CN108086957A - A kind of method of the U-shaped coal bed gas well construction in double coal seams - Google Patents

A kind of method of the U-shaped coal bed gas well construction in double coal seams Download PDF

Info

Publication number
CN108086957A
CN108086957A CN201711411010.4A CN201711411010A CN108086957A CN 108086957 A CN108086957 A CN 108086957A CN 201711411010 A CN201711411010 A CN 201711411010A CN 108086957 A CN108086957 A CN 108086957A
Authority
CN
China
Prior art keywords
well
shaped
coal
coal seam
vertical
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201711411010.4A
Other languages
Chinese (zh)
Inventor
何庆宏
郭盛强
李峰
秦辉
樊利沙
常凌霄
王雪晴
苗媛媛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHANXI LANYAN COALBED METHANE GROUP CO Ltd
Original Assignee
SHANXI LANYAN COALBED METHANE GROUP CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHANXI LANYAN COALBED METHANE GROUP CO Ltd filed Critical SHANXI LANYAN COALBED METHANE GROUP CO Ltd
Priority to CN201711411010.4A priority Critical patent/CN108086957A/en
Publication of CN108086957A publication Critical patent/CN108086957A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B43/00Methods or apparatus for obtaining oil, gas, water, soluble or meltable materials or a slurry of minerals from wells
    • E21B43/12Methods or apparatus for controlling the flow of the obtained fluid to or in wells

Landscapes

  • Life Sciences & Earth Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Geology (AREA)
  • Mining & Mineral Resources (AREA)
  • Physics & Mathematics (AREA)
  • Environmental & Geological Engineering (AREA)
  • Fluid Mechanics (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Solid Fuels And Fuel-Associated Substances (AREA)

Abstract

The present invention relates to coal bed gas and coal mining technologies, the problems such as existing input is big when using conventional u-shaped well construction for the coal field comprising upper and lower two kinds of coal seams, the wasting of resources, extraction efficiency are low, the present invention provides a kind of methods of double U-shaped coal bed gas well constructions in coal seam, two layers of different purpose coal seam is drilled into using 1 mouthful of U-shaped well, and mining is carried out using with 1 mouthful of vertical well;It first constructs during construction vertical well, U-shaped well of constructing afterwards;Vertical well drives a well body structure using two, and U-shaped well drives a well body structure using three, and the three of U-shaped well drives a well after figure orientation is docked to vertical well, extends to projected depth forward.Double U-shaped well construction costs in coal seam are less than traditional common u-shaped well, can save the engineering cost of 1 mouthful of vertical well, and 1 mouthful of U-shaped well can produce the coal bed gas of two layers of coal, and economic benefit is apparent.

Description

A kind of method of the U-shaped coal bed gas well construction in double coal seams
Technical field
The present invention relates to coal bed gas and coal mining technologies, are specially the side that a kind of U-shaped coal bed gas well in double coal seams is constructed Method.
Background technology
Due to the geological characteristics of some coal fields, comprising upper and lower two kinds of coal seams, simultaneous beam loess hills rises and falls, ravines and guillies criss-cross The features such as, cause well location selection difficult, according to traditional U-shaped well construction, at least need 1 mouthful of engineering well and 1 mouthful of mining well, together When also need to two well sites and corresponding road, project inputs are larger, serious waste soil, while extraction efficiency is relatively low.
The content of the invention
The present invention for the coal field comprising upper and lower two kinds of coal seams existing input when using conventional u-shaped well construction it is big, The problems such as the wasting of resources, extraction efficiency is low, and then the method for providing a kind of U-shaped coal bed gas well construction in double coal seams.
The present invention adopts the following technical scheme that:
A kind of method of the U-shaped coal bed gas well construction in double coal seams, is drilled into two layers of different purpose coal seam using 1 mouthful of U-shaped well, and uses Mining is carried out with 1 mouthful of vertical well;It first constructs during construction vertical well, U-shaped well of constructing afterwards;Vertical well drives a well body structure using two, U-shaped Well drives a well body structure using three, and the three of U-shaped well drives a well after figure orientation is docked to vertical well, extends to projected depth forward.
According to U-shaped well three drive a well figure and the docking location of vertical well be divided into near-end dock U-shaped well and distal end dock it is U-shaped Well, U-shaped well three drive a well the first section of body when being docked with vertical well and dock U-shaped well for near-end, U-shaped well three drive a well body endpiece with hanging down When straight well docks U-shaped well is docked for distal end;
The near-end docks the two of U-shaped well and drives a well the landing point position on purpose coal seam(A, B point in Fig. 1)In purpose coal seam Middle and lower part, subsequent three open the beginning after vertical well creeps into along going up a slope;
Dock two landing points to drive a well on purpose coal seam of U-shaped well in the distal end(C, D point in Fig. 2)Positioned at purpose coal seam Middle and upper part, subsequent three start to creep into along descending.
The two of the U-shaped well open drilling process include deflecting, 3 stages of increasing hole angle and hold angle, kickoff point (KOP) opened two after 30 ~ 50m then begins to increasing hole angle, and hold angle makes 90 degree of the landing point hole deviation infinite approach into after purpose coal seam.
Build angle rate in build-up process is no more than 15 °.
The two of vertical well spud in is into work progress:
One opens:Horizon d 10m, tripping in surface pipe are drilled into using drill bit, cementing concrete returns up to ground;
Two open:30m below lower purpose coal seam, tripping in production casing are drilled into using drill bit, cementing concrete returns up to upper purpose coal seam More than 200m;The tripping in glass reinforced plastic pipe in upper purpose coal seam and lower purpose coal seam then carries out making cave reaming.
The three of U-shaped well spud in is into work progress:
One opens:Horizon d 10m, tripping in surface pipe are drilled into using drill bit, cementing concrete returns up to ground;
Two open:It is drilled into upper purpose coal seam and lower purpose coal seam, tripping in protective casing respectively using drill bit, cementing concrete is returned on up to Purpose coal seam more than 200m;
Three open:It is docked to after vertical well and crept into forward again to projected depth using geosteering along two purpose coal seams using drill bit.
The innovative point of the present invention is 2 groups of traditional U-shaped wells merging into 1 group of U-shaped well, be closed by 2 mouthfuls of original engineering wells And construct in 1 wellbore, and reduce by 1 mouthful of mining vertical well, it has the advantages that:
(1)For mountain area mountain ridge landform, well site and road are reduced;
(2)Mining vertical well well number is reduced, reduces project inputs;
(3)Block coal bed gas well in Jincheng has bored 2500 mouthfuls of wells at present, can bore that region is less, on the basis for economizing on resources floor space On, reasonable development coal bed gas resource increases methane output.
2)Change popularization and application situation or expected popularization situation
U-shaped well can also be constructed into multi-branched horizontal well, and vertical well can be used and do not drill 15# coal seams, and another mouthful of purpose coal seam is The U-shaped well in 15# coal seams uses the direct mining of jet pump.
(1)It is tested in Jincheng Mining Area different coal region, well bore design and construction technique is specifically adjusted according to live, Different constructions are then promoted according to different coal;
(2)And then it may extend to the similar mining area in Shanxi Province or even the whole nation, the use of similar coal seam.
3)Economic benefit and social benefit
(1)Double U-shaped well construction costs in coal seam are less than traditional common u-shaped well, save about 400,000 yuan of the engineering cost of 1 mouthful of vertical well, And 1 mouthful of U-shaped well can produce the coal bed gas of two layers of coal, economic benefit is apparent.
(2)Promote coal bed gas resource utilization, while exploit the coal bed gas of two layers of coal, save the extraction time, ensure coal Ore deposit safety, has good safety benefit.
(3)Substantial amounts of extraction coal bed gas can effectively supplement the energy, advantageously reduce greenhouse gas emission, have significant Social benefit.
Description of the drawings
Fig. 1 is the constructing structure schematic diagram that near-end docks U-shaped well;
Fig. 2 is the constructing structure schematic diagram that U-shaped well is docked in distal end;
A/B/C/D- landing points.
Specific embodiment
With reference to attached drawing, the specific embodiment of the present invention is described further:
Using 1 mouthful of U-shaped well and 1 mouthful of vertical well in this method, 1 mouthful of U-shaped well is constructed in same wellbore, be drilled into two layers it is different Purpose coal seam, and share 1 vertical well and carry out mining.It first constructs vertical well, U-shaped well of constructing afterwards, U-shaped well three opens horizontal segment orientation After being docked to vertical well, projected depth is extended to forward.
By taking the Permian System 3# coal seams in somewhere and Carboniferous System 15# coal seams as an example, 3# coal average layer thickness 6m(Upper purpose coal seam), 15# coal average layer thickness 4m(Lower purpose coal seam), coal measure strata is generally an east northeast to inclined monoclinal structure, and stratigraphic dip is general For 5 ° or so, wide slow secondary fold is relatively developed, and tomography is rare and small in block, suitable for U-shaped horizontal well operations;This area It is most of to be covered for loess, and beam loess hills rises and falls, ravines and guillies criss-cross, well location selection is difficult;Conventional u-shaped well needs 1 mouthful of engineering well and 1 mouthful Mining well, and need 2 well sites and corresponding road.
It for the ground coal seam conditions, is constructed using the method for the invention, there is near-end to dock U-shaped well and remote in Specific construction Dock U-shaped 2 kinds of well in end.
(1)Near-end docks U-shaped well
It first constructs vertical well(Mining well), U-shaped well of constructing afterwards(Engineering well), U-shaped well three open horizontal segment orientation be docked to vertical well Afterwards, projected depth is extended to forward.
Vertical well:It drives a well body structure using two, wherein an exploitation is drilled into horizon d 10m, tripping in the drill bit of 311.15mm The surface pipe of 244.5mm, cementing concrete return up to ground;Two exploitations are drilled into 30m below 15# coal seams with the drill bit of 215.9mm, The production casing of tripping in 177.8mm, cementing concrete return up to 3# coal seams more than 200m;3# coal seams and 15# coal seams can tripping in glass Steel pipe then carries out making cave reaming.
U-shaped well:It drives a well body structure using three, wherein an exploitation is drilled into horizon d 10m, tripping in the drill bit of 311.15mm The surface pipe of 244.5mm, cementing concrete return up to ground;Two exploitations are drilled into 3# coal seams or 15# coals with the drill bit of 215.9mm Layer, the protective casing of tripping in 177.8mm, cementing concrete return up to 3# coal seams more than 200m, and two open and can divide by drilling technology For deflecting, increasing hole angle, 3 stages of hold angle, if repeating deflecting and increasing hole angle section when well is deeper, the coal for the 400m that is averaged according to Jincheng Mining Area Layer buried depth, 30 ~ 50m after kickoff point (KOP) is generally opened two then begins to increasing hole angle, into coal seam after landing point hole deviation close to 90 degree, make Slope is determined according to specific well depth, is usually no more than 15 °;Three exploitations utilize geosteering with 152.4mm drill bits along purpose coal seam It is docked to after vertical well and creeps into forward to projected depth again, according to the soft or hard degree in coal seam, cherry coal can the prefabricated slot production set of tripping in Pipe(Stainless steel tube or pvc pipe), so that the later stage carries out fracturing yield increasing transformation.For ease of later stage mining, two open landing point in coal seam Middle and lower part, subsequent three open the beginning after vertical well, along drilling of going up a slope, determines specific according to specific coal seam thickness and horizontal section length Inclination angle.Since U-shaped well straight well section is using same wellbore, therefore subdrilling 15# coal seams, subsequent tripping in separator again, since two When, that is, side-drilling windowing progress 3# drilling in coal, it is opened using after casing guide tripping in casing two at well cementation to windowing, then takes out and divide Every device, finishing drilling.
(2)Dock U-shaped well in distal end
Distal end docks U-shaped well and equally first constructs vertical well(Mining well), U-shaped well of constructing afterwards(Engineering well), U-shaped well three opens horizontal segment Vertical well is docked to using geosteering extension.
Vertical well:The vertical well of U-shaped well is docked with near-end.
U-shaped well:The U-shaped well of U-shaped well is docked with near-end, for ease of later stage mining, two open landing point in coal seam middle and upper part, with Three start to creep into along descending afterwards, specific inclination angle are determined according to specific coal seam thickness and horizontal section length, followed by geosteering Extension is docked to vertical well.

Claims (6)

  1. A kind of 1. method of the U-shaped coal bed gas well construction in double coal seams, it is characterised in that:Two layers of different mesh is drilled into using 1 mouthful of U-shaped well Coal seam, and carry out mining using with 1 mouthful of vertical well;It first constructs during construction vertical well, U-shaped well of constructing afterwards;Vertical well uses two Drive a well body structure, and U-shaped well drives a well body structure using three, and the three of U-shaped well drives a well after figure orientation is docked to vertical well, extends forward To projected depth.
  2. 2. the method for the U-shaped coal bed gas well construction in double coal seams according to claim 1, it is characterised in that:It is opened according to U-shaped well three Well bore section and the docking location of vertical well are divided into that near-end docks U-shaped well and U-shaped well is docked in distal end, and U-shaped well three drives a well the first section of body Dock U-shaped well when being docked with vertical well for near-end, U-shaped well three drive a well when the endpiece of body dock with vertical well be distally dock it is U-shaped Well;
    Two landing points to drive a well on purpose coal seam that the near-end docks U-shaped well are located at purpose coal seam middle and lower part, and subsequent three It opens and starts after vertical well along drilling of going up a slope;
    Two landing points to drive a well on purpose coal seam that U-shaped well is docked in the distal end are located at purpose coal seam middle and upper part, and subsequent three Start to creep into along descending.
  3. 3. the method for the U-shaped coal bed gas well construction in double coal seams according to claim 2, it is characterised in that:The two of the U-shaped well Opening drilling process includes deflecting, 3 stages of increasing hole angle and hold angle, and 30 ~ 50m after kickoff point (KOP) is opened two then begins to increasing hole angle, and hold angle Make 90 degree of the landing point hole deviation infinite approach into after purpose coal seam.
  4. 4. the method for the U-shaped coal bed gas well construction in double coal seams according to claim 3, it is characterised in that:In build-up process Build angle rate is no more than 15 °.
  5. 5. the method for the U-shaped coal bed gas well construction in double coal seams according to claim 4, which is characterized in that the two of vertical well open Drilling construction process is:
    One opens:Horizon d 10m, tripping in surface pipe are drilled into using drill bit, cementing concrete returns up to ground;
    Two open:30m below lower purpose coal seam, tripping in production casing are drilled into using drill bit, cementing concrete returns up to upper purpose coal seam More than 200m;The tripping in glass reinforced plastic pipe in upper purpose coal seam and lower purpose coal seam then carries out making cave reaming.
  6. 6. the method for the U-shaped coal bed gas well construction in double coal seams according to claim 5, which is characterized in that the three of U-shaped well spud in It is into work progress:
    One opens:Horizon d 10m, tripping in surface pipe are drilled into using drill bit, cementing concrete returns up to ground;
    Two open:It is drilled into upper purpose coal seam and lower purpose coal seam, tripping in protective casing respectively using drill bit, cementing concrete is returned on up to Purpose coal seam more than 200m;
    Three open:It is docked to after vertical well and crept into forward again to projected depth using geosteering along two purpose coal seams using drill bit.
CN201711411010.4A 2017-12-23 2017-12-23 A kind of method of the U-shaped coal bed gas well construction in double coal seams Pending CN108086957A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711411010.4A CN108086957A (en) 2017-12-23 2017-12-23 A kind of method of the U-shaped coal bed gas well construction in double coal seams

