
CN (1) CN106499070B (en)

Families Citing this family (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108035539A (en) * 2018-01-08 2018-05-15 上海建工二建集团有限公司 A kind of sleeper plate device and the method using its construction assembled building sleeper
CN109505368B (en) * 2018-12-25 2024-05-14 湘潭远大住宅工业有限公司 Wallboard connecting node for assembled building
CN110552440B (en) * 2019-08-16 2024-06-18 青岛一建集团有限公司 Safe and environment-friendly construction process for high-strength assembled integral sandwich heat-insulating shear wall
CN110409637B (en) * 2019-08-22 2020-12-01 华北理工大学 Grout seam plugging device of prefabricated assembled structure
CN110803902A (en) * 2019-12-09 2020-02-18 盛业建设有限公司 Self-leveling environment-friendly ground construction method
CN111946050A (en) * 2020-07-01 2020-11-17 北京住总第六开发建设有限公司 Aluminum alloy formwork construction method applied to assembly type engineering
CN113338476B (en) * 2021-06-16 2023-02-14 重庆渝能建筑安装工程有限公司 Assembled shear force wall concatenation seam waterproof construction
CN114541774A (en) * 2022-03-28 2022-05-27 中建八局第二建设有限公司 Construction method of assembled building outer wall structure
CN115030398B (en) * 2022-06-30 2024-01-26 中铁二十局集团市政工程有限公司 External wall board embedded structure and construction method thereof

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2037758U (en) * 1988-10-14 1989-05-17 宁波市机电工业研究设计院 Assembled commodity house
JP2001227119A (en) * 2000-02-18 2001-08-24 Toshin Komu:Kk Roof top construction method for wooden house
CN103147529A (en) * 2013-04-03 2013-06-12 东南大学 Assembly type energy dissipation and seismic mitigation shear wall structure system
CN103556749A (en) * 2013-10-10 2014-02-05 南京工业大学 Hanging flexible connection of precast concrete infill wall
CN104264798A (en) * 2014-09-12 2015-01-07 北京首钢建设集团有限公司 Method for constructing prefabricated cladding panel and steel frame column split joint seam
CN104452961A (en) * 2014-12-08 2015-03-25 上海应用技术学院 Rural low-rise assembled damping building structure system

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2037758U (en) * 1988-10-14 1989-05-17 宁波市机电工业研究设计院 Assembled commodity house
JP2001227119A (en) * 2000-02-18 2001-08-24 Toshin Komu:Kk Roof top construction method for wooden house
CN103147529A (en) * 2013-04-03 2013-06-12 东南大学 Assembly type energy dissipation and seismic mitigation shear wall structure system
CN103556749A (en) * 2013-10-10 2014-02-05 南京工业大学 Hanging flexible connection of precast concrete infill wall
CN104264798A (en) * 2014-09-12 2015-01-07 北京首钢建设集团有限公司 Method for constructing prefabricated cladding panel and steel frame column split joint seam
CN104452961A (en) * 2014-12-08 2015-03-25 上海应用技术学院 Rural low-rise assembled damping building structure system

Also Published As

Publication number Publication date
CN106499070A (en) 2017-03-15

Similar Documents

Publication Publication Date Title
CN106499070B (en) The construction method of connecting sewing between assembled architecture component and component
CN105401605B (en) Deformation joint structure and its construction method
CN207582663U (en) Connecting elements between concrete folding plate and shear wall Side fascia
CN103410317A (en) Construction method for site assembly and casting integral wall body by adopting wall body prefabricated part
CN209482591U (en) Prefabricated molds shell structure column construction structure
CN107574842A (en) Basement post-pouring zone advance water stop construction method
CN213952303U (en) Basement outer wall post-cast strip assembled protection wall construction structures
CN105464396A (en) Reinforcing method for external wall of protective historical building
CN106120870A (en) The advanced enclosed construction of poured band of outer wall of basement and construction method
CN103276916A (en) Constructing method and infill board for solidly sealed lightweight concrete board wall hole
CN209633298U (en) The prefabricated shell mold molding die of constructional column
CN107503450A (en) A kind of cast-in-place hollow armored concrete filling wall and its construction technology
CN108005255A (en) A kind of construction method of wall
CN107313532A (en) Assembled heat insulation concrete walls structural connection and connection structure and method
CN108240045A (en) A kind of compound late poured band structure of outer wall precast slab and its construction method
CN109610665A (en) Oil depot assembled fire wall construction method
CN211114261U (en) Precast concrete shear force wall panel structure
CN109113068A (en) A kind of inverse construction joint structure for building construction of deep basal pit
CN108978729A (en) A kind of subway station hole for hoist method for blocking
CN108396761A (en) The non-fully pile foundation cushion cap and production method under precipitation state inside a kind of foundation pit
CN107237448A (en) A kind of prefabricated interior fill concrete wallboard and its manufacture method
CN107237408A (en) It is a kind of to prevent the construction method of expansion joint position seepage
CN207092299U (en) A kind of cast-in-place hollow armored concrete filling wall
CN206800665U (en) A kind of basement side wall late poured band structure
CN109057066A (en) A kind of flexible connection anti-seismic structure and construction method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant