CN108978729A - A kind of subway station hole for hoist method for blocking - Google Patents

A kind of subway station hole for hoist method for blocking Download PDF

Info

Publication number
CN108978729A
CN108978729A CN201810981669.1A CN201810981669A CN108978729A CN 108978729 A CN108978729 A CN 108978729A CN 201810981669 A CN201810981669 A CN 201810981669A CN 108978729 A CN108978729 A CN 108978729A
Authority
CN
China
Prior art keywords
hole
hoist
subway station
cover board
blocking
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810981669.1A
Other languages
Chinese (zh)
Inventor
黎浩昀
郑伋
刘晟
丁剑敏
刘伯成
过迅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuxi Metro Group Co Ltd
China Railway Erju Co Ltd
China Railway No 2 Engineering Group Co Ltd
Original Assignee
Wuxi Metro Group Co Ltd
China Railway Erju Co Ltd
China Railway No 2 Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuxi Metro Group Co Ltd, China Railway Erju Co Ltd, China Railway No 2 Engineering Group Co Ltd filed Critical Wuxi Metro Group Co Ltd
Priority to CN201810981669.1A priority Critical patent/CN108978729A/en
Publication of CN108978729A publication Critical patent/CN108978729A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/16Arrangement or construction of joints in foundation structures
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/04Making large underground spaces, e.g. for underground plants, e.g. stations of underground railways; Construction or layout thereof
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them

Abstract

The invention discloses a kind of subway station hole for hoist method for blocking, and support end is arranged at hole for hoist when including the following steps the hole for hoist of A production subway station;Several prefabricated cover boards of B, all cover boards successively spliced shape adaptation hole for hoist have gap, have gap between two neighboring cover board between each cover board and hole for hoist side wall;All cover boards of C handling are arranged at hole for hoist, and all cover boards are supported end support;All gaps D are formed using concreting.With this method, in such a way that the prefabricated cover board of handling blocks hole for hoist, compared with traditional support cast-in-place construction, it does not need to set up bracket, installation template, assembling reinforcement and the work of a large amount of casting concretes, difficulty of construction reduces, while noise is small, pollution is small, construction efficiency is high, short time limit used, while gap is crammed using concrete, so that cover board has waterproofness after blocking hole for hoist, meet subway station waterproof requirement, this method step is simple, easy to operate, works well.

Description

A kind of subway station hole for hoist method for blocking
Technical field
The present invention relates to subway work technical field, in particular to a kind of subway station hole for hoist method for blocking.
Background technique
With the continuous development of raising and the transport development of china's overall national strength, China's underground traffic infrastructure is rapidly sent out Exhibition, each big city starts to build subway engineering successively;Subway station generally can all select AT STATION during design and construction Preformed hole is set on the top plate and middle plate above the area Gui Hang to meet a variety of materials equipment hoisting needs such as the section of track, shield machine;It stands Interior construction then needs to block these ducts close to complete working hour;Open cut of subway station reserving hole closure at present is generally adopted With support cast-in-place construction technique, intensive labor is needed, at high cost, low efficiency is unfavorable for the duration.
Summary of the invention
It is an object of the invention to overcome the existing open cut of subway station reserving hole in the presence of the prior art to block one As use support cast-in-place construction technique, need intensive labor, at high cost, low efficiency is unfavorable for the above-mentioned deficiency of duration, provides A kind of subway station hole for hoist method for blocking.
In order to achieve the above-mentioned object of the invention, the present invention provides following technical schemes:
A kind of subway station hole for hoist method for blocking, comprising the following steps:
A, when making the hole for hoist of subway station, support end is set in the hole for hoist installation site surrounding;
B, several prefabricated cover boards, all cover boards successively hole for hoist described in spliced shape adaptation are each described There is gap between cover board and the hole for hoist side wall contacted, there is gap between the two neighboring cover board;
C, all cover boards of handling are arranged at the correspondence hole for hoist, and all cover boards are corresponded to by the hole for hoist The support end support;
D, all gaps are formed using concreting, are completed the hole for hoist and are blocked.
Using a kind of subway station hole for hoist method for blocking of the present invention, hole for hoist is blocked using the prefabricated cover board of handling Mode do not need to set up bracket, installation template, assembling reinforcement and largely pour mixed compared with traditional support cast-in-place construction The work of soil is coagulated, difficulty of construction reduces, while noise is small, pollution is small, and construction efficiency is high, short time limit used, while utilizing coagulation Soil crams gap, so that cover board has certain waterproofness after blocking hole for hoist, meets subway station waterproof requirement, the closure side Method step is simple, easy to operate, works well.
Preferably, each cover board connects the side of the support end and is arranged in mismatch, and the top of the side compared with Lower part is prominent, so that each cover board is overlapped on the support end.
Preferably, the lower shape of each cover board is adapted to the notch that the support end surrounds.
Preferably, in the step D, all gaps are poured using C40 slightly expanded concrete.
Preferably, the size in each gap is 5cm-10cm.
Preferably, concrete is poured using hanging modulus method in the gap between the two neighboring cover board, i.e., described Sunpender is set in gap, and the sunpender connects bed die, and the sunpender tenses, and the bed die fits in two adjacent lids Plate, then casting concrete, maintenance remove the bed die after forming in the gap.
Preferably, water-swellable water-stop glue is equipped in each gap, the water-swellable water-stop glue is connected to described Cover sidewall.
Since subway station needs strict waterproof performance, in this way, part water is leaked into the gap After concrete, percolating water is after encountering water-swellable water-stop glue, since water-swellable water-stop glue is water expansion one-pack-type sealant, One it is hardened reform into own vol expansion after the good rubber elastomer of restoration, immersion, filling gap play it is certain only Water effect.
Preferably, pre-buried angle steel at two angles being oppositely arranged on the two neighboring cover board, when executing the step D, After pouring all gaps, the welding steel on two adjacent angle steel.
Since subway station needs strict waterproof performance to can be improved two neighboring prefabricated lid in this way Globality between plate, the waterproof performance of enhancing structure.
Preferably, after executing the step D, cast-in-situ steel reinforced concrete layer is set on all cover boards.
In this way, the integral waterproofing effect after hole for hoist blocks is further increased, simultaneously because cover board is overlap joint On support end, hole for hoist needs backfill after blocking, and cast-in-situ steel reinforced concrete layer is arranged on the cover board and is capable of enhancing structure Stability.
Preferably, the cast-in-situ steel reinforced concrete layer with a thickness of 10cm-20cm.
In conclusion by adopting the above-described technical solution, the beneficial effects of the present invention are:
1, with a kind of subway station hole for hoist method for blocking of the present invention, lifting is blocked using the prefabricated cover board of handling The mode in hole is not needed to set up bracket, installation template, assembling reinforcement and largely be poured compared with traditional support cast-in-place construction The work of concrete, difficulty of construction reduce, while noise is small, pollution is small, and construction efficiency is high, short time limit used, while utilizing mixed Solidifying soil crams gap, so that cover board has certain waterproofness after blocking hole for hoist, meets subway station waterproof requirement, the closure Method and step is simple, easy to operate, works well;
2, it is equipped with that meet water swollen with a kind of subway station hole for hoist method for blocking of the present invention, in each gap Swollen water-stop glue, the water-swellable water-stop glue are connected to the cover sidewall, since subway station needs strict waterproof performance, In this way, part water leaks into the gap after concrete, percolating water after encountering water-swellable water-stop glue, by It is water expansion one-pack-type sealant in water-swellable water-stop glue, one hardened reforms into the good rubber elastomer of restoration, leaching Own vol expansion, filling gap play certain water-stagnating effect after water;
3, opposite on the two neighboring cover board to set with a kind of subway station hole for hoist method for blocking of the present invention Pre-buried angle steel at two angles set, when executing the step D, after pouring all gaps, in two adjacent angle steel Upper welding steel, since subway station needs strict waterproof performance to can be improved two neighboring prefabricated in this way Globality between cover board, the waterproof performance of enhancing structure;
4, with a kind of subway station hole for hoist method for blocking of the present invention, after executing the step D, in all institutes Setting cast-in-situ steel reinforced concrete layer on cover board is stated, in this way, further increases the integral waterproofing effect after hole for hoist blocks Fruit, simultaneously because cover board is overlapped on support end, hole for hoist needs backfill after blocking, and it is mixed that cast in place reinforced bar is arranged on the cover board Solidifying soil layer is capable of the stability of enhancing structure.
Detailed description of the invention
Fig. 1 is the structure section signal using the subway station of hole for hoist method for blocking in subway station of the present invention Figure;
Fig. 2 is the partial top view of Fig. 1;
Structure section schematic diagram of the Fig. 3 between two neighboring cover board.
Marked in the figure: 1- hole for hoist, 2- support end, 3- cover board, 31- angle steel, 32- steel plate, the gap 4-, 5- water-swellable stop Glue, 6- cast-in-situ steel reinforced concrete layer.
Specific embodiment
Below with reference to test example and specific embodiment, the present invention is described in further detail.But this should not be understood It is all that this is belonged to based on the technology that the content of present invention is realized for the scope of the above subject matter of the present invention is limited to the following embodiments The range of invention.
Embodiment
As shown in Figure 1-3, a kind of subway station hole for hoist method for blocking of the present invention, comprising the following steps:
A, when making the hole for hoist 1 of subway station, support end 2 is set in the 1 installation site surrounding of hole for hoist;
B, several prefabricated cover boards 3, all cover boards 3 successively hole for hoist 1, Mei Gesuo described in spliced shape adaptation Stating has gap 4 between cover board 3 and 1 side wall of the hole for hoist contacted, have gap 4 between the two neighboring cover board 3;
C, all settings of cover board 3 of handling are at the corresponding hole for hoist 1, and all cover boards 3 are by the hole for hoist 1 The corresponding support end 2 supports;
D, all gaps 4 are formed using concreting, are completed the hole for hoist 1 and are blocked.
As a preferred embodiment of the present embodiment, the side that each cover board 3 connects the support end 2 is set in mismatch It sets, and the top lower part of the side is prominent, so that each cover board 3 is overlapped on the support end 2, each lid The lower shape of plate 3 is adapted to the notch that the support end 2 surrounds.
As a preferred embodiment of the present embodiment, in the step D, all gaps 4 use C40 microdilatancy coagulations Soil pours, and the size in each gap 4 is 10cm;Concrete uses in the gap 4 between the two neighboring cover board 3 It hangs modulus method to pour, i.e., sunpender is set in the gap 4, the sunpender connects bed die, and the sunpender tenses, the bed die fitting In two adjacent cover boards 3, then the casting concrete in the gap 4, removes the bed die after maintenance molding;Each Water-swellable water-stop glue 5 is equipped in the gap 4, the water-swellable water-stop glue 5 is connected to 3 side wall of cover board, due to ground Iron car station needs strict waterproof performance, and in this way, part water leaks into the gap 4 after concrete, leakage Water is after encountering water-swellable water-stop glue 5, since water-swellable water-stop glue 5 is water expansion one-pack-type sealant, once hardened Become own vol expansion after the good rubber elastomer of restoration, immersion, filling gap plays certain water-stagnating effect.
It is pre-buried at two angles being oppositely arranged on the two neighboring cover board 3 as a preferred embodiment of the present embodiment Angle steel 31, when executing the step D, after pouring all gaps 4, the welding steel on two adjacent angle steel 31 32, since subway station needs strict waterproof performance, in this way, can be improved two neighboring prefabricated cover board 3 it Between globality, the waterproof performance of enhancing structure;After executing the step D, cast in place reinforced bar coagulation is set on all cover boards 3 Soil layer 6 further increases the integral waterproofing effect after hole for hoist 1 blocks in this way, simultaneously because cover board 3 is overlap joint On support end 2, hole for hoist 1 needs backfill after blocking, and cast-in-situ steel reinforced concrete layer 6 is arranged on cover board 3 can enhance knot The stability of structure, the cast-in-situ steel reinforced concrete layer 6 with a thickness of 20cm.
With a kind of subway station hole for hoist method for blocking of the present invention, lifting is blocked using the prefabricated cover board 3 of handling The mode in hole 1 blocks a hole for hoist 1 and needs 7 days, this method does not need to set up branch compared with traditional support cast-in-place construction Frame, installation template, assembling reinforcement and the work of a large amount of casting concretes, reduce construction cost and difficulty of construction, while noise It is small, pollution is small, construction efficiency is high, blocks a hole for hoist 1 it is only necessary to 1 day, shortens the construction period 6 days, and general support cast-in-place blocks, Old concrete face need to be cut, is plugged into using pre-buried reinforcing bar and carries out reinforcing bar connection after-pouring concrete, this construction technology, reinforcing bar Mechanical connection quality is uncontrollable, and using this method there is no need to above-mentioned technique, quality is guaranteed, while being filled out using concrete Stifled gap 4 meets subway station waterproof requirement, the closure side so that cover board 3 has certain waterproofness after blocking hole for hoist 1 Method step is simple, easy to operate, works well.
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not intended to limit the invention, all in essence of the invention Made any modifications, equivalent replacements, and improvements etc., should all be included in the protection scope of the present invention within mind and principle.

Claims (10)

1. a kind of subway station hole for hoist method for blocking, which comprises the following steps:
A, when making hole for hoist (1) of subway station, support end (2) are set in the hole for hoist (1) installation site surrounding;
B, several prefabricated cover boards (3), all cover boards (3) successively hole for hoist (1) described in spliced shape adaptation, each There are gap (4) between the cover board (3) and the hole for hoist (1) side wall contacted, between the two neighboring cover board (3) With gap (4);
C, all cover board (3) settings of handling are at the corresponding hole for hoist (1), and all cover boards (3) are by the lifting Corresponding support end (2) support in hole (1);
D, all gaps (4) are formed using concreting, complete the hole for hoist (1) closure.
2. hole for hoist method for blocking in subway station according to claim 1, which is characterized in that each cover board (3) is even The side for connecing the support end (2) is arranged in mismatch, and the top lower part of the side is prominent, so that each cover board (3) it is overlapped on the support end (2).
3. hole for hoist method for blocking in subway station according to claim 2, which is characterized in that each cover board (3) Lower shape is adapted to the notch that the support end (2) surrounds.
4. hole for hoist method for blocking in subway station according to claim 1, which is characterized in that in the step D, Suo Yousuo Gap (4) are stated to pour using C40 slightly expanded concrete.
5. hole for hoist method for blocking in subway station according to claim 1, which is characterized in that each gap (4) Size is 5cm-10cm.
6. hole for hoist method for blocking in subway station according to claim 1, which is characterized in that the two neighboring cover board (3) concrete use is hung modulus method and is poured in the gap (4) between, i.e., sunpender, the sunpender are arranged in the gap (4) Bed die is connected, the sunpender tenses, and the bed die fits in the cover board (3) of adjacent two, then in the gap (4) Casting concrete.
7. hole for hoist method for blocking in subway station according to claim 1, which is characterized in that in each gap (4) Equipped with water-swellable water-stop glue (5), the water-swellable water-stop glue (5) is connected to the cover board (3) side wall.
8. hole for hoist method for blocking in subway station according to claim 1, which is characterized in that the two neighboring cover board (3) pre-buried angle steel (31) at two angles being oppositely arranged on, when executing the step D, after pouring all gaps (4), Welding steel (32) on the angle steel (31) of adjacent two.
9. hole for hoist method for blocking in subway station according to claim 1-8, which is characterized in that execute the step After rapid D, cast-in-situ steel reinforced concrete layer (6) are set on all cover boards (3).
10. hole for hoist method for blocking in subway station according to claim 9, which is characterized in that the cast in place reinforced bar coagulation Soil layer (6) with a thickness of 10cm-20cm.
CN201810981669.1A 2018-08-27 2018-08-27 A kind of subway station hole for hoist method for blocking Pending CN108978729A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810981669.1A CN108978729A (en) 2018-08-27 2018-08-27 A kind of subway station hole for hoist method for blocking

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810981669.1A CN108978729A (en) 2018-08-27 2018-08-27 A kind of subway station hole for hoist method for blocking

Publications (1)

Publication Number Publication Date
CN108978729A true CN108978729A (en) 2018-12-11

Family

ID=64546953

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810981669.1A Pending CN108978729A (en) 2018-08-27 2018-08-27 A kind of subway station hole for hoist method for blocking

Country Status (1)

Country Link
CN (1) CN108978729A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112177369A (en) * 2020-09-23 2021-01-05 中建二局第三建筑工程有限公司 Building floor hoist and mount mouthful seal structure
CN112323965A (en) * 2020-11-13 2021-02-05 杭州绿锦建筑设计咨询有限公司 Blocking structure of basement equipment room and construction method thereof
CN112814036A (en) * 2021-01-05 2021-05-18 中国电建集团华东勘测设计研究院有限公司 Waterproof sealing cover plate structure for underwater manhole and construction method thereof

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN203923887U (en) * 2014-06-27 2014-11-05 中铁第一勘察设计院集团有限公司 The anti-freeze thawing board connecting structure of pier in a kind of bridge water
CN204097884U (en) * 2014-09-28 2015-01-14 广州瀚阳工程咨询有限公司 A kind of Novel stopper for precast segment beam lifting hole
CN204609008U (en) * 2015-05-14 2015-09-02 江苏筑森建筑设计有限公司 A kind of basement roof reserves equipment hoisting mouth plugging structure
US20160369473A1 (en) * 2015-06-18 2016-12-22 Berndorf Baderbau S.R.O. Closure, particularly for closing construction and technological apertures
CN106988436A (en) * 2017-03-28 2017-07-28 中国水利水电第十二工程局有限公司 A kind of method of reserving hole closure

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN203923887U (en) * 2014-06-27 2014-11-05 中铁第一勘察设计院集团有限公司 The anti-freeze thawing board connecting structure of pier in a kind of bridge water
CN204097884U (en) * 2014-09-28 2015-01-14 广州瀚阳工程咨询有限公司 A kind of Novel stopper for precast segment beam lifting hole
CN204609008U (en) * 2015-05-14 2015-09-02 江苏筑森建筑设计有限公司 A kind of basement roof reserves equipment hoisting mouth plugging structure
US20160369473A1 (en) * 2015-06-18 2016-12-22 Berndorf Baderbau S.R.O. Closure, particularly for closing construction and technological apertures
CN106988436A (en) * 2017-03-28 2017-07-28 中国水利水电第十二工程局有限公司 A kind of method of reserving hole closure

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
刘福等: "北京雁栖湖某小区配套公建结构设计", 《建筑结构》 *
张昭等: "地下室顶板预留洞临时封堵施工技术探讨", 《科研》 *
张美玲: "吊模法在地铁车站预留孔封堵施工中的应用", 《铁道建筑》 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112177369A (en) * 2020-09-23 2021-01-05 中建二局第三建筑工程有限公司 Building floor hoist and mount mouthful seal structure
CN112323965A (en) * 2020-11-13 2021-02-05 杭州绿锦建筑设计咨询有限公司 Blocking structure of basement equipment room and construction method thereof
CN112814036A (en) * 2021-01-05 2021-05-18 中国电建集团华东勘测设计研究院有限公司 Waterproof sealing cover plate structure for underwater manhole and construction method thereof

Similar Documents

Publication Publication Date Title
CN108978729A (en) A kind of subway station hole for hoist method for blocking
CN105839667B (en) The construction manufacture craft of complete prefabricated overlapping assembled underground pipe gallery
CN103410317A (en) Construction method for site assembly and casting integral wall body by adopting wall body prefabricated part
CN101158161A (en) Underwater no-bottom closing concrete boxed cofferdam and method of use thereof
CN106499070B (en) The construction method of connecting sewing between assembled architecture component and component
CN104652495B (en) Internal support of foundation pit column and base plate node waterproof construction technology
CN106284412A (en) A kind of prefabricated pipe gallery and construction method
CN106759563A (en) A kind of device for pile foundation repairing and reinforcing and the construction method using the device
CN201943086U (en) Underground building wall body
CN205776348U (en) A kind of overlapping monoblock type pipe gallery prefabricated assembly structural
CN206052778U (en) A kind of steel and Combined concrete piping lane
CN108560588A (en) Assembled pipe gallery and its construction method
CN211114261U (en) Precast concrete shear force wall panel structure
CN105862894B (en) A kind of installation method of catch pit anti-floating integral mold plate
CN107237408A (en) It is a kind of to prevent the construction method of expansion joint position seepage
CN108726348B (en) Horizontal prefabrication, overturning and hoisting method for pipe gallery segments
CN110965473A (en) Construction method of bridge bearing platform
CN207633546U (en) Toilet concrete sealing prefabricated components
CN106930391B (en) Cast-in-place drainage channel structure of top plate for formwork-free construction and construction method
CN207686288U (en) The manufacture of the horizontal hole to be provided of wall and plugging device
CN109653223A (en) River anti-floating weighting board construction method
CN103541372A (en) Concrete poured communication through-type 4.0 manhole and construction method thereof
CN109371906B (en) Upgrading structure and construction method for road at top of active embankment dam
CN207813015U (en) Floor slab preformed hole tool-typed formwork support construction
CN105951987A (en) Sub-frame post-cast joint with external permanent aluminum plate outer mold

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20181211