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711411010.4A CN108086957A (en) 2017-12-23 2017-12-23 A kind of method of the U-shaped coal bed gas well construction in double coal seams

Publications (1)

Publication Number Publication Date
CN108086957A true CN108086957A (en) 2018-05-29

Family

ID=62177692

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711411010.4A Pending CN108086957A (en) 2017-12-23 2017-12-23 A kind of method of the U-shaped coal bed gas well construction in double coal seams

Country Status (1)

Country Link
CN (1) CN108086957A (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110318662A (en) * 2019-07-10 2019-10-11 台州长天能源技术有限公司 Gravity head beats U-shaped well method device product
CN111119789A (en) * 2019-12-30 2020-05-08 河南工程学院 Well completion method for coal bed gas ground L-shaped pre-pumping well with double-well-opening structure
CN112081558A (en) * 2020-10-10 2020-12-15 西安科技大学 Coal underground gasification and coalbed methane collaborative mining method, structure and construction method
CN112160738A (en) * 2020-09-18 2021-01-01 西安交通大学 Well arrangement structure for underground in-situ pyrolysis of coal and construction method thereof
CN113107589A (en) * 2021-04-14 2021-07-13 中煤科工集团西安研究院有限公司 Method for pre-draining water in advance on ground of coal seam roof aquifer
CN113153146A (en) * 2021-01-06 2021-07-23 北京奥瑞安能源技术开发有限公司 Communicated horizontal well and drilling method thereof
CN113605874A (en) * 2021-08-10 2021-11-05 山西蓝焰煤层气集团有限责任公司 Method for extracting coal bed gas of broken soft coal bed top and bottom double-layer horizontal well
CN114607318A (en) * 2022-03-24 2022-06-10 中煤科工集团西安研究院有限公司 Fracturing cooperative construction method for combined production and drilling of multi-layer horizontal well for deep coal bed methane

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US7493951B1 (en) * 2005-11-14 2009-02-24 Target Drilling, Inc. Under-balanced directional drilling system
CN102116140A (en) * 2011-01-25 2011-07-06 煤炭科学研究总院西安研究院 Construction method for enhancing extraction effect of ground coal bed gas
CN103850671A (en) * 2013-09-11 2014-06-11 华北石油管理局 Well distributing method for pumping and draining coal bed gas on ground
CN105156089A (en) * 2015-08-28 2015-12-16 中国神华能源股份有限公司 U-shaped well system and well drilling method thereof
CN206220946U (en) * 2016-11-17 2017-06-06 山西页岩气有限公司 The gas of coal measures three adopts the U-shaped well pattern structure of multiple-limb altogether
CN106869875A (en) * 2017-01-05 2017-06-20 中国神华能源股份有限公司 The method for exploiting two-layer coal bed gas

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US7493951B1 (en) * 2005-11-14 2009-02-24 Target Drilling, Inc. Under-balanced directional drilling system
CN102116140A (en) * 2011-01-25 2011-07-06 煤炭科学研究总院西安研究院 Construction method for enhancing extraction effect of ground coal bed gas
CN103850671A (en) * 2013-09-11 2014-06-11 华北石油管理局 Well distributing method for pumping and draining coal bed gas on ground
CN105156089A (en) * 2015-08-28 2015-12-16 中国神华能源股份有限公司 U-shaped well system and well drilling method thereof
CN206220946U (en) * 2016-11-17 2017-06-06 山西页岩气有限公司 The gas of coal measures three adopts the U-shaped well pattern structure of multiple-limb altogether
CN106869875A (en) * 2017-01-05 2017-06-20 中国神华能源股份有限公司 The method for exploiting two-layer coal bed gas

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110318662A (en) * 2019-07-10 2019-10-11 台州长天能源技术有限公司 Gravity head beats U-shaped well method device product
CN110318662B (en) * 2019-07-10 2023-12-19 台州长天能源技术有限公司 Gravity head U-shaped well drilling method and equipment product
CN111119789A (en) * 2019-12-30 2020-05-08 河南工程学院 Well completion method for coal bed gas ground L-shaped pre-pumping well with double-well-opening structure
CN112160738A (en) * 2020-09-18 2021-01-01 西安交通大学 Well arrangement structure for underground in-situ pyrolysis of coal and construction method thereof
CN112081558A (en) * 2020-10-10 2020-12-15 西安科技大学 Coal underground gasification and coalbed methane collaborative mining method, structure and construction method
CN113153146A (en) * 2021-01-06 2021-07-23 北京奥瑞安能源技术开发有限公司 Communicated horizontal well and drilling method thereof
CN113107589A (en) * 2021-04-14 2021-07-13 中煤科工集团西安研究院有限公司 Method for pre-draining water in advance on ground of coal seam roof aquifer
CN113107589B (en) * 2021-04-14 2023-08-15 中煤科工集团西安研究院有限公司 Advanced pre-drainage method for coal seam roof aquifer ground
CN113605874A (en) * 2021-08-10 2021-11-05 山西蓝焰煤层气集团有限责任公司 Method for extracting coal bed gas of broken soft coal bed top and bottom double-layer horizontal well
CN113605874B (en) * 2021-08-10 2023-02-10 山西蓝焰煤层气集团有限责任公司 Method for extracting coal bed gas of broken soft coal bed top and bottom double-layer horizontal well
CN114607318A (en) * 2022-03-24 2022-06-10 中煤科工集团西安研究院有限公司 Fracturing cooperative construction method for combined production and drilling of multi-layer horizontal well for deep coal bed methane

Similar Documents

Publication Publication Date Title
CN108086957A (en) A kind of method of the U-shaped coal bed gas well construction in double coal seams
CN102979498B (en) A kind of multi-lateral horizontal well system for coal bed gas
CN105298463B (en) Gas hydrates big well multiple-limb radially horizontal well completion method
CN102116140B (en) Construction method for enhancing extraction effect of ground coal bed gas
CN110397428B (en) Displacement coalbed methane yield increasing method for coalbed methane jointly mined by vertical well and U-shaped butt well
CN110242301A (en) A kind of modified water-protection coal-mining method of two step slip casting of top plate water-bearing layer
CN101749005B (en) Protection process of underground drilling hole
CN103256025B (en) A kind of composite well net type coal bed methane exploring method
CN102392677A (en) Permeability improvement technology for coal bed gas reservoir cap by using three-dimensional fracture network modification
CN104481495A (en) Coalbed methane (CBM) cluster double multi-branch horizontal well and drilling method relative to discharging and mining vertical well system
CN110425003A (en) It is a kind of improve cbm development straight well, in directional well well group coal bed gas recovery ratio recovery method
CN111043780B (en) Hydrothermal multi-branch directional mining and grouting geothermal well and construction method
CN112593910B (en) Efficient mining method for broken low-permeability coal bed gas short horizontal well group
CN110306965A (en) A kind of method for increasing for coal bed gas low yield wellblock
CN103161440A (en) Single-well coalbed methane horizontal well system and finishing method thereof
CN110173301A (en) Fully mechanized mining goaf grouting method based on cluster type multilateral well directional drilling
CN112081558A (en) Coal underground gasification and coalbed methane collaborative mining method, structure and construction method
CN103422813B (en) Individual well eye multi-lateral horizontal well system for coal bed gas and boring method
CN104612691A (en) Single borehole multilateral directional butted well salt mining method
CN1317483C (en) Method of entering target geologic body and system
CN110486022A (en) The advanced Regional pattern classification in seat earth water-bearing layer determines method
CN206000529U (en) A kind of coal bed gas well with multi-lateral horizontal well system based on straight well transformation
CN101749028B (en) Cross-pulling construction method for soft soil zone with high ground water level
CN207715128U (en) A kind of U-shaped coal bed gas well casing programme in double coal seams
CN116357383A (en) Multi-layer-multi-angle old goaf grouting filling method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination