CN206000529U - A kind of coal bed gas well with multi-lateral horizontal well system based on straight well transformation - Google Patents
A kind of coal bed gas well with multi-lateral horizontal well system based on straight well transformation Download PDFInfo
- Publication number
- CN206000529U CN206000529U CN201621033008.9U CN201621033008U CN206000529U CN 206000529 U CN206000529 U CN 206000529U CN 201621033008 U CN201621033008 U CN 201621033008U CN 206000529 U CN206000529 U CN 206000529U
- Authority
- CN
- China
- Prior art keywords
- well
- horizontal
- straight
- straight well
- section
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Solid Fuels And Fuel-Associated Substances (AREA)
Abstract
This utility model is related to a kind of coal bed gas well with multi-lateral horizontal well system based on straight well transformation, and it includes:The first straight well, the second straight well and the 3rd straight well setting gradually;Multi-lateral horizontal well system, including horizontal main shaft and some horizontal branch wells, horizontal main shaft includes vertical section, turn section and the horizontal segment being sequentially connected, vertical section is made up of the top of the first straight well, turn section is stretched out by the side window of vertical section, horizontal segment includes first level section, the second horizontal segment and the 3rd horizontal segment being sequentially connected, first level section one end connects turn section, the other end is connected with the second straight well, second horizontal segment one end is connected with the second straight well, the other end is connected with the 3rd straight well, and the 3rd horizontal segment is connected with the 3rd straight well.Whereby, not only effectively raise space availability ratio, substantially increase the gas production of whole region, more can effectively utilize resource, decrease construction volume and wellbore construction amount and the removal charge of horizontal well ground preliminary work for spudding, saved cost.
Description
Technical field
This utility model belongs to coal bed gas resource production technique field and in particular to a kind of many based on having of straight well transformation
The coal bed gas well of branch horizontal well system.
Background technology
Coal bed gas refers to be stored in coal seam with methane as main component, to adsorb based on the matrix of coal particle surface, portion
Divide and be free in coal hole or be dissolved in the hydrocarbon gas in coal seam water, be the associated minerals resource of coal, belong to Unconventional forage,
It is cleaning, high-grade energy and the industrial chemicals that nearly ten or twenty year emerges in the world.It is commonly called as " gas ", calorific value is the 2- of general coal
5 times, the calorific value of 1 cubic metre of pure coal bed gas is equivalent to 1.13kg gasoline, 1.21kg standard coal, and its calorific value is suitable with natural gas, can
With with natural gas mix defeated mixed, and burn after very clean, be nearly free from any waste gas, be first-class industry, chemical industry, generating
With resident living fuel.When coal bed gas air concentration reaches 5%-16%, meeting naked light will explode, and this is coal mine gas from explosion thing
Therefore root.Coal bed gas is directly discharged in air, and its greenhouse effect is about 21 times of carbon dioxide, to environmental destruction
Extremely strong.If first exploiting coal bed methane before mining, coal mine gas from explosion rate will reduce by 70% to 85%.The exploitation profit of coal bed gas
With having functions that to achieve many things at one stroke:Clear energy sources, commercialization can produce huge economic benefit, is national strategy resource.
Typically contain water in coal seam, therefore before being exploited, pressure drop funnel need to be formed by draining and reduce average reservoir
Pressure is it is seen that the output of coal bed gas is the process that a complicated depressurization desorption spreads seepage flow.This is also bed gas reservoir
The main distinction with normal gas pools.Adopting barefoot completion pattern coal bed gas finishing drilling horizontal well at present more, but, horizontal well is in mining
Easily collapsed in generation coal seam, coal dust blocks well accident period, is the one of the main reasons causing the individual well daily output low.Therefore study
Coal bed gas U-shaped well coal dust output mechanism, can provide important theoretical foundation to the high-efficiency mining realizing coal bed gas.
China's coalbed methane ground extraction technology, initially majority be used for reference external beat straight well and then pressure break production technique,
A lot of straight wells are beaten in coal-bed gas exploitation initial stage the whole country by this China, straight well uncovering coal plane amasss few, along with coal
The impact of layer hypotonicity geological conditions, the gas production of most of straight well is undesirable.
Up to the present, more than 14,000 mouthfuls, wherein 70% coal bed gas well produces Coalbed Methane In China ground extraction well quantity
Tolerance does not reach business gas production standard (1000 sides/sky), in order to vitalize these coal bed gas wells, we make full use of original old
On the basis of well, these old wells are carried out with well type transformation, increase gas production, make veteran send out sprouting, allow these old wells to come back to life,
Again shine brilliance.
Utility model content
(1) technical problem to be solved
In order to solve the problems referred to above of prior art, this utility model provides a kind of has multiple-limb based on straight well transformation
The coal bed gas well of horizontal well system, it can increase the bare area in coal seam, preferably links up seepage channel, increases single well-controlled
Reserves, can improve region gas production.
(2) technical scheme
In order to achieve the above object, the main technical schemes that this utility model adopts include:
A kind of coal bed gas well with multi-lateral horizontal well system based on straight well transformation, it includes:
The first straight well, the second straight well and the 3rd straight well setting gradually;
Multi-lateral horizontal well system, including horizontal main shaft and some horizontal branch wells, horizontal main shaft includes being sequentially connected
Vertical section, turn section and horizontal segment, vertical section is made up of the top of the first straight well, turn section from vertical section side window to extension
Stretch, horizontal segment includes first level section, the second horizontal segment and the 3rd horizontal segment being sequentially connected, the connection of first level section one end turns
Trisection, the other end is connected with the second straight well, and second horizontal segment one end is connected with the second straight well, and the other end is connected with the 3rd straight well,
3rd horizontal segment is connected with the 3rd straight well.
By the setting of said structure, not only effectively raise space availability ratio, substantially increase the product of whole region
Tolerance, more can effectively utilize resource, decrease construction volume and wellbore construction amount and the compensation for removal of horizontal well ground preliminary work for spudding
With having saved cost.Except increased the inter-well interference of each coal bed gas well, simultaneously as the horizontal segment docking in horizontal main shaft
Change to coal seam prime stratum stress in the drilling process of second, third two mouthfuls of straight wells, also substantially increases the infiltration in coal seam
Rate, is conducive to desorbing, diffusion and the migration of coal bed gas, is that the release of the internal coal bed gas in coal seam creates good condition, increased
The recovery ratio of coal bed gas.
In an embodiment of the present utility model, the part in some horizontal branch wells is located at first level section, another
Part is located at the second horizontal segment.
In an embodiment of the present utility model, there is a predetermined angle α, in advance between first level section and the second horizontal segment
Determine angle α between 170 ° to 180 °.
Preferably, horizontal segment entirety is in substantially a straight line.
In an embodiment of the present utility model, the 3rd horizontal section length is between 100m to 200m.
In an embodiment of the present utility model, vertical section is provided with PE pipe or glass reinforced plastic pipe.
In an embodiment of the present utility model, turn section is provided with PE pipe or glass reinforced plastic pipe.
In an embodiment of the present utility model, horizontal segment is provided with PE screen casing or fiberglass screen casing.
In an embodiment of the present utility model, mill off forged in advance by the sleeve pipe of the corresponding horizontal main shaft position of the second straight well.
In an embodiment of the present utility model, mill off forged in advance by the sleeve pipe of the corresponding horizontal main shaft position of the 3rd straight well.
In an embodiment of the present utility model, the position that the second straight well corresponds to horizontal segment is provided with connecting elements, supplies
Horizontal segment wears connection.
Preferably, being provided with transition interlayer between horizontal segment and connecting elements, transition interlayer is made using elastic material, mistake
Cross interlayer and be bonded in connecting elements.So as to preventing from vibrating the collision leading to.
(3) beneficial effect
The beneficial effects of the utility model are:Coal bed gas well of the present utility model not only effectively raises space utilization
Rate, substantially increases the gas production of whole region, more effectively can utilize resource, decrease applying of horizontal well ground preliminary work for spudding
Work amount and wellbore construction amount and removal charge, have saved cost.Coal bed gas well of the present utility model is except increased each coal bed gas
The inter-well interference of well, simultaneously as dock in the drilling process of second, third two mouthfuls of straight wells to coal in the horizontal segment of horizontal main shaft
The change of layer original reservoir stress, also substantially increases the permeability in coal seam, is conducive to desorbing, diffusion and the migration of coal bed gas,
Release for coal seam inside coal bed gas creates good condition, increased the recovery ratio of coal bed gas.In addition, the construction of later stage mining
In, during well workover, two mouthfuls of straight wells can successively set up circulation, and well-flushing is more fully and thoroughly.
Brief description
Fig. 1 is the schematic diagram of the integral level projection structure of coal bed gas well of this utility model first embodiment;
Fig. 2 is the overall structure diagram of the coal bed gas well of this utility model first embodiment;
Fig. 3 is the cutting structural representation of the coal bed gas well of this utility model first embodiment.
【Description of reference numerals】
1:First straight well;
2:Second straight well;
3:3rd straight well;
4:Horizontal main shaft;
41:Vertical section;
42:Turn section;
43:Horizontal segment;
431:First level section;
432:Second horizontal segment;
433:3rd horizontal segment;
5:Horizontal branch well.
Specific embodiment
In order to preferably explain this utility model, in order to understand, below in conjunction with the accompanying drawings, by specific embodiment, right
This utility model is described in detail.
Referring to Fig. 1, Fig. 2 and Fig. 3, this utility model first embodiment multi-branched horizontal well had based on straight well transformation
The coal bed gas well of system, it includes:
The first straight well 1, the second straight well 2 and the 3rd straight well 3 setting gradually;
Multi-lateral horizontal well system, including horizontal main shaft 4 and some horizontal branch wells 5, horizontal main shaft 4 includes being sequentially connected
Vertical section 41, turn section 42 and horizontal segment 43, vertical section 41 is made up of the top of the first straight well 1, and turn section 42 is by vertical section
41 side window stretches out, and horizontal segment 43 includes first level section 431, the second horizontal segment 432 and the 3rd level being sequentially connected
Section 433, first level section 431 one end connects turn section 42, and the other end connects with the second straight well 2, the second horizontal segment 432 one end and
Second straight well 2 connects, and the other end is connected with the 3rd straight well 3, and the 3rd horizontal segment 433 is connected with the 3rd straight well 3.
By the setting of said structure, not only effectively raise space availability ratio, substantially increase the product of whole region
Tolerance, more can effectively utilize resource, decrease construction volume and wellbore construction amount and the compensation for removal of horizontal well ground preliminary work for spudding
With having saved cost.Except increased the inter-well interference of each coal bed gas well, simultaneously as the horizontal segment 43 in horizontal main shaft 4 is right
Connect the change to coal seam prime stratum stress in the drilling process of second, third two mouthfuls of straight wells, also substantially increase oozing of coal seam
Rate, is conducive to desorbing, diffusion and the migration of coal bed gas thoroughly, is that the release of the internal coal bed gas in coal seam creates good condition, increases
The recovery ratio of coal bed gas.
Wherein, located at first level section 431, another part is located at the second level for the part in some horizontal branch wells 5
Section 432.
Wherein, there is between first level section 431 and the second horizontal segment 432 a predetermined angle α, predetermined angle α between
Between 170 ° to 180 °.
Preferably, horizontal segment 43 entirety is in substantially a straight line.
As shown in figure 3, horizontal segment 43 can be an entirety, i.e. first level section 431, the second horizontal segment 432 and the 3rd
Do not separate between horizontal segment 433.
Wherein, the 3rd horizontal segment 433 length is between 100m to 200m.
Wherein, vertical section 41 is provided with PE pipe or glass reinforced plastic pipe.
Wherein, turn section 42 is provided with PE pipe or glass reinforced plastic pipe.
Wherein, horizontal segment 43 is provided with PE screen casing or fiberglass screen casing.
Wherein, mill off forged in advance by the sleeve pipe of corresponding horizontal main shaft 4 position of the second straight well 2.
Wherein, mill off forged in advance by the sleeve pipe of corresponding horizontal main shaft 4 position of the 3rd straight well 3.
In an embodiment of the present utility model, the position that the second straight well 2 corresponds to horizontal segment 43 is provided with connecting elements,
Wear connection for horizontal segment 43.
Specifically, connecting elements has four connecting interfaces and some openings, and wherein, four connecting interfaces are two-by-two relatively
Setting, two connecting interfaces of a pair of opposing connect upper semisection and the lower semisection of the second straight well 2 respectively, and second to relatively
Two connecting interfaces of setting connect first level section 431 and second horizontal segment 432 of horizontal segment 43 respectively, and some openings include
Triangle open mouth and rounded triangle opening.
Wherein, the PE screen casing of horizontal segment 43 or fiberglass screen casing wear and are supported in connecting elements, preferably, horizontal segment 43
PE screen casing or fiberglass screen casing and connecting elements between be provided with transition interlayer, transition interlayer is made using elastic material, such as
Rubber, transition interlayer is bonded in connecting elements.
During application, this utility model can implement (so that existing straight well is transformed as a example illustrating) as follows:
Step 1, is analyzed to the well history data and creation data of existing straight well first, and collects other of relevant range
Geologic information, preferably suitable three mouthfuls of straight wells, set up threedimensional model;
Step 2, in selected target area, determines pre-transformation for the first of the vertical section 41 of multi-lateral horizontal well system
Straight well 1 and another two mouthfuls of second straight wells 2 being used for docking and the 3rd straight well 3, for example, select a bite straight well of distalmost end as first
Straight well 1, the coordinate of each well head of repetition measurement, make design;
Step 3, using existing casing firing milling technology, by the sleeve pipe forging of the target coal seam section of two mouthfuls of straight wells being used for docking
Mill off, forging milling after the completion of, under enter RMRS instrument (i.e. Rotary Magnetic Ranging System, rotary magnetic range finding system
System), survey data, determine that the magnetic disturbance of target phase does not affect later stage docking construction, forging milling success, measure the hole deviation number of straight well in passing
According to, know the wellbore trajectory of straight well move towards data (note:The length of sleeve pipe milling determines according to the requirement of docking instrument RMRS);
Step 4, carries out casing sidetracking operation to the vertical section 41 transformed by the first straight well 1, after first setting angle,
Start windowing task, start horizontal well operations afterwards, after windowing, window must be repaiied, it is to avoid the generation of trip-out accident;
Step 5, starts horizontal main shaft 4 inclination section construction, gets hold of rate of over-all angle change, select suitable landing point, and
Angle during land;
Step 6, the construction of horizontal segment 43, main after objective Shi Xian branch, go forward hand in hand, work progress designs branch
Leave angle, should prevent coal seam from collapsing during horizontal segment 43 construction and cause the accidents such as bit freezing, burying;
Step 7, connects for the first time, during 2 remaining 100 meters about of distance the second straight well, enters strong magnetic joint under trip-out, and simultaneously the
Enter RMRS instrument under two straight wells 2, start to connect operation;
Step 8, after connection completes for the first time, seals the well head of the second straight well 2, beginning the second horizontal segment 432 is constructed and (applied
Work method is referring to step 6);
Step 9, the second horizontal segment 432 apart from remaining 100 meters of target spot when, start to connect operation that (construction method is referring to step
7), after the completion of connection, continue construction, then beat about 100-200 rice, finishing drilling;
Step 10, after finishing drilling, fully cleans horizontal branch well 5 with mud cleans agent solution, removes mud in drilling process
Pollution (the note that coal surface is caused:Scavenging period is no less than 8 hours), under horizontal main shaft 4, then enter PE screen casing support
Coal seam, completion;
Step 11, will enter to carry out mining (note in two mouthfuls of straight wells of docking under conventional mining equipment:The mining initial stage notes controlling
The speed that liquid level declines).
In sum, coal bed gas well of the present utility model not only effectively raises space availability ratio, substantially increases whole
The gas production in individual region, more can effectively utilize resource, decrease construction volume and the wellbore construction of horizontal well ground preliminary work for spudding
Amount and removal charge, have saved cost.Coal bed gas well of the present utility model is except increased the inter-well interference of each coal bed gas well, same
When, because the horizontal segment in horizontal main shaft docks in the drilling process of second, third two mouthfuls of straight wells to coal seam prime stratum stress
Change, also substantially increase the permeability in coal seam, be conducive to desorbing, diffusion and the migration of coal bed gas, be the internal coal seam in coal seam
The release of gas creates good condition, increased the recovery ratio of coal bed gas.In addition, in the construction of later stage mining, during well workover, two mouthfuls straight
Circulation can successively be set up by well, and well-flushing is more fully and thoroughly.
Claims (10)
1. a kind of coal bed gas well with multi-lateral horizontal well system based on straight well transformation is it is characterised in that it includes:
The first straight well, the second straight well and the 3rd straight well setting gradually;
Multi-lateral horizontal well system, including horizontal main shaft and some horizontal branch wells, it is vertical that horizontal main shaft includes being sequentially connected
Section, turn section and horizontal segment, vertical section is made up of the top of the first straight well, and turn section is stretched out by the side window of vertical section, water
Flat section includes first level section, the second horizontal segment and the 3rd horizontal segment being sequentially connected, and first level section one end connects turn section,
The other end is connected with the second straight well, and second horizontal segment one end is connected with the second straight well, and the other end is connected with the 3rd straight well, the 3rd water
Flat section is connected with the 3rd straight well.
2. the coal bed gas well with multi-lateral horizontal well system based on straight well transformation as claimed in claim 1, its feature exists
In:, located at first level section, another part is located at the second horizontal segment for a part in some horizontal branch wells.
3. the coal bed gas well with multi-lateral horizontal well system based on straight well transformation as claimed in claim 1, its feature exists
In:There is between first level section and the second horizontal segment a predetermined angle α, predetermined angle α is between 170 ° to 180 °.
4. the coal bed gas well with multi-lateral horizontal well system based on straight well transformation as claimed in claim 3, its feature exists
In:Horizontal segment is overall to be in substantially a straight line.
5. the coal bed gas well with multi-lateral horizontal well system based on straight well transformation as claimed in claim 1, its feature exists
In:3rd horizontal section length is between 100m to 200m.
6. the coal bed gas well with multi-lateral horizontal well system based on straight well transformation as claimed in claim 1, its feature exists
In:Vertical section and/or turn section are provided with PE pipe or glass reinforced plastic pipe.
7. the coal bed gas well with multi-lateral horizontal well system based on straight well transformation as claimed in claim 1, its feature exists
In:Horizontal segment is provided with PE screen casing or fiberglass screen casing.
8. the coal bed gas well with multi-lateral horizontal well system based on straight well transformation as claimed in claim 1, its feature exists
In:Mill off forged in advance by the sleeve pipe of the second straight well and/or the corresponding horizontal main shaft position of the 3rd straight well.
9. the coal bed gas well with multi-lateral horizontal well system based on straight well transformation as claimed in claim 1, its feature exists
In:The position that second straight well corresponds to horizontal segment is provided with connecting elements, wears connection for horizontal segment.
10. the coal bed gas well with multi-lateral horizontal well system based on straight well transformation as claimed in claim 9, its feature exists
In:It is provided with transition interlayer, transition interlayer is made using elastic material, and transition interlayer is bonded between horizontal segment and connecting elements
Connecting elements.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201621033008.9U CN206000529U (en) | 2016-08-31 | 2016-08-31 | A kind of coal bed gas well with multi-lateral horizontal well system based on straight well transformation |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201621033008.9U CN206000529U (en) | 2016-08-31 | 2016-08-31 | A kind of coal bed gas well with multi-lateral horizontal well system based on straight well transformation |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206000529U true CN206000529U (en) | 2017-03-08 |
Family
ID=58193801
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201621033008.9U Active CN206000529U (en) | 2016-08-31 | 2016-08-31 | A kind of coal bed gas well with multi-lateral horizontal well system based on straight well transformation |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206000529U (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106948860A (en) * | 2017-05-27 | 2017-07-14 | 中煤科工集团重庆研究院有限公司 | The method for cooperateing with progressive draining coal seam gas with directional drilling based on U-shaped well |
CN108868617A (en) * | 2018-07-13 | 2018-11-23 | 北京市华清地热开发集团有限公司 | Circular hole drilling tool |
CN110185389A (en) * | 2019-05-05 | 2019-08-30 | 重庆城开能源有限公司 | A kind of discarded deeps mines well Geothermal Exploitation and Utilization system and method |
CN110306965A (en) * | 2019-07-08 | 2019-10-08 | 河南理工大学 | A kind of method for increasing for coal bed gas low yield wellblock |
-
2016
- 2016-08-31 CN CN201621033008.9U patent/CN206000529U/en active Active
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106948860A (en) * | 2017-05-27 | 2017-07-14 | 中煤科工集团重庆研究院有限公司 | The method for cooperateing with progressive draining coal seam gas with directional drilling based on U-shaped well |
CN108868617A (en) * | 2018-07-13 | 2018-11-23 | 北京市华清地热开发集团有限公司 | Circular hole drilling tool |
CN110185389A (en) * | 2019-05-05 | 2019-08-30 | 重庆城开能源有限公司 | A kind of discarded deeps mines well Geothermal Exploitation and Utilization system and method |
CN110306965A (en) * | 2019-07-08 | 2019-10-08 | 河南理工大学 | A kind of method for increasing for coal bed gas low yield wellblock |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102080526B (en) | Method for extracting gas from bedding level fractured well of ground coal seam roof | |
CN206000529U (en) | A kind of coal bed gas well with multi-lateral horizontal well system based on straight well transformation | |
CN105298463B (en) | Gas hydrates big well multiple-limb radially horizontal well completion method | |
CN102116140B (en) | Construction method for enhancing extraction effect of ground coal bed gas | |
CN110397428B (en) | Displacement coalbed methane yield increasing method for coalbed methane jointly mined by vertical well and U-shaped butt well | |
CN106437662A (en) | Hybrid temporary plugging volume fracturing method suitable for deep shale gas horizontal well | |
CN104806217A (en) | Combined separated layer fracturing, grouping and layer-combining mining method for coal bed well group | |
CN103256025B (en) | A kind of composite well net type coal bed methane exploring method | |
CN108798608B (en) | Natural gas hydrate exploitation system and method | |
CN102392677A (en) | Permeability improvement technology for coal bed gas reservoir cap by using three-dimensional fracture network modification | |
CN108086957A (en) | A kind of method of the U-shaped coal bed gas well construction in double coal seams | |
CN110306965A (en) | A kind of method for increasing for coal bed gas low yield wellblock | |
CN104100244A (en) | Well spacing method for coal bed gas communication well groups and application of well spacing method in fracturing yield increase | |
CN109209474A (en) | A kind of method that dual-lateral well extracts lower coal seam and top more goaf gas and ponding | |
CN108301866A (en) | Mining of closed distance coal seam group adjacent layer gas pressure relief directional drilling stops pumping method | |
CN108843320A (en) | Shift to an earlier date outburst elimination method in the tunnel of coal mine tight roof full face | |
CN106640018A (en) | Method for mining coalbed gas through V-shaped well set | |
CN111827936B (en) | Batch drilling rolling type well group natural gas hydrate exploitation system and method | |
CN108894765A (en) | The major-minor well construction and its method of deep water shallow layer gas hydrate exploitation | |
CN115680653A (en) | Hydraulic fracturing and permeability increasing extraction method for coal seam roof of coal roadway driving face | |
CN205858313U (en) | A kind of air for LOW PERMEABILITY RESERVOIR drives well pattern structure | |
CN205936553U (en) | Raising output is transformed and novel coal seam gas well of formation to old well | |
CN107100666A (en) | Quick-fried crowded extinction and dust-removing method under a kind of Coal Seam Prone To Outburst coal roadway tunneling | |
CN200985782Y (en) | Operating tool string for gas well fracturing and production put | |
CN111734359A (en) | Natural gas hydrate horizontal branch well exploitation method based on deepwater suction anchor |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